ID Task Task Name Duration Start Finish Predecessors 07 Aug '17 14 Aug '17 21 Aug '17 28 Aug '17

Predecessors 07 Aug '17 14 Aug '17 21 Aug '17 28 Aug '17 04 Sep '17
Mode S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T
1 Dynamics 365 Implementation 106 days Mon 07/08/17 Wed 17/01/18
2 Prerequisites 0 days Mon 07/08/17 Mon 07/08/17 07/08
3 Arrange Project Kick Off meeting 0 days Mon 07/08/17 Mon 07/08/17 07/08
4 Environments 0 days Mon 07/08/17 Mon 07/08/17 07/08
5 Confirm number of environments 0 days Mon 07/08/17 Mon 07/08/17 07/08
6 Access to environments 0 days Mon 07/08/17 Mon 07/08/17 07/08
7 Licensing 0 days Mon 07/08/17 Mon 07/08/17 07/08
8 What level/plan of licence is required 0 days Mon 07/08/17 Mon 07/08/17 07/08
9 How many licences are required and when 0 days Mon 07/08/17 Mon 07/08/17 07/08
10 Integration 0 days Mon 07/08/17 Mon 07/08/17 07/08
11 Technical overview of Integration 0 days Mon 07/08/17 Mon 07/08/17 07/08
12 Access to test environment 0 days Mon 07/08/17 Mon 07/08/17 07/08
13
14
15 Discovery 21 days Mon 07/08/17 Tue 05/09/17
16 Analysis 10 days Mon 07/08/17 Fri 18/08/17
17 Requirement Workshops 3 days Mon 07/08/17 Wed 09/08/17 Dynamics 365 Consultant,Customer
18 Author Functional Requirements Document 2 days Thu 10/08/17 Fri 11/08/17 17 Dynamics 365 Consultant
19 Milestone - FRD issued to <customer> 0 days Fri 11/08/17 Fri 11/08/17 18 11/08
20 Review FRD 5 days Mon 14/08/17 Fri 18/08/17 19 Customer
21 Milestone - FRD Approved 0 days Fri 18/08/17 Fri 18/08/17 20 18/08
22 Design 11 days Fri 18/08/17 Tue 05/09/17
23 Dependency - FRD Approved 0 days Fri 18/08/17 Fri 18/08/17 21 18/08
24 Design Workshops 3 days Mon 21/08/17 Wed 23/08/17 23 Dynamics 365 Consultant,Customer
25 Author High Level Solution Design 1 day Thu 24/08/17 Thu 24/08/17 24
26 Author Functional Design Document 1 day Fri 25/08/17 Fri 25/08/17 25 Dynamics 365 Consultant
27 Author Technical Design Document 1 day Tue 29/08/17 Tue 29/08/17 26
28 Milestone - Design documents issued to 0 days Tue 29/08/17 Tue 29/08/17 27 29/08
<customer>
29 Review Design documents 5 days Wed 30/08/17 Tue 05/09/17 28 Customer
30 Milestone - Design documents Approved 0 days Tue 05/09/17 Tue 05/09/17 29 05/09
31 Milestone - Discovery Phase Complete 0 days Tue 05/09/17 Tue 05/09/17 16,22 05/09
32 Development 45 days Tue 05/09/17 Tue 07/11/17 31
33 Dependency - Design documents Approved 0 days Tue 05/09/17 Tue 05/09/17 23,30 05/09
34 Build of agreed functionality 25 days Wed 06/09/17 Tue 10/10/17
35 Integration build 15 days Wed 11/10/17 Tue 31/10/17 34
36 System Testing 45 days Wed 06/09/17 Tue 07/11/17
37 Write System Test Scripts 10 days Wed 06/09/17 Tue 19/09/17 31
38 Execute System Testing 5 days Wed 01/11/17 Tue 07/11/17 37,34,35
39 Milestone - System Test Phase Completed 0 days Tue 07/11/17 Tue 07/11/17 38
40 Milestone - Development Phase Completed 0 days Tue 07/11/17 Tue 07/11/17 34,35,39

Task Project Summary Manual Task Start-only Deadline

Project: Example Dynamics Hig Split Inactive Task Duration-only Finish-only Progress
Date: Tue 15/08/17 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 1
ID Task Task Name Duration Start Finish Predecessors 07 Aug '17 14 Aug '17 21 Aug '17 28 Aug '17 04 Sep '17
Mode S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T
41 Deployment 82 days Wed 06/09/17 Fri 12/01/18
42 UAT 62 days Wed 06/09/17 Thu 30/11/17
43 Dependency - System Testing Phase Complete 0 days Tue 07/11/17 Tue 07/11/17 39
44 Dependency - UAT data imported 0 days Tue 14/11/17 Tue 14/11/17 62
45 UAT Scripts prepared by <customer> 10 days Wed 06/09/17 Tue 19/09/17 31
46 UAT Cycle 1 5 days Thu 16/11/17 Thu 23/11/17
47 Dependency - UAT Training competed 0 days Thu 16/11/17 Thu 16/11/17 56,43,45,39,44
48 UAT Execution 3 days Fri 17/11/17 Tue 21/11/17 47
49 UAT Issue Resolution 2 days Wed 22/11/17 Thu 23/11/17 48
50 UAT Cycle 2 5 days Fri 24/11/17 Thu 30/11/17
51 UAT Execution 3 days Fri 24/11/17 Tue 28/11/17 49
52 UAT Issue Resolution 2 days Wed 29/11/17 Thu 30/11/17 51
53 Milestone - UAT Phase Completed 0 days Thu 30/11/17 Thu 30/11/17 46,50
54 Training 30 days Wed 08/11/17 Tue 19/12/17
55 Preparation 5 days Wed 08/11/17 Tue 14/11/17 40
56 UAT Training 2 days Wed 15/11/17 Thu 16/11/17 55
57 Train the Trainer 3 days Fri 01/12/17 Tue 05/12/17 53
58 Training of end users 10 days Wed 06/12/17 Tue 19/12/17 57
59 Milestone - Training Phase Completed 0 days Tue 19/12/17 Tue 19/12/17 58
60 Data Migration 36 days Wed 01/11/17 Fri 05/01/18
61 Data Templates prepared 10 days Wed 01/11/17 Tue 14/11/17 34,35
62 Initial data load into UAT 5 days Wed 08/11/17 Tue 14/11/17 39
63 Production Data load 5 days Thu 14/12/17 Fri 05/01/18 67SF-1 day
64 Go-Live 7 days Tue 19/12/17 Fri 12/01/18
65 Dependency - UAT and Training Completed 0 days Tue 19/12/17 Tue 19/12/17 59
66 Go/No-Go meeting 1 day Thu 04/01/18 Thu 04/01/18 65
67 GO LIVE 0 days Fri 05/01/18 Fri 05/01/18 66FS+1 day
68 Go live and floor walking 5 days Mon 08/01/18 Fri 12/01/18 67
69 Operation 3 days Mon 15/01/18 Wed 17/01/18
70 Hand over to Support document 1 day Mon 15/01/18 Mon 15/01/18 68
71 Support Training 1 day Tue 16/01/18 Tue 16/01/18 70
72 Project Closure 1 day Wed 17/01/18 Wed 17/01/18 71
73 Milestone - Project Complete 0 days Wed 17/01/18 Wed 17/01/18 72

Task Project Summary Manual Task Start-only Deadline

Project: Example Dynamics Hig Split Inactive Task Duration-only Finish-only Progress
Date: Tue 15/08/17 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 2
11 Sep '17 18 Sep '17 25 Sep '17 02 Oct '17 09 Oct '17 16 Oct '17 23 Oct '17 30 Oct '17 06 Nov '17 13 Nov '17
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S

Customer
05/09
05/09

05/09
Dynamics 365 Consultant
Dynamics 365 Consultant

Dynamics 365 Consultant


Dynamics 365 Consultant
07/11
07/11

Task Project Summary Manual Task Start-only Deadline

Project: Example Dynamics Hig Split Inactive Task Duration-only Finish-only Progress
Date: Tue 15/08/17 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 3
11 Sep '17 18 Sep '17 25 Sep '17 02 Oct '17 09 Oct '17 16 Oct '17 23 Oct '17 30 Oct '17 06 Nov '17 13 Nov '17
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S

07/11
14/11
Customer

16/11

Dynamics 365 Con


Dynamics 3

Customer,Dynami
Dynamics 365 Con

Task Project Summary Manual Task Start-only Deadline

Project: Example Dynamics Hig Split Inactive Task Duration-only Finish-only Progress
Date: Tue 15/08/17 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 4
20 Nov '17 27 Nov '17 04 Dec '17 11 Dec '17 18 Dec '17 25 Dec '17 01 Jan '18 08 Jan '18 15 Jan '18 22 Jan '18 29 Jan '18
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M

Task Project Summary Manual Task Start-only Deadline

Project: Example Dynamics Hig Split Inactive Task Duration-only Finish-only Progress
Date: Tue 15/08/17 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 5
20 Nov '17 27 Nov '17 04 Dec '17 11 Dec '17 18 Dec '17 25 Dec '17 01 Jan '18 08 Jan '18 15 Jan '18 22 Jan '18 29 Jan '18
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M

16/11
Customer,Dynamics 365 Consultant
Dynamics 365 Consultant

Customer,Dynamics 365 Consultant


Dynamics 365 Consultant
30/11

Dynamics 365 Consultant


Dynamics 365 Consultant,Customer
Dynamics 365 Consultant,Customer
Customer
19/12

Customer,Dynamics 365 Consultant


Dynamics 365 Consultant,Customer
Customer,Dynamics 365 Consultant

19/12

05/01
Dynamics 365 Consultant

Dynamics 365 Consultant


Customer,Dynamics 365 Consultant
Customer,Dynamics 365 Consultant
17/01

Task Project Summary Manual Task Start-only Deadline

Project: Example Dynamics Hig Split Inactive Task Duration-only Finish-only Progress
Date: Tue 15/08/17 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 6

S-ar putea să vă placă și