Documente Academic
Documente Profesional
Documente Cultură
Flag question
Question text
Which of the following generally cannot be validated using a work breakdown structure
Select one:
a. Risk Management
b. Schedule control
c. Cost control
d. Quality control
Question 2
Not yet answered
Marked out of 1.00
Flag question
Question text
One of the most condition reasons why projects undergo scope change is
Select one:
a. Lack of resources
b. Poorly defined statement of work
c. Lack of Funding
d. Poor Work breakdown structure
Question 3
Not yet answered
Marked out of 1.00
Flag question
Question text
Top - down approach is used for time and cost estimating when
Select one:
a. Unstable scope
b. Customer wants details
c. Cost and time are important
d. Fixed - price contract
Question 4
Not yet answered
Marked out of 1.00
Flag question
Question text
When an unusual amount of uncertainty surrounds a project, we use
Select one:
a. Range Estimating
b. Phase Estimating
c. Top-down approach
d. Bottom-up approach
Question 5
Not yet answered
Marked out of 1.00
Flag question
Question text
The high risk and high vale projects are called
Select one:
a. bread and butter project
b. Oysters
c. Pearls
d. White elephants
Question 6
Not yet answered
Marked out of 1.00
Flag question
Question text
If Internal rate of return is less than the cost of capital
Select one:
a. Accept the project
b. Indifferent
c. Postpone the project
d. Reject the project
Question 7
Not yet answered
Marked out of 1.00
Flag question
Question text
The source of many estimating risks is
Select one:
a. Lack of management support during estimating
b. Poorly defined requirements
c. An inexperienced project manager
d. All of the above
Question 8
Not yet answered
Marked out of 1.00
Flag question
Question text
Time - Constrain and Cost - Acceptable means
Select one:
a. Time is optimized, cost overrun/under run is not acceptable
b. Time is fixed , cost can be optimized
c. Time is fixed, cost overrun/under run is acceptable
d. Time is fixed, cost is fixed
Question 9
Not yet answered
Marked out of 1.00
Flag question
Question text
The length of time required to recover the initial cash outlay on the project taking into account time
value of money is called
Select one:
a. Payback period
b. Internal rate of return
c. Discounted payback period
d. Return of Investment
Previous page
Question 10
Not yet answered
Marked out of 1.00
Flag question
Question text
The Bottom-up Approach for time and cost estimating is used when
Select one:
a. Strategic and decision-making
b. Fixed price contract
c. Unstable Scope
d. High uncertainty in project
Question 11
Not yet answered
Marked out of 1.00
Flag question
Question text
Phase Estimating uses the following system over the life cycle of the project
Select one:
a. None of the above
b. Three-time estimate
c. All of the above
d. Two-time system
e. One - time estimate
Question 12
Not yet answered
Marked out of 1.00
Flag question
Question text
A significant event in a project that occurs at a point in time is called
Select one:
a. Objective
b. Deleverable
c. Milestones
d. Exclusions
Question 13
Not yet answered
Marked out of 1.00
Flag question
Question text
Increase in unsecured loans and deposits will be tabulated under
Select one:
a. Disposition of Funds
b. All of the above
c. Sources of Funds
d. None of the above
Question 14
Not yet answered
Marked out of 1.00
Flag question
Question text
Estimating pitfalls can result from
Select one:
a. Failure to account for risks in the estimate
b. Poorly defined statement of work
c. Using the wrong estimating techniques
d. All of the above
Question 15
Not yet answered
Marked out of 1.00
Flag question
Question text
"Must to do" projects are called
Select one:
a. Strategic Projects
b. Compliance Projects
c. Operational Projects
d. All of the above
Question 16
Not yet answered
Marked out of 1.00
Flag question
Question text
Which of the following is a valid way of evaluating the financial feasibility of a project
Select one:
a. Return on Investment
b. All of the above
c. Internal rate of return
d. Net Present Value
Question 17
Not yet answered
Marked out of 1.00
Flag question
Question text
When the project size and scope are small, we prefer
Select one:
a. Process break down structure
b. Organization break down structure
c. Responsibility Matrix
d. Work breakdown structure
Question 18
Not yet answered
Marked out of 1.00
Flag question
Question text
The change control board, of which you are a member approves a significant scope change. The
first document that the project manager should updated would be the
Select one:
a. Scope baseline
b. Budget
c. Work break down structure
d. Schedule
Question 19
Not yet answered
Marked out of 1.00
Flag question
Question text
When work packages have significant uncertainty associated with the time or cost to complete, we
use
Select one:
a. Bottom-up approach
b. Top-down approach
c. Range estimating
d. Phase Estimating
Question 20
Not yet answered
Marked out of 1.00
Flag question
Question text
One of your contractors sends you an e-mail request to use high quality raw materials in your project
stating that this will be value-added and improve quality. What should be the project manager do
first?
Select one:
a. Ask the contractor to put forth a change request
b. Change the work break down structure
c. Change the scope baseline
d. Ask your sponsor for his or her opinion
Previous page
Question 21
Not yet answered
Marked out of 1.00
Flag question
Question text
For a project, if Net Benefit cost ratio is greater than 0
Select one:
a. Indifferent
b. Accept the project
c. Reject the project
d. Postpone the project
Question 21
Not yet answered
Marked out of 1.00
Flag question
Question text
For a project, if Net Benefit cost ratio is greater than 0
Select one:
a. Indifferent
b. Accept the project
c. Reject the project
d. Postpone the project
Question 22
Not yet answered
Marked out of 1.00
Flag question
Question text
The lowest level of work break down structure is called
Select one:
a. Deleverables
b. Work Accounts
c. Work Package
d. Lowest Deliverables
Question 23
Not yet answered
Marked out of 1.00
Flag question
Question text
The document that officially sanctions the project is the
Select one:
a. Project Plan
b. Feasibility Study
c. Project Charter
d. Cost-benefit analysis
Question 24
Not yet answered
Marked out of 1.00
Flag question
Question text
The work breakdown structure "control points" for the management of a project are the
Select one:
a. Activities
b. Constraints
c. Milestones
d. Work Packages
Question 25
Not yet answered
Marked out of 1.00
Flag question
Question text
Delphi Method is used in the following estimating methods
Select one:
a. Consensus Method
b. Ratio Method
c. Apportion Method
d. Function Points