plan in Primavera P6
Posted Sat, 2016-11-26 02:27 by Khuong Do
In a project plan beside the Start and Finish date of activity, we also need to know When we need
resource, and How many resource we need.
First we need to make some configuration. Go to menu Admin -> Admin Preferences. Click on
Time Periods tab. Edit the Hours value to match with your Project calendar.
For example if you use 6 days work-week, you have to adjust Hours/Week is 48, Hours/Month is
208 (8 x 26), Hours/Year is 2496 (208 x 12)
But all data is in Units format. We may don't care number of unit, we only care number of
person or equipment.
You will right click on the table and select Spreadsheet Options
Now you can see the figure show in number of person and equipment.
On the week of 29-Sep you will need total 35 workers and 3 cranes.