DAFTAR ISI
A. INTRODUCTION……………….………………………………………………. 3
B. EQUIPMENT AND TOOLS………..…………………………………………… 3
C. METHOD OF WORKS ...………………………………………………..……… 3
Service Crane
Pontoon
Total Station
Generator Set
Crane Mat.
Others.
C. METHOD OF WORK
Rebar Fixing
After the installation of precast is done. Rebar instalment is needed for casting concrete.
Rebar position and distance shall be checked. This step is need to acquire the bond
strength needed and to meet the specification procedure.
Install Rebar
Casting Concrete
After precast installment and rebar installment is done, concrete can be casted.