Sunteți pe pagina 1din 5

2013 First International Conference on Artificial Intelligence, Modelling & Simulation

An Improved Protection Scheme for Smart Distribution Grid

Hana A. Halim, Melaty Amirruddin, Nur S. Noorpi, Nurhakimah M. Mukhtar


School of Electrical Systems Engineering
Universiti Malaysia Perlis (UniMAP)
Perlis, Malaysia
hanahalim@unimap.edu.my, melaty@unimap.edu.my, nursabrina@unimap.edu.my, nurhakimah@unimap.edu.my

Abstract—This paper presents an implementation to enhance their perspective protection scheme. For example, fast
the protection scheme of smart distribution grid. In order to current protection was at high speed action [2], which is
improve the existing protection scheme used in Malaysia that is good for protection system purpose but despite this
“Current Differential Protection”, to a new level of protection
advantage, the traditional fast current protection cannot
that used the idea of combining the “Current Differential
Protection” and “Fast Current Protection”. This project was protect the whole line [3]. While the differential current
developed to increase the efficiency of protection, decrease any protection was the most ideal selection for protection
unnecessary cost regarding the protection maintenance or scheme, but the cost for making one was high due to
equipment used, and space used for installing a particular requirement of breaker and current transformer to be
protection scheme. Besides that, neither “Current Differential installed on both side of a line. To achieve Smart Grid label,
Protection” nor “Fast Current Protection” has their own there are several characteristic that been included in Title
advantages and disadvantages for their perspective protection XIII of the recently signed Energy Independence and
scheme. The results were proven by simulating the design Security Act of 2007 included the use of digital control and
using PSCAD software, which the new design, combined both
information technology in the current real time, the
theories of “Current Differential Protection” and “Fast
Current Protection”. The building cost for the new design can operability must be dynamic optimization, the demand side
be reduced in installation or maintenance. response inclusion and also smart metering deployment
[4].Table 1 shows the different between common grids with
Keywords-Fast Current Protection; Differential Current smart grid [5].
Protection; protection scheme

TABLE I DIFFERENCE BETWEEN COMMON GRID AND SMART


I. INTRODUCTION
GRID
A. Background of Project Common Grid Smart Grid
If we speak the common term of grid, it is used for an Electromechanical Digital
electric system that can support neither all or selective One-way communication Two-way communication
operation, the operation include electricity generation, Centralized generation Distributed generation
electricity transmission, electricity distribution, and Few sensors Sensors throughout
electricity control [1]. It generally used to carry power from Manual monitoring Self-monitoring
a few central generators to a large number of user customer. Manual restoration Self-healing
But, in this project we used smart grid, which use two-way Failures and blackouts Adaptive and islanding
flows of electricity and information to create an automated Limited control Pervasive control
and distributed advanced energy delivery network. Few customer choices Few customer choices
The protection scheme of smart distribution grid was
developed with the purpose to improve the existing
protection scheme used in Malaysia which is “Current B. Problem Statement
Differential Protection” to a new level of protection which
uses the idea of combining the “Current Differential The improved protection scheme that was often been used
Protection” and “Fast Current Protection”. Furthermore, the is current differential protection which required circuit
breaker and current transformer to be installed in both sides
improved protection scheme was developed to increase the
of line. By combining differential current protection and fast
efficiency of protection, decrease any unnecessary cost
regarding the protection maintenance or equipment used, current protection, the reliability can be increased, save cost
and space used for installing a particular protection scheme. and also save space. To acknowledge the results, PSCAD
was used to simulate the combination between the
“Current Differential Protection” and “Fast Current
Protection” has their own advantages and disadvantages for differential current protection and fast current protection.

978-1-4799-3251-1/13 $31.00 © 2013 IEEE 292


298
DOI 10.1109/AIMS.2013.62
II. FAST CURRENT PROTECTION IV. APPROACH AND METHOD

A. Introduction
A new type of protection emerges and develops which is
fast current protection. After the traditional protection was
developed, there is a tension of conventional energy sources
and increasingly serious environmental problems, the
Distributed Generation (DG) technologies using renewable
energy for electricity generation are developed rapidly. DGs
are allowed to be connected with network in order to take
full advantage of their strengths. For convenience DGs are
often connected to local medium or low voltage distribution
system [6].
This protection was developed because it is necessary for
distribution grids to maintain network operation during
normal fault clearing time. Improving the speed of
protection is conducive can reduce the damage to
distribution grids. The fast current protection proposed a fast
current protection scheme for distribution network with
distribution grid by adding communication channel. This
scheme could not only solve most of the problems caused
by DGs, but also effectively improve the speed of protection
[6].
III. DIFFERENTIAL CURRENT PROTECTION

The differential is indeed very reliable method of


protection system that generally protect generator or
transformer by using current transformer and circuit breaker
in both side because each current transformer and circuit
breaker can only protect one line. The current on both sides
will be measured by current transformer to be compared.
Fig. 1 shows connection for one phase, the theory remain
the same for their phase because the similarity on each Fig. 2: Design and Analysis for the Combining of Fast Current Protection
phase of protected equipment. and Differential Current Protection Flow Chart

A systematic approach, tools, and techniques were


applied in order to achieve the project objectives. Fig. 2
shows the step by step flow chart in executing this project
based on designing a circuit of Fast Current Protection and
Differential Current Protection. The results were based on
the voltage and current behavior before and during fault on
various places in the circuit.
A simple circuit was selected to simulate the result for
protecting the distribution system from fault or overcurrent.
Fig 1: Theoretical Differential Protection of a Generator The circuit only requires two circuit breakers to protect both
transmission lines three-phase voltage source, and four
Under normal conditions, or for a fault outside of the positions of fault in the circuit to analyze each behavior of
protected zone, current I1 is equal to current I2. Therefore current and voltage during and before fault occurrence.
the currents in the secondary’s current transformers are also When a fault occurred, the circuit breaker will be opened,
equal, i.e. i1 = i2 and no current flows through the current thus theoretically make the current became stable.
relay. If a fault develops inside of the protected zone,
currents I1 and I2 are no longer equal, therefore i1 and
i2 are not equal and there is a current flowing through the
current relay.

299
293
B. PSCAD Simulation A. Analysis of Protection System During No Fault
The simulation is to achieve the three results which are: Condition
i. Simulation waveform of circuit breaker before and during During no fault condition, the voltage and current
fault. waveform are stable which show no disturbance in the
ii. Simulation waveform of current behavior before and waveform. Same thing happened to circuit breaker, where
during fault. the breaker has not seen any abnormal condition which
iii. Simulation waveform of voltage behavior before and result unnecessary requirement to operate. This situation can
during fault. be seen in Fig. 4. Furthermore, the reason for the graph to
For this work, Power System Computer Aided Design start from 0 V because to minimize any harmonic
(PSCAD) tool was used. This software is both dominant and interference, compared to high value from the start.
undemanding to the user [7, 8]. Using PSCAD, it can make
use of intelligent techniques to computerize the power
quality evaluations for improved accuracy and efficiency
which the manual analysis takes considerable time and
would require special knowledge [9].

V. RESULTS AND DISCUSSION

Using PSCAD/EMTDC, the protection system can be


simulated according to the desire outputs and circumstances.
The power system comprises of three phase voltage source
at both ends of line consisting 230kV with 100MVA using
100 km transmission line between them. The behavior of Fig. 4 Voltage Waveform during No Fault Condition
voltage, current and breaker were been studied by
Fig.5 shows the voltage waveform was initially started
simulating the fault at different location.
Due to same action characteristic between circuit from low voltage input and begins to stabilize at 0.15 sec.
breaker 1 and circuit breaker 2 before, during or after fault, There was no interference until the end of graph because the
fault was not triggered.
this report will only focused on analysis on characteristic in
circuit breaker 1 only. Fig. 3 shows the circuit design used,
while Table 2 shows the symbol for each measurement
used:

TABLE II SYMBOL AND MEASUREMENT USED

Symbol Measurement Subscript


V1a Voltage During No Fault
V1b Voltage During Fault at Part A
I1a Current During No Fault
I1b Current During Fault at Part A
Br1a Breaker 1 Condition at Part A During No Fault
Br1b Breaker 1 Condition at Part B During Fault
Fig.5 Current Waveform during No Fault Condition

Fig. 3 Circuit Simulation Design

300
294
through to ground during fault at part A connected to
ground, but as the distribution line been open during circuit
breaker detect the fault, the voltage become unstable during
the period. After that, the voltage reached 162kV to its
original peak voltage.

Fig. 6 Circuit Breaker Condition during No Fault Condition

Fig. 6 shows a low stable reading because the circuit


breaker was not initialized. This is due to the circuit breaker
did not detect any fault or any abnormal activities in
distribution line.
Fig. 8 Current Waveform during Fault Condition

B. Analysis of Protection System During Fault at Part A


Connected to Ground Condition Fig. 8 shows the current, I1b waveform where the
current value turned zero during 0.32 sec to 0.37 sec
For analysis for fault current and voltage analysis during because of the open circuit at circuit breaker. During fault,
fault, this paper will focused only on fault between the the current will become unstable due to interference from
source and first breaker. The reason behind this action is fault. For the current to reach back its normal value, it takes
because every graph will remain the same due to same about 0.3 sec.
action if the breaker detects fault or any abnormal activities.
The same thing happened in the beginning of graph where
the graph starts from zero, which is lays in minimizing
harmonic interference problem.
The different was from 0.2 sec to 0.45 sec time. The
other time on the graph remain the same as no fault
condition graph. The fault that has been set in the simulation
was at 0.2 sec and continued for 0.12 sec, thus ended at 0.32
sec as the circuit breaker open at 0.32 sec as shown in Fig.
8. The breaker have been set to hold for 0.05 sec, thus it
ended at 0.37 sec.

Fig. 9 Circuit Breaker Condition during Fault Condition

Fig. 9 shows a low stable reading because the circuit


breaker was not initialized until 0.32 sec to 0.37 sec. The
circuit breaker was only initialized because it detects the
fault in 0.32 sec due to relay that been set.

C. Cost Effective
The project was developed to reduce cost whether on
building cost or maintenance cost. For this project, it can
protect the whole line without any different set of protection
Fig. 7 Voltage Waveform during Fault Condition system even if in a long line, compared to fast current
protection. This will make the maintenance simpler than fast
Fig. 7 shows the graph explains voltage, V1b current protection. Besides that, it does not required two sets
characteristic during fault. The fault start at 0.2 sec then the of current transformer and capacitor voltage transformer to
voltage become zero because all the voltage have been protect a line, compared to differential current protection.
This prove that the building cost were cheaper because of

301
295
this two sets of equipment. This two factors can be made ACKNOWLEDGMENT
significant different to industrial used for saving cost. The authors would like to thank Universiti Malaysia
D. Discussion Perlis for providing the technical and financial support for
this research. We also wish to express my appreciation to all
The paper has shown one way of protection system to
School of Electrical Systems Engineering staffs for helping
protect distribution system from fault or overload. The
us throughout the research project. Special thanks to the
results show how important the protection system to
families for the constant encouragement. To all of them, the
distribution system by simulates the value of current and
success of this project is partly due to your support and
voltage during fault, while connected to breaker. The
blessings. Thank you.
breaker will be opened if it detects fault or any abnormal
activities in distribution system, with the purpose to protect
distribution system from damage because of the fault or any REFERENCES
abnormal condition. [1] Xi Fang, Satyajayant Misra, Guoliang Xue, Dejun Yang. Smart Grid
The purpose of this project was to improve distribution – The New and Improved Power Grid:A Survey , IEEE
protection system by referring on the combination of fast Communications Surveys & Tutorials, Vol. 14, No. 4, Fourth Quarter
current protection and differential current protection. This 2012, pp. 944-980.
mean that the project want to take both advantages, and [2] Zhiqiang Wang, Xiaojie Shi, Leon M. Tolbert,Benjamin J. Blalock,
Madhu Chinthavali. A Fast Overcurrent Protection Scheme for IGBT
eliminate the disadvantages of the fast current protection Modules Through Dynamic Fault Current Evaluation, pp.577-583.
and differential current protection by dismissing the current 2013.
protection in both sides and also to protect the whole line of [3] Fast current protection method for distribution network containing
protection by using one set of protection system. distributed power. CN 101562333 B. Filing May 27, 2009. Published
Jul 4, 2012.Available: www.google.com/patents/CN101562333A
Thus this simulation results proved that the new type of
[4] Auropean Academies Science Advisory Council, “Transforming
protection design is able to protect a whole line using one Europe’s Electricity Supply- An Infrastructure Startegy for a
set of protection only compared to fast current protection, Reliable, Renewable and Secure Power System,” EASAS Policy
and the new type of protection does not need two current Report II, May 2009.
transformers to detect any fault or abnormal activities and [5] Jia Tian, Houlei Gao, Meiyi Hou, Jun Liang, Yishu Zhaot. A Fast
give the circuit breaker signal to open like differential Current Protection Scheme for Distribution Network with
Distribution Generation, Developments in Power System Protection
current protection. (DPSP 2010). Managing the Change, 10th IET International
This method can be used in future if our country decides Conference, pp. 4-5. March 29 2010-April 1 2010.
on using smart grid as our main distribution system, which [6] Global Environment Fund, Center for Smart Energy, “The Emerging
logically is a better choice when comparing the benefit and Smart Grid: Investment and Entrepreneurial Potential in the Electric
function. Power Grid of the Future”. Available:
http://www.public.asu.edu/~xfang5/survey_smartgrid_2011.pdf
VI. CONCLUSION AND RECOMMENDATION [7] Hana A. Halim, Nur S. Noorpi, Melaty Amirruddin, Nurhakimah M.
Mukhtar, Analysis of Cross Blocking Method Implementation for
Overcoming Sympathetic Inrush Current Phenomena, 2012 4th
The existing protection scheme used in Malaysia which International Conference on Computational Intelligence, Modelling
and Simulation, September 2012, pp 288-293, ISBN 978-0-7685-
is “Current Differential Protection” can be improved to a 4871-5
new level of protection which used the idea of combining [8] A.A. Mohd Zin, Hana Abdull Halim & S. P. Abdul Karim,
the “Current Differential Protection” and “Fast Current “Sympathetic Inrush Current Phenomenon Analysis and Solution for
Protection”. The objectives are to increase the efficiency of a Power Transformer”, International Review on Modelling and
protection, decrease any unnecessary cost regarding the Simulations (IREMOS), April 2011
protection maintenance or equipment used, and space used [9] (n.d). The Electronicmagnetic Transient .Power Quality in Electrical
System. Received April 23, 2012, from
for installing a particular protection scheme. http://www.powerqualityworld.com/2011/06/pscad-power-systems
Thus, the combination of fast current protection and
differential current protection can be upgraded by
dismissing the current protection in both side and also can
protect the whole line of protection by using one set of
protection system even if in a long line, compared to fast
current protection. Besides that it does not required two sets
of current transformer and capacitor voltage transformer to
protect a line, compared to differential current protection.
These two factors can be make significant different to
industrial used.
For long term, this enhanced protection scheme can
change the distribution system in Malaysia because of its
low cost building and low cost maintenance.

302
296

S-ar putea să vă placă și