Documente Academic
Documente Profesional
Documente Cultură
a r t i c l e i n f o a b s t r a c t
Article history: Using expanding excavation based on shield tunnel can be regarded as a new approach to construct a
Received 21 November 2010 metro station, especially when traditional methods cannot be implemented. This paper focuses on the
Received in revised form 6 December 2011 ground movement property caused by shield tunneling and expanding construction. Ground movement
Accepted 22 December 2011
property and construction influence scope, which happens during the construction process, are obtained
Available online 14 January 2012
by large numbers of numerical calculations and monitoring measurements. Results show that expanding
excavation is the main factor which affects ground movement, and its influence will increase as the sta-
Keywords:
bility of surrounding rock deteriorates. Besides, horizontal displacement and vertical displacement
Shield tunneling
Expanding excavation
(uneven settlement) are the two important factors which lead to building deformation and cracks; there-
Ground movement fore, more attention should be given to these areas where the maximum displacement may occur during
Building deformation the construction process. Analysis of the two parameters, length to diameter ratio and depth to diameter
ratio, indicates their relationship with safety of tunnel and building. Influence degree and scope of ground
settlement are obtained due to change of the two parameters. The practical importance of this analysis is
that we can judge whether building and tunnel are in a dangerous zone and thereby adopt relevant pre-
reinforcements to ensure their safety. Later with the comparison of numerical simulation and in-situ data,
we verify the accuracy of simulation.
Ó 2011 Elsevier Ltd. All rights reserved.
1. Introduction this subject, are mostly about construction schemes. For example,
Nakamura et al. (2003) introduced a method to excavate a rectangu-
At present, when building a metro station, conventional pro- lar cross-section for the Kyoto Municipal Subway. Shirai et al. (2005)
cesses and technologies cannot be implemented smoothly because reported a new technology, namely using the large-diameter curved
of restrictions caused by surrounding environment (e.g., launching pipe roof construction method to construct large underground
and receiving shafts cannot be constructed on the line because of spaces. Kunihiko and Kenichi et al. (2006) presented that a large
the existence of buildings and underground utilities). However, diameter shield tunnel was used for the construction of subway,
these problems can be effectively solved when the shield tunneling and he also described a non-cut-and-cover method which was used
method or the expanding shield tunnels method are utilized to con- for cutting the ground between two large-diameter shield tunnels.
struct a metro station directly. Meanwhile, construction period can Hiroshi et al. (2006) showed that shield tunneling is utilized to build
be shortened significantly and construction quality will also be im- the Central Circular Shinjuku Route of Tokyo Metropolitan Express-
proved, which will definitely bring practical and economic signifi- way, and the space enlargement method was adopted to construct
cance (Lu, 2007; Li, 2007; Liu, 2010). Both shield tunneling and branch connections and ramps. Hiroshi (2007) described an Open-
expanding construction will induce disturbance to the surrounding Cut Method which was used for the construction of enlarging road
rock and cause ground movement; however, what exactly the two shield tunnel. However, there is little research about the effect of
processes ‘‘contribute’’ to the ground movement is still unknown; this construction method on the ground movement property are
besides, considering the existence of a building, when H/D and L/D few. This paper presents a detailed research on such problems, with
change (H is the depth of tunnel, L is the horizontal distance be- the background of a left line platform tunnel of Dongshankou metro
tween tunnel and building, D is diameter of shield tunnel), the influ- station Guangzhou metro line 6 in China.
ence of two construction processes on stratum movement is also
unknown. Currently, some published papers, which are related to 2. Engineering situation
⇑ Corresponding author. Tel.: +33 0668259478. The use of expanding excavation based on shield tunnels is
E-mail address: jeafliu@gmail.com (J. Liu). adopted in an under-construction left line platform tunnel of
0886-7798/$ - see front matter Ó 2011 Elsevier Ltd. All rights reserved.
doi:10.1016/j.tust.2011.12.005
288 J. Liu et al. / Tunnelling and Underground Space Technology 28 (2012) 287–296
Dongshankou metro station Guangzhou metro line 6, China. The in contrast to shield tunneling, ground settlement caused by
distance from the tunnel vault to the ground surface is 18.800– expanding construction is larger. As shown in Table 2, in the
19.845 m, and the distance between invert and ground is places of surface, depth of 1D, depth of 2D and vault, the settle-
27.045–27.534 m. The left line of station crosses a six storied ment caused by expanding construction accounts for 54.96%,
building of the Second Light Industry Group. The terrane through 54.80%, 53.70%, and 50.86% of the total settlement. With the in-
which the left line platform tunnel passes consists mainly of mod- crease of depth (above the vault), ground settlement rises sharply.
erately weathered zones and silky weathered zones. The top of After expanding construction, the settlement amount of surface,
tunnel crosses mainly through strong weathered zones, and it goes depth of 1D, depth of 2D and vault are 9.17 mm, 10.11 mm,
partly through fully weathered zones. The formation parameter 14.47 mm, and 20.84 mm respectively. It can be seen clearly that
and the geological section map are shown in Table 1 and Fig. 1, the settlement value of vault is two times bigger than surface
respectively. subsidence.
Table 1
Soil properties (according to exploration data).
Note: 4.09 103 MPa and 13.2 103 MPa are modulus of elasticity.
Fig. 2. FD model and skeleton map of excavation. Note: P1 – outline of upper bench excavation; P2 – outline of lower bench excavation; P3 – area of shield driving; P4 –
segment; P5 – influence area due to of pre-grouting with sleeve valve pipes; P6 – influence area of large-pipe-shed.
290 J. Liu et al. / Tunnelling and Underground Space Technology 28 (2012) 287–296
Table 2
Some key points displacement.
Construction process Construction step Ground surface Buried depth of 1D Buried depth of 2D Buried depth of 3D (Vault)
Shield tunneling The sixth step 1.45 1.68 2.83 4.57
The tenth step 2.55 2.95 5.11 8.76
The fourteenth step 3.35 3.81 6.14 9.79
The eighteenth step 3.81 4.28 6.51 10.09
The twenty-fifth step 4.13 4.57 6.70 10.24
Expanding excavation The sixth step 4.67 5.17 7.52 11.06
The twentieth step 5.24 5.83 8.71 13.32
The twenty-eighth step 7.29 8.16 12.30 18.38
The thirty-sixth step 8.14 9.07 13.41 19.74
The forty-sixth step 9.04 9.99 14.37 20.75
The fiftieth step 9.17 10.11 14.47 20.84
Proportion Expanding excavation 54.96% 54.83% 53.41% 50.86%
Fig. 4. Stratum settlement at different buried depths (shield driving). conditions. As in chapter 4.1, key points are chosen to analyse the
effect of formation condition on ground movement, see Table 4. It
is clear that the influence of expanding excavation construction
4.4. Analysis of ground movement happened in different geological on ground movement increases gradually as condition of surround-
conditions ing rock becomes deteriorated. For instance, from IV class sur-
rounding rock to VI class surrounding rock, ground settlement
Considering the complexity of formation condition in different caused by expanding construction accounts for 60%, 70%, and 75%
places of China, we choose three different formation conditions to of the total settlement. Especially for VI class surrounding rock, hor-
simulate. This section focuses on ground settlement property due izontal displacement, caused by expanding excavation, accounts for
to construction of a metro station occurred in different geological more than 80% of the total displacement. Therefore, it is essential to
J. Liu et al. / Tunnelling and Underground Space Technology 28 (2012) 287–296 291
Table 3
Sphere of influence due to construction.
adopt some pre-reinforcement measures before expanding excava- 5.1. Effect of building location on the ground movement
tion when formation condition is worse than IV class. Besides, mon-
itoring measurement is an effective way to assure construction In order to better understand the effect of the horizontal dis-
safety. placement L on the ground movement, here we chose the lengths
292 J. Liu et al. / Tunnelling and Underground Space Technology 28 (2012) 287–296
Table 4
Some key points’ displacements of different surrounding rock classification.
Surrounding rock classification Construction process Settlement (mm) Horizontal displacement (mm)
Ground surface Buried depth of 1D Buried depth of 2D Stretching Compression
IV-grade After shield driving 2.0 3.0 3.37 1.0 2.0
After expanding excavation (mm) 5.0 7.5 8.29 1.5 4.9
Proportion (expanding excavation) 60% 60% 59% 32% 59%
V-grade After shield driving 3.0 4.0 4.9 1.0 2.3
After expanding excavation (mm) 10.0 12.0 14.9 5.0 15.19
Proportion (expanding excavation) 70% 67% 67% 80% 85%
VI-grade After shield driving 5.0 7.5 10.2 7.0 3.9
After expanding excavation (mm) 20.0 30.0 41.7 40.0 90.0
Proportion (expanding excavation) 75% 75% 76% 83% 96%
Table 5
Parameters table ground movement under building.
(during the range of 120°); and two rows of horizontal sleeve valve
pipes are set up within range of the tunnel’s vault (during the
range of 120°), with the purpose of grouting to the rock of tunnel’s
vault. Specific process is presented in Fig. 17. The whole aim is to
ensure the stability of host rock during the construction process.
Now the platform of left line has been completed and it does not
have any problems during the construction process; in addition,
the building deformation is also under control. This could indicate
that the pre-reinforcement measures have played a good role (Liu
et al., 2010).
The monitoring data is shown in Table 6. In order to verify the
accuracy of numerical simulation, we chose section I (horizontal)
and section II (longitudinal) to analyse, see Fig. 16. Section I is near
to the boundary of the metro station and the running tunnel, and
section II is close to the central line of the metro station. Compar-
ison of numerical simulation and monitoring data are presented in
Figs. 18–20, which provide a verification of the predictions ob-
tained from the finite difference analysis.
Based on the obtained results of measurements, the maximum the existence of building will affect adjacent ground movement, and
settlement of taken points is 14.06 mm and the minimum surface on the other hand movement of stratum and ground surface will also
settlement is 8.3 mm, which are among the permissible range of exert some influence on building deformation, leading to stress
+10–30 mm, see Table 6. It means that these pre-reinforcements redistribution of building interior load. The displacement of four
have played a good control effect on ground settlement. In addition, building monitoring points J4, J5, J12 and J15 are larger than adjacent
monitoring values dovetail nicely with the result of simulation, see surface monitoring points. For example, the displacement of moni-
Figs. 18–20; however, the calculated amount of settlement from toring point J12 is 14.6 mm (12.9 mm), while the displacement of
FLAC3D is a little smaller than the results of local surveys. The reason monitoring point D9 is 12.8 mm (11.1 mm), see Figs. 18 and
is that the effect of underground water is not considered when per- 19(the value which is presented in parenthesis is simulation value).
forming calculation, and the soil parameters are deemed to be un- It means that existence of the building really has an effect on the sur-
changed at grade. Meanwhile, there are some uncertainties of face settlement. In addition, differential settlement of building really
solum condition and underground water state during the construc- occurs during construction process, see Fig. 18. For instance, dis-
tion process. In transverse section, both monitoring data and simu- placements of four building monitoring points J4, J5, J12 and J15 (lo-
lation value are in accordance with the law of settlement trough (Liu cated at the four corners of the building) are 10.3 mm (9.0 mm),
et al., 2008), and their values are not completely symmetrical along 11.46 mm (10.0 mm), 14.6 mm (12.9 mm), and 12.21 (9.7) mm,
the axis, see Fig. 19. In the longitudinal section, ground settlement of respectively. The maximum differential settlement of the length
monitoring points decreases gradually with vertical distance, see direction and the width direction are d1 = 4.3 mm (3.9 mm),
Fig. 20. This is largely due to consolidation settlement of stratum d2 = 2.39 mm (3.2 mm). According to the Code for Building Ground
(Lin et al., 2011; Zangerl et al., 2008a,b). Sill and Foundation Design (GB50007 – 2002), the allowable differ-
Tunnel-soil-building interaction is a complicated process, one as- ential settlement of frame structure are shown in Table 7.
pect may affect another during construction process (Cheng et al., As this building has been built for many years and the soil is al-
2007; Burd et al., 2000; Keshuan and Lieyun, 2008). On the one hand ready compressed to a certain extent, it is considered as medium
Fig. 16. Layout of ground monitoring points. Note: YDK14 (km) + 869.602 (m); ZDK14 (km) + 960.702 (m).
J. Liu et al. / Tunnelling and Underground Space Technology 28 (2012) 287–296 295
Table 6
Monitoring Report of ground settlement (Donshankou station).
in length; d1 = 4.3 mm (3.9 mm) < 80 mm; and the allowable differ-
ential settlement of the building is [0.002 14,000 mm] = [28 mm]
in width; d2 = 2.39 mm (3.2 mm) < 28 mm. This means that ad-
vanced large pipe shed and sleeve-valve-pipe grouting have played
a good role in controlling differential settlement of building. Mean-
while, the monitoring values and numerical results dovetail nicely.
7. Conclusions
Fig. 18. Settlement of monitoring points (monitoring data and simulation value).
In this article, at first we analyse the ground movement prop-
erty caused by shield tunneling and expanding excavation. Consid-
ering the different formation condition of China, we chose three
different formation conditions to analyse; and then we conducted
some research on parameter sensitivity analysis about L/D and H/D
under existence of building. Finally, accuracy of numerical simula-
tion is verified by comparing with in situ monitoring data. The re-
sults of the present study are summarized below:
take some relevant pre-reinforcement measures to ensure con- Li, W., 2007. Study on Design and Constructions Schemes for Metro Station Based on
NATM by Using Sh1e1d Tunnel. Dissertation for Master’s Degree, Southwest
struction safety. At present, we have successfully applied this
Jiaotong University (in Chinese).
conclusion to Dongshankou metro station. Liao, H.J., Qing, W.C., Zhang, Z.G., Mochizuki, A., 2006. Research on the effect of
– Analysis is performed on the basis of both in situ data and underground tunnelling on the settlement of the building and the ground
numerical simulation, which can assist us to verify the accuracy surfaces. Tunnelling and Underground Space Technology 21 (3–4), 290.
Lin, C.G., Zhang, Z.M., W, S.M., 2011. Case study of long-term ground settlements
of numerical data and to understand the influence of construc- induced by slurry shield tunnelling. Advanced Materials Research 243–249,
tion on ground movement. 3078–3081.
Liu, J.F., 2010. Research on the Ground Movement Law Due to Metro Station Driven
with Enlarging Shield Tunnels [D]. Dissertation for Master’s Degree, Southwest
The use of shield tunneling and expanding excavation for metro Jiaotong University (in Chinese).
station construction is a new construction method in China. Be- Liu, H.Y., Small, J.C., Carter, J.P., 2008. Full 3D modeling for effects of tunnelling on
sides, Dongshankou station is the first station which adopts this existing support systems in the Sydney region. Tunnelling and Underground
Space Technology 23 (4), 399–420.
method to construct a metro station. There are not too many expe- Liu, J.F., Qi, T.Y., Kuang, W.T., 2010. Analysis on ground settlement caused by
riences which can be used for reference; therefore, we hope we can enlarging shield tunnelling. Railway Standard Design 4, 80–82 (in Chinese).
supply some useful information to the following projects. Lu, M.L., 2007. Study on Schemes and Risk Analysis of the Expanded Metro Station
under Shield Running Tunnel. Dissertation for Doctor’s Degree, Beijing Jiaotong
University (in Chinese).
Nakamura, H., Kubota, T., Furukawa, M., Nakao, T., 2003. Unified construction of
running track tunnel and crossover tunnel for subway by rectangular shape
References double track cross-section shield machine. Tunnelling and Underground Space
Technology 18 (2–3), 253–262.
Burd, H.J., Houlsby, G.T., Augarde, C.E., Liu, G., 2000. Modelling tunnelling-induced Neaupanea, K.M., Adhikarib, N.R., 2005. Prediction of tunnelling-induced ground
settlement of masonry buildings. Geotechnical Engineering 143 (1), 17–29. movement with the multi-layer perceptron. Tunnelling and Underground Space
Cheng, C.Y., Dasari, G.R., Chow, Y.K., 2007. Finite element analysis of tunnel -soil- Technology 21 (2), 151–159.
pile interaction using displacement controlled model. Tunnelling and Shirai, S., Kano, M., Watabe, S., Hujiya, T., Ito, Y., Nakamura, M., Akiyama, H.,
Underground Space Technology 22 (4), 450–466. Yamamoto, Y., 2005. Construction of non-open-cut large underground space by
Hiroshi, N., 2007. Construction of enlarging road shield tunnel for the non-open-cut the large-diameter curved pipe roof. Construction Machinery and Equipment
method. In: The Fourth China–Japan Exchange of Shield Driving Tunnel 489 (41), 40–43.
Technique, China, pp. 265–273. The National Standards Compilation Group of People’s Republic of China. Technical
Hiroshi, N., Takuya, M., Akio, M., 2006. Space Enlargement Methods of Shield Code for Building Ground Sill and Foundation Design (GB5007-2002).
Tunnels for Constructing Branch Connections-Examples of the Open Cut Zangerl, C., Eberhardt, E., Evans, K., Loew, S., 2008a. Consolidation settlements above
Method and the Non-Open Cut Method. Technical Research Report of Hazama deep tunnels in fractured crystalline rock: Part 2 – Numerical analysis of the
Corporation (CD-ROM), vol. 38. Gotthard highway tunnel case study. International Journal of Rock Mechanics
Keshuan, M., Lieyun, D., 2008. Finite element analysis of tunnel-soil-building and Mining Sciences 45, 1211–1225.
interaction using displacement controlled model. In: 7th WSEAS Int. Conf. on Zangerl, C., Evans, K., Eberhardt, E., Loew, S., 2008b. Consolidation settlements
Applied Computer & Applied Computational Science (ACACOS’08), Hangzhou, above deep tunnels in fractured crystalline rock: Part 1 – Investigations above
China, pp. 306–311. the Gotthard highway tunnel. International Journal of Rock Mechanics and
Kunihiko, T., Kenichi, Y., 2006. The state of affairs of large diameter shield tunnel Mining Sciences 45, 1195–1210.
method for subway and the recent trend of shield technology in Japan. In: Zhang, Y.T., Tao, L.J., Bian, J., Guo, J., 2006. Numerical modeling of shield tunnelling
International Symposium on Underground Excavation and Tunnelling, Bangkok, based on the stress release ratio method. In: The 10th IAEG International
Thailand, pp. 57–66. Congress, Nottingham, United Kingdom.