DEC 3235 Object-Oriented Programming

6.0 TIMELINE - GANTT CHART


12/6/2018 - 1/5/2019

DURATIO PERCENT
START END TEAM WEEK 1 WEEK 2 WEEK 3 WEEK 4 WEEK 5
TASK NAME N (WORK COMPLET
DATE DATE MEMBER
DAYS) E S M T W TH F S S M T W TH F S S M T W TH F S S M T W TH F S S M T W TH F S
Planning Stage
Project Initiation 12/6 12/11 6 Abu/Haidal 1%
Research Relate to System 12/12 12/14 3 Abu/Haidal 10%
Find System Requirement 12/14 12/15 2 Abu/Haidal 15%
Create Project Plan 12/16 12/18 3 Abu/Haidal 30%
Analysis Stage
Understand System Requirement 12/19 12/19 1 Abu/Haidal 45%
Gather Information 12/20 12/21 2 Abu/Haidal 60%
Sketch layout of system 12/22 12/26 5 Abu/Haidal 100%
Design Stage
Layout Design 12/27 12/31 4 Abu/Haidal 20%
Interface Design 1/1 1/29 29 Abu/Haidal 55%
Record Any Issues With Prototypes 1/30 1/31 2 Abu/Haidal 60%
Implementation Stage
System Construction 2/1 3/2 30 Abu/Haidal 90%
Testing The System 3/2 3/2 1 Abu/Haidal 95%
Fixing Any Bug In The System 3/3 3/11 9 Abu/Haidal 100%

12
DEC 3235 Object-Oriented Programming

12
DEC 3235 Object-Oriented Programming

12
DEC 3235 Object-Oriented Programming

12
DEC 3235 Object-Oriented Programming

12
DEC 3235 Object-Oriented Programming

12
DEC 3235 Object-Oriented Programming

12
DEC 3235 Object-Oriented Programming

12
DEC 3235 Object-Oriented Programming

12
DEC 3235 Object-Oriented Programming

12
DEC 3235 Object-Oriented Programming

12
DEC 3235 Object-Oriented Programming

12
DEC 3235 Object-Oriented Programming

12
DEC 3235 Object-Oriented Programming

12
DEC 3235 Object-Oriented Programming

12
DEC 3235 Object-Oriented Programming

12
DEC 3235 Object-Oriented Programming

12
DEC 3235 Object-Oriented Programming

12

S-ar putea să vă placă și