ABB ACS5000 Training

ACS5000 Operation & ACS5000


Maintenance
Operation
Course G730
ACS5000 Training -RevA1
© ABB Ltd - 1 -

© ABB Ltd Page 1


ABB ACS5000 Training

Operation
Training objectives

Upon completion of this part the student will be able to operate


the drive:
n Are able to energize, de-energize, start, stop, adjust speed etc.
n Knows starting and stopping sequences
n Knows doors interlocking system
n Knows emergency shutdown and process stop functions
n Are able to use the control panel
ACS5000 Training -RevA1
© ABB Ltd - 2 -

© ABB Ltd Page 2


ABB ACS5000 Training

Operation
General
Important information about operation of the drive
n See Users manual chapters 6 (Operation) and 7
(CDP control panel)
n When the ACS 5000 is controlled by a PLC or operated from remote
stations, the reference value, the open and close commands for the
Main Circuit Breaker (MCB) and the start and stop commands are
received via digital inputs or a fieldbus adapter module. In these cases
the control interface is adapted to the specific ACS 5000
configuration. These project specific control interfaces are not
described in this chapter.
ACS5000 Training -RevA1
© ABB Ltd - 3 -

© ABB Ltd Page 3


ABB ACS5000 Training

Operation
Local Control elements
Control Panel
§ used to start and stop the motor
§ displays status messages of the
converter
§ displays alarm and fault messages
§ used to reset alarm and fault messages

Illuminated Pushbuttons
Alarm / Fault Lamp § OFF opens the main circuit
§ ALARM: flashing light breaker
§ Fault: permanent light § ON charges the DC link and
closes the
Emergency off Switch
§ Main circuit breaker
§ prevents starting when
ACS5000 Training -RevA1

actuated at standstill Emergency off Reset Switch


§ main circuit breaker opens
© ABB Ltd - 4 -

and DC link discharges


§ when actuated during operation

The chapter outlines the local operation of the converter using the
CDP
control panel and the control switches. Remote control of the
converter via a PLC or remote stations is not described in this
chapter. If the converter is controlled from remote, see the applicable
manuals for information.

© ABB Ltd Page 4


ABB ACS5000 Training

Operation
ACS5000 Training -RevA1
© ABB Ltd - 5 -
CDP Control panel

The CDP control panel is the basic user interface for operating,
controlling and monitoring the converter.
Keypad Modes The CDP control panel provides the following modes:
• Identification mode
• Actual Signal Display mode, selected by the ACT button
• Parameter mode, selected by the PAR button
• Function mode, selected by the FUNC button
• Drive Selection mode, selected by the DRIVE button.

© ABB Ltd Page 5


ABB ACS5000 Training

Operation
Grounding switches

§ The three grounding switches are installed in the Line Supply Unit (LSU).
§ The switches can only be actuated if released by the converter

Window
indicates switch position:

Indicator lamp
signals when grounding
switches can be turned to
ACS5000 Training -RevA1

position “grounded”
© ABB Ltd - 6 -

Medium voltage units of the converter include an interlocking system


which operates in conjunction with the grounding switches and the
electrical interlocks from the main circuit breaker.
The interlocking system ensures that power cannot be initialized to
the converter unless all doors have been closed and the grounding
switches have been turned to position "not grounded".
The interlocking system also ensures that the doors of medium
voltage units cannot be opened until the main power source has been
disconnected, the DC link capacitors have been discharged and the
grounding switches have been turned to position "grounded".
Doors of control and cooling cabinets are not integrated into the
interlocking system and can always be opened.

© ABB Ltd Page 6


ABB ACS5000 Training

Operation
Checks before starting-up

1. Check that no tools and foreign objects are left inside the converter.
2. All internal circuit breakers of the converter have been closed,
3. The auxiliary power supply of the converter has been switched on.
4. Check that the water cooling system is ready for operation.
5. Check that all doors have been closed and locked and all covers have been
mounted.
6. Check that the grounding switches are in position “not grounded”
7. Check that the main circuit breaker is in operating position.
ACS5000 Training -RevA1

Grounding Switch in Position “Not Grounded”


© ABB Ltd - 7 -

See Users Manual Appendix D - Electrical Diagrams to identify


the circuit breakers.
See also User’s Manual in Appendix A - Water Cooling Unit.

NOTICE!
The cooling system may start automatically as soon as the auxiliary
voltage has been switched on.

DANGER!
High Voltage!
All bolted covers must be fitted to prevent unintended touching of
energized components.

© ABB Ltd Page 7


ABB ACS5000 Training

Operation
Starting the Converter
8. Set the CDP control panel to LOCAL mode by pressing the button.
9. Check that the converter is ready.
No alarm or fault message on the CDP control panel must be present.
10. When a fault message is displayed on the CDP control panel reset the fault,
by pressing the button.
11. When the converter is ready, the control panel of an INU displays ReadyOn:
ACS5000 Training -RevA1
© ABB Ltd - 8 -

See User’s Manual, Chapter 7 - CDP Control Panel, for


information on selecting this mode.

© ABB Ltd Page 8


ABB ACS5000 Training

Operation
Charging the Converter
1. Press the ON button on the door of the COU to charge
the DC link. The ON button flashes during charging:
The status line of the INU control panel changes to
:

2. After charging has been finished, the main circuit breaker


closes automatically, the ON button lights up permanent-
ly and the display of the first INU control control panel
and the additional control panels (if present) changes to
ACS5000 Training -RevA1
© ABB Ltd - 9 -

3. All inverters can now be started.

© ABB Ltd Page 9


ABB ACS5000 Training

Operation
Starting the motor

1. Enter a setpoint. See User’ Manual, Chapter 7 - CDP Control Panel, for
information on entering a setpoint.

2. Press the button on the INU control panel of the motor


to be started up. At first, the motor is magnetized.

3. After the motor has been magnetized, the motor speed is ramped up to the
setpoint. As soon as the motor starts to turn the display of the INU control
ACS5000 Training -RevA1

panel shows Running:


© ABB Ltd - 10 -

© ABB Ltd Page 10


ABB ACS5000 Training

Operation
Starting sequence
NOT RDY ON

- No fault
- Aux supply on
- WCU ok
- Doors closed
- Ground switch open

RDY ON

ON
(PUSHBUTTO
N)

Charge DC-link
Close MCB
Close EXU contactor
(SD)

RDY RUN

- Local : START
(INU ctrl panel)
- Remote: RUN
ACS5000 Training -RevA1

START MODULATION
© ABB Ltd - 11 -

RDY REF

© ABB Ltd Page 11


ABB ACS5000 Training

Operation
Stopping the motor

1. To stop a motor, press the button on control panel.


The motor stops according to the preset stop function
and the converter stops modulating. Stop modes are
preset in parameters. While the motor stops, the
status line of the display shows Stopping:

2. When the converter has stopped modulating, the CDP


control panel displays Ready to Start:
ACS5000 Training -RevA1
© ABB Ltd - 12 -

As long as the main circuit breaker has not been


opened, the motor can be started again.

© ABB Ltd Page 12


ABB ACS5000 Training

Operation
Stop sequence
RDY REF

- Lo ca l : S T O P
( IN U c t r l p a n e l)
- R em ote : R U N

R a m p d o wn sp e e d
S to p m o d u la ti o n

R D Y R UN

- Local : O FF
( P u sh b u tto n )
- R em o te: O FF

Open M C B
Ope m E XU
D i s c h a r g e D C li n k

RD Y ON
ACS5000 Training -RevA1

G r o u n d in g
© ABB Ltd - 13 -

NO T R D Y ON

© ABB Ltd Page 13


ABB ACS5000 Training

Operation
De-energizing

To disconnect the converter from the main power supply, do the following:
1. Press the Offline button to disconnect the converter from the main power
supply. The following happens:
• Main circuit breaker opens
• DC link discharges
• Offline button lights up
After the DC link has been discharged, the display shows:

2. Rack-out, lock-out and tag-out the main circuit breaker.


3. Turn the grounding switches to the position “grounded”. After the
grounding switches are in position “grounded”, the CDP control panel
ACS5000 Training -RevA1

displays:
© ABB Ltd - 14 -

IMPORTANT!
Do not turn a grounding switch to position “grounded”, before the
light GROUNDING SWITCH UNLOCKED is on. Otherwise, the
switch will be damaged.

© ABB Ltd Page 14


© ABB Ltd
ACS5000 Training -RevA1
ABB

© ABB Ltd - 15 -