Qurrpa Classic Schedule Layout 26-Dec-16 22:36

Activity ID Activity Name Original Start Finish 2016 2017


Duration Oct Nov Dec Jan Feb Mar Apr May Jun Jul
114 05-Oct-16 15-Feb-17 15-Feb-17, Qurrpa
Qurrpa
Piles works 61 05-Oct-16 15-Dec-16 15-Dec-16, Piles works

A1000 Construction works for the reinforced concrete Piles (391 piles) 61 05-Oct-16 15-Dec-16 Construction works for the reinforced concrete Piles (391 piles)

Cap beam works 20 08-Dec-16 31-Dec-16 31-Dec-16, Cap beam works

A1010 Construction works for the Piles' Cap beam 20 08-Dec-16 31-Dec-16 Construction works for the Piles' Cap beam

Escavation works 53 17-Dec-16 15-Feb-17 15-Feb-17, Escavation works

A1020 Excavation works for constructing the anchors at level (- 3) 15 17-Dec-16 02-Jan-17 Excavation works for constructing the anchors at level (- 3)

A1050 Excavation works for constructing the anchors at level (-7) 10 10-Jan-17 21-Jan-17 Excavation works for constructing the anchors at level (-7)

A1080 Excavation works from level (-7) to level (- 9.45) 10 05-Feb-17* 15-Feb-17 Excavation works from level (-7) to level (- 9.45)

Anchors works 33 24-Dec-16 30-Jan-17 30-Jan-17, Anchors works

A1030 construction works for the anchors at level (-3) 12 24-Dec-16 05-Jan-17 construction works for the anchors at level (-3)

A1060 Construction works for the anchors at level (-7) 12 17-Jan-17 30-Jan-17 Construction works for the anchors at level (-7)

Steel beam works 34 27-Dec-16 04-Feb-17 04-Feb-17, Steel beam works

A1040 Installation works for the anchors' steel beam at level (-3) 12 27-Dec-16 09-Jan-17 Installation works for the anchors' steel beam at level (-3)

A1070 Installation works for the anchors' steel beam at level (-7) 12 22-Jan-17 04-Feb-17 Installation works for the anchors' steel beam at level (-7)

Actual Work Critical Remaining ... Page 1 of 1 TASK filter: All Activities

Remaining Work Milestone © Oracle Corporation