NLC India Limited
WELCOMES THE BANKERS

Page 9 of 50
Financial Appraisal of
Revised Cost Estimate of NNTPP
Chimney NNTPP COOLING TOWERS NDCT1, NDCT2

Page 10 of 50
POWER TRANSFORMERS Circulating Water Pump House

Page 11 of 50
BOP AERIAL VIEW LDO / HFO Tank

Page 12 of 50
Project background
NLCIL is installing a 2*500MW Lignite based power project at Neyveli
 The Project was sanctioned by GOI vide Order No.43014/01/2008/CPAM dated 09.06.2011
 PPAs signed with TANGEDCO, Karnataka Discoms, Kerala Discom, AP Discoms (Andhra &
Telangana) and Pondicherry Discoms.
 The project has also got Mega Power Project status and is entitled for associated tax benefits.
 The project has been Initially delayed due to the retendering of NTA-1 (Steam generator
&Auxiliaries Package) all the package. Anticipated CoD is 15th December 2018 (Unit 1) and
15th December 2018 (Unit-2)

Financial details
 Sanctioned project cost of Rs.5907.11 crore on Oct, 2010 price level with an import
component of Rs. 969.81crore (USD 217.009 million @ Rs. 44.69/USD).
 Actual expenditure incurred for the project till 31st July, 2018 has reached a level of about
79.02% (Accrual basis) of the Revised cost.
 The Revised estimated project cost is Rs 7080.41 crore.

Page 13 of 50
NTA 1-STEAM GENERATOR (BOILER) NTA 2-TURBO GENERATOR NTA 3-BALANCE OF PLANT
Pkg. Contractor M/s BHEL, New Delhi Pkg. Contractor M/s BHEL, New Delhi Pkg. Contractor M/s ESSAR Projects,
Contract value.Rs-2099 Cr& Euro 5.63 Cr. Contract value.Rs-1038.90 Cr Mumbai.
Date of LOA-31.10.2013. Date of LOA-23.12.2013. Contract value.Rs-1163.39 Cr
Date of completion. Date of completion. Date of LOA-30.04.2014.
Unit-I-48 Months[31.10.2017] Unit-I-42 Months[23.06.2017] Date of completion.
Unit-II-54 Months[30.04.2018] Unit-II-48 Months[23.12.2017] 46 Months[28.02.2018]
 Boiler- 500 MW-2 No’s.  Turbine- 500 MW multi cylinder, horizontal  Lignite Handling System- Two stream of
 Boiler capacity: 1600 T/hr.179 Ksc, 540°c. tandem compounded, reheat & regenerative capacity-2400 T/hr. Stock yard capacity-2,
 Boiler Type: Drum less, once through ,tower type Condensing, throttle governing and directly 30,000 Tons. Capacity of closed shed-70,000
& sub critical coupled with generator. Tons.
 Lignite firing system: Tangential, pulverised fuel  HP Turbine- 17 reaction stages, Double casing  Ash Handling System- Fly ash collection
firing system with 8 no’s Beater wheel mills & single flow. Inlet pressure-170 Ksc. design-86 T/hr. Bottom ash collection design-
capacity-85 T/hr. Temperature-537°c. Flow-1457 T/hr. 20 T/hr.
 Dry bottom furnace with After Burning Grate &  IP Turbine-Double flow-2X12 stages & double  Raw water from fertilizer lake for both units-
Slag conveyor system. casing. Inlet pressure-40 Ksc. Temperature- 3800 M³/hr.
 Oxygenated internal treatment of feed water. 565°C. Flow-1302 T/hr.  Circulating water pump-4 No’s, Capacity-
 Balanced draft systems with FD fans & ID fans,  LP Turbine-Double flow-2X6 stages & double 32000M³/hr each.
Regenerative air preheaters & steam coil air casing. Inlet pressure-7.08 Ksc. Temperature-  DM water generation-125 M³/hr.
preheaters. 308°c. Flow-1081 T/hr.  Biflue RCC chimney height-275 Metres.
 Electrostatic precipitators with 99.703%  Generator- 500 MW, 2 pole 3 phase &  NDCT-2 No’s. Height-135 Metre, Dia- 122
Efficiency and exit concentration less than 50 cylindrical rotor. Water cooled stator, Hydrogen Metre, cooling range-10°C.
mg/Nm3. cooled rotor, Class-F insulation.  400 KV & 220 KV Gas Insulated Switch Yard
 Total height of Boiler-130 Meters. GIS.
 Total weight of Boiler with auxiliaries-55,000MT  Power transformers-GT-2 Sets, UT-4 No’s, ST-
2 No’s, ICT-2 Sets.
Original Project Cost:- Rs 5907.11 Cr.,

Page 14 of 50
Revised Cost Estimation
Neyveli New Thermal Power Project (2X500MW)- (Base Date Feb 2018)
GoI Sanctioned Revised Cost Variation
Sl. No. Items % Variation
Cost Rs. Cr. Estimate Rs. Cr. Rs. Cr.
1 Preliminary Expenses 1.20 1.16 -0.04 0.00%
2 Land & Land Development 14.50 11.56 -2.94 -0.05%
3 Civil & Structural works 967.05 903.69 -63.36 -1.07%
4.i Main Power equipment 2489.57 2594.75 105.18 1.78%
4.ii Other mechanical equipment 316.10 327.56 11.46 0.19%
4.iii Electrical items and C&I 427.80 579.95 152.15 2.58%
4.iv Spares 80.83 133.67 52.84 0.89%
4.v Erection Charges 323.35 399.29 75.94 1.29%
4.vi Freight & Insurance 156.86 67.70 -89.16 -1.51%
4.vii Basic Duties 150.67 258.51 107.84 1.83%
5 Overheads 420.15 542.08 121.93 2.06%
6 Capital cost without IDC 5348.08 5819.92 471.84 7.99%
7 IDC 559.03 772.78 213.75 3.62%
8 Capital cost with IDC 5907.11 6592.70 685.59 11.61%
Statutory requirement of additional scope
9 Borosilicate Lining 0.00 58.21 58.21 0.99%
10 Flue Gas De-Sulphurization 0.00 460.00 460.00 7.79%
Total Project Cost incl. Statutory requirement 7110.91 1203.80 20.38%
11 Less: Receipt of Infirm power Generation -30.50 -30.50 -0.52%
12 Project Cost including IDC 5907.11 7080.41 1173.30 19.86%
Total cost Exchange Rate : 1Euro = Rs 77.99 –Original Sanction
7

Page 15 of 50
Reasons for Cost Escalation NNTPP Project (Rs. In Crore)
Sl. No. Name of the Head RCE Inc/Dec PERCENTAGE
1 Changes Due to Statutory
a) FGD Package 460.00 7.79%
b) Borosilicate Lining 58.21 0.99%
c) Due to GST 25.40 0.43%
d) Due to Basic Taxes & Duties 82.44 1.40%
Variation Due to Statutory (A) 626.05 10.60%
2 Changes Other than Statutory
e) Price Variation in Packages 308.41 5.22%
f) Overhead 121.93 2.06%
g) IDC 213.75 3.62%
h) Decrease in Sub Packages (66.34) -1.12%
i) Revenue from Infirm Power (30.50) -0.52%
Variation Due to Cost overrn + Time
547.25 9.26%
overrun (B)
Grant Total (A + B) 1,173.30 19.86%

Original Cost 5,907.11


Revised Cost 7,080.41
NET INCREASE 1,173.30

Time overrun : 3.62% of initial project cost


Cost overrun : 5.64% of initial project cost
9 August 2018 8

Page 16 of 50
Reason for Cost Overrun
 This necessitates the additional investment for the project in the form of
installation of Flue Gas Desulphurization (FGD) plant at an estimated cost
of Rs 460.00 Crores. The contract finalizing works are under progress and
anticipated award of contract by Sep-2018 (Cost overrun)

 To avoid cold end corrosion of the Chimney flue can (made up of Corton
Steel) due to reduction of flue gas exit temperature after commissioning of
Flue Gas Desulphurization (FGD) plant, the chimney flue can to be
insulated with Borosilicate lining at an cost of Rs 58.21Cr and works are
nearing completion (Cost overrun)

The Overhead is increased from Rs.420.15 Cr to Rs.542.08 Cr resulting in


increase of Rs.121.93Cr. (Cost overrun)
 In the other parameters, the IDC in INR increased by Rs 269.86 Cr but it is
partially offset by the decrease in the foreign currency portion by Rs.-
56.11Cr. Resulting in net increase on account of IDC of Rs 213.75 Cr (Time
9
overrun)

Page 17 of 50
PPA signed for 25 years from COD as below.

Andhra 52.46 MW (5.25%) --PPA signed with United AP Discoms on 30.11.2010


&Amendment of PPA signed as on 21.02.2015

Telengana 61.31 MW (6.13%)- PPA signed with United AP Discoms on 30.11.2010


& Amendment of PPA signed as on 1.02.2015

Karnataka 70.54 MW (7.05%) --PPA signed with Karnataka Escoms on 19.11.2010.

Kerala 32.38 MW (3.24%) --PPA signed with KSEB on 10.12..2010

Tamil Nadu 653.07 MW(65.31%) -- PPA signed with TANGEDCO on 26.11.2010

Puduchery 4.24 MW (0.42%) -- PPA signed with PED/Puducherry on 04.01.2011

NLC 66.00 MW (6.60%)


Un allocated power- 60.00 MW (6.00%) - (Total -1000 MW)
10

Page 18 of 50
Technology Adopted
• Implementation of new MoEF environmental norms, Power Plants from 01.01.2017 have to

follow the revised standard emission norms.

• Changes in statutory requirements:


In Mg/ Nm3
Sl.No Details Norms while Revised
awarding Contract Standards

1 Suspended Particulate matter (SPM) 50 Mg/ Nm3 30 mg/ Nm3

2 Sulphur Dioxide ( So2 ) NA 100 mg/ Nm3


260 grams of NoX
Oxides of Nitrogen ( Nox )
3 per gigajoules of heat 100 mg/ Nm3
input
4 Mercury ( Mg ) NA 0.03 mg/ Nm3

11

Page 19 of 50
Summary of key observations

Capital cost
 The capital cost has increased as on account of both delay in completion and inclusion of
additional equipment such as FGD for compliance with statutory requirements.
 The increase in capital cost due the delay in project is around 11% which appears to be an
allowable increase.
 The costs on account of FGD and associated costs would be allowed by the regulator given
the statutory nature of the requirement
Tariff
 Fuel cost has increased nearly two folds leading to significant increase in the tariff.
 NNTPP should look for alternatives to bring down the fuel cost so as to be more competitive
on the Merit order dispatch of Tamil Nadu.
 However, NNTPP would be competing with the other NLC power plants as the energy charges
are in the same range as the others. This would give an opportunity to NLC to ensure the
proper utilization of all the units.
12

Page 20 of 50
NNTPP - Annual Production Plan ( 25 years)
Year 0 1 2 3 4 5 6 7 8 9 10 11 12

Year Ending Mar-19 Mar-20 Mar-21 Mar-22 Mar-23 Mar-24 Mar-25 Mar-26 Mar-27 Mar-28 Mar-29 Mar-30 Mar-31
Days 92 365 365 365 365 365 365 365 365 365 365 365 365

Installed Cacpacity (MW) 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000

Gross Generation MU 1876.8 7446.0 7446.0 7446.0 7446.0 7446.0 7446.0 7446.0 7446.0 7446.0 7446.0 7446.0 7446.0
PLF (%) % 85% 85% 85% 85% 85% 85% 85% 85% 85% 85% 85% 85% 85%
Auxiliary Energy
Consumption % 7.75% 7.75% 7.75% 7.75% 7.75% 7.75% 7.75% 7.75% 7.75% 7.75% 7.75% 7.75% 7.75%

Generation (Ex-bus) MU 1731.35 6868.94 6868.94 6868.94 6868.94 6868.94 6868.94 6868.94 6868.94 6868.94 6868.94 6868.94 6868.94

Year 13 14 15 16 17 18 19 20 21 22 23 24 25

Year Ending Mar-32 Mar-33 Mar-34 Mar-35 Mar-36 Mar-37 Mar-38 Mar-39 Mar-40 Mar-41 Mar-42 Mar-43 Nov-43
Days 365 365 365 365 365 365 365 365 365 365 365 365 273

Installed Cacpacity (MW) 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000

Gross Generation MU 7446.0 7446.0 7446.0 7446.0 7446.0 7446.0 7446.0 7446.0 7446.0 7446.0 7446.0 7446.0 5569.2
PLF (%) % 85% 85% 85% 85% 85% 85% 85% 85% 85% 85% 85% 85% 85%
Auxiliary Energy
Consumption % 7.75% 7.75% 7.75% 7.75% 7.75% 7.75% 7.75% 7.75% 7.75% 7.75% 7.75% 7.75% 7.75%

Generation (Ex-bus) MU 13 5137.59


6868.94 6868.94 6868.94 6868.94 6868.94 6868.94 6868.94 6868.94 6868.94 6868.94 6868.94 6868.94

Page 21 of 50
Present status of the project
The progress in all the three packages as on 31.07.2018 are as follows:

Package % Physical Progress


NTA -1 83.07%
NTA -2 87.92%
NTA-3 89.19%
OVERALL 87.48%
The progress made in terms of the investments and payments is as follows:

Rs. In Crore
Capital Overall financial
Terms of Payment
Expenditure progress wrt RCE
Cash Basis 5007.18 70.07%
Accrual Basis 5595.03 79.02%

Schedule Date of Commissioning


•Unit-1: 15th December -2018
•Unit-2: 15th December – 2018 14

Page 22 of 50
NNTPP CAPITAL PHASING (Rs. Crore)
YEAR PFC HDFC NEW TOTAL
2014-15 500.00 500.00
2015-16 695.00 695.00
2016-17 1805.00 1805.00
2017-18 750.00 750.00
2018-19 385.00 200.00 585.00
2019-20 621.00 621.00
TOTAL 3000.001135.00 821.00 4956.00
70% DEBT 4956.00

30% EQUITY 2124.00

PROJECT COST
7080.00

15

Page 23 of 50
Page 24 of 50
2 X 500 MW NEYVELI NEW THERMAL POWER PROJECT, NEYVELI

SITE PROGRESS
REPORT
AS ON JULY-2018

SUBMITTED BY

TRACTEBEL ENGINEERING PVT.LTD

CONSULTING ENGINEERS

PROJECT SITE

TEPL/M.501053/18-19/MPR-90 08-08-2018

Page 25 of 50
2X500 MW NEYVELI NEW THERMAL POWER PROJECT JULY’2018

GOI Sanction Date: 09.06.2011

Sanction Cost: Rs 5907.11Cr

Consultant: Tractebel Engineering Pvt Ltd

NTA 1(SG)
CONTRACTOR -M/s BHARAT HEAVY ELECTRICALS LIMITED

VALUE -Rs.2099.0 Crs & Euro 56.35 Million

LOA DATE -31.10.2013

Date of Commissioning: Unit-1:31 st October 2017 (48 months from the date of LOA)
(EOT 31st October 2018)
Unit-2:30 th April 2018 (54 months from the date of LOA)
st
(EOT 31 December 2018)
NTA 2(STG)
CONTRACTOR -M/s BHARAT HEAVY ELECTRICALS LIMITED

VALUE -Rs.1037.85 + 1.05 Crs

LOA DATE -23.12.2013

Date of Commissioning: Unit-1:23 rd June 2017 (42 months from the date of LOA)
(EOT 31st October 2018)
Unit-2:23 rd Dec 2017 (48 months from the date of LOA)
(EOT 31st December 2018)

NTA-3 (BALANCE OF PLANT)


CONTRACTOR -M/s EPC CONSTRUCTIONS INDIA LIMITED

VALUE -Rs.1159.08 + 4.31 Crs

LOA DATE -30.04.2014

Page 26 of 50
2X500 MW NEYVELI NEW THERMAL POWER PROJECT JULY’2018

Progress of NTA-1 (SG)

Major Events during the month:-

1. 02-07-18: ESP AC plant mechanical erection work commenced


2. 07-07-18: ID fan 1A mechanical erection work completed
3. 07-07-18:Unit-1 Boiler side Instrument air flushing completed
4. 10-07-18: ESP unit-1 of pass C & D motor trial run completed
5. 12-07-18 Unit-1 pressure part Air leak test completed
6. 13-07-18: Unit-1 Mill 4 mechanical erection commenced
7. 19-07-18: LDO oil received and unloaded to tank no-2
8. 21-07-18: Unit-1 Mill 8 1st stage RCC completed
9. 23-07-18: Unit-2 Mill 7 1st stage RCC completed
10. 25-07-18: Unit-1 Fuel Oil Control Station Service air header flushing completed

Physical Progress:-

Sl. Up-to
No During this
Description Unit Scope Previous Cumulative
Month
Month
1 RCC CuM 70000 63007 431 63438

2 Supply MT 135000* 129100 572 129672

3 Erection MT 113092* 96746 3159 99905

*Scope revised based on BHEL report

Progress in detail:-Civil

i. RCC Cumulative progress of 90.62% achieved.

ii. Unit 1: Mill No.1, 2, 3 & 4 deck slab completed, also retaining wall work completed
on Mill no.1, 2 & 3. Mill no. 8 Deck 1st stage RCC completed. Mill no.5 work is in
progress.
iii. Unit-2: Mill no.4, 5 & 6 deck slabs completed and retaining wall work is in progress.
Mill no.7 deck 1st stage RCC completed. Further rebar work is under progress.
iv. Pipe & Cable Rack Foundation: Unit-1: RCC foundation & Pedestal work is in
progress. Pipe rack & Structural gallery erection work is in progress.
Unit-2: RCC foundation and pedestal work completed.
3

Page 27 of 50
2X500 MW NEYVELI NEW THERMAL POWER PROJECT JULY’2018

For boilers 1&2, Footing 50/65 no’s completed, Pedestal 104/129 no’s completed &
Gallery erected 117/ 139 no’s completed.
v. Cement concrete road work completed in ESP east and it is in progress for boiler
bunker bay area.

Progress in detail:-Mechanical

Supply cumulative progress is 96.05 % & Erection cumulative progress is 88.33%.


a. Boilers:

Boilers-1:

Mill: Mill no 1, 2, 3 & 4 erection work is in progress.

Pressure parts Coil erection work is in progress (6347/6900 MT). HP joints welding for
51241/51254 no’s Joint completed. Hydro test–39752/39752 joints completed and
further work is in progress. RH joints completion: 11502/11502. Stud welding is in
progress.
Flue gas re-suction duct erection is in progress. (568/630)
Air Duct: Erection work is in progress. Erected (1449/1528MT)
Gas Duct (Eco-APH – ESP): Erection work is in progress. Erected (1655/1951MT)
Burner & coal pipe: (P6 – 45): Erection work is in progress. Erected (470/582MT)

Boiler-2:
Mill: Mill no 6 erection work is in progress.

Pressure parts Coil erection work is in progress (6015/6900MT). HP joints welding for
49136/51254 no’s completed. Hydro test -38972 out of 40350 joints completed and
further work is in progress. RH joints completion 10154/11502.

Flue gas re-suction duct erection is in progress. (527/630)


Air-Duct: Erection work is in progress. (1239/1528MT)
Gas Duct: (Eco – APH – ESP): Pre assembly& erection work is in progress.
(728/1951MT)
Burner & coal pipe: (P6 – 45): Pre assembly & erection work is in progress.
(376/582MT)

b. ESP
Unit-1:
LVSW panel were charged. Trial run of EER motors for all passes completed in
coupled condition. CERM of pass A & B motor trial run completed in coupled
condition and Pass C&D motor trial run completed.
11KV power cable laying is in progress. Illumination at ‘0’ & 4.5 M level for pass A &
B completed. Further pass ‘D’ illumination work is in progress.
4

Page 28 of 50
2X500 MW NEYVELI NEW THERMAL POWER PROJECT JULY’2018

HVRTs of all Pass oil circulation completed. (48 Nos)

Unit-2:
Cable tray erection is in progress. Cable laying for HVRT completed for all the
passes. Earthing & illumination work is in progress.
EERM of pass ‘A’ trial run in coupled condition completed. EERM of Pass A& B trial
run in coupled condition completed.

ESP AC plant mechanical erection is in progress.

c. Bunker bay Erection:


Unit-1: Structure erection work is in progress. 6459/6800 MT (Including CCR)
Bunker 4 &3 Inside SS liner is in progress. All the Bins were erected, inside welding is in
progress. Bunker no.5 erection is in progress.
Level 56.5 M floor bunker no 1, 2, 3 & 4 Deck sheet laid.

Unit-2: Structure erection work is in progress. 5097/5354 MT


Erection of bunkers 4, 5, 6, 7 & 8completed, Bunker no 1erection is in progress.
Level 56.5 M floor bunker 5 & 6 floor cleared, Bunker 7 is in progress. Inside welding is
in progress.
d. Standing Structure Erection:
Unit-1: Erection work is in progress. 9411/9800MT. Left, right& front side completed.
Platform work is under progress
Unit-2: Erection work is in progress 8527/9800 MT. Front& RHS & LHS side completed.
Platform work is under progress.
e. Hanging Structure erection:
Unit-1: Erection is in progress, (3115/4396 MT).
Unit-2: Erection is in progress, (2381/4396 MT).
f. APH Erection:
Unit-1: Erection of APH structure is in progress.(3269/3524 MT). APH erected:
1097/1118 MT.
Unit-2: Erection of APH structure is in progress.(3414/3524 MT). APH erected:
1103/1118 MT.

Commissioning: Unit 1 & 2: 1B support bearing completed. 2B & 2A support bearing


flushing is under progress. Trial run of RAPH 1A completed. Cooling water line to
RAPH flushing 1A is in progress. Fire water spray & water wash to RAPH 1B flushing is
in progress.

g. Refractory works:
Unit-1: FGRS duct 1, 2, 3 & 8 refractory work completed up-to 67 M level. FGRS duct
4, 5&6 refractory work completed up-to 45 M level. FGRS 7 vertical portion erection
is in progress.

Page 29 of 50
2X500 MW NEYVELI NEW THERMAL POWER PROJECT JULY’2018

Unit-2: FGRS duct 1, 2, 5, 6, 7 & 8 refractory work completed up-to 45 M level.


Further FGRS duct 3& 4 refractory work vertical portion is in progress.

h. Fuel Oil Pump House:


Hydro test completed. Hoist erection and load test to be completed.
LDO instrument system completed. Power & control cable laying completed. HFO
A&B motor trial run completed. Motor no C erection under progress
i. Fuel oil Unloading pump house:
Hydro test completed. Hoist erection and load test to be completed.
UL platform approach road completed up to EPCC office.
j. FD Fans: All the FD fans LOS flushing completed. FD Fan-1A fan started from DCS
on 23-05-18. FD 1A area paving is in progress.
k. ID Fan:
All ID fans Lube oil flushing completed. Erection of cooling water line is in progress.
Cable laying completed & termination in progress. Fan 1A motor trial run
completed on 13-06-18.
l. HFO & LDO Tanks: HFO Tank No.1& 2: Tank Inspection completed. LDO Tank
No.1&2: Oil receiving started from 19-07-18
m. C&I: Unit-1&2 DCS panel erection completed in CCR area.
Unit-1 boiler Local instrument enclosure (LIE) erected 13/45Nos.
Unit-1 boiler Junction box erected 11/232 Nos.
NTA1 DCS power supply panel charged on 13-06-18.

Power cycle Piping:

S.No Description Unit-1 Unit-2


Scope This Actual Scope This Actual
month month
1 P91 Piping Joints 320 12 292 320 7 250

2 HP Piping Joints 3411 144 2494 2225 82 2061


3 LP Piping Joints 16293 226 5988 13732 295 4666

4 SS Piping Joints 777 61 1041 243 0 222


Total 20801 443 9815 16520 384 7199

Page 30 of 50
2X500 MW NEYVELI NEW THERMAL POWER PROJECT JULY’2018

Major Concern:

a. Structural erection could not be started for mill maintenance and boiler
maintenance building due to space constraint(Pressure parts erection is in
progress)
b. Completion of boiler hydro test got delayed due to incomplete work.
c. Completion of boiler structure and duct erection got delayed.
d. Completion of civil work for boiler Mill deck slab got delayed for both the units.
e. Slow progress due to man power shortage and material shortage.
f. Boiler unit-1: All civil activities got slowed down from 03-05-18 due to NCLT
insolvency proceedings against EPCCIL (Sub contractor of M/s BHEL) on 20-04-
18

Important activities which got slipped against the scheduled target

a. Boiler Hydro test Erection Completion for unit-1 – 30-06-2016- Miles stone activity

b. Boiler Hydro test Erection Completion for unit-2 – 30-12-2016- Miles stone activity

c. Readiness for boiler light up at ESP-1- 15-04-2017

d. Readiness for boiler light up at Boiler C&I unit-1 -15-04-2017

e. Completion of Boiler Light-up unit-1- 30.04.2017 Miles stone activity

f. Commencement of steam blowing at unit-1- 30-05-2017 Mile Stone activity

g. Completion of steam blowing at unit-1- 30-06-2017 Mile Stone activity

h. Completion of erection & commissioning of DCS & Control equipment unit-1- 30-06-17

i. Safety valve floating of Boiler unit-1 (Sch date is 15-07-2017)Mile Stone activity

j. Readiness for synchronization of Boiler unit-1 (Sch date is 31-07-2017)Mile Stone activity

k. Completion of Boiler Light-up unit-2- 30.10.2017 Miles stone activity

Page 31 of 50
2X500 MW NEYVELI NEW THERMAL POWER PROJECT JULY’2018

Percentage of Physical Progress: 83.07 % against 100.0 %( target).

100.0

83.07

Percentage of Progress during each month:


Month Jan’18 Feb’18 Mar’18 Apr’18 May’18 Jun’18 Jul’18

Target 0.05 0.04 0.03 0.03 - - -


Progress
% Actual 0.74 0.82 0.89 0.73 0.42 0.41 0.49

Page 32 of 50
2X500 MW NEYVELI NEW THERMAL POWER PROJECT JULY’2018

Progress of NTA-2 (STG)

Major Events during the month:-


1. 06-07-18: Unit-2: HT of ACW system completed
2. 13-07-18: Unit-2 CCR area A/C duct completed
3. 16-07-18: Unit-2 TG thermal shock commenced
4. 18-07-18: Unit-2 Detergent flushing stage-1 completed
5. 18-07-18: Unit-2 Detergent flushing Stage 1bCDE completed
6. 20-07-18: Unit-2 Mill-5 mechanical erection commenced
7. 20-07-18: Unit-1 –Generator Air leak test commenced
8. 24-07-18: Unit-1 Generator air tightness test 1st phase completed
9. 26-07-18 :Unit-2 ACW erection of SCS drain work commenced
10. 27-07-18: Unit-1 TDBFP 1A oil filling completed
11. 27-07-18: Unit-2 TDBFP 2B oil line erection completed

Physical Progress:

Up-to During
Sl. Description Unit Scope Previous this Cumulative
No Month Month
1 RCC Cum 48420* 43462 23 43485
2 Supply of TG & auxiliary MT 16903* 14142 88 14230
4 Fabrication of TG MT 18319* 15215 0 15215
Structure
5 Erection of TG structure MT 18319* 13867 0 13867
*Scope revised based BHEL Report

Progress in Details: Civil

RCC cumulative progress of 89.80 % achieved.


a. 1) Power house -Unit-1: Brick & Plastering work is in progress. Cladding & window
fixing completed & painting work is in progress. Roof extraction fan fixing work is in
progress.

2) Power house -Unit-2: Brick work completed & plastering work is in progress.
Window fixing & painting work is in progress. ‘0’ M floor finishing work is in progress.

‘A’ row framing work is in progress. ‘A’ row drain concrete work is in progress.

CCR area: Brick work and plastering work is in progress. Doors fixing work
completed.

Page 33 of 50
2X500 MW NEYVELI NEW THERMAL POWER PROJECT JULY’2018

False ceiling & lighting work is in progress. 230 V UPS & charger room duct erection
is in progress.

b. Service Building: External plastering & painting work is in progress. AC duct


erection and smoke test is in progress.
c. Rail Road: Unit-1 ‘A’ row RCC rail road work yet to be completed (Grid A1 to A2)

Progress in details for Mechanical Work:

Supply of TG and auxiliary 84.16 % & Structural Erection progress 75.69 %.

Power House:
a. Steam Turbine Generator

Unit-1:
Turbine rotor put on barring gear on 30-04-18. Final barring gear is to be completed
Turbine Insulation work is in progress.
Turbine MAL drain system is in progress.
Generator Gas room to generator piping work completed.
Lube oil line drained to DOT on 08-05-18
MOT oil filling completed on 28-06-18
Detergent flushing completed on 19-05-18

Unit-2:
Turbine lube oil flushing commenced. Thermal shock started and it is in progress.
IPBD erection is in progress.
Gas room to Generator piping is in progress.
Detergent flushing is in progress. Stage 1A completed & stage 1B CDE completed
on 18-07-18.

b. Condenser Erection:
Unit-1: CW line charged on 23-04-18.
Condenser flood test phase -1 completed on 22-06-18.
COLTCS-Pipe line completed. Cabling is in progress for control panels & actuators.
Unit-2: Condenser charging preparatory work is in progress. Condenser inlet &
outlet butterfly valve actuator operation to be checked.
c. Generator:
Unit-1: Generator air tightness test commenced on 20-07-18 & 1st phase completed
on 24-07-18
Unit-2: Flushing preparatory work is in progress.
d. ACW Pumps:
Unit-1: ACW system lines flushing completed, except Vacuum pump cooler. SCS
PLC charging is to be completed.

10

Page 34 of 50
2X500 MW NEYVELI NEW THERMAL POWER PROJECT JULY’2018

Unit-2: Hydro test of ACW system completed on 06-07-18. Erection of SCS drain is in
progress.
e. DMCW Pump:
Unit-1: Trial run of TG DMCW pumps completed. SG DMCW pumps commissioned
from DCS on 23-05-2018. Compressor house cooling water line flushing completed.
Generator gas cooler flushed. Exciter cooler flushing is in progress.
Unit-2: TG DMCW system flushing completed. Pump B started on 23-05-18. TG Pump
A&B trial run completed. SG DMCW motor trial run completed. SG DMCW flushing is
to be done. Generator gas cooler lines are to be flushed. Exciter cooler line flushing
is to be done.
f. MD-BFP Erection:
Unit-1: MD-BFP started from DCS on 30-04-2018.
Unit-2: Deck floating completed. Motor DOR checked on 24-05-2018.
g. TD-BFP Erection:
Unit-1: 1A Normalization is in progress. Oil filling completed on 27-07-18.
1B Lube Oil line erection work completed.
3 Nos. Pneumatic operated recirculation valves erection completed.
Unit-2: 2A- Lube oil flushing is in progress. Oil sample collected.
2B- Lube oil line erection is under progress.
h. Condensate transfer system commissioning:
Unit-1:
Deaerator line commissioned.
Hot well make up system pipe line erection completed on 27-05-18.
Primary water systems make up line erection completed on 27-05-18.
Hydro test completed on 28-05-18.
Unit-2: Hot well make up System & primary water system pipe line erection is in
progress.
i. Deaerator: Unit-1 Insulation under progress.
Unit-2: Platform painting completed.
j. CPU Regeneration building: Trial run of motors 6/8 completed. Pipe line erection is
in progress in CPU regeneration building and DE bay, service vessel area pipe rack.
k. CEP: Unit-1&2. All the pumps erected. Motor 1 A & 1B trial run completed through
DCS.

l. Electrical:
1. Unit-2 battery bank –set 1 erection completed, Set-2 erection work is under
progress.
2. IPBD erection work for unit-1 is in progress. Unit-2 IPBD erection is in progress.

m. C&I:
1. TG Unit-1 area Junction boxes erection completed.
2. TG Unit-1 area LIR erection completed.
3. Panel erection in CCR completed for Unit-1 &2.

11

Page 35 of 50
2X500 MW NEYVELI NEW THERMAL POWER PROJECT JULY’2018

4. DCS power up was done on 20-03-18.


5. Drives 20/31 nos loop checking completed.

Major Concern:

a. Delay in completion of LP dosing system commissioning for unit-1.


b. Delay in completion of turbine integral piping & LP piping for unit-1.
c. Delay in completion of Condenser commissioning for unit-1&2.
d. Slow progress due to man power shortage.
e. TG unit-1: All civil activities got slowed down from 03-05-18 due to NCLT insolvency
proceedings against M/s. EPCCIL (Sub contractor of M/s BHEL) on 20-04-18

Important activities which got slipped against the scheduled target.

a. Completion of erection and commissioning of condenser unit-1 22-02-17


b. Compl. of erection & commissioning of Turbine integral piping & LP piping unit-1 28-02-17
c. Completion of erection & commissioning of TD BFP unit-1 on 05.03.2017
d. Completion of TG Rolling & synchronization of unit-1 on 23.03.2017(Milestone activity)
e. Trial operation completion of Unit-1 23.06.2017(Milestone activity)
f. Completion of Turbine oil flushing of unit-2 on 21-08-2017(Milestone activity)
g. Completion of erection and commissioning of condenser unit-2 22-08-17
h. PG test completion of unit-1 TG on 23.09.2017(Milestone activity)
i. Completion of TG Rolling & synchronization of unit-2 on 23.09.2017(Milestone activity)
j. Completion of trial operation of unit-2 on 23-12-2017(Milestone activity)

12

Page 36 of 50
2X500 MW NEYVELI NEW THERMAL POWER PROJECT JULY’2018

Percentage of Physical Progress: 87.92% against 100.0 %( target).

100.0

87.92

Percentage of Progress during each month:

Month Jan’18 Feb’18 Mar’18 Apr’18 May’18 Jun’18 Jul’18

Target - - - - - - -
Progress
Actual 0.52 0.69 0.68 0.88 0.46 0.19 0.41
%

13

Page 37 of 50
2X500 MW NEYVELI NEW THERMAL POWER PROJECT JULY’2018

Progress of NTA-3 (BOP)

All activities of NTA 3 got slowed down from 03-05-18 due to NCLT insolvency proceedings
against M/s. EPCCIL on 20-04-18

Major Events during the month:

1. Fire water line pipe laying is in progress.

Physical Progress:-
Sl. Up to
During this
No Description Unit Scope Previous Cumulative
Month
Month
1 RCC Cum 169591* 154966 4 154970
2 Structural Fabrication MT 10598* 9890 0 9890
3 Structural Erection MT 10598* 7806 0 7806

4 Technological structure MT 791* 532 0 532


erection
5 Equipment Erection MT 2524* 2241 0 2241
*Scope revised based on EPCC report

Progress in Detail:
RCC cumulative progress of 91.37 % achieved.
Structural erection progress is 73.65%, Equipment erection progress is 88.78%.

Group I
1. Raw water intake system. Initial operation completed on 22-11-2017.
2. PT & DM Plant:
a) DM Plant: Initial operation For DM plant along with its PT plant was completed on
11-11-2017. Trial operation completed on 31-03-2018.
b) Softening plant: Initial operation completed on 30-11-2017.

3. A) 220KV Switch yard (GIS)


220 KV System: Initial operation completed on 24-08-17.

B) Two Nos. Station (Power) transformer:


Station Transformer: Initial operation completed on 31-08-17.

14

Page 38 of 50
2X500 MW NEYVELI NEW THERMAL POWER PROJECT JULY’2018

Group II
1. Circulating water system:

CW pump house pump-1A, 1B & 2B started. CW pump 1A 8 hrs trial run completed
2. NDCTs:
Unit-1: Aviation lamp energized. Permanent cable is to be laid.
Lightning spikes & earth pits completed and connection with grid is in progress in
slow pace.
Unit-2: Aviation lamp to be energized. Lightning spikes erected. Earth pits work is in
progress in slow pace.

Group III

1. Chimney:
For boiler-1: Flue can inner lining (borosilicate) work nearing completion.
For boiler-2: Flue can inner lining (borosilicate) work is in progress.
Aviation lamp commissioned with temporary supply.
2. General illumination:
High-mast erection work completed. Erection of street light pole stooped. Erected
& energized 64/450 nos.
3. Inter plant communication:
Exchange commissioned in service building and cable laying is in progress in slow
pace. UHF tower erection is to be start.
Telephone Cables and Instruments: Two numbers 100 pairs cable laying is in
progress in slow pace.
C&I: Erection of CCTV cameras and Monitoring Equipment: Location being
finalized
4. Hydrogen Plant:
Plant material is being received. (80%)
Chiller, Electrolyzer, Heavy duty Compressor and Vacuum pump were placed on
the foundation.
Pipes for Service air, Instrument air, service water & potable water is in progress in
slow pace.

Group IV
1. LHS
i. Stacker:
a) Stacker Commissioned & Lignite received on 28-03-18. Operations from
Operators cabin to be checked. Electrical & C&I work stopped.

a) Reclaimer No. 1: Work stopped due to payment issue from their sub-contractor
M/s Elecon. Mechanical: Balancing partially completed & Operations from
Operators cabin to be checked. Transformer & MCC charged on 18-04-2018.
Reclaimer No. 2: Civil work stopped.
15

Page 39 of 50
2X500 MW NEYVELI NEW THERMAL POWER PROJECT JULY’2018

b) Reclaimer No. 2: Civil work & Mech equipment erection stopped due to
payment issue.
RC1&2: Erected (883/900MT)

ii. Conveyor: BCN 1, 2, 3 & 4 started from PLC.


Fabrication work stopped (2613/2678MT).
Structural erection stopped (Erected: 535 /2678 MT).
Fabrication of technological Structure (Stand Stringer post) stopped (362/370 MT)
Erection of technological Structure (Stand Stringer post) stopped (305/370 MT).
Deck sheet, roof sheeting & side cladding sheet erection stopped.
iii. Crusher House: Mech: Two No. screens & crushers erected. Grouting completed.
Crusher & Screen B trial run completed.
iv. Junction Tower:
a) JNT Column fabrication work stopped (1376/1388MT fabricated)
b) For JNT 1, 2& 3 erection stopped. Other all JNT structural erection works
completed. (1370/1388MT erected).
v. Covered shed: Fabrication work stopped (2480/3011 MT)
Structural erection work stopped. (565/3011MT)
vi. HGTU: Fabrication& erection work stopped. Erected (43/55MT).
vii. Pulley Frame: Fabrication & erection work stopped. Erected (80/102MT).
viii. Deck Plate: Fabrication & erection work stopped. Erected(146/314MT)
ix. Seal Plate: Fabrication & erection work stopped. Erected (134/140MT).
x. LHS Main Control Room: Finishing work stopped. 11Kv panel charged on 15-02-18.
3.3Kv & 0.4Kv Panels charged on 21-02-18. Battery commissioning preparatory work
is in progress
xi. LHS Mini Control room: 3.3 KV panels charged on 01-03-18. 3.3 KV/0.4 KV Tr
Charged on 17-03-18. Battery commissioning work stopped.
xii. Compressor Cum pump house: Finishing work stopped.
xiii. Chemical house and tube settler: Civil work stopped.
xiv. LHS : Equipment erection work:
a) Crusher & Screen erected : 170/234 MT
b) Rollers & idlers : 884/ 892 MT
c) Pulleys : 33/228 MT

2. AHS:
i. In all Silo mechanical erection completed.
ii. Silo utility Building: 415 V panels charged on 24-03-18. Equipment trial run completed
for unit-1. Earthing, cable tray and laying work stopped. OFC cable laying work
stopped.
iii. Ash pipe rack concrete work completed. Structural & gallery erection work stopped.
(Erected: 520/528MT).
iv. Ash slurry PH: Slurry pump erection completed, LP & HP flush pump erection stopped.
v. ISH unit1&2: Stair case erection for ISHs stopped.(10/92 Mt erected)

16

Page 40 of 50
2X500 MW NEYVELI NEW THERMAL POWER PROJECT JULY’2018

vi. Vacuum PHU-1: Civil and Mechanical work stopped. Mech: Trial run completed for all
equipment. Motor Trial run for one no conveying Air compressor taken on 25-04-18.
Transformer & 3.3 KV panels charged on 10-03-18. Battery system 1st bank
commissioned, 2nd Bank erection to be completed.
vii. Vacuum PHU-2: Civil and Mechanical work stopped. Brick work & plastering work to
be completed.
Mech: Vacuum pumps erection completed. Pipe line erected. Transformer placed on
the foundation. Cable tray support erection is to be completed.
viii. Ash slurry pipe line: Pipe erection to be completed. Civil and Mechanical work
stopped
3. C& I:
RWPH- Cable laying work completed. PLC commissioned.
DM plant PLC panel erected. Cable laying work completed. Field instrument erection
completed. PLC commissioned.
PT Plant: Cable laying work completed. Field instrument erection completed.
Softening plant Cable laying work completed. Field instrument erection completed
Station C&I DCS panel for Unit-1 & 2 erection completed in CCR.
LHS stacker, slew feeder, BCN 1 and BCN 2 PLC panel erected & commissioned.
Cable laying, termination & loop checking work stopped.
TG area cabling to NTA3 DCS stopped.

4. 400 KV switch yard:


GIB erected for all except 2 nos.
GIS Equipment erection In door: Testing to be completed. Earth mat work completed.
400 KV Second bus was charged on 27-04-18.
Civil: Cable trench & drain work stopped. Fencing work to be completed.

5. Power Transformer (GT, UT, UAT, ICT):

i. GT-1: Transformer work completed. Spare Cooler bank erection to be completed.


ii. GT-2: Oil circulation completed.
iii. UT: Oil circulation completed.
iv. UATs of 1A&1B charged, 2A charged on 23-12-2017. 2B charged on 22-02-2018.
v. ICT-1: Cooler system erection completed. Bushing erection completed.
vi. ICT-2: Charged from 220 KV bus. Spare transformer erection to be completed.

6. Fire protection system:

a. Fire Water Pump House: Alignment completed in all pumps except pump no.7.
b. Fire water line: Excavation and pipe laying is in progress. 47465/52773 RM laid after
conducting hydro test.
c. Fire water Trench: Trench work is in progress in slow pace at STs& A row Power
Houseunit-1 area.

17

Page 41 of 50
2X500 MW NEYVELI NEW THERMAL POWER PROJECT JULY’2018

d. Fire fighting: Fire hydrant pipe laying completed up-to JNT-9, for boilers, vertical
raisers erection completed up-to 65 M. Further is in progress in slow pace along with
vertical risers.
e. Fire alarm panel erection is in progress in slow pace (8/9 (Including Main FAP).
f. In Power House fire fighting line erection work is in progress in slow pace in Cable
gallery.
g. Foam PH: Foam line SS & water line work completed.
h. Booster pump House near JNT-3: Pump erection yet to start.
i. Booster pump house (Near CPU Re Gen Bldg): Pipe line excavation from Booster
pump house to JNT-1 commenced. Pump erection started.
j. Spray system at GT2, ICT1 & Spare transformers & reactor - 2/9 completed.

Group V:
1. Sewage Treatment plant: RCC work stopped. (122/600 Cum)
Effluent Treatment plant:
a) Chemical & Tube settler: RCC work stopped. (91/250 Cum)
b) Guard Pond: RCC work stopped. (173/500 Cum)
2) Mechanical& Electrical Workshops: EPIL had placed order to M/s HMT.
Supply of equipment is under progress in slow pace.
3) General civil works:
Grading& backfilling work stopped in LHS stockyard area. (65 % grading work
Completed)
Road work stopped at LHS & switch yard area.
Cable trench/ Overhead Gallery: Excavation, PCC & RCC work stopped.
Water Tower: Excavation, PCC & RCC work stopped.
Drains & Garland Drain: RCC work stopped (3582/4690cum).

Major Concern:

a. Delay in Completion of PG test of RWIS


b. Delay in Completion of PG test of raw water PT&DM
c. Delay in Completion of PG test of 220kV GIS switchyard
d. Delay in Completion of PG test of Transformer yard equipment
e. Delay in Completion of PG test of LHS system unit-1
f. Delay in Completion of PG test of AHS system unit-1
g. Delay in Completion of PG test of Station C&I unit-1
h. Delay in Completion of PG test of Transformer yard unit-1
i. Delay in Completion of PG test of FPS & Fire alarm system unit-1
j. Slow progress due to man power shortage.

18

Page 42 of 50
2X500 MW NEYVELI NEW THERMAL POWER PROJECT JULY’2018

Important activities which got slipped against the scheduled target.

Group-1

a.
Non Completion of PG test of RWIS(Sch.Comp date 31-08-2016)
b.
Non Completion of PG test of raw water PT&DM(Sch.Comp date 31-08-2016)
c.
Non Completion of PG test of 220kV GIS switchyard(Sch.Comp date 31-08-2016)
d.
Non Completion of PG test of Transformer yard equipment(Sch.Comp date 31-08-
2016)
Group-2
e. Non completion of initial operation of CW system unit-1 (Sch.compl date 31-01-17
Milestone activity)
f. Non completion of initial operation of CW system unit-1 (Sch.compl date 31-07-17
Milestone activity)
Group-3
g. Non completion of Mechanical completion of Bi flue Chimney (Sch.compl date 31-
01-17 Milestone activity)
h. Non completion of Mechanical completion of General illumination (Sch.compl
date 31-01-17 Milestone activity)
i. Non completion of Mechanical completion of Interplant communication
(Sch.compl date 31-01-17 Milestone activity)
j. Non completion of initial operation of Hydrogen plant (Sch.compl date 31-01-17
Milestone activity)
k. Non Successful Completion of trial operation of Hydrogen plant (Sch. Completion
date 30-04-2017)
l. Completion of PG test of hydrogen plant(Sch.date 30-06-2017)
Group-4
m. Non completion of preliminary Operation & initial operation for LHS unit-1
(Sch.compl date is 31.03.2017)(Milestone activity)
n. Non completion of preliminary Operation & initial operation for AHS unit-1
(Sch.compl date is 31.03.2017) (Milestone activity)
o. Non completion of preliminary Operation & initial operation for each sub package
C&I unit-1 (Sch.compl date is 31.03.2017) (Milestone activity)
p. Non completion of preliminary Operation & initial operation for 400 kV GIS
switchyard unit-1 (Sch.compl date is 31.03.2017) (Milestone activity)
q. Non completion of preliminary Operation & initial operation for Transformer yard
unit-1 (Sch.compl date is 31.03.2017) (Milestone activity)
r. Non completion of preliminary Operation & initial operation for Fire protection
(area wise progress completion) unit-1 (Sch.compl date is 31.03.2017) (Milestone
activity)
s. Successful completion of Trial operation in LHS-1 (Sch.date 30-06-2017)

19

Page 43 of 50
2X500 MW NEYVELI NEW THERMAL POWER PROJECT JULY’2018

t.
Successful completion of Trial operation in AHS-1 (Sch.date 30-06-2017)
u.
Successful completion of Trial operation for DCS system-unit-1 (Sch.date 30-06-17)
v.
Successful completion of Trial operation for 400 Kv switch yard unit-1(Sch.date 30-
06-2017)
w. Successful completion of Trial operation for Transformer yard unit-1 (Sch.date 30-06-
2017)
x. Successful completion of Trial operation for Fire protection system unit-1 (Sch.date
30-06-2017)
y. Non completion of mechanical completion for LHS unit-2 (Sch.compl date is
31.07.2017)(Milestone activity)
Group-5

z. Non completion of equipment erection in ETP Sch.compl.date is 31.03.2017


aa. Non completion of Electrical testing of lab equipment in Mechanical and electrical
workshop (Sch.compl date is 01-03-2017)
bb. Non completion of mechanical erection for Effuent treatment plant (Sch.compl
date is 15.04.2017) (Milestone activity)
cc. Non start of preliminary Operation & initial operation for Effuent treatment plant
(Sch.compl date is 16.04.2017) (Milestone activity)
dd. Non completion of equipment erection and mechanical completion of workshop
31.05.2017
ee. Completion of preliminary operation & initial operation for Effuent Treatment plant
31.05.2017

20

Page 44 of 50
2X500 MW NEYVELI NEW THERMAL POWER PROJECT JULY’2018

Percentage of Physical Progress: 89.19* % against 100.0 %( target)

100.0

89.19*

* After reconcile of M/s. EPCC supply & erection payment, the percentage was revised.

Percentage of Progress during each month:

Month Jan’18 Feb’18 Mar’18 Apr’18 May’18 Jun’18 Jul’18


Target 0.25 0.15 - - - - -
Progress
% Actual 2.16 1.26 1.69 1.23 0.09 0.02 0.0

21

Page 45 of 50
2X500 MW NEYVELI NEW THERMAL POWER PROJECT JULY’2018

Over All Percentage of Progress

Percentage of Physical Progress: 87.48 % against 100.0 %( target).

100.0

87.48

Percentage of Progress during each month:

Month Jan’18 Feb’18 Mar’18 Apr’18 May’18 Jun,18 Jul’18

Target 0.17 0.14 0.11 0.01 - - -


Progress
% Actual 1.14 0.92 1.09 0.95 0.32 0.21 0.30

22

Page 46 of 50
2X500 MW NEYVELI NEW THERMAL POWER PROJECT JULY’2018

Site Progress Photos:


BOILER -1 FGD DUCT ERECTION IS IN PROGRESS BOILER -2 FGD DUCT ERECTION IS IN PROGRESS

BOILER -1 MILL ERECTION IS IN PROGRESS BOILER -2 MILL ERECTION IS IN PROGRESS

FD FAN 1A INSULATION IS IN PROGRESS LDO UL PUMP COMMISSIONED

23

Page 47 of 50
2X500 MW NEYVELI NEW THERMAL POWER PROJECT JULY’2018
UNIT 1 &2 TURBINE INSULATION WORK IS IN PROGRESS

UNIT 1 &2 TDBFP COMMISSIONING WORK IS IN PROGRESS

POWER CYCLE PIPING AT 17 M BC BAY ERECTION IS IN PROGRESS

24

Page 48 of 50
Page 49 of 50
(formerly Neyveli lignite Corporation limited)
GOl/errlment of India Fnt,prnri",,,\

~/Tel j;1dlrn<'l ~ g3frJT / Corporate Contracts Division


~/Fax: 04142 - 252026/252645/252646 j;1dlTJ:l<'l Cfi!llh;lll / Corporate Office
~-i-rN/E.rnail: gmconts_co@nlcindia.com ~-11 Block-1, ~ / Neyve!i - 607 801
gmconts@gmaii.com ~~, ~ /Tamil Nadu, India
gmconts_co@rediffmaiLcom ISO 9001 REGISTERED CiN: L930"'90TN1956GO 1003507

CORRIGENDUM - I, Dt.14.08.2018

Sub: Borrowing ofRs.S21 Crore for Neyveli New Thermal Power Project (NNTPP) - Corrigendum-I -
Reg.
Ref: Tender No.: CO CONTSI 0027G/LTEINNTPP/RTLIe-conts/201S dated:OS-OS-201S

*****
1.0 Please refer to the tender cited.
2.0 The Date of Pre-bid conference is modified as below:

Particulars As in Tender Modified as


Pre Bid Meeting Date & 22.08.2018 @ 11.00 Hrs., 23.08.2018 @ 11.00 Hrs.,
Venue Corporate Contracts Corporate Contracts Division,
Division, NLCIL, Neyveli. NLCIL, Neyveli ..

Note: All the terms and conditions of the Tender Document for the above referred tender stand
unaltered. All the Corrigenda are to be signed and enclosed along with the Bid.
Bidders are requested to visit NLCIL Website (www.nlcindia.com) & CPPP
(www.eprocure.gov.in) to know about latest clarification I corrigendum, if any issued by NLCIL.

~ ~ : ~'ffiif, if.8, ~~Us, 1J'CI>.\ffi.gr,3fmft~nill~1itm:r,'(ramn;T~, me, ~-600031


Registered Office: First Floor, No.8, Mayor Sathyamurthy Road, FSD, Egmore Complex of Food Corporation of India, Chetpet, Chennai-600031.
Page 50 of 50 ~eb site: www.nlcindia.com