A ELECTRICAL SYSTEM
1 HV power incoming system Y Y
2 Sub-station system Y Y
3 Generator system Y Y
4 Main fedder system for general Y Y
5 MSB Y Y
Power supply to Production machinery: From DB to Machinery's panel
6 Y Y
included: cable, cable tray/trunking/ladder, hanger/support, accessories, …
7 From MSB to DB Y Y DB is included
8 Power supply to mechanical equipment Y Y
9 Lighting fixture and socket outlet system Y Y
10 External lighting system Y Y
11 Tel-data system Y Y
12 Door access system Y Y
13 Public address system Y Y
14 Fire alarm system Y Y
15 CCTV system Y Y
16 Grounding & lightning protection system Y Y
17 Grounding for production machinery Y Y
18 Grounding for ELV Y Y
19 BMS system (only for ACMV system) Y Y
20 Exit & emegency system Y Y
B MECHANICAL SYSTEM
HVAC SYSTEM
Ventilation Fan Y Y
Piping c/w insulation Y Y
Ducting Y Y
Aiir grille, Louver Y Y
Split air conditioning for Domitary Y Y
C PLUMBING SYSTEM
Scope of work 1 / 2
Project: WINSON PLACTIC FACTORY
Location: Hue City, Vietnam
Package: CAS/MEP Design & Build
Item: MEP Scope of works
Sanitaryware Y Y
Pump Y Y
Valve Y Y
Floor drain Y Y
Water meter Y Y
Piping uPVC, HDPE Y Y
Foundation Y Y
Waste water ouside Y Y
Irrigation system Y Y
Waster water treatment plan Y Y
Scope of work 2 / 2