Documente Academic
Documente Profesional
Documente Cultură
ir
http://www.itrans24.com/landing1.html
Department of Electrical and Computer Engineering School of Electrical and Computer Engineering
Democritus University of Thrace (DUTH) National Technical University of Athens (NTUA)
Xanthi, Greece Athens, Greece
{vnikolai, konsarse, asafig}@ee.duth.gr vournas@power.ece.ntua.gr
Abstract—This paper investigates the application of distance tance relaying principle to protect distribution systems with
relays in distribution systems with distributed generators. An DG seems a promising option [4], [5], [6]. This paper exam-
analysis of the parameters that influence the effectiveness of ines the application of distance relays in radial distribution
distance relaying in distribution networks is performed. Protec- systems with DG. The organization of this paper is as follows.
tion coordination between the distance relays and the existing Section II includes a brief introduction to distance protection
protection means on the line is studied with the help of a realistic applications in distribution systems. Section III describes the
distribution network. Coordination problems are identified and proposed distance-based protection scheme. Section IV pre-
a simple distance-based protection scheme is proposed. sents the simulation results and the effect of some influencing
Index Terms—Distance protection, distributed generation, dis-
parameters on the distance relay performance, while the con-
tribution systems, protection coordination. clusions are drawn in Section V.
III. PROPOSED DISTANCE PROTECTION SCHEME The first zone is set to instantaneously (t1 ≈ 0) clear faults
occurring within the 85% of the distance between the DR lo-
To illustrate the setting rules for the distance-based protec- cation and the first lateral. Thus, the largest expected fault
tion scheme, the radial overhead line distribution system de- currents will be interrupted instantaneously and the equipment
picted in Fig. 2 is considered again. The fuses F1-F4 protect will be exposed to the worst through-fault damage for the
the main laterals, while the fuses F1.r-F.4.r protect the remot- shortest time duration. This is especial critical for the substa-
est tapped distribution transformer in each lateral. We assume tion transformer which should not be exposed to large
fuses at the laterals because they are the most encountered through-fault currents. The second zone is set to cover the
protection means in overhead distribution lines and because total impedance (Z2) up to the end of the first lateral. Since the
fuses are more difficult to coordinate with the main feeder first lateral is protected by the main fuse F1, the second zone
protection (recloser/distance relay) than overcurrent relays due is coordinated to operate with a time delay t2 that is larger than
to their non-settable characteristic. A fuse-saving philosophy the largest of the total clearing times of this fuse. An appropri-
is further adopted. Coordination between the main fuse and ate minimum Coordination Time Interval (CTImin) is taken for
the fuses at the primary of the tapped transformers is assumed. this purpose. The third zone is set to cover the total impedance
The distance relay DR is installed at the beginning of the (Z3) up to the end of the second lateral. Again, coordination
line replacing the conventional overcurrent relay. The radial must be guaranteed between the zone 3 element and the fuse
line is divided into protection zones each of them (except of F2. Hence, an appropriate time delay t3 for the zone 3 opera-
the first) covers part of the main line and the whole length of tion must be specified. Finally, the fourth zone is set to protect
one of the laterals. Attention should be given so that none of the line up to the end of the third lateral with an appropriate
the protection zones of the distance relay will overreach the time delay t4. Note again that in all cases coordination between
protection zone of any of the distribution transformers that are the main fuse and the fuses on the transformers is assumed at
tapped on the laterals. To complete this fulfillment the positive each lateral.
sequence impedance seen by the DR for a fault at the remotest If there is a short line section beyond the third lateral or a
end of the lateral should be compared with the smallest possi- fourth lateral as in Fig. 2, zone 4 can be extended to cover the
ble positive sequence impedance seen for a fault on the secon- main line up to its remotest end including the fourth lateral. If
dary winding of any of the distribution transformers at this the distribution line has more than four laterals, a second dis-
lateral. tance relay named DR2 should be installed in the main line, in
Most distance relay manufacturers provide the availability the section immediately after the third lateral (Fig. 4). Then,
to choose between any possible combination of phase and DR2 should be coordinated following the same setting phi-
ground elements in terms of a mho or a quadrilateral charac- losophy as described previously. Since the phase and ground
teristic. However there are manufacturers that restrict the use short-circuits have smaller magnitudes as the fault location
of mho (resp. quadrilateral) characteristics only to phase or moves away from the substation, the clearing times of the
ground elements. For example, one well established manufac- downstream fuses will become larger. Thus, although coordi-
turer provides phase elements with a mho characteristic, while nation between the DR2 and the fuses beyond the third lateral
quadrilateral characteristics are provided only for the ground can easily be achieved, coordination between the DR2 and the
elements. Moreover, most manufacturers provide four inde- DR1 is not so straightforward. By determining the appropriate
pendent phase/ground elements, whereas there are some spe- time delays of the phase and ground elements of the DR2, the
cial cases where five independent phase/ground distance ele- required CTImin between the DR1 and DR2 should be pre-
ments are provided with the relay. served. In some cases, this leads to an additional increase of
the time delay of a zone element. For example, in Fig. 4 the
In this paper, it is assumed that the DR provides four inde- time delay t1,4 of the DR1 should be increased to the value t’1,4
pendent mho and four independent quadrilateral elements, in order to keep coordination. However, according to our ex-
which can interchangeably be used for phase and ground pro- perience based on protection coordination studies for radial
tection. Finally, each phase and ground element has been set overhead lines in Greece, a sufficient CTI between the protec-
with a quadrilateral characteristic. The quadrilateral character- tion devices can be achieved even for long lines supplied from
istic has been selected over the mho one because of its advan- a weak external grid.
tages, especially in regard with the fault resistance coverage.
The setting procedure concerns equally the phase and ground It is obvious that the first distance relay is commanded to
elements and takes into account the infeed effect. This proce- protect up to three laterals, while any downstream distance
dure is described below in a detailed manner. relay, if needed, can protect at maximum four laterals each.
Downloaded from http://iranpaper.ir
http://www.itrans24.com/landing1.html
IV. SIMULATION RESULTS Four zones have been set to cover the line up to its remot-
est end. These zones are shown with the blue quadrilateral
A. Test System Description characteristics in the complex impedance plane of Fig. 6. The
phase and ground elements have been set to have the same
The proposed distance protection scheme has been tested reach, whereas they have different time delays determined
on a typical overhead distribution line configuration in Greece, from the maximum fuse clearing times plus the minimum re-
which consists of one radial 20 kV, 50 Hz, 25 km long over- quired CTImin which is equal to 0.3 s. The positive resistive
head line shown in Fig. 5. ACSR conductor is used with a reach (+R) of the quadrilateral characteristics has been se-
cross-section of 95 mm2 on the first segment, which constantly lected to cover a fault resistance that is at maximum equal to
decreases to 50 mm2 and 35 mm2 on the subsequent segments. four times the positive reactance reach (+X). This is a quite
In most of the laterals, a 16 mm2 ACSR conductor is used. effective assumption [6] for considering fault resistances in
The total line load is 3.42 MW and 1.99 MVAR. The trans- medium voltage distribution systems.
mission grid is represented by an equivalent source, having a
maximum short-circuit power of 2000 MVA at 150 kV. The It is obvious that both the third and fourth zone reaches far
feeder is supplied from the external grid through a 150/20 kV inside the load encroachment area, illustrated with the red line
distribution transformer. A conventional 1.5 MVA, 20 kV, 50 in Fig. 6. Having in mind that the load encroachment holds
Hz round-rotor synchronous machine has been assumed as a only for symmetrical three-phase conditions, only three-phase
DG unit, operating with a unity power factor when grid- fault conditions with a large fault resistance may not be
connected. Standard models available in DigSilent Power Fac- cleared effectively by the relay. However, such conditions are
tory 15 have been used for representing the described system. rare and even smaller fault resistances cannot be sensed from
In addition, actual fuse links have been modeled at the laterals common overcurrent relays without a sensitive earth-fault
and at the primary side of the load transformers. element. Since no DG production has been assumed up to
now, the reclosing element of the distance relay can be set to
B. Distance Relay Setting perform a fast reclosing operation for faults occurring every-
where on the line. This reclosing element is represented by the
At first, the case without DG production has been exam-
mho characteristic, shown with the brown circle in Fig. 6,
ined. Phase and ground faults with zero fault resistance have
which encircles the whole network.
been simulated at critical locations on the line and the maxi-
mum total clearing times of the fuses have been determined.
Table I summarizes the maximum clearing times of all the
main fuses in the network. In general, the single-phase (1Φ)
short-circuit resulted to the maximum clearing times.
Downloaded from http://iranpaper.ir
http://www.itrans24.com/landing1.html
TABLE I. MAXIMUM TOTAL CLEARING TIME (NO DG) TABLE II. TIME-DISTANCE ZONE SETINGS (WITH DG)
Fuse TC time (ms) Fault type No DG 1 DG unit 2 DG units 3 DG units
F1 179 1Φ +X Delay +X Delay +X Delay +X Delay
F2 264 1Φ (Ω) (ms) (Ω) (ms) (Ω) (ms) (Ω) (ms)
F3 389 1Φ P1 1.42 55 1.42 55 1.42 55 1.42 55
F4 537 1Φ P2 4.00 400 4.00 400 4.50 400 4.50 400
P3 6.00 500 6.00 500 6.50 500 7.00 400
P4 10.0 600 11.0 600 11.5 600 12.0 600
Next, the setting procedure has been repeated by consider- G1 1.42 55 1.42 55 1.42 55 1.42 55
ing DG units connected to the line. Three different penetration G2 4.00 500 6.00 500 7.00 500 7.60 500
G3 6.00 700 10.0 600 12.5 500 14.0 500
levels have been examined; 42%, 83%, and 125%, meaning G4 10.0 900 19.0 700 23.0 700 26.0 700
respectively one, two, or three fully rated DG units simultane-
ous in operation. The DG units have been assumed to produce TABLE III. MAXIMUM TOTAL CLEARING TIME (WITH DG)
their 100% rated power because they are conventional syn-
chronous machines, thus the power production is fully control- 1 DG unit 2 DG units 3 DG units
lable and independent from the weather conditions. Moreover, Fuse TC (ms) TC time (ms) TC time (ms) Fault type
F1 133 129 127 1Φ
it will be seen in the next subsection that the influence of the F2 151 142 137 1Φ
penetration level on the distance relay settings is more pro- F3 365 345 388 1Φ
nounced as the penetration level gets larger, while the DG unit F4 365 345 388 1Φ
connection point plays also an important role.
Now, the critical factor is how the infeeds affects the reach
of the zones. It should be noted that for the DG units to be
considered as infeeds, the DG protection should be very thor-
oughly taken into account meaning that it is important to know
if the DG protection will instantaneously disconnect the units
or not in case of a fault. The under/over-voltage and un-
der/over-frequency settings suggested from various standards
[8], indicate that even for the worst short-circuit conditions,
the DG will remain connected for a minimum of 0.1 s. Defi-
nitely, there are also other DG protection functions (intercon-
nection relay, overcurrent relay etc) that should be taken into
consideration. Since this time delay is in general comparable
with the total clearing time of most of the fuses for phase
faults and because of the fact that not all the DG units in a
distribution system are simultaneously exposed to the worst
voltage/frequency/overcurrent conditions during a fault, we Figure 7. Phase and ground elements of DR with 2 DG units in operation
consider that the DG units contribute constantly to the fault
within the time frame of the distance relay operation. In other Obviously, if an active management system was available
words, DG units are considered as infeeds in the protection for this distribution system, different setting groups could be
coordination procedure. beforehand programmed and stored inside the distance relay.
Then, based on the information retrieved from the DG units
The main difference observed when considering DG pro- through communications about their operating status (on/off),
duction in the coordination study is that the phase and ground the appropriate setting group can be uploaded to the relay.
elements of the distance relay must be set uniquely because of
the different contribution of the DG units under different fault C. Effect of Influencing Quantities
types. Table II summarizes the time-distance settings of all the
In order to investigate the influence of the fault resistance
phase (P) and ground (G) elements of the relay as determined
on the performance of the distance relay, we subsequently
based on the three different DG penetration levels. Only the
simulated single-phase and three-phase faults at the end of
positive reactance reach (+X) is shown, since the resistive
each zone assuming different values of fault resistances from
reach (+R) is taken equal to four times the reactance one. As a
zero up to RF = 40 Ω. Again, the case with two DG units con-
graphical example, Fig. 7 depicts the characteristics of the
nected is assumed, to easily compare with the Fig. 7. Fig. 8
phase and ground characteristics for the case of two DG units
(resp. Fig 9) illustrates the modification required in the posi-
connected to the network simultaneously. In this figure, the
tive reactance reach setting (+X) of the zone 4 phase (resp.
blue solid characteristics correspond to the phase elements and
ground) element depending on the fault resistance magnitude
the dashed magenta ones to the ground elements. The phase
and the DG connection point. The resistive reach (+R) is al-
and ground elements operate with different time delays deter-
ways taken equal to four times the reactive one.
mined from the maximum total clearing times of the main
fuses. Table III shows the total clearing times of the main
fuses for all the examined penetration levels.
Downloaded from http://iranpaper.ir
http://www.itrans24.com/landing1.html
Figure 8. Influence of the fault resistance on the reactance reach setting of Figure 10. Influence of the DG penetration on the reactance reach setting of
the phase element the phase element