Documente Academic
Documente Profesional
Documente Cultură
3DSHU
&,5('6HVVLRQ 3DSHU1R
&,5(' QG,QWHUQDWLRQDO&RQIHUHQFHRQ(OHFWULFLW\'LVWULEXWLRQ 6WRFNKROP-XQH
3DSHU
&ĂƵůƚ ƌĂƚĞƐ
EĞƚǁŽƌŬ Fault rate [faults/100km] Forest Roadside Field
ƚŽƉŽůŽŐLJ >ŽĂĚ ƐƚĂƚŝƐƚŝĐƐ ŽĨ
Bare overhead line 18 10 3 ƚŚĞŶĞƚǁŽƌŬ
Covered overhead line 9 5 1.5
Underground cable 1 1 1
8.00
6.00
4.00
ĚũƵƐƚŵĞŶƚ ŽĨƚŚĞƐƚŽƌĂŐĞ ƐŝnjĞ ƚŽƉƌĞǀĞŶƚ
2.00
• ϱϬйƚŝŵĞ ŽĨƚŚĞŽƵƚĂŐĞƐ
0.00
1 21 41 61 81 101 121 141 161 181 201 221 241 261 281 301 321 341 361 381 401 421 441 461 481
• ϳϱйƚŝŵĞ ŽĨƚŚĞŽƵƚĂŐĞƐ
Fault • ϵϬйƚŝŵĞ ŽĨƚŚĞŽƵƚĂŐĞƐ
0.05 %
Proportion
15 %
simulation contains a significant number of simulation
loops of which each describes one year. The simulation 10 %
0.00 %
30 40 50 60 70 80 90 100 110 120
&,5('6HVVLRQ 3DSHU1R
&,5(' QG,QWHUQDWLRQDO&RQIHUHQFHRQ(OHFWULFLW\'LVWULEXWLRQ 6WRFNKROP-XQH
3DSHU
network includes several reserve power opportunities and 1000 loops of simulations, which each represents a period
switching devices, it always takes time to isolate the of one year. The total number of interruptions during the
faulted network section. If the separation is carried out simulation is 2261 that makes approximately 2.3 faults
using remote controlled disconnectors, the switching time per year. The length of the interruptions varies from nine
can be 10 or 15 minutes. If manually operated hours to ten minutes. As it can be observed, most of the
disconnectors are used, the switching time can be around interruptions are relatively short that is provided by
one hour. However, if the customers locate at the faulted several disconnectors and back-up supplies. The
section, the only possibility is to repair the faulted line or switching times of the disconnectors are predetermined
to provide an alternative source of electrical power such for both manually controlled and remote-controlled
as reserve power aggregate [7] or energy storage that has disconnectors that explain the constant values in the
been studied in this paper. interruption duration curve for both 1.6 and 0.17 hours.
1.6 hours is the switching time of the normally open
MV Feeder:
disconnector to supply reserve power and 0.17 hours is
- 52 km
- Pmax = 3.2 kW
Secondary substation
(MV/LV), where the
the switching time of remote controlled disconnectors to
- 63 distribution substations
- 50 % main line
storage is planned to be
installed separate the faults occurring in other disconnector
- 80 % in fields and 10 % in forest
- 95 % overhead line and
• 6 customers
• Avg power 11 kW sections. The longest interruptions are due to fault
• Peak power 45 kW
5 % covered conductor
- manually controlled disconnectors 15 pcs
incidents on the same disconnector zone where the
- remote-controlled disconnector stations 2 pcs considered LV substation locates.
(remote-controlled disconnectors 6 pcs)
- back-up supplies 4 10
- energy consumption divided to Interruption duration [h] 9
customer groups 8
domestic 84 % 7
agriculture 3 % 6
industry 11 % 5
public 1 % 4
HV/MV 3
services 1 %
substation 2
1
0
1 146 291 436 581 726 871 1016 1161 1306 1451 1596 1741 1886 2031 2176
Figure 4. Considered rural area MV network feeder. Secondary
Sim ulated fault interruptions (total 2261)
substation, of which LV network the energy storage is planned
Figure 6. Interruption duration of the customers in the
to installed, is highlighted.
considered MV/LV substation.
The calculations of the energy storage are carried out for
Figure 7 shows ENS distribution related to interruption
LV network of a secondary substation that is marked in
duration in Figure 6. The ENS values in the simulated
Figure 4. The criteria of LV network selection were the
interruptions vary from 150 kWh to 1 kWh. The figure
location at the end of MV network, because the
indicates that significant part of the interruptions can be
customers at the end of the network experience longer
avoided with relatively small storage capacity. For
interruptions than the customers nearby the primary
instance, 10 kWh energy storage decreases about half of
substation (HV/MV). The selected LV network contains
the interruptions.
six customers, which all are residential households, and
180
Energy not supplied within
160
LV network is illustrated in Figure 5. The peak power of 140
120
the LV network is 44.5 kW while the average power is 11 100
80
kW. Annual energy use of the customers is about 100 60
MWh, where the consumption of single customer varies 40
20
from 9 MWh to 28 MWh. The loads are typical for 0
1 135 269 403 537 671 805 939 107312071341147516091743187720112145
Finnish detached households. All the LV networks, Simulated fault interruptions (total 2261)
which are wanted to be protected against interruptions
Figure 7. ENS within the simulated interruptions.
utilising energy storages, require their own storage unit,
and therefore a separate study. One of the main results of the study is the amount of
50
45
interruptions that can be avoided utilising energy storage.
40
35
Figure 8 illustrates the percentages of the interruptions
that can be avoided with different size of energy storages.
Power [kW]
30
25
20
15
In the study the considered energy storage capacities have
10 been from 0 to 50 kWh. It can be seen from Figure 8 that
5
0 50% of interruptions can be avoided with seven kWh
1 445 889 1333 1777 2221 2665 3109 3553 3997 4441 4885 5329 5773 6217 6661 7105 7549 7993 8437
Hours of year energy storage as well as 25% of interruption can be
Figure 5. Load curve of analysed LV network. avoided with two kWh energy storage. However, in the
case of small-size energy storages, a problem of
CASE SIMULATION insufficient power capacity may arise, because the energy
storage may not be able to supply enough power.
Figure 6 presents simulated duration of interruptions with
&,5('6HVVLRQ 3DSHU1R
&,5(' QG,QWHUQDWLRQDO&RQIHUHQFHRQ(OHFWULFLW\'LVWULEXWLRQ 6WRFNKROP-XQH
3DSHU
100 %
CONCLUSION
Percentage of the interruptions that
90 %
80 %
70 %
This paper presents a methodology to assess the
can be avoided
60 %
50 % utilisation of energy storages to prevent customer
40 %
30 % interruptions. The study shows that in the case network a
20 %
10 %
considerable proportion of the interruptions can be cut
0% with relatively small energy storages. Even 7 kWh
1 5 9 13 17 21 25 29 33 37 41 45 49
Size of energy storage [kWh]
storage, which means 1 kWh per supplied customer,
Figure 8. Interruptions avoided with different energy storage decreases the number of customer experienced
capacities interruptions by 50%. Also a significant benefit that can
be achieved with energy storages is decreasing the
Other benefits of the energy storages can be, for instance, number of momentary interruptions, which do not require
decreasing of momentary interruptions caused by high energy capacity. However, a problem with small-
reclosings. Often, they are more common in electricity size storages to supply enough power to the loads may
distribution than permanent interruptions. This indicates arise that may decrease the benefits.
that considerable benefit from the end-customer point of Also, the paper shows that there are potential to utilise
view can be achieved decreasing the number of energy storages economically. The economic profitability
momentary interruptions. When the momentary is not far with current energy storage prices. Thus, the
interruptions are considered, the requirements of the future work is to develop methodology to analyse the
energy storage are not usually focused on energy economic effects of the storages.
capacity, because the interruptions are very short, but the
power rating plays the key role, which is also the case in REFERENCES
the reduction of the shortest long interruptions. [1] A. Joseph, M. Shahidehpour, “Battery storage
Economic aspect of storages systems in electric power systems”, Power
Engineering Society General Meeting, 2006. IEEE
Economic benefit of the storages consists of decreasing
[2] S.W. Mohod, M.V. Aware, “Energy storage to
of customer outage costs (COC) due to customer
strengthen the wind generator in integrated power
experienced interruptions. Thus, the storage is
system”, ICSET, 2010 IEEE Int. Conf. on
economically feasible investment if the savings of COC
Sustainable Energy Technologies, Dec. 2010
are bigger than investment costs of the storage.
[3] D. Aming, A. Rajapakse, T. Molinski, E. Innes, “A
The study indicates that half of the interruptions can be
Technique for Evaluating the Reliability
avoided with the 7 kWh storage. With the price of 1000
Improvement Due to Energy Storage Systems”,
€/kWh the investment is 7000 €. The annuity of the
CCECE 2007. Canadian Conf. on Electrical and
storage is thus 670 €/a, when lifetime of the storage is 15
Computer Engineering, pp. 413–416, April 2007
years and interest is 5%. If half of the annual faults (2.3
[4] J. Haakana, T. Kaipia, J. Lassila and J. Partanen,
faults per year in the case network, average interruption
“Simulation Method for Evaluation of the Challenges
duration 2 h) can be avoided with the storage, the annual
in the Reliability Performance of Medium-Voltage
interruption cost saving is with Finnish interruption unit
Networks”, PSCC 2011. in Proceedings 17th Power
costs (1.26 €/kW and 12.6 €/kWh) [8]
Systems Computation Conference
fault § € € · € [5] J. Haakana, J. Lassila, S. Honkapuro, J. Partanen,
COC saving = 11.4kW ⋅ 50% ⋅ 2.3 ⋅ ¨1.26 + 12.6 ⋅ 2h ¸ = 346
a © kW kWh ¹ a “Renovation Strategies and Economic Regulation in
Savings of avoided permanent faults are 346 €/a that is Electricity Distribution”, IET Generation,
not enough to cover the expenses of the storage. Transmission and Planning, Vol. 6, Iss. 10, 2012
However, often a considerable part of the benefit comes [6] T. Kaipia, J. Haakana, J. Lassila and J. Partanen, “A
from decreasing of momentary interruptions. Thereby Stochastic Approach for Analysing Availability of
including them in the COCsaving calculation with the Electricity Supply,” in Proc. 9th Nordic Distribution
Finnish interruption unit costs [8], where the unit cost of and Asset Management Conf. NORDAC, Sept. 2010
high speed automatic reclosings (HSAR) is 0.63 €/kW Aalborg, Denmark
and delayed automatic reclosings (DAR) 1.26 €/kW, the [7] J. Haakana, T. Kaipia, J. Lassila and J. Partanen, “On
total benefit is higher. The average number of HSAR is in Considering Topology Changes in Network
the case network 20 fault/a and DAR 5 fault/a. Renovation”, in Proc. 10th Nordic Conf. on
Electricity Distribution System Management and
§ fault € fault € · €
COC saving = 11.4kW ⋅ ¨ 20 ⋅ 0.63 +5 ⋅ 1.26 ¸ = 216 Development NORDAC, September 2012
© a kW a kW ¹ a
[8] Energy market authority of Finland, “Sähkön
Together the savings are 560 €/a, which is near cost- jakeluverkkotoiminnan ja suurjännitteisen
effective investment. Thus, the simple economic jakeluverkkotoiminnan hinnoittelun kohtuullisuuden
approach shows that economic feasibility of storages is valvontamenetelmien suuntaviivat vuosille 2012-
reasonable to study more in the future. 2015”, http://www.energiamarkkinavirasto.fi
&,5('6HVVLRQ 3DSHU1R