Exclusion List of Contractor

No Description Remark
1 Custom duties in UAE
Maintain & repair the
access to the site if
2 Temperory access to site
needed by the Contractor
for his use only
Temperory Area for Accomodation, site fabrication and equipment Construction and security
3
storage. is in Constractor's scope
4 Vehicles for plant operation of Owner (including fire Truck)
Engineering design is in
6 Maintenance road construction of OLBC
Contractor's scope
7 Landscape
8 Furniture of non plant buildings

Any work outside of boundary lines (Wall fence in General layout)


9
except specified items in this Contract

Design and construction


of foundation and
structures shall take into
10 CPP and WHR consideration arrangment
and loads of Waster Heat
Recovery Boiler and
Auxillary systems.
Water and electricity and fuel for the cold-run tests, commissioning
11
and operation of the plant.
Raw materials and additives for the commissioning and operation of
12
the plant.
13 Mining Machinery
Any engineering, design, supply, construction and any other activity of
14
quarry
15 Quarry preparation
16 Vehicle for transportation of raw materials to and within plant
17 Moving exisiting structure if any

18 Facilities of any Office and accommodation for Owner's staff at site