Documente Academic
Documente Profesional
Documente Cultură
Report No.
Date
Spread
INPECTION AND TES PLAN FOR INSTALLATION OF
Drawing No LTSWITCHBOARDS
Contractor
LEGEND: S - Surveillance W - Witness Inspection Point H - Mandatory Hold Point for Inspection
CONTRACTOR REAL THIRD PARTY
Date
Name
Signatu
re
2-PL-QM-ITP-MLV-EL-004
Contractor Logo PROJECT NAME
Report No.
Date
Spread
INPECTION AND TES PLAN FOR INSTALLATION OF
Drawing No LT SWITCHBOARDS
Contractor
Activities Controlling Acceptance Verifying Contractor Reliance Client/Third
Sl. Document criteria Specifications / Discipline Party
No. Records / Forms Engineer
GA Drawing Approved
5.3 Check the panel base dimensions w.r.t cut out Drawing H W S
Check layout and leveling of base frame before GA Drawing
Approved
5.4 installation of switchgear panel. Drawing H W S
Report No.
Date
Spread
INPECTION AND TES PLAN FOR INSTALLATION OF
Drawing No LT SWITCHBOARDS
Contractor
Activities Controlling Acceptance Verifying Contractor Reliance Client/Third
Sl. Document criteria Specifications / Discipline Party
No. Records / Forms Engineer
6.12 Check for panel door interlocks & padlocking Control Drawing Approved
H W S
arrangement. Drawing
6.13 Check for presence of explosion vents / ventilation Approved
wherever applicable. Vendor drawing Drawing
H H S
6.14 Check for provision of surge arrestors wherever Approved Approved
applicable. H W S
drawing Drawing
Current
Approved
6.15 Current limiting reactor installed wherever specified limiter H W S
drawing
installed
LEGEND: S - Surveillance W - Witness Inspection Point H - Mandatory Hold Point for Inspection DR-Document Review
COTRACTOR REAL THIRD PARTY
Date
Name
Signature
2-PL-QM-ITP-MLV-EL-004
Contractor Logo PROJECT NAME
Report No.
Date
Spread
INPECTION AND TES PLAN FOR INSTALLATION OF
Drawing No LT SWITCHBOARDS
Contractor
Activities Controlling Acceptance Verifying Contractor Reliance Client/Third
Sl. Document criteria Specifications / Discipline Party
No. Records / Forms Engineer
No foreign
Check whether any loose items are left inside the
6.17 items are H W S
panel and ensure general cleanliness of panels
permitted
LEGEND: S - Surveillance W - Witness Inspection Point H - Mandatory Hold Point for Inspection DR-Document Review
COTRACTOR REAL THIRD PARTY
Date
Name
Signature
2-PL-QM-ITP-MLV-EL-004
Contractor Logo PROJECT NAME
Report No.
Date
Spread
INPECTION AND TES PLAN FOR INSTALLATION OF
Drawing No LT SWITCHBOARDS
Contractor
Activities Controlling Acceptance Verifying Contractor Reliance Client/Third
Sl. Document criteria Specifications / Discipline Party
No. Records / Forms Engineer
7.2 Check bus bar connections are correct, properly As per Drawing Correct size
aligned and torque applied. Also ensure proper size and rust free
items shall H W S
and quality of Bolts and nuts.
be used
7.3 Check for phase separators & their position.
H W W%
7.4 Check for condition of bus bar support insulators / Visual
bushings / shrouds. H W W%
LEGEND: S - Surveillance W - Witness Inspection Point H - Mandatory Hold Point for Inspection DR-Document Review
COTRACTOR REAL THIRD PARTY
Date
Name
Signature
2-PL-QM-ITP-MLV-EL-004
Contractor Logo PROJECT NAME
Report No.
Date
Spread
INPECTION AND TES PLAN FOR INSTALLATION OF
Drawing No LT SWITCHBOARDS
Contractor
Activities Controlling Acceptance Verifying Contractor Reliance Client/Third
Sl. Document criteria Specifications / Discipline Party
No. Records / Forms Engineer
Physical
9.5 Check for provision of test terminal block. Control Drawing
inspection
H W S
Check for provision of protective relays as per
Physical
9.6 drawings. Control Drawing
inspection
H W S
LEGEND: S - Surveillance W - Witness Inspection Point H - Mandatory Hold Point for Inspection DR-Document Review
COTRACTOR REAL THIRD PARTY
Date
Name
Signature
2-PL-QM-ITP-MLV-EL-004
Contractor Logo PROJECT NAME
Report No.
Date
Spread
INPECTION AND TES PLAN FOR INSTALLATION OF
Drawing No LT SWITCHBOARDS
Contractor
Activities Controlling Acceptance Verifying Contractor Reliance Client/Third
Sl. Document criteria Specifications / Discipline Party
No. Records / Forms Engineer
Check the relays are tested and set as per Drawing, relay Test Applicable relay test
9.7 settings certificate format H W S
recommendations
Check for appropriate range & size of meters. Control Drawing Physical
9.7 inspection H W W%
LEGEND: S - Surveillance W - Witness Inspection Point H - Mandatory Hold Point for Inspection DR-Document Review
COTRACTOR REAL THIRD PARTY
Date
Name
Signature
2-PL-QM-ITP-MLV-EL-004
Contractor Logo PROJECT NAME
Report No.
Date
Spread
INPECTION AND TES PLAN FOR INSTALLATION OF
Drawing No LT SWITCHBOARDS
Contractor
Activities Controlling Acceptance Verifying Contractor Reliance Client/Third
Sl. Document criteria Specifications / Discipline Party
No. Records / Forms Engineer
Physical
Check rack in / out arrangement of CB trolley for
11.3 Inspection H W W%
its smooth operation and contact alignment.
Physical
Check for provision of CB earthing.
11.4 Inspection H W W%
LEGEND: S - Surveillance W - Witness Inspection Point H - Mandatory Hold Point for Inspection DR-Document Review
COTRACTOR REAL THIRD PARTY
Date
Name
Signature
2-PL-QM-ITP-MLV-EL-004
Contractor Logo PROJECT NAME
Report No.
Date
Spread
INPECTION AND TES PLAN FOR INSTALLATION OF
Drawing No LT SWITCHBOARDS
Contractor
Activities Controlling Acceptance Verifying Contractor Reliance Client/Third
Sl. Document criteria Specifications / Discipline Party
No. Records / Forms Engineer
11.9 Check for locking facility & its indication at Approved Physical
service / test / earth position. drawing Inspection H W W%
11.10 Check the operation of breaker interlock mechanism Vendor drawing Physical
verification
H W W%
11.11 Check for provision of phase barriers wherever
As per applicable Applicable
applicable. Specification Specification
H W W%
11.12 Check for proper opening and closing timings of As per Correct time 2-PLQM-FMT-EL006 /
Specification of operation
H W W%
breaker 2-PL-QM- FMT- EL042
11.13 Check the operation of breaker in test position,
operation of master trip relay and hence the circuit Physical
As per drawing
verification
H W W%
breaker, interlocks for motor space heater supply.
LEGEND: S - Surveillance W - Witness Inspection Point H - Mandatory Hold Point for Inspection DR-Document Review
COTRACTOR REAL THIRD PARTY
Date
Name
Signature
2-PL-QM-ITP-MLV-EL-004
Contractor Logo PROJECT NAME
Report No.
Date
Spread
INPECTION AND TES PLAN FOR INSTALLATION OF
Drawing No LT SWITCHBOARDS
Contractor
Activities Controlling Acceptance Verifying Contractor Reliance Client/Third
Sl. Document criteria Specifications / Discipline Party
No. Records / Forms Engineer
12.1 Check for correct methods of cable termination. As per approved Physical H W W%
test procedure inspection
LEGEND: S - Surveillance W - Witness Inspection Point H - Mandatory Hold Point for Inspection DR-Document Review
COTRACTOR REAL THIRD PARTY
Date
Name
Signature
2-PL-QM-ITP-MLV-EL-004
Contractor Logo PROJECT NAME
Report No.
Date
Spread
INPECTION AND TES PLAN FOR INSTALLATION OF
Drawing No LT SWITCHBOARDS
Contractor
Activities Controlling Acceptance Verifying Contractor Reliance Client/Third
Sl. Document criteria Specifications / Discipline Party
No. Records / Forms Engineer
13.1 Check for availability of AC / DC control bus bars. Control Drawing Control H W W%
Drawing
Check for correctness and tightness of control H W W%
As per Applicable
13.2 wiring. specification Specification
Check for correct component & ferrule numbering Approved H W W%
13.3 As per Drawing
as per approved drawings. drawing
Proper
13.4 Check for proper dressing of control cables dressed & H W W%
clamped
14 Check that no loose items are left inside the panel. Clean & no
foreign parts H W W%
are permitted
15 Check that no spare openings / holes/ relay or Physical
H W W%
meter slots are left un blocked. verification
LEGEND: S - Surveillance W - Witness Inspection Point H - Mandatory Hold Point for Inspection DR-Document Review
COTRACTOR REAL THIRD PARTY
Date
Name
Signature
2-PL-QM-ITP-MLV-EL-004
Contractor Logo PROJECT NAME
Report No.
Date
Spread
INPECTION AND TES PLAN FOR INSTALLATION OF
Drawing No LT SWITCHBOARDS
Contractor
Activities Controlling Acceptance Verifying Contractor Reliance Client/Third
Sl. Document criteria Specifications / Discipline Party
No. Records / Forms Engineer
LEGEND: S - Surveillance W - Witness Inspection Point H - Mandatory Hold Point for Inspection DR-Document Review
COTRACTOR REAL THIRD PARTY
Date
Name
Signature
2-PL-QM-ITP-MLV-EL-004