Documente Academic
Documente Profesional
Documente Cultură
PLANT
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING
PLANT
EXECUTIVE SUMMARY
In this section forms of PGMs and gold are outlined together with their uses in all possible
industries. Markets of the final products are also identified, competition anticipated also
outlined. Availability of all raw materials required in the processing of PGMs is also put into
consideration in this section. In processing of PGMs there are many process routes which can
be used depending on a number of factors, for example the ore type. Therefore, alternative
process routes are outlined and then the most economic and efficient route is selected in this
section.
Material and safety data sheets are also outlined, a preliminary economic evaluation carried
out for the chosen process and lastly but not least site choice for facility is chosen.
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING
PLANT
SPECIFIC OBJECTIVES
To detail the uses of PGMs and their forms
To describe the markets and competition anticipated
To detail the availability of raw materials for the processing of PGMs
To describe all alternative process routes and select the best route for this plant
To perform a preliminary economic evaluation for the selected process route
To select an optimum site for the facility
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING
PLANT
TABLE OF CONTENTS
EXECUTIVE SUMMARY.........................................................................................................i
SPECIFIC OBJECTIVES..........................................................................................................ii
TABLE OF CONTENTS.......................................................................................................a
LIST OF FIGURES..................................................................................................................iii
LIST OF TABLES......................................................................................................................v
1.0 INTRODUCTION.......................................................................................................1
1.1 PLATINUM......................................................................................................................1
1.1.1 FORMS.....................................................................................................................1
1.1.2 PROPERTIES...........................................................................................................1
1.1.2 USES.........................................................................................................................2
1.2 PALLADIUM...................................................................................................................7
1.2.1 FORMS.....................................................................................................................7
1.2.2 PROPERTIES...........................................................................................................7
1.2.3 USES.........................................................................................................................8
1.3 RHODIUM.......................................................................................................................9
1.3.1 FORMS.....................................................................................................................9
1.4.1 FORMS...................................................................................................................11
1.4.2 PROPERTIES..........................................................................................................11
1.4.3 USES.......................................................................................................................11
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING
PLANT
1.5.1 FORMS...................................................................................................................12
1.5.2 PROPERTIES.............................................................................................................12
1.5.2 USES.......................................................................................................................12
1.6.1 FORMS...................................................................................................................14
1.6.2 PROPERTIES.........................................................................................................14
1.6.2 USES.......................................................................................................................14
1.7.1 FORMS...................................................................................................................14
1.7.2 USES.......................................................................................................................15
1.8.1 NICKEL..................................................................................................................18
1.8.2 COPPER..................................................................................................................18
1.9 CONCLUSION..............................................................................................................19
2.0 INTRODUCTION..........................................................................................................20
2.1.4 MIMOSA................................................................................................................24
2.1.5 ZIMPLATS..............................................................................................................24
2.1.6 UNKI.......................................................................................................................25
PLANT
2.2.1 RHODIUM..............................................................................................................27
2.2.2 PLATINUM.............................................................................................................31
2.2.3 PALLADIUM..........................................................................................................34
3.0 INTRODUCTION..........................................................................................................40
3.2 UTILITIES.....................................................................................................................45
3.2.1 WATER....................................................................................................................45
3.2.2 FUEL.......................................................................................................................46
3.2.3 REAGENTS............................................................................................................48
4.0 INTRODUCTION..........................................................................................................50
4.1.1 GEOLOGICAL.......................................................................................................51
4.1.2 MINERALOGICAL...............................................................................................51
4.1.3 METALLURGICAL...............................................................................................51
4.1.4 ENVIRONMENTAL..............................................................................................52
4.1.5 GEOGRAPHICAL..................................................................................................52
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING
PLANT
4.2.1 COMMUNITION...................................................................................................55
4.2.2 CLASSIFICATION.................................................................................................63
4.2.4 CONCENTRATION...............................................................................................64
4.2.6 SMELTING.............................................................................................................74
4.2.7 CONVERTING.......................................................................................................80
4.2.8 REFINING..............................................................................................................85
6.0 INTRODUCTION........................................................................................................153
PLANT
6.6.1 REVENUES..........................................................................................................163
6.6.2 MARGINS................................................................................................................164
6.6.3 PROFITS...............................................................................................................164
7.0 INTRODUCTION........................................................................................................170
PLANT
7.1.10 CLIMATE........................................................................................................174
8.0 REFERENCES.................................................................................................................180
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING
PLANT
LIST OF FIGURES
PLANT
Figure 22 The general possible configuration of the process routes is given below...............44
Figure 26 Single toggle jaw crusher and double toggle jaw crusher.......................................50
Figure 37 Separation process for treatment of the anode slime from the electrolysis of nickel
..................................................................................................................................................82
Figure 39 Separation Process where process steps are carried out on the same solution........85
PLANT
LIST OF TABLES
Table 1 Electricity supply from all Zimbabwe power stations.................................................37
1.0 INTRODUCTION
The platinum group metals (PGMs) are a family of six structurally and chemically similar
elements that are most valued for their wide range of industrial, medical, and electronic
applications. These versatile metals play a significant role in many of the products we use every
day.
1.1 PLATINUM
1.1.1 FORMS
Platinum has six naturally occurring isotopes: 190Pt, 192Pt, 194Pt, 195Pt, 196Pt, and 198Pt. The most
abundant of these is 195Pt, comprising 33.83% of all platinum. 190Pt is the least abundant at only
0.01%. Of the naturally occurring isotopes, only 190Pt is unstable, though it decays with a half-
life of 650×109years. 198Pt undergoes alpha decay, but because its half-life is estimated as being
greater than 320×1012 years, it is considered stable.
Platinum also has 31 synthetic isotopes ranging in atomic mass from 166 to 202, making the
total number of known isotopes 37. The least stable of these is 166Pt with a half-life of 300 µs,
while the most stable is 193Pt with a half-life of 50 years. Most of platinum's isotopes decay by
some combination of beta decay and alpha decay. 188Pt, 191Pt, and 193Pt decay primarily by
electron capture. 190Pt and 198Pt have double beta decay paths.
1.1.2 PROPERTIES
Platinum is a lustrous silvery-white, malleable and ductile metal. It has the third highest density,
behind osmium and iridium. It is unaffected by air and water, but will dissolve in hot aqua regia,
in hot concentrated phosphoric and sulphuric acids and in molten alkali. It is as resistant as gold
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING PLANT
to corrosion and tarnishing. It has a specific gravity of 21.4 at 20 degrees Celsius, melting point
of 1772 and boiling point of 3800 degrees Celsius.
1.1.2 USES
Platinum is one of the most valuable metals today because it is applied in many industries. It is
estimated that one-fifth of everything we use either contains platinum or requires platinum in its
manufacture.
Petroleum Industry
Beyond cleaning up our air, platinum's excellent catalytic properties also extend to another
important industry - the petroleum industry.
Platinum mesh or gauze is used in cracking processes in oil refineries. Platinum catalysts play a
critical role in extracting gasoline from crude oil and for making high octane fuels.
Jewelry
Platinum is a beautiful silvery-white metal, when pure, and is malleable and ductile. Its wear-
and tarnish-resistance characteristics are well suited for making fine jewelry. It provides a secure
setting for diamonds and other gemstones enhancing their brilliance. Platinum jewelry demand
was forecast to account for roughly 25% of total platinum demand in 2006 (down from 50% in
2000). High and volatile prices have adversely affected purchases of platinum across the major
regions.
Hard discs
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING PLANT
Platinum is used in the production of hard disk drive coatings and fiber optic cables. The
increasing number of personal computers will have a positive effect on platinum demand in the
future.
Hard drives contain one or more platters or disks where data is stored on magnetic surfaces. The
amount of data that can be recorded on a given surface depends very much on the strength of the
magnetic field generated by the surface layer.
Platinum is thus added to the cobalt alloy to enhance its magnetic properties allowing data to be
stored at higher densities.
With so much digital content being created (at higher and higher definitions) and then shared
online by millions of people over high speed broadband internet, the strong demand for higher
capacity disk drives has resulted in more platinum being used in the manufacture of hard disks to
enhance their storage capacity. The proportion of platinum in the magnetic alloy has gone up
from less than 10 percent in 2002 to 35 percent in 2007.
Electrical and Electronics
Platinum is used in the making of thermocouples that measure temperature in the glass, steel and
semiconductor industries or infra-red detectors for military and commercial applications. It is
also used in multi-layer ceramic capacitors and crucibles to grow single crystals.
Chemical
Platinum is used in fertilizers and explosives as a gauze for the catalytic conversion of ammonia
to nitric acid. It is also used in the fabrication of silicones for the aerospace, automotive and
construction sector.
In the fuel sector it is important as a petrol additive to enhance combustion and reduce engine
emissions. Moreover, it is a catalyst in the production of biodegradable elements for household
detergents.
Medicine
Cancer drugs & treatment
PGMs' help in the fight against cancer in two ways, as the active ingredient in chemotherapy
drugs and in radio-active implants for radiation therapy. In the first of these, platinum
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING PLANT
compounds cisplatin, carboplatin and oxaliplatin have the unique quality of inhibiting the
splitting and growth of cancerous cells.
These compounds have been particularly successful in the treatment of testicular and ovarian
cancers. More recently, palladium compounds have also been successfully tested. In radiation
therapy, implants are made of platinum with the active ingredient of iridium isotopes. These are
placed directly into tumours, giving a high radiation dose to the tumour while reducing the effect
on surrounding healthy tissue.
Dental
Palladium, and to a much lesser extent platinum, are the principal platinum group metals used in
dental restorations. The metals are usually mixed with gold or silver as well as copper and zinc
in varying ratios to produce alloys suitable for dental inlays, crowns and bridges. Small amounts
of ruthenium or iridium are sometimes added. The most common application is in crowns, where
the alloy forms the core onto which porcelain and other materials are bonded to build up an
artificial tooth. The aim of using PGMs in dental alloys is to provide strength, stiffness and
durability whilst the other alloyed metals provide malleability.
Implants
Platinum is used in aural implants that electrically stimulate the auditory nerve to replace
damaged or malfunctioning cochleas in those suffering from deafness. The electrical
conductivity, durability, biological compatibility and oxidation resistance of these PGMs make
them perfect for the electrodes in the implants. Also platinum can be found in retinal implants to
improve damaged or deteriorating eyesight.
Forensic staining
The science of forensics is most famous for its detection of fingerprints and, in more recent
times, the matching of DNA samples. Osmium tetroxide (the metal's most common form) is used
as a stain for fingerprints and DNA. It is relatively inert and does not harm the samples while
efficiently revealing fats by binding at double bonds of unsaturated lipids and imparting a dense
brownish or black colour.
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING PLANT
Fuel Cells
The most common type of fuel cell is the proton exchange membrane (PEM) fuel cell, which
contains platinum catalysts. Besides being used to power automobiles, PEM fuel cells can also
be used in power generation for buildings, instead of batteries or generators in portable
equipment.
Glass and other products manufacturing
Platinum is used in glassmaking equipment. It is used in the manufacturing of fiberglass
reinforced plastic and of glass for liquid crystal displays (LCD). In this context, some new
developments in the production of LCD glass and cathode ray tubes, both used in computer
screens should be mentioned.
A thermocouple consists of two wires of different metals joined together at one end to enable the
temperature of the joint between the two metals to be calculated. Platinum and platinum-
rhodium alloys are used for three high temperature standard grades of thermocouples.
Because of their hardness, high melting points and high temperature stability PGMs are the
perfect materials for industrial crucibles where high temperatures are necessary to produce
chemicals and synthetics with the utmost efficiency. The high temperature stability, melting
points and corrosion resistance of platinum, rhodium, and iridium and their alloys allow for
higher temperatures to be achieved in crucibles, a key factor in any chemical process. The
“nobility” of PGMs is also crucial. High purity conditions are required for these processes and
PGMs' high temperature stability means that they do not contaminate the products being
fabricated.
Aircraft turbines
Civilian air craft are primarily propelled by turbofan jet engines. Air is forced into the
combustion chamber by a series of fans and compressors, then mixed with fuel and ignited. The
gas temperature increases as the gas is compressed throughout the engine, and the efficiency of
the engine rises dependent on this gas temperature. Advances in technology have led to an
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING PLANT
increase in the operating temperature, meaning that the materials used have to withstand higher
and higher temperatures. In order to protect the blades from these extreme temperatures, internal
air cooling and coatings are used. Also, the blades must be protected against corrosion.
Platinum-aluminide coatings are a well-established technology to provide protection against
corrosion and their surface allows a further thermal barrier layer to be applied that protects the
blade from high temperatures.
1.2 PALLADIUM
1.2.1 FORMS
102
Naturally occurring palladium (Pd) is composed of six stable isotopes Pd, 104 Pd, 105 Pd, 106 Pd,
108
Pd, and 110 Pd. Two of these isotopes are theoretically unstable. The most stable radioisotopes
are107 Pd with a half-life of 6.5 million years, 103
Pd with a half-life of 17 days, and 100
Pd with a
half-life of 3.63 days. Twenty-three other radioisotopes have been characterized with atomic
weights ranging from 90.949 u (91 Pd) to 123.937 u (124 Pd). Most of these have half-lives that are
less than a half an hour except 101 Pd (half-life: 8.47 hours), 109 Pd (half-life: 13.7 hours), and 112
Pd (half-life: 21 hours).
1.2.2 PROPERTIES
Palladium is a lustrous silver-white metal. It has a face-centered cubic crystalline structure, at
ordinary temperatures it is strongly resistant to corrosion in air and to the action of acids. It is
attacked by hot acids, and it dissolves in aqua regia. It forms many compounds and several
complex salts. Palladium has a great ability to absorb hydrogen (up to 900 times its own
volume). It has a specific gravity of 11.9 at 20 degrees Celsius, a melting point and boiling point
of 1560 and 2927 degrees Celsius respectively.
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING PLANT
1.2.3 USES
Palladium is chemically stable and like platinum has excellent catalytic properties so it can
be used as a substitute for the more expensive platinum in catalytic converters.
Jewelry
Like platinum, palladium is ductile, malleable and unreactive thus it is also used in the
jewelry industry as a substitute for the more expensive platinum. It is silvery white therefore
is alloyed with gold yield the best white gold.
Membranes
Under suitable conditions (80 °C [176 °F] and 1 atmosphere), palladium absorbs more than
900 times its own volume of hydrogen. Since hydrogen passes rapidly through the metal at
high temperatures, heated palladium tubes impervious to other gases function as
semipermeable membranes and are used to pass hydrogen in and out of closed gas systems
or for hydrogen purification.
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING PLANT
1.3 RHODIUM
1.3.1 FORMS
Naturally occurring rhodium (Rh) is composed of only one stable isotope, 103 Rh. The most
stable radioisotopes are 101 Rh with a half-life of 3.3 years, 102 Rh with a half-life of 207 days,
and 99 Rh with a half-life of 16.1 days. Thirty other radioisotopes have been characterized
with atomic weights ranging from 88.949 u (89 Rh) to 121.943 u (122 Rh).
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING PLANT
Most of these have half-lives that are less than an hour except 100 Rh (half-life: 20.8 hours)
and 105 Rh (half-life: 35.36 hours).
There are also numerous Meta states with the most stable being 102m Rh (0.141 MeV) with a half-
life of about 3.7 years and 101mRh (0.157 MeV) with a half-life of 4.34.
The major use of rhodium is in catalytic converters for cars (80%). It reduces nitrogen oxides
in exhaust gases.
Catalyst
Rhodium is also used as catalysts in the chemical industry, for making nitric acid, acetic acid
and hydrogenation reactions.
Electrical
It is used as an electrical contact material as it has a low electrical resistance and is highly
resistant to corrosion.
Glass
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING PLANT
Rhodium is used to make glass due to its high melting point and temperature stability. Its
alloys are also used to coat mirrors and in headlight reflectors because they reflect light very
well.
Jewelry
Rhodium is lustrious and silvery white and is thus used to plate jewelry since it is also
tarnish resistant.
1.4.2 PROPERTIES
Iridium is a hard, brittle, lustrous, dense, transition metal of the platinum family. It is silvery-
white and it is notable for being the most corrosion resistant element known. It is unaffected by
air, water and acids. It has a specific gravity of 22.4 at 20 degrees Celsius, meting point of 2450
and boiling point of 4527 degrees Celsius.
1.4.3 USES
Compass bearings
Iridium was used in making the international standard kilogram, which is an alloy of 90%
platinum and 10% iridium
Electrical
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING PLANT
It is also used for the contacts in spark plugs because of its high melting point and low
reactivity.
Hardening agent
Equipment
Iridium is used in making crucibles and other equipment that is used at high temperatures.
Medicine
Radioactive isotopes of iridium are used in radiation therapy for the treatment of cancer. It is
also used in making retinal implants.
1.5.2 PROPERTIES
Although brittle, ruthenium is very hard and is a good alloying agent for platinum and
palladium. Like the other PGMs, it has a high melting point and superior catalytic properties.
Ruthenium is used in the electrical and electrochemical industries for its conductive properties
and durability.
1.5.2 USES
Electronics
Most is used in the electronics industry for chip resistors and electrical contacts.
Chemical
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING PLANT
Ruthenium oxide is used in the chemical industry to coat the anodes of electrochemical cells
for chlorine production. Ruthenium is also used in catalysts for ammonia and acetic acid
production.
Solar
Ruthenium compounds can be used in solar cells, which turn light energy into electrical
energy.
Jewelry
Hardening agent
Ruthenium is one of the most effective hardeners for platinum and palladium, and is alloyed
with these metals to make electrical contacts for severe wear resistance.
Medicine
Ruthenium-106 is used for medical purposes. When ruthenium-106 breaks down, it gives off
a form of radiation called beta rays. These beta rays act somewhat like X rays. They attack
and kill cancer cells. As an example, ruthenium-106 has been used to treat certain forms of
eye cancer.
Alloys
Ruthenium can also be alloyed with other metals. It is sometimes added to titanium to make
that metal more resistant to corrosion (rusting). Only 0.1 percent of ruthenium in titanium
makes titanium a hundred times more corrosion resistant.
Catalyst
Ruthenium is a versatile catalyst. It can be the catalyst to split hydrogen sulfide (H2S)
through light, using an aqueous suspension of cadmium sulfide (CdS) particles loaded with
ruthenium dioxide. This ability could help to remove of H 2S from oil refining and other
industrial processes.
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING PLANT
1.6.1 FORMS
Osmium has 34 isotopes whose half-lives are known, with mass numbers from 162 to 196. Of
187 188 190 192
these, five are stable: Os, Os, 189Os, Os and Os. Naturally the most common
isotope is 192Os, with an abundance of 40.1%.
1.6.2 PROPERTIES
1.6.2 USES
Medicine
An alloy of 90% platinum and 10% osmium is used in surgical implants such as pacemakers
and replacement heart valves.
Microscopy
Osmium tetroxide obtained from the powdered or spongy form of the metal, is used as a
stain for fatty tissue for microscope slides and in fingerprint detection.
Equipment
Because of its density, osmium is often alloyed with other precious metals to make products
such as instrument pivots, phonograph needles, and electrical contacts.
1.7.1 FORMS
The following are the types of gold ore:
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING PLANT
1. Free milling gold ores: These consist of the most profitable gold ores. Over 90% of the
gold can be recovered by conventional cyanidation. Ores of this nature are easily
crushed, washed and milled to recover the gold contained within it. Examples are quartz
rose ores and sugar quartz.
2. Refractory ores: These ores contain sulphides and organic carbon and entail lesser gold
recoveries, which at times can be as low as 50%. However, they are of significance since
free milling ores are too scarce in nature to meet the increasing demand of the gold. The
refractory ores are mainly comprised of sub microscopic gold deposits.
3. Preg-robbing ores- These are found in cyanide leached solution nature. Gold particles
get lost by absorption into fine-grained carbonaceous material present in the ore; an
example is chalcopyrite that is strongly preg-robbing.
4. Complex ores: These are extremely difficult to segregate from their natural source. An
example of a complex ore is a copper-rich gold ore.
1.7.2 USES
The uses of gold are:
1. Gold alloying: Gold is highly malleable and easy to manipulate, thus it forms alloys with
many metals and metalloids. Pure gold is too soft to withstand the stresses applied to
many jewellery items, hence alloying gold with other metals increases its durability. The
most important alloys are composed of elements of the same group in the periodic table
(Ag, Cu) and from neighboring groups (Ni, Pd, Pt less often Zn, Cd and Hg). Most of the
gold that is used to make jewellery is an alloy with one or more metals.
2. Investment bars (Financial Gold): Gold can be stored in a bars that are known as gold
bullion. In this form they are used as a way of financially backing a currency. The use of
gold bars keeps manufacturing costs to a minimum and allows convenient handling and
storage. Most central banks, officials and individuals hold investment in the convenient
form of bullion, this is because gold is a secure asset and it is indestructible. Gold is
universal and is often used in political or economic crises because it is valuable
throughout the world. Gross weight, gold content, the manufacturing firm and reference
number are stamped on the bars, to provide direct and binding information to their value.
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING PLANT
3. Jewellery: Properties of gold that make it suitable for manufacturing jewellery include
very high lustre, tarnish resistance, desired yellow colour, ability to be drawn into wires,
hammered into sheets or cast into shapes and corrosion resistance. It is used to
manufacture different types of jewellery such as wedding rings, bracelets, watches and
eye brow rings. Gold value of jewellery is determined by their gold content. In most
countries laws govern the terms used on designating the fineness of gold jewellery for
manufacturers and dealers.
4. Catalysts: Gold can be used as a catalyst because it can accelerate the rate of a chemical
reaction without being consumed. It is a proven material for use in catalytic convertors,
which reduce the toxicity of exhaust fumes, and plays a role in the production of a range
of chemicals such as paint and glue. New gold catalysts are currently being developed to
reduce impact of airborne and waterborne pollution. An interesting new use of gold
catalysts is that they are now being used to remove odours from public toilets in Japan.
5. Construction and aerospace industry: Gold’s reflective ability renders it suitable for
use in the construction and aerospace industries. Gold has been used in the construction
industry to adorn buildings because of its resistance to corrosion and it outlasts paint.
Cockpit windows are coated with a thin film of gold over them to reflect the harmful
effects of sun rays. Gold is also used in modern buildings as it helps retain heat in winter
and reflects it in summer. It is estimated that it cuts heating and cooling costs by 40%. On
estimation one ounce of gold will cover 1000 square feet of glass. In aerospace industry,
the craft’s reflective ability is improved by covering the space shuttle with a thin sheet of
gold. Astronauts protect their eyes by wearing gold sunglasses. Gold is used as a
lubricant between metal parts, in the vacuum of space, organic lubricants will volatise
and they will be broken down by the intense radiation beyond the Earth’s atmosphere.
Gold has very low shear strength and thin films of gold between critical parts serve as a
lubricant. Gold particles slide past over one another under frictional forces and that
provides a lubricating action.
6. Electronics: Gold is an indispensable component in electronics due to its ability to
conduct electricity. Gold is an undisputed material of choice to guarantee reliability in a
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING PLANT
7. Automotives: Gold is used in electronic components of cars. Crash sensors for air bags,
electronic fuel injectors, and anti-lock braking systems have gold connectors.
8. Medicine: Gold’s biocompatibility rarely has negative effects when placed in the human
body and resistance to infection makes it a suitable choice for sensitive implants such as
those in the inner ear or eyelids. Small amounts of gold are used to remedy a condition
known as Lagophthalmos, which is the inability of a person to close their eyes
completely. Small amounts of gold are implanted in the upper eyelid. The implanted gold
weighs down the eyelid and the force of gravity helps to keep the eyelid fully closed.
Gold-based drugs such as aurothioglucose have been developed to treat rheumatoid
arthritis. Particles of a radioactive gold isotope are implanted in tissues to serve as a
radiation source in the treatment of certain cancers. Radioactive gold is also used in
diagnosis. It is injected in a colloidal solution that can be tracked as a beta emitter as it
passes through the body. One of the latest uses of gold is drug-delivery microchips that
are injected or swallowed into the body. These chips contain drug-filled reservoirs that
are covered with thin gold membranes. Drugs are then released into the system at the
required time.
9. Dentistry: Materials that are used in prosthetic dentistry must meet a certain criteria:
i. They must be resistant to normal conditions in the mouth,
ii. They must be of a suitable colour,
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING PLANT
1.8.2 COPPER
Copper is a kind of non-ferrous metal which possesses excellent properties. Therefore, it is
widely used in electrical power, electronics, energy, petrochemicals, transportation, machinery,
metallurgy, light and other new industries.
Copper is used in electric power transmission to make wire and cable, transformers, switches,
plug components and connectors. In motor manufacturing, copper is used, for instance as a
stator, rotor, shaft head and hollow wire. Communication cables and residential electrical circuits
also uses a large quantity of copper wires.
Copper is used to make vacuum electronic devices such as high frequency and ultra-high
frequency tubes, crossing the catheter and magnetron. Copper printed circuits require a lot of
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING PLANT
copper foil and copper base brazing material. In integrated circuits, copper replaces aluminium
in silicon chips for interconnection and lead frames.
Heat exchangers in air conditioners, clock movements, gridding cloth of paper machines, copper
plate printing, fermentation tank lining, distillation pots and architectural decoration components
are all manufactured by using copper and its alloys
1.9 CONCLUSION
Uses of PGMs have increased in the last three decades and this trend is likely to continue as
society requires sophisticated and reliable materials. Due to its rarity and high price,
manufacturers are looking for substitutes to reduce amount of PGMs used in making jewellery
and electrical connections. The value and importance of gold will increase steadily overtime due
to growing demand, few substitutes and limited supply.
sustaining the economy of a nation and Zimbabwe is one country which is highly dependent on
its mining sector as the main pillar of the economy.
The aim of this document is the review of the local and global markets for rhodium, platinum,
palladium, gold, nickel and copper. This document also reviews the competition the product will
likely face when in the market.
The market of PGMs can be geographically categorized into local, regional and global markets.
The availability and the size of the market are dependent on the following main factors:
1. Demand (local, regional and international)
2. Price and quality (purity)
3. Rate of production (supply)
The trade and marketing of PGMs has been practiced for centuries and it has become mature and
well understood. The competition anticipated is mainly influenced by the following factors:
1. The design capacity
2. Country’s laws, regulations, codes and standards
3. Availability of raw materials
4. Product pricing and product quality
The PGMs market comprises two distinct market categories namely the physical PGMs market
and the paper PGMs market.
The price is greatly influenced by the demand and supply of the gold as well as the level of
purity. For each market there is an acceptable weight and level of purity usually authenticated by
a stamp of refining company.
The physical PGMs market operates on the principle of the actual transfer of PGMs. On this
market PGMs are traded as bullion as well as official and imitation jewelry and medallions of
high PGMs content. These act as the market instruments and standards for trade. The paper gold
market is conducted in form of claims of physical stocks of gold not the actual gold itself.
The only way to get increase the supply of PGMs is through mining. Supply will continue to
increase as long as mining companies are able to cost-effectively detect PGMs and remove it
from the earth, but the market will probably remain relatively stable for at least the next few
years as PGMs mining and processing companies plan for expansion.
There are no good estimates of the amount of PGMs left in the earth, because finding new
deposits requires a great deal of time and mines generally seek known reserves for only five to
ten-year production increments. Thus, it is safe to assume that, as long as economic profits do
not fall below zero due to increased extraction costs, gold mines have an opportunity to be
producing for centuries to come.
There are three broad categories which fuel the demand of PGMs: industry, investment and
jewelry as predicted below:
High-tech industries account to approximately 12% as PGMs have become a necessity in this
area. Given that PGMs have so many favorable elemental properties, such as its malleability,
ductility, non-corrosiveness, reflectivity, and conductibility, there are no good substitutes for it in
many applications. PGMs have become a necessity in the high-tech industries. In jewelry
manufacturing, PGMs have for millennia been the metal of choice, even in the face of substitutes
such as gold, silver, zinc, and copper.
Approximately 35% is used as a safe investment during periods of high inflation or when the
real rate of return on other investment vehicles is low. As an investment, PGMs are strong and
growing stronger, with recession afflicted investors looking to grow their savings by planting
them in non-perishable metals.
Overall, demand is not very elastic but varies by application, with areas such as dentistry seeing
more elasticity due to recent viable substitutes. The two most important countries driving the
demand for PGMs are India and China, and together they account for half of the PGMs
consumed in the past 2 years. India’s demand is driven mostly by jewelry while China’s is more
equally driven by the above mentioned three categories.
The demand is not expected to decline soon given that overall demand for PGMs is relatively
inelastic and that PGMs are increasingly used as a financial investment by governments and
private companies alike. Further it is interesting to note that, in our technological age that
increasingly requires PGMs for the production of electronics for the private sector, the military,
and personal consumption, it is likely that demand for gold will rise as time goes by.
If supply of PGMs is constrained and the demand increases the price of PGMs dramatically
rises. Closure of mines (due to rising costs and politics), not only are PGMs deposits rare, but
ones that are economically viable are like a diamond in the rough. That’s why it’s rare to hear of
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING PLANT
companies going into production and it’s clear that the supply of PGMs and PGMs deposits is
dwindling, while demand is rising. Factoring in these shifts into the supply and demand chart it
is inevitable that these pull factors will simply force the price of PGMs to move higher as supply
cannot keep up with demand.
Government has also introduced policies to increase PGMs capacity such as:
Currently there are no PGMs value addition industries like the jewelry industry and the
electronics industry in Zimbabwe. This means that all the PGMs produced in Zimbabwe are
either exported to other countries or serves as PGMs reserve for the government. Therefore the
sole driver of demand in Zimbabwe is the government through the Reserve Bank of Zimbabwe.
In light of the deficit cited above there is demand in Zimbabwe to satisfy the nation’s
requirement. The PGMs traded by miners in Zimbabwe is sold in its unrefined form.
Previously PGMS miners in Zimbabwe could independently export to South Africa. This had
been done to allow the miners to earn profit faster so as to step up production. However a lot of
the gold was and is still being sold on the informal market while some is being smuggled to
South Africa and other countries.
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING PLANT
2.1.4 MIMOSA
Zimbabwe's oldest platinum mine is the Mimosa operation, located in the southern part of the
Great Dyke on the Wedza Geological Complex. Ownership is currently split 50:50 between
Impala Platinum and Aquarius Platinum. Since 2002, output at Mimosa has gradually been
expanded, and the mine which has been among the lowest-cost platinum producers in the world
extracts around 100,000 oz of platinum annually.
2.1.5 ZIMPLATS
During the early 1990s, a second mine, the Hartley Platinum Project, was developed by a joint
venture between the Australian companies BHP and Delta Gold. It opened in 1995, but
following a string of geological and metallurgical problems, underground operations were
suspended in June 1999. BHP's interest in Hartley Platinum was sold to Zimbabwe Platinum
Mines (Zimplats), a spin-off of Delta Gold's platinum assets, which began to develop a new
open-cast mine further south, at Ngezi.
In 2011, Ngezi produced about 185,000 oz of platinum from a series of underground portals
(declines), and an expansion programme is underway which will see output rise to 270,000 oz of
platinum annually.
2.1.6 UNKI
A third platinum mine, Anglo American's Unki project, was commissioned in late 2010 and
produced around 50,000 oz of platinum in 2011. The mine is designed to extract and process
120,000 tonnes of ore per month, which should yield around 70,000 oz of platinum annually at
full capacity.
are sent to South Africa, Anglo Platinum and Aquarius Platinum for refining. About 7 500tonnes
and 6 000tonnes of nickel and copper respectively are also produced as by-products of PGM
refining.
The companies projected production period extending to between 2038 and 2055 depending on
reserves and resources and the estimated extraction rates. Capacity utilisation in 2013 for the
sector was more than 77 percent. The production of PGMs takes place in a few countries since
the reserves are found in a few countries that include South Africa, Russia and Zimbabwe,
among a few others, see Error: Reference source not found. South Africa has 88 percent of
known world reserves of PGMs followed by Zimbabwe and then Russia. Worldwide, there are
fewer than 10 PGM mining companies. Russia is the world’s largest source of palladium through
Norilsk. Norilsk was also reported to be a significant producer of platinum (13 percent) and
rhodium (11 percent), yielding 28 percent of the world’s PGM supply.
These comparative figures show that Zimbabwe’s production of platinum is very small
compared to South African production. However, Russian production of platinum, though
greater than Zimbabwe’s is comparable. Zimbabwe’s palladium is significantly lower than South
Africa and Russia’s production. This is despite the fact that Zimbabwe’s PGM reserves are
reported to be larger than Russia’s. Therefore Zimbabwe has the potential to overtake Russia in
production through expansion of mining operations as well as increasing processing capacity.
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING PLANT
concentrated supply with South Africa alone producing roughly 80% of the world's rhodium.
Prices are normally volatile. The metal once reached a price of $10,025 an ounce just before the
2008 financial crisis hit, but would drop 90% before the end of that year.
The price of rhodium is trading 32% up so far this year and has added nearly $400 an ounce
since hitting 12-year lows mid-2016. Rhodium (and sister metal ruthenium) stands out when it
comes to price swings.
80.00%
2.2.2 PLATINUM
Currently platinum is at $970 an ounce which means it has advanced 8% in 2017, with South
African being the largest platinum supplier, producing 69% of the world’s platinum.
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING PLANT
Ca na da 12.38%
Other Countri es
Rus s i a
South Afri ca
Uni ted States of Ameri ca
Zi mbabwe
69.52%
2.2.3 PALLADIUM
Two thirds of global palladium usage is attributed to catalytic converter production. Other areas
of application for palladium include electronics, jewellery, medical purposes, dentistry, hydrogen
purification, groundwater treatment and other chemical applications. Palladium is a key
constituent of fuel cells, which are used to convert chemical energy from fuel to electricity
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING PLANT
firms increasing buyer power. However use of long term contracts can impose switching costs
on buyers reducing their power slightly. Overall buyer power can be assessed as moderate.
The threat of substitute in the PGMs industry is assessed as weak and will not have a significant
effect on short term profits but may have increase in the future, which may be fueled by
ecological concerns and limited ore resources.
1. PGM ore
2. Utilities
3. Processing Chemicals
The Great Dyke is a geological feature running through the heart of Zimbabwe for about 550
kilometers in a roughly north-south direction. The PGM occur in a layer known as the Main
Sulphide Zone, which is typically about 3 meters thick. However, the economic mining width
may be as little as one meter, depending on grade, metal prices and the chosen mining method.
The PGM content is lower than that of South African ores, with head grades generally below 4
grams per tonne, of which about 55 per cent is platinum. Nickel and copper values are typically
higher than those found in South African platinum ores.
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING PLANT
3.1.1.3 BRAGGITE
Braggite is a sulphide mineral of platinum, palladium and nickel with chemical formula: (Pt, Pd,
Ni) S. It is a dense (specific gravity of 10), steel grey, opaque mineral which crystallizes in the
tetragonal crystal system.
The braggite composition series is between the platinum rich cooperite and palladium rich
vysotskite end members in solid solution and is thus considered of primary economic importance
as an ore for both of these precious metals. Braggite, as well as vysotskite, was named prior to
knowledge of phase relations in the Pt-Pd-S System and prior to the extensive microprobe
analyses now available. Using electron probe analyses the average proportions for metal in the
sulphide structure were determined to be 64 percent Pt, 27 percent Pd, and 14 percent Ni. When
based on the unit cell content, this approximates to Pt5Pd2NiS8.
Braggite appears steel grey to silvery white to the naked eye. When viewed through a
petrographic microscope, under plane polarized light, braggite is white and slightly bireflectant
and lacks reflectance pleochroism. Observing between crossed polar, its anisotropy is distinct in
air and is characterized by a purplish-grey to brown-grey tint. Relatively large crystals (up to 8
mm long) are not unusual for braggite and fracturing is common. Braggite has a measured
specific gravity of 10 and calculated specific gravity of 9.383.
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING PLANT
3.2 UTILITIES
3.2.1 WATER
Water is essential to mineral processing. It is used in various steps in the process to recover
valuable metals from ore. The water use is quite high – for example, around 1600 litres of water
are used to obtain the 19 kilograms of platinum found in a medium-sized plant.
Water is not always readily available for processing operations. In many locations where mining
operations occur, such as in remote areas, water is a scarce resource. Even in environments
where water is readily accessible, making that water suitable for use in the ore refining process,
such as through desalination, can add significant costs and increase energy use. As ore grades
decline the amount of water required increases because more intensive processing is required.
The industry, particularly in Africa, is increasingly mining lower-grade ores and interest in
reducing water use is high.
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING PLANT
3.2.2 FUEL
Fuel is mainly used for PGM smelting which is a pyro metallurgical process. All PGMs would
have melted at 3050ºC. Smelting uses heat and a chemical reducing agent to decompose the ore,
driving off other elements as gases or slag and leaving the metal base behind. The reducing agent
is commonly a source of carbon, such as coke—or, in earlier times, charcoal. The commonly
used fuel for smelting is diesel because of its high calorific value and its availability.
The table below shows electricity supply from all Zimbabwe power stations:
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING PLANT
Availability
The power supply in Zimbabwe is sourced from local generation and imports. The domestic
generation comes from Kariba Hydropower, Hwange coal-fired Power Station, and three small
thermal power plants Harare, Munyati and Bulawayo Power Stations. Supplementary power is
imported from Mozambique, Democratic Republic of Congo (DRC), and Zambia. The
Zimbabwe Electricity Transmission and Distribution Company (ZETDC) is responsible for
transmitting, distributing and selling electric power, including meter reading, billing, cash
collection, and credit control of the retail business.
It is also responsible for regional trade in power. In addition to these government entities, a
number of independent private producers (IPPs) are active in power generation in Zimbabwe.
ZETDC is responsible for the development, operation, and maintenance of the transmission and
distribution network in Zimbabwe. The transmission system is made up of 420kV, 330kV,
220kV, 132kV, 88kV and 66kV lines and substations. (AFDB, 2012) ZETDC charges US
9.83c/KWhr, a far much lower figure as compared to the regional tariff of US 14c/KWhr.
(Official ZESA website, 2014).
Energy provision has however been non consistent from the National Grid. Reliable energy
capacity is a low 1320 MW, installed capacity is 1900 MW against a national demand of
2200MW.
This was mainly caused by breakdowns at the main power generation utilities, and the economic
downturn of 2000-2012 that caused a slump in the provision capacity of the national utility.
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING PLANT
Renewable sources of energy generation do however offer sustainable solutions to emergent new
facilities.
3.2.3 REAGENTS
In the processing of PGMs, various chemicals or reagents will be required to enable the
extraction process such as flotation and leaching. As such, these chemicals must be readily
available. The chemicals required for PGMs processing are readily available in Zimbabwe and
the following is a list of some of the suppliers in Zimbabwe:
1. Ricnob Suppliers
2. Efe Mining Chemicals (Harare)
3. Chemplex
4. Acol Chemicals
5. Curechem (Harare)
6. CPS Africa (Pvt) Ltd (Harare)
The main purpose of a frother is to stabilize bubble formation which happens in the pulp phase,
to create reasonably stable froth. This is important to:
Ensure that while froth is on the surface of the flotation cell, drainage of entrained
material can occur.
Ensure bubbles do not burst before they have reached the concentrate launder.
The stability of the froth phase is critical to flotation performance. When a bubble bursts, it
drops the mineral particle back into the pulp. It is said, that once the mineral particles have been
attached, then dropped again, the chances of it being re-floated is extremely low.
Depressants
Depressant is a modifier which has the main purpose of reducing the floatability of a mineral.
This is done by:
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING PLANT
The main unwanted mineral like Talc (magnesium silicate hydroxide), which is a naturally
hydrophobic substance. It occurs in unusually high quantities in ores from the Great Dyke, and is
very problematic as it:
effectiveness by employing the most appropriate technology. For PGM extraction, this procedure
has two major objectives namely:
Development of a process that satisfies the entirety of the project’s requirements, and this
includes environmental and political considerations.
Process selection is affected by various factors. The chemical response of the particular PGMs
ore in the available process options is a key parameter in attaining these objectives.
i. Geological
ii. Mineralogical
iii. Metallurgical
iv. Environmental
v. Geographical
vi. Economic and Political
4.1.1 GEOLOGICAL
The grade and size of reserves of economic minerals in an ore body define the type and scale of
processing technology that can be employed. Low-grade ores (<0.5 to 1.5 g/t PGMs that is Pt, Ir,
Rh) require low-cost treatment such as heap and dump leaching.
High-grade ores (>1.5 g/t PGMs) require higher-cost processes such as grinding, leaching, and
carbon in-pulp (CIP).
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING PLANT
The additional processing costs are offset by the higher sales revenue of PGMs. Complex
carbonaceous refractory and sulphidic ores justify additional cost incurred in the use oxidative
pre-treatment due to their high-grade. Economies of scale may be utilized in processing low-
grade ores using the higher-cost processes. The cut-off grade applied to a particular extraction
process is a function of metallurgical response of the individual ore, processing costs, capacity,
and also the grades and reserves of other minerals of potential economic interest for example
copper, uranium and silver. The geometry of an ore body dictates the mining method. Variations
in ore properties (hardness, mineral composition, degree of fracturing and clay content) affect
the process selection.
4.1.2 MINERALOGICAL
The mineralogical properties determined from ore composition and textural properties are used
to indicate process options and the subsequent environmental impact of each process. The
quality of mineralogical information needed for process selection is governed by the type and
variability of the ore body. Ores with simple mineralogy or similar mineralogical and geological
properties to those of well-understood deposits require less rigorous analysis than those with
complex or unknown mineralogy. Nevertheless, small variations in mineralogy can greatly affect
process selection and overall process economics.
4.1.3 METALLURGICAL
The metallurgical response of an ore to the process scheme determines the process economics.
The major factors to be considered are:
Test work done on the ore, together with process design data, mineralogical information and
operating experience from similar operations are used to select the optimum process.
4.1.4 ENVIRONMENTAL
An assessment must be done on each unit process to determine the impact on water quality, air
quality, land degradation, visual impact, noise, flora and fauna, rare and endangered species,
cultural resources, sustainable and social development. Methods of dealing with the waste or
emissions from the process must also be developed and these must be able to bring emissions to
acceptable levels as the determined by EMA.
4.1.5 GEOGRAPHICAL
Location of ore body and the proposed treatment facility affect process selection. The major
factors to consider are:
Figure 20 below have various options for combining them into a complete g extraction process.
The choice of process route is a function of the nature of the gold ore, its chemical and physical
properties.
The unit operations given in Table 2 above have various options for combining them into a
complete PGMs extraction process. The choice of process route is a function of the nature of the
PGMs ore, its chemical and physical properties. The general possible configuration of the
process routes is given below:
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING PLANT
Figure 22 The general possible configuration of the process routes is given below
4.2.1 COMMUNITION
Comminution is the size reduction of the ore in order to liberate the mineral that is dispersed
within the unwanted material (gangue). Comminution is done to liberate PGMs, gold-bearing
minerals and other metals of economic value to make them amenable to subsequent PGMs
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING PLANT
extraction stages. Comminution facilitates handling of materials between stages. The degree of
comminution depends on the following factors:
The optimum particle size achieved is a balance between PGMs recovery and processing costs
(reaction kinetics and consumptions of chemical reagents), and comminution cost for a particular
comminution method. Comminution is carried out in two broad stages which are crushing and
grinding. Under crushing, we have primary, secondary and tertiary crushing. Grinding has both
primary and secondary stages. Size reduction can be done concurrently with other chemical
extraction methods like leaching. Comminution is accomplished through two methods, namely,
the conventional method and Autogenous/ Semi-autogenous (AG/SAG) method. Both methods
can be used in PGMs processing.
i. A change in hardness of the ore has less effect on ore breakage, than for AG/SAG mills.
ii. A change in feed size distribution has less effect on ore breakage, than for AG/SAG
mills.
iii. Power draw is stable.
iv. Bench scale grinding tests are enough to use to select the size reduction equipment.
v. Grinding rods/ balls are easily obtained in required sizes and their actions during milling
can be easily predicted.
Disadvantages:
Advantages:
Disadvantages:
From this discussion, considering the large expense incurred in doing the extensive test works in
order to establish the right AG/SAG process, it is more economical to select the conventional
way of comminution. A critical factor to consider in comminution with chemical extraction is
mineral surface preparation.
4.2.1.3 CRUSHING
Crushing is the first mechanical stage in the process of comminution in which the main objective
is the liberation of the valuable minerals from the gangue. An open circuit or a closed circuit can
be employed in crushing of PGMs ROM.
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING PLANT
Primary crushers are heavy-duty machines, used to reduce the run-of-mine ore down to a size
suitable for transport and for feeding the secondary crushers or AG/SAG mills. They are always
operated in open circuit, with or without heavy-duty scalping screens (grizzlies). There are two
main types of primary crusher in metalliferous operations - jaw and gyratory crushers- although
the impact crusher has limited use as a primary crusher and will be considered separately.
The following factors all have a more or less important bearing upon the choice of the primary
crusher.
JAW CRUSHER
Jaw crushers are used for primary crushing of a wide variety of materials in the mining, iron and
steel and pit and quarry industries. Furthermore they are used in recycling processes. There are
various different types of jaw crushers used within the industry. The more commonly used types
are: Blake (Double Toggle), Overhead Pivot (Double Toggle) Similar applications to Blake and
Overhead Eccentric (Single Toggle).
Figure 26 Single toggle jaw crusher and double toggle jaw crusher
Advantages
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING PLANT
GYRATORY CRUSHER
The gyratory is popular due to its high throughput capacity (up to ~10,000 tph possible) and the
large sized opening. This means the crusher is well suited to handling direct feed from haul
trucks, with minimal fuss. When required throughput’s are around 700 tph or greater, essentially
a gyratory must be used. Feeding directly into the crushing chamber eliminates the need for bins
and feeders before the gyratory. Oversize rocks can be broken with a rock breaker within the
chamber itself.
SECONDARY CRUSHING
In mineral processing, it is assumed, for the present purpose that intermediate crushing is not
necessary and that the run-of-mine or quarried mineral has, in one pass, been reduced in size so
that all is below say 6-in. ring size.
From this stage forward the utilization of the product assumes primary importance. For example,
if the economic mineral is wolfram or scheelite, necessitating separation from the matrix by
hydro-gravity separation, the further size reduction must be effected with the aim of minimizing
the production of ‘fines’, whereas if flotation separation is to be used no such consideration
applies. Similarly, in the production of road-surfacing aggregate the shape of the secondary
crushed product is important and here particles approaching cubic shape are preferable.
Prior to secondary crushing it is important and desirable to remove the fines already below the
set of the crusher.
Run-of-mine and quarry product when accepted into the plant comprises rock of varying sizes
some of which is below the primary crusher open setting, but its removal from the crusher feed
at this stage is not important as in secondary crushing where the feed is of a shorter range and
hence packing by fines more serious.
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING PLANT
It is desirable to remove undersize material from the crushing unit for a number of reasons:
power has been expended in effecting its size reduction; its presence in the crushing unit and the
packing of the voids between the uncrushed oversize not only reduces throughput but results in
increased wear and higher power costs. If, in addition, the fines are of an argillaceous character
the presence of such in the crusher will prove to be an intolerable nuisance.
4.2.1.3.2 GRINDING
Grinding is the last stage in the process of comminution; in this stage the particles are reduced in
size by a combination of impact and abrasion, either dry or in suspension in water. According to
the ways by which motion is imparted to the charge, grinding mills are generally classified into
two types: tumbling mills and stirred mills.
The choice of mill design depends on the particle size distribution in the feed and in the product
wanted. Often the grinding is more economic when executed in a primary step, followed by a
secondary step, giving a fine size product.
Ball mills
The final stages of comminution are performed in tumbling mills using steel balls as the grinding
medium and so designated “ball mills” Since balls have a greater surface area per unit weight
than rods, they are better suited for fine finishing. The term ball mill is restricted to those having
a length to diameter ratio of 1.5 to 1 and less. Ball mills in which the length to diameter ratio is
between 3 and 5 are designated tube mills. These are sometimes divided into several longitudinal
compartments, each having a different charge composition; the charges can be steel balls or rods,
or pebbles, and they are often used dry to grind cement clinker, gypsum, and phosphate.
Closed circuit grinding consists of one or more mills discharging ground product to classifiers
which in turn return the coarse product from the size separation back to the mill for further
grinding.
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING PLANT
Although closed circuit grinding offers many choices for arrangement of the equipment as well
as combinations of equipment, some of the more common circuits are rod mill/classifier, Ball
mill/Classifier, Rod mill/Ball mill/Classifier and Rod mill/Classifier/Ball mill/Classifier.
4.2.2 CLASSIFICATION
Classification is the separation of mixtures of minerals into two or more products based on the
velocity with which the mineral grains fall through a fluid medium. The velocity of the mineral
particles is a function of density, size and shape of the particles. In PGMs extraction, a
combination of cyclones and screens are used within grinding circuits to optimize grinding
efficiency and to obtain the desired particle size for subsequent processing.
Advantages:
Disadvantages:
i. Require the use of water in addition to the water already present in the pulp.
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING PLANT
4.2.4 CONCENTRATION
Ore concentration during is usually done prior to extractive metallurgy and is required because
platinum ores contain only 3–4 g/tonne of the PGM minerals which is too low for processing as
is. Heating, melting and leaching of the huge amounts of waste rock in ore would require far too
much energy and equipment of great capacity. The techniques which can be applied in the
concentration of PGMs are:
gravity concentration
froth flotation
magnetic separation
DMS
The resulting concentrates are treated by direct smelting, converting, flotation, or intensive
leaching, depending on their mineralogy.
H −F
Concentration criterion =
L−F
Where:
If the concentration criterion is more than 2.5 then separation would be relatively easy.
Centrifugal separation technologies available are Knelson and Falcon concentrators. Gravity
concentration is useful when there is significant coarse PGMs present (>250 µm) that is more
difficult to recover effectively by flotation. Combining gravity concentration and flotation is
effective for ores containing a wide PGMs size distribution.
Advantages:
Disadvantages:
i. It cannot be employed to separate valuable mineral and gangue if the densities are almost
equal.
Flotation reagents
Collectors – These bind to the surface of the particles. They are organic compounds
which render the selected minerals water repellent by adsorption of molecules or ions
onto the mineral surface, reducing the stability of the hydrated layer separating the
mineral surface from the air bubble to such a level that attachment of the particle to the
bubble can be made on contact.
Frothers – These are added to stabilize bubble formation in the pulp phase, to form a
reasonably stable froth to allow selective drainage from the froth of entrained gangue and
to increase flotation kinetics.
Regulators – These are used to modify the action of the collectors either by intensifying
or by reducing its water repellent effect on the mineral surface. They can be classified as
activators, depressants or pH modifiers.
Advantages:
i. PGMs values are liberated at a fairly coarse particle size (28 mesh) hence ore grinding
costs are minimized.
ii. Froth flotation reagents are generally not toxic.
iii. Tailings disposal costs are low due to the non-toxicity of the chemical reagents used.
iv. Can easily separate PGMs in association with minerals like copper, cobalt or gold.
Disadvantages:
Magnetic separators exploit the difference in magnetic properties between the ore minerals and
are used to separate either valuable minerals from non-magnetic gangue. Low and high intensity
magnets are used to separate magnetic material from nonmagnetic material. Separation can be
operated wet or dry. This type of separation is usually done on the Upper Group 2 Reef which is
the chromite ore.
The comminuted ore is subjected to magnetic separation in order to separate the magnetic
chromite particles from the nonmagnetic gangue particles which contain a substantial portion of
the platinum group metals in the ore.
In the wet high intensity magnetic separation process a thoroughly mixed slurry of the
comminuted ore and water is subjected to a magnetic flux while the slurry is passing through a
vessel containing metallic media such as grooved plates, steel wool or balls shaped to intensify
the magnetic flux perpendicular to the flow direction of the slurry. The magnetic particles,
chromite, are retained on the media and the nonmagnetic gangue particles pass through the
vessel. Intermittently the flow of slurry to the vessel is stopped, the magnetic material adhering
to the media is washed to remove entrained non-magnetics and weakly magnetic particles and
then the magnetic field is removed, permitting the magnetic particles to be washed from the
media. The magnetic field is restored and the slurry is again passed through the vessel in the
same series of steps. This intermittent cycle is conveniently automated by fabricating the vessels
as annular segments of a ring which rotates continuously perpendicular to fixed electromagnets
located around the periphery of the ring.
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING PLANT
Principle of DMS
Most of the liquids used in laboratory tests are either expensive or toxic thus dense medium used
in industrial separations is a thick suspension, or pulp of some heavy solid in water, which
behaves as a heavy liquid.
DMS vessels
Several types of vessels are in use and these may be classified as gravitational and centrifugal
vessels.
Gravitational vessels
Gravitational units comprise some form of vessel into which the feed and medium are
introduced and the floats are removed by paddles or merely by overflow. Removal of the sinks is
the most difficult part of the separator design. The aim is to discharge the sink particles without
removing sufficient medium to cause disturbing downward currents in the vessel.
Centrifugal vessels
These provide high centrifugal force and a low viscosity in the medium, enabling much finer
separations to be achieved than in gravitational separators.
Feed to these devices is typically de-slimed at about 0.5mm to avoid contamination of the
medium with slimes and to minimise medium consumption. A finer medium is required than
with gravitational vessels to avoid medium instability. The mostly used centrifugal DM separator
is a cyclone.
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING PLANT
Ability to make sharp separations at any required density, with a high degree of
efficiency even in the presence of high percentages of near-density material.
The density of separation can be closely controlled.
The separation density can be changed at will, and fairly quickly, to meet varying
requirements.
Applicable to any ore after a certain degree of liberation of the mineral.
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING PLANT
Disadvantages of DMS
Process is expensive due to the ancillary equipment used to clean the medium and the
cost of the medium itself.
Particles should be larger than 4mm and separation of particles that are less than 500µm
requires the use of a centrifuge.
7. Separation efficiency – The chosen technology should have a high separation efficiency.
High separation efficiency means less cost incurred in recovering PGMs lost to the
tailings. Also, efficient separation reduces the amount of revenue in circulation through
recycling of streams through concentration circuit.
8. Energy requirements – A technology that is less energy intensive is desirable.
9. Maintenance costs – Maintenance costs of the machinery should be low.
10. Skills requirements – The chosen technology should have equipment that is relatively
easy to operate and fix so as to reduce labour costs.
From the KT analysis above the best concentration method to use on PGM ore concentration is
froth flotation.
The concentrate is dried in a spray drier or flash drier. This reduces the energy requirement for
smelting, as well as decreasing the occurrence of ‘blowbacks’ or explosions in the furnace. The
dry concentrate is transferred pneumatically from the drier into the furnace.
Pyrometallurgy
Pyrometallurgy, extraction and purification of metals by processes involving the application of
heat. The most important operations are roasting, smelting, and refining.
Roasting, or heating in air without fusion, transforms sulfide ores into oxides, the sulfur escaping
as sulfur dioxide, a gas. Smelting is the process used in furnaces to reduce mineral ores.
Advantages
There are several natural advantages that Pyrometallurgy has in the processing of ores:
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING PLANT
At high temperatures, reactions are much faster than they are in slurries or in aqueous
solutions. This equates to lower capital costs.
Mineral characteristics are lost in melts, making the reactions controllable by known
universal thermodynamic and kinetic laws. Bench-top planning and verification is
possible.
In sulphide systems the energy release of oxidation to SO2 can be utilised instead of
carbon emission. SO2 is easier to dispose of safely than CO2
Realization of the values in ores by high temperature routes are well above those
experienced in mineral separation/leach routes.
4.2.6 SMELTING
Smelting is a process of applying heat to ore to melt out a base metal. It is a form of extractive
metallurgy. It is used to extract many metals from their ores, including silver, iron, copper,
PGMs and other base metals.
Smelting uses heat and a chemical reducing agent to decompose the ore, driving off other
elements as gases or slag and leaving the metal base behind. The reducing agent is commonly a
source of carbon, such as coke or, in earlier times, charcoal.
The carbon (in form of carbon monoxide) removes oxygen from the ore, leaving the elemental
metal. The carbon thus oxidizes in two stages, producing first carbon monoxide and then carbon
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING PLANT
dioxide. As most ores are impure, it is often necessary to use flux, such as limestone, to remove
the accompanying rock gangue as slag.
In PGMs, smelting separates the gangue (oxide and silicate) minerals from the sulphide minerals
associated with the noble metals. The sulphide minerals form a matte that is treated further; the
gangue is discarded as slag. As the concentrate melts, two liquid phases form: a lighter silicate-
and iron-rich slag with a relative density around 2.7 to 3.3, and a denser molten matte (rich in
nickel and copper sulphides, and other base and precious metals) with a relative density of about
4.8 to 5.3.
Smelting typically takes place at temperatures around 1350ºC, although smelting of some
concentrates require temperatures in the region of 1600ºC or higher.
Because of the low concentration of valuable minerals in the concentrate, the PGMs smelting
furnace is operated at a high slag: matte ratio (between about 4 and 9). These two phases are
tapped separately from the furnace (from opposite ends, in the case of a rectangular furnace).
The unwanted slag constituents are discarded (usually after being subjected to granulation using
a high-flow water stream, milling, and flotation to re-capture any entrained droplets of matte).
The furnace matte contains nickel, copper, cobalt, iron, sulphur, and the PGMs. The furnace
matte is tapped into ladles and transferred by crane to a converter vessel.
The furnaces are normally operated with a ‘black top’, i.e. with a layer of unsmelted concentrate
on top of the molten bath. This limits the amount of radiation from the surface of the bath to the
walls and roof of the furnace. In one documented case (19), a 15 cm layer of concentrate covers
a 100 cm layer of slag, which in turn covers a 58 cm layer of matte.
1. Relative cost of heat from electric power and heat from coke.
3. Improvement in milling practices, especially differential flotation, and its bearing on use
of electric furnaces.
FURNACE OPERATIONS
The electric arc furnace operates as a batch melting process producing batches of molten PGMs
concentrate. The electric arc furnace operating cycle is called the tap-to-tap cycle and is made up
of the following operations:
Furnace charging
Melting
Refining
De-slagging
Tapping
Furnace turn-around
Off-gas handling
It used to be common practice for furnace exhaust gases to pass through an electrostatic
precipitator and then to be discharged to the atmosphere through a tall stack. The SO 2 in the gas
can be used in the production of sulphuric acid, but the low concentration produced from the
furnaces, and the intermittent production from the converters makes this challenging.
Environmental issues
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING PLANT
Although the modern electric arc furnace is a highly efficient furnace, operation of an arc
furnace shop can have adverse environmental effects. Much of the capital cost of a new
installation will be devoted to systems intended to reduce these effects, which include:
One of the benefits is flexibility: while blast furnaces cannot vary their production by
much and can remain in operation for years at a time, EAFs can be rapidly started and
stopped, allowing the PGMs mill to vary production according to demand.
As EAFs require large amounts of electrical power, many companies schedule their
operations to take advantage of off peak electricity pricing.
Rectangular six-in-line submerged-arc electric furnaces are the most widely used in PGM
processing, although there are also some circular three-electrode furnaces in operation. (Steve
Cole, 2003). The rectangular furnace is in effect a flexible box of bricks provided with spring-
loaded walls to allow for movement of the bricks with temperature changes.
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING PLANT
In the six-electrode furnace, each adjacent pair of electrodes is fed from its own
transformer and may thus be operated, if required, at voltages and currents very different
from those in the other electrode pairs. This can be a very useful feature in a long
rectangular matte smelter where molten-slag conditions may vary considerably over the
length of the furnace.
Environmentally cleaner than the Revebaratory and Blast furnace
More energy efficient
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING PLANT
Rectangular shape has ‘dead zones’ in corners, but binding systems easier to make
The emission of SO2 (sulphur dioxide) from furnaces and converters is hard to avoid
when using a sulphur-based matte-smelting process
PGM smelting in Southern Africa takes place exclusively in electric furnaces at present.
Rectangular six-in-line submerged-arc electric furnaces are the most widely used, although there
are also some circular three-electrode furnaces in operation.
Environmentally cleaner. No fuel is burnt in the furnace, hence the volume of waste gas
and the quantity of flue dust is small. The off-gas contains mainly sulphur oxides, and
carbon oxides (from electrodes).
4.2.7 CONVERTING
Converting has traditionally been accomplished in Pierce-Smith converters to oxidize the matte.
Flash furnace technology can also be used but recently the Ausmelt process has been used to
convert the furnace mattes. The conversion process involves the injection of air, enriched air or
oxygen in the matte in order for selective oxidation according to the affinity for oxygen.
Hot matte transfer is a requirement for the converters and they are limited in their ability
to process cold revert material.
The converters are poorly sealed, leading to fugitive SO2 and fume emissions. It leaks
SO2-bearing gas into the workplace during charging and pouring causing hygiene and
environmental issues.
Due to the intense, localised reaction zone, high energy efficiency is obtained and the physical
size of the plant is relatively small compared to that of most competing technologies. Capital
cost can thereby be minimised.
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING PLANT
The furnace is well enclosed, such that fugitive emissions and ingress of diluting air to the gas
stream are both minimised. The oxygen potential in the slag can be varied over a wide range
such that the system can be applied in both oxidizing and reducing duties.
Matte may be converted continuously in an Ausmelt furnace, which is a top bottom blown
reactor where oxygen (enriched air), fuel and other fossil combustibles are directly inserted via a
lance in the molten or melting charge.
The Ausmelt process produces a continuous off-gas stream with a high sulphur dioxide content
that can be treated at the acid plant.
A single Ausmelt furnace may be capable of treating the same tonnage of matte as a
series of PS converters.
Refractory life should be better than in a Peirce- Smith converter. Even in small Ausmelt
units involving high temperatures and multiple semi-batch processes, refractory life of
about 5 months has been demonstrated in normal operation.
The conventional converter aisle and overhead gantry cranes could in theory be eliminated, if
molten transfer is no longer required.
The waste gas from an Ausmelt converter will probably contain greater than 10% sulphur
dioxide by volume at a temperature of about 1300oC. The potential exists to produce more
sulphuric acid than can be achieved using Peirce- Smith converters, because of the greatly
reduced dilution with cold air.
Tuyères are used to introduce air into the converter. Severe refractory wear occurs along
the line of the tuyères, necessitating the replacement of at least this portion of the brick
lining after only a few months.
The converting operation is highly exothermic. It is therefore necessary to add cold solid
material to the converter (reverts and flux), to remove as much heat as possible in waste
gas, and to interrupt the converting operation periodically in order to keep the
temperature down.
Limitations of the conventional smelting and converting processes (Jones, 1999) include:
SO2 emissions from the converting process are a continuing environmental concern.
Intermittent operation of the converters makes handling of the off-gas in a sulphuric acid
plant difficult.
If ores with low sulphide contents are processed, additional base metal concentrates need
to be purchased to provide sufficient matte to allow for effective coalescence of the
droplets and collection of valuable metals.
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING PLANT
To meet SO2 dispersion criteria in some parts of the world, smelters have to be shut down
during certain climactic periods (low wind velocities, temperature inversions).
Discontinuous operation of converters is not conducive to stable plant operations.
The dried Sulphide concentrates are fed to the roaster where it is exposed to oxidizing conditions
at high temperature, in order to remove essentially all of the contained Sulphur as a continuous
stream of SO2 of an appropriate strength for feeding to a sulphuric acid plant. In the case of a
low Sulphur feed materials the gas could be instead scrubbed and neutralized. The dead-roasted
concentrate is fed hot into the DC arc furnace thus reduces the energy requirement for the
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING PLANT
smelting process. The smelting process is alloyed-based rather than matte based as there is
effectively no Sulphur present at this stage.
Allows great flexibility with respect to the selection of ore types as it does not impose the
limits on the minimum quantities of contained base metals or Sulphur and can tolerate
very high contents of chromite in the concentrate.
The environmental benefits with respect to Sulphur emission reduction are considerable.
Reduction of the energy requirement for the smelting process
The furnace is operated under quite strongly reducing conditions at high temperature and
this avoids the problem of magnetite and chromite build-up. In turn this also removes the
contrainst on the maximum permissible content of Cr3O3 in the concentrate.
Environmental concerns have focused on the problem of SO 2 emissions, especially the stray
emissions around the mouth of the converter. Even with a large fume hood above the mouth of
the converter, fugitive emissions remain a problem. A sulphuric acid plant is probably the most
effective means of capturing the sulphur. However, the intermittent nature of converting
operations makes this rather challenging.
The conventional process requires sufficient matte (at least 10% of the mass of the slag) to be
present to allow for effective coalescence of droplets and collection of the valuable metals. This
causes limits to be placed on the mining of ore such that only material containing more than a
specified amount of nickel and copper is acceptable to the process. This limitation can be lifted
only if additional collector material is available.
The intermittent batch mode of converting is not conducive to good plant operation, and there is
a significant move towards the development of continuous converting processes.
4.2.8 REFINING
Concentrate Dissolution
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING PLANT
The concentrate feed to the refinery contains between 50% and 60% PGMs. The concentrate,
consisting mostly of leached magnetic concentrate from the magnetic concentrator plant, is
dissolved in hydrochloric acid solution using chlorine gas. The temperature is 120 degrees
Celsius and the pressure is 4 bar.
In this dissolution step, osmium is oxidized to OsO 4, which is volatile. The osmium is recovered
from the off gas as potassium osmate, K 2OsO4, using KOH. In addition, there is a separate
circuit for the leaching of the gravity concentrates that are obtained from the mill cyclones of the
company’s ore concentrators. At the end of the dissolution period, the slurry is filtered. The
residue is processed for silver, while the solution is transferred to the solvent extraction of gold.
A solvent-extraction step is used to remove the gold from the filtrate from dissolution. This is
achieved by solvent extraction at high acidity. The solvent used is methyl isobutyl ketone
(MIBK), which has an advantage that most of the selenium, tellurium and antimony are co
extracted, thus removing them from the main production stream.
Although solvent extraction with MIBK is advantageous because it removes the selenium,
tellurium and antimony from the stream carrying the main products, there are significant
disadvantages to this process step. MIBK has a low flash point. As a result, the mixer-settlers are
enclosed for fire protection.
Following solution conditioning, palladium is removed from the gold raffinate by solvent
extraction with a ketoxime, b-hydroxyoxime, which is sold commercially as LIX 84A. The
kinetics of the extraction of palladium are slow. An organic amine compound is added as an
accelerator, but this decreases the selectivity of the extraction. This decreased selectivity results
in decreased purity of the palladium extracted.
The strip solution is treated in a manner similar to that of the precipitation process: palladium is
precipitated from solution with ammonium hydroxide as diaminopalladous dichloride,
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING PLANT
(NH3)2PdCl2. This salt is dissolved and reduced to metal with hydrazine, N 2H4, and then calcined
to produce palladium metal with a purity in excess of 99.95%.
Following solution conditioning, platinum is removed from the palladium raffinate by solvent
extraction with a secondary amine. The iridium in solution must be in its lower oxidation state to
prevent it from co-extracting with the platinum.
The loaded organic is scrubbed with weak acid to remove base metals that may have been co-
extracted. The platinum is then stripped from the loaded organic with 11 M HCl.
Ammonium chloride is then added to the strip solution to precipitate the platinum as ammonium
hexachloroplatinate salt. The salt is re-dissolved, and the platinum is reduced to metal using
hydrazine. The metal is melted and cast to produce pure platinum.
1. The selectivity of the solvent-extraction steps is much higher than the precipitation
methods;
2. The first-pass yields are significantly higher than the precipitation methods; and,
3. The handling of materials, and hence exposure by refinery workers to allergenic platinum
chemicals, is greatly reduced.
1. The solutions are generally more dilute than those of the precipitation process, which
means that the volumes of solution that are treated in the process and in the barrens
recovery are higher than the precipitation methods;
2. The kinetics of the solvent extraction for two of the key separations, palladium and gold,
are slow, which means that hold-up, although better than in the precipitation process, is
not as high as in the ion-exchange process;
3. The solvents are highly flammable and introduce significant risk of fire into the refinery;
4. Entrainment of organics in the aqueous phases, particularly where the next step involves
oxidants, is undesirable; and,
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING PLANT
5. The primary separation of palladium by a secondary amine, while better than the
precipitation techniques, co-extracts small amounts platinum, ruthenium and iridium,
which increases the complexity of the secondary purification of platinum.
There are different configurations of the process discussed above. The configurations are
discussed in the section below.
KELL PROCESS
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING PLANT
The Kell Process was developed for extraction of platinum group metals (PGM), gold silver and
base metals from sulphide flotation concentrates without having to use smelting.
The hydrometallurgical process has been successfully demonstrated on several different flotation
concentrates. It provides high (95 to 99 %) and selective extraction efficiencies for the key base
metals and precious metals, i.e. Pt, Pd, Rh, Au, Ni, Co, Cu.
The Kell Process consists of several unit operations. S, Ni, Co and Cu are first selectively
removed by use of a pressure oxidation step during which the dissolution of PGM is minimized.
The residue from pressure oxidation is subjected to a thermal treatment to ensure efficient PGM
recovery by subsequent chlorination.
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING PLANT
Disadvantages
Used in small scale
Difficult to extract Pa, Rh and Ir using this process.
SEPARATION PROCESS FOR TREATMENT OF THE ANODE SLIME FROM THE
ELECTROLYSIS OF NICKEL
Process A is highly suitable for treatment of the anode slime from the electrolysis of nickel.
Here, selective dissolution of Pt-Pd can be achieved since the refractory PGMs are concentrated
in separate particles. Some special process steps are used, including alloying with lead, and
selective dissolution of rhodium, ruthenium and iridium by salt fusion.
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING PLANT
Figure 37 Separation process for treatment of the anode slime from the electrolysis of nickel
Figure 39 Separation Process where process steps are carried out on the same solution
SEPARATION PROCESS INVOLVING ION EXCHANGE
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING PLANT
A process used mainly in mining operation has, as its most notable feature, solvent extraction of
platinum, which is the metal present in high concentration. Oximes are better than thioethers for
solvent extraction, the higher rate of complex formation enables column technology to be used.
Also the separation process can be set up as an integrated unit. Ion exchange, which is also
carried out on columns, results only in separation of base metals.
Solvent extraction in dialkyl sulphide is used. Unlike the fifth process it provides a quantitative
and sharp separation of palladium which yields great separation conditions for palladium and
platinum. Solvent extraction of Iridium is carried out and is very useful when Iridium content is
low. Use of crystallization precipitation results in excessive amounts of iridium remaining as
soluble (NH4)2(IrCl6) in the mother liquor.
Disadvantages
chlorine or high concentrations of chlorine gas get into the eyes, flush
eyes immediately with a direct stream of water for at least 15 minutes.
Do not attempt chemical neutralization of any kind. Get medical attention
immediately. Contact lenses should not be worn when working with
chlorine.
NOTE: Do not use anything other than clean fresh water, or sterile saline
on the eye.
Ingestion: Ingestion is not considered a potential route of exposure.
Never give anything by mouth to an unconscious person. If swallowed do
not induce vomiting. Give large quantities of water. If vomiting occurs
spontaneously, keep air way clear and give more water. Get medical
attention immediately.
Note to physician: No known antidote. Treatment for inhalation is
symptomatic and supportive. Keep patient at rest until respiratory
symptoms subside. Sedation for apprehension or restlessness may be
considered as well as diuretics and antibiotics to alleviate edema and
protect against secondary infection. Steroid therapy, if given early, has
been reported effective in preventing pulmonary edema.
Fire Fighting Suitable extinguishing media: Water spray, fog or foam. Large fire:
Measures flood with fine water spray.
Use water to keep fire - exposed containers cool and continue until well
after fire is out.
Unsuitable extinguishing media: Do not use carbon dioxide or
halogenated extinguishing agents.
Exposure hazards: Although non-flammable, chlorine is a strong
oxidizer and will support the burning of most combustible materials.
Flammable gases and vapours can form explosion mixtures with chlorine.
Moist chlorine can react violently when in contact with many materials
and generate heat with possible flammable and explosive vapour.
Chlorine gas is heavier than air and will collect in low-lying areas. Wet
chlorine is very corrosive.
Protection of fire-fighters: Fire-fighters must use self-contained
breathing apparatus operated in positive pressure mode, eye protection
and full protective clothing when fighting fire in which chlorine is
involved.
Hazardous combustion products: None, but combustible materials burn in
chlorine as they do in oxygen.
Accidental Personal precaution: Restrict access to the area until completion of the
Release clean-up. Keep unnecessary and unprotected personnel away from
Measures entering. Issue a warning: Poison Gas, Do not touch spilled liquid.
Wear self-contained breathing apparatus and full protective equipment.
Use general or local ventilation to keep the noxes in the requirements
limits. Minimum Personal Protective Equipment should be Level A:
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING PLANT
triple gloves (rubber gloves and nitrile gloves, over latex gloves), fully
encapsulating chemical resistant suit and boots, hard-hat, and self-
contained breathing apparatus.
Warning! Direct contact of liquid chlorine with any personal protective
equipment item can rapidly destroy the equipment, leading to injury and
death.
Environmental precautions: Isolate area until gas has dispersed.
Uncontrollable leaks may require evacuation of surrounding area. Keep
material off water courses and sewers. Use water spray to reduce vapour
but do not apply water to point leak or spill area. Use general or local
exhaust ventilation. Keep combustibles (such as wood, paper, oil) away
from spilled material.
Methods of cleaning up: If source of leak is a cylinder and the leak
cannot be stopped in place, remove the leaking cylinder to a safe place in
the open air and repair the leak or allow the cylinder to empty through a
reducing agent such as caustic soda, soda ash, or hydrated lime solutions.
Chlorine gas will disperse to the atmosphere leaving no residue. One
volume of liquid chlorine released from a container at ambient
temperature and pressure will dissipate into approximately 500 volumes
of gaseous chlorine. Therefore, if a chlorine container is leaking, if
possible, try to position it so that gas, rather than liquid leaks out.
Chlorine vapours are heavier than air, and pockets of chlorine are likely
to be trapped in low lying areas.
Use water fog to dampen a chlorine cloud and reduce vapours. Do not
spray water directly on the leak or chlorine container. Liquid or solid
residues must be disposed of in a permitted waste management facility.
Dispose according to all applicable federal, state, or local environmental
regulations.
Handling and Handling: Special attention is required when chlorine containers are
storage handled. Use only in well ventilated areas. Do not drag, slide or roll
cylinders. Use a suitable hand truck for cylinders movement. Protect
cylinders and containers from physical damage. Keep containers tightly
closed when not in use. For handling chlorine is necessary specially
trained, assigned personnel with approved equipment and clothing.
Chlorine emergency equipment should be available near the point of use.
Storage: Store chlorine containers and cylinders in cool, dry, well
ventilated areas of non-combustible construction away heavily trafficked
areas and emergency exit. Do not allow temperature where cylinders are
stored to exceed 45oC. Cylinders should be stored upright and firmly
secured to prevent falling or being knocked over. Full and empty
cylinders should be segregated. Full cylinders should not be stored for
more than six months. Liquid levels should be less than 85 % of
container or cylinder capacity. Use only compatible materials for
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING PLANT
Consideration local, regional and national regulations. Do not discharge into any place
s where its accumulation could be dangerous. Toxic and corrosive gases
formed during combustion should be scrubbed before discharge to
atmosphere.
Avoid discharge to atmosphere.
Packaging treatment: The chlorine containers/cylinders are dedicated
packaging which are used only in conformity with the specific legal
regulation. Until each refilling chlorine containers/cylinders
must be checked by authorized laboratories
oxygen
Accidental General Information: Use proper personal protective equipment
Release Spills/Leaks: Absorb spill with inert material, (e.g., dry sand or earth),
Measures then place into a chemical waste container. Neutralize spill with a weak
acid such as vinegar or acetic acid
Fire Fighting General Information: Does not apply.
Measures Extinguishing Media: Does not apply.
Auto ignition Temperature: Does not apply.
Flash Point: Does not apply.
Handling and Handling: Wash thoroughly after handling. Remove contaminated
Storage clothing and wash before reuse. Use with adequate ventilation. Do not
get in eyes, on skin, or on clothing. Do not ingest or inhale.
Storage: Store in a tightly closed container. Store in a cool, dry, well-
ventilated area away from incompatible substances. Keep away from
strong acids
Exposure Engineering Controls: Use adequate general or local exhaust
Limits and ventilation to keep airborne concentrations below the permissible
Personal exposure limits.
Protection Exposure Limits
OSHA Vacated PELs:
Potassium hydroxide: C 2 mg/m3
Water: No OSHA Vacated PELs are listed for this chemical.
Personal Protection Equipment
Eyes: Wear appropriate protective eyeglasses or chemical safety
goggles as described by OSHA's eye and face protection regulations in
29 CFR 1910.133
Skin: Wear appropriate gloves to prevent skin exposure
Clothing: Wear appropriate protective clothing to prevent skin exposure
Respirators: Follow the OSHA respirator regulations found in 29CFR
1910.134. Always use a NIOSH-approved respirator when necessary.
Physical and Physical State: Liquid
Chemical Appearance: clear to slightly turbid
Properties Odour: odourless
pH: 12.0 (0.1 M sol.)
Vapour Pressure: 2.6 mm Hg @ 20 C
Vapour Density: 0.62
Evaporation Rate: Not available.
Viscosity: 3.7 cP
Boiling Point: 271 - 293 F
Freezing/Melting Point: 48 deg F
Decomposition Temperature: Not available.
Solubility: Completely soluble in water
Specific Gravity/Density: 1.51
Molecular Formula: Solution
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING PLANT
FHSLA regulations.
Eyes: Corrosive in accordance with FHSLA regulations. Eye irritation
score: 24 hours = 41.67; 48 hours = corrosive
Inhalation: Inhalation of dust may cause irritation to the upper
respiration tract.
Carcinogenicity: None as per NTP, OSHA, and IARC.
First Aid Swallowing: Give large amounts of milk or water. Induce vomiting.
Measures Call Poison Control Center or a physician.
Skin: Wash thoroughly with soap and water. Remove and wash
contaminated clothing before reuse.
Eyes: Immediately flush eyes with plenty of water for 15 minutes. Hold
eyelids apart during irrigation. Call a physician.
Inhalation: Remove person to fresh air and call a physician.
Carcinogenicity: None
Handling Personal Protective: Equipment Chemical safety goggles. Rubber
gloves and rubber apron may be worn.
Ventilation: TWA = 1 mg/l for Copper Sulphate. When TWA exceeds
this limit in the workplace, provide appropriate ventilation. Wear an
approved respirator for dusts or mists: MSHA/NIOSH approved
number prefix TC-21C, or a NIOSH approved respirator with any R, P
or HE filter.
Environment Aquatic: Toxicity LC50, 24 hours, Daphnia magna equals 0.182 mg/l.
and Disposal Rainbow Trout equals 0.17 mg/l. Blue Gill equals 1.5 mg/l. All values
Information are expressed as Copper Sulphate Pentahydrate. Test water was soft.
Spills and Leaks: Comply with Federal, State and local regulations on
reporting spills. Do not wash away crystals or powder.
Recover dry if possible. If product is in a confined solution, react with
soda ash to form an insoluble Copper Carbonate solid that can be
scooped up.
Waste Disposal: Do not reuse container. Comply with Federal, State
and local regulations. Sweep up crystals, powder or insoluble Copper
Carbonate and dispose of in an approved landfill.
Environmental Effects: May be dangerous if it enters the public water
systems. Follow local regulation. Toxic to fish and plants. Fish toxicity
critical concentration is 235 mg/l and plant toxicity is 25 mg/l.
Special Storage: Store in a dry place.
Precautions Other Precautions: None other than those stated in the MSDS or on the
package.
Regulatory NOTE: Regulatory requirements are subject to change and may differ
Information from one location to another. It is the buyer’s responsibility to ensure
that its activities comply with Federal, State and local laws.
Transport DOT Shipping Name: Environmentally Hazardous Substance, Solid,
Information N.O.S., (CUPRIC SULFATE), 9,UN3077, PGIII, Marine Pollutant,
ERG 171
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING PLANT
Equipment (PPE):
The selection of PPE is dependent on a detailed risk assessment. The
risk assessment should consider the work situation, the physical form
of the chemical, the handling methods, and environmental factors.
OVERALLS, SAFETY SHOES, CHEMICAL GOGGLES,
GLOVES, DUST MASK.
Wear overalls, chemical goggles and impervious gloves. Avoid
generating and inhaling dusts. If determined by a risk assessment an
inhalation risk exists, wear a dust mask/respirator meeting the
requirements of AS/NZS 1715 andAS/NZS 1716. Always wash
hands before smoking, eating, drinking or using the toilet. Wash
contaminated clothing and other protective equipment before storage
or re-use.
Physical and Physical state: Powder or Pellets
Chemical Colour: Yellow or Grey
Properties Odour: Unpleasant Sulphurous
Solubility: Soluble in water
Specific Gravity: Not available
Relative Vapour Density (air=1): Not available
Vapour Pressure (20 °C): Not available
Flash Point (°C): Not applicable
Flammability Limits (%): Not available
Autoignition Temperature (°C): Not available
Melting Point/Range (°C): Not available
pH: Not available
Reactivity and Reactivity: Reacts exothermically on dilution with water.
Stability Chemical stability: Stable under normal conditions of use.
Hygroscopic: absorbs moisture or waterfrom surrounding air.
Possibility of hazardous reactions: Hazardous polymerisation will
not occur. Can react with water producing carbon disulphide.
Conditions to avoid: Avoid dust generation. Avoid exposure to heat,
sources of ignition, and open flame. Avoid exposure to moisture.
Incompatible materials: Incompatible with oxidising agents,
combustible materials, acids, water, phosgene, sulphur chlorides ,
copper , copper alloys .
Hazardous decomposition products: Carbon disulphide. Hydrogen
sulphide.
Toxicological Ingestion: Swallowing can result in nausea, vomiting, diarrhoea,
Information abdominal pain, convulsions and loss of consciousness. Death may
occur if large amounts are ingested.
Eye contact: An eye irritant.
Product Name: SODIUM ISOBUTYL XANTHATE
Skin contact: Contact with skin will result in irritation. Will liberate
carbon disulphide upon contact with moist skin. Carbon disulphide
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING PLANT
Most important symptoms and effects, both acute and delayed: Aside
from the information found under Description of first aid measures
(above) and Indication of immediate medical attention and special
treatment needed (below), any additional important symptoms and
effects are described in Toxicology Information.
Indication of any immediate medical attention and special treatment
needed
Notes to physician: Maintain adequate ventilation and oxygenation
of the patient. No specific antidote. Treatment of exposure should
be directed at the control of symptoms and the clinical condition of
the patient.
Fire Fighting Suitable extinguishing media: Water fog or fine spray. Dry
Measures chemical fire extinguishers. Carbon dioxide fire extinguishers.
Foam. Alcohol resistant foams (ATC type) are preferred. General
purpose synthetic foams (including AFFF) or protein foams may
function, but will be less effective.
Unsuitable extinguishing media: Do not use direct water stream.
May spread fire.
Special hazards arising from the substance or mixture
Hazardous combustion products: During a fire, smoke may contain
the original material in addition to combustion products of varying
composition which may be toxic and/or irritating.Combustion
products may include and are not limited to: Carbon monoxide.
Carbon dioxide.
Unusual Fire and Explosion Hazards: Violent steam generation or
eruption may occur upon application of direct water stream to hot
liquids.
Advice for fire-fighters
Fire Fighting Procedures: Keep people away. Isolate fire and deny
unnecessary entry. Use water spray to cool fire exposed containers
and fire affected zone until fire is out and danger of reignition has
passed. Burning liquids may be extinguished by dilution with water.
Do not use direct water stream. May spread fire. Burning liquids
may be moved by flushing with water to protect personnel and
minimize property damage.
Special protective equipment for fire-fighters: Wear positive-
pressure self-contained breathing apparatus (SCBA) and protective
firefighting clothing (includes firefighting helmet, coat, trousers,
boots, and gloves). For protective equipment in post-fire or non-fire
clean-up situations, refer to the relevant sections.
Accidental Personal precautions, protective equipment and emergency
Release Measures procedures: Keep unnecessary and unprotected personnel from
entering the area. Keep upwind of spill. Ventilate area of leak or
spill.
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING PLANT
Exposure time: 28 d
Method: OECD Test Guideline 301F or Equivalent
Theoretical Oxygen Demand: 2.09 mg/mg
Chemical Oxygen Demand: 2.02 mg/mg Dichromate
Bioaccumulative potential
Bioaccumulation: Bioconcentration potential is low (BCF < 100 or
Log Pow < 3).
Disposal Disposal methods: do not dump into any sewers, on the ground, or
Considerations into any body of water. All disposal practices must be in compliance
with all Federal, State/Provincial and local laws and regulations.
Regulations may vary in different locations. Waste characterizations
and compliance with applicable laws are the responsibility solely of
the waste generator. As your supplier, we have no control over the
management practices or manufacturing processes of parties
handling or using this material. The information presented here
pertains only to the product as shipped in its intended condition as
described in msds section: Composition Information.
Transport DOT: Not regulated for transport
Information Classification for SEA transport (IMO-IMDG):
Not regulated for transport
Transport in bulk according to Annex I or II of MARPOL 73/78 and
the 12IBC or IGC Code
Consult IMO regulations before transporting ocean bulk
Classification for AIR transport (IATA/ICAO):
Not regulated for trans
medical attention.
Skin Contact: After contact with skin, wash immediately with plenty
of water. Gently and thoroughly wash the contaminated skin with
running water and non-abrasive soap. Be particularly careful to clean
folds, crevices, creases and groin. Cold water may be used. Cover the
irritated skin with an emollient. If irritation persists, seek medical
attention. Wash contaminated clothing before reusing.
Serious Skin Contact: Wash with a disinfectant soap and cover the
contaminated skin with an anti-bacterial cream. Seek medical
attention.
Inhalation: Allow the victim to rest in a well-ventilated area. Seek
immediate medical attention.
Serious Inhalation: Not available.
Ingestion: Do not induce vomiting. Loosen tight clothing such as a
collar, tie, belt or waistband. If the victim is not breathing, perform
mouth-to-mouth resuscitation. Seek immediate medical attention.
Serious Ingestion: Not available.
Fire and Flammability of the Product: May be combustible at high
Explosion Data temperature.
Auto-Ignition Temperature:370°C (698°F)
Flash Points: Not available.
Flammable Limits: Not available.
Products of Combustion: Flammability of the Product: May be
combustible at high temperature.
Auto-Ignition Temperature: 370°C (698°F)
Fire Hazards in Presence of Various Substances: Not available.
Explosion Hazards in Presence of Various Substances:
Risks of explosion of the product in presence of mechanical impact:
Not available. Risks of explosion of the product in presence of static
discharge: Not available.
Fire Fighting Media and Instructions:
SMALL FIRE: Use DRY chemical powder. LARGE FIRE: Use
water spray, fog or foam. Do not use water jet.
Special Remarks on Fire Hazards: Material in powder form,
capable of creating a dust explosion.
Special Remarks on Explosion Hazards: Not available.
Fire Hazards in Presence of Various Substances: Not available.
Explosion Hazards in Presence of Various Substances:
Risks of explosion of the product in presence of mechanical impact:
Not available. Risks of explosion of the product in presence of static
discharge: Not available.
Fire Fighting Media and Instructions:
SMALL FIRE: Use DRY chemical powder. LARGE FIRE: Use
water spray, fog or foam. Do not use water jet.
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING PLANT
medical attention.
Inhalation: If inhaled, remove to fresh air. If not breathing, give
artificial respiration. If breathing is difficult, give oxygen. Get
medical attention immediately.
Serious Inhalation: Evacuate the victim to a safe area as soon as
possible. Loosen tight clothing such as a collar, tie, belt or
waistband. If breathing is difficult, administer oxygen.
If the victim is not breathing, perform mouth-to-mouth resuscitation.
WARNING: It may be hazardous to the person providing aid to give
mouth-to-mouth resuscitation when the inhaled material is toxic,
infectious or corrosive. Seek immediate medical attention.
Ingestion: Do NOT induce vomiting unless directed to do so by
medical personnel. Never give anything by mouth to an unconscious
person. Loosen tight clothing such as a collar, tie, belt or waistband.
Get medical attention if symptoms appear.
Serious Ingestion: Not available.
Fire and Flammability: Non-flammable.
Explosion Data Auto-Ignition Temperature: Not applicable.
Flash Points: Not applicable.
Flammable Limits: Not applicable.
Products of Combustion: Products of combustion are not available
since material is non-flammable. However, products of
decomposition include fumes of oxides of sulphur. Will react with
water or steam to produce toxic and corrosive fumes. Reacts with
carbonates to generate carbon dioxide gas. Reacts with cyanides and
sulphides to form poisonous hydrogen cyanide and hydrogen
sulphide respectively.
Fire Hazards in Presence of Various Substances: Combustible
materials
Explosion Hazards in Presence of Various Substances: Risks of
explosion of the product in presence of mechanical impact: Not
available. Risks of explosion of the product in presence of static
discharge: Not available. Slightly explosive in presence of oxidizing
materials.
Fire Fighting Media and Instructions: Not applicable.
Special Remarks on Fire Hazards: Metal acetylides (Monocesium
and Monorubidium), and carbides ignite with concentrated sulphuric
acid. White Phosphorous +boiling Sulphuric acid or its vapour
ignites on contact. May ignite other combustible materials. May
cause fire when sulphuric acid is mixed with Cyclopentadiene,
cyclopentanone oxime, nitroaryl amines, hexalithium disilicide,
phosphorous (III) oxide, and oxidizing agents such as chlorates,
halogens, permanganates.
Accidental Small Spill: Dilute with water and mop up, or absorb with an inert
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING PLANT
Release Measures dry material and place in an appropriate waste disposal container. If
necessary: Neutralize the residue with a dilute solution of sodium
carbonate.
Large Spill: Corrosive liquid. Poisonous liquid. Stop leak if without
risk. Absorb with DRY earth, sand or other non-combustible
material.
Do not get water inside container. Do not touch spilled material. Use
water spray curtain to divert vapour drift. Use water spray to reduce
vapours. Prevent entry into sewers, basements or confined areas;
dike if needed. Call for assistance on disposal.
Neutralize the residue with a dilute solution of sodium carbonate. Be
careful that the product is not present at a concentration level above
TLV. Check TLV on the MSDS and with local authorities
Handling and Precautions: Keep locked up.. Keep container dry. Do not ingest. Do
Storage not breathe gas/fumes/ vapour/spray. Never add water to this
product.
In case of insufficient ventilation, wear suitable respiratory
equipment. If ingested, seek medical advice immediately and show
the container or the label. Avoid contact with skin and eyes. Keep
away from incompatibles such as oxidizing agents, reducing agents,
combustible materials, organic materials, metals, acids, alkalis,
moisture. May corrode metallic surfaces. Store in a metallic or
coated fibreboard drum using a strong polyethylene inner package.
Storage: Reacts violently with water. Keep container tightly closed.
Keep container in a cool, well-ventilated area. Do not store above
23°C (73.4°F).
Exposure Engineering Controls: Provide exhaust ventilation or other
controls/ Personal engineering controls to keep the airborne concentrations of vapours
protection below their respective threshold limit value. Ensure that eyewash
stations and safety showers are proximal to the work-station location.
Personal Protection: Face shield. Full suit. Vapour respirator. Be
sure to use an approved/certified respirator or equivalent. Gloves.
Boots.
Personal Protection in Case of a Large Spill: Splash goggles. Full
suit. Vapour respirator. Boots. Gloves. A self-contained breathing
apparatus should be used to avoid inhalation of the product.
Suggested protective clothing might not be sufficient; consult a
specialist BEFORE handling this product.
Physical and Physical state and appearance: Liquid. (Thick oily liquid.)
Chemical Odour: Odourless, but has a choking odour when hot.
properties Taste: Marked acid taste. (Strong.)
Molecular Weight: .08 g/mole
Colour: Colourless.
pH (1% soln/water): Acidic.
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING PLANT
facilities) and revenues. Detailed (and more accurate) cost estimates are usually required after
the detailed design work has been completed, including design and sizing of all equipment,
determination of pipework layouts, and specification of control and instrumentation schemes.
The additional time and effort (and cost) required to produce a more (5-10%) cost estimate is
rarely justified in the feasibility stage of the design. In this section, a preliminary (approximate)
capital cost estimate, with accuracy +/-30%, will be made.
The quickest way to make an order-of-magnitude estimate of plant cost is to scale it from the
known cost of an earlier plant that used the same technology or from published data. This
requires no design information other than the production rate. An estimate of the PGM
processing plant will be made by scaling it from the Platreef capital cost and subtracting the
mining costs of the Platreef plant. The total capital cost of the Platreef plant was then added with
20% for smelting, 7% for base metal refinery and 9% for refining of PGMs from the Anglo-
Platinum plants. Where CT represents the total capital cost from the Platreef Plant.
CT = $750 + 0.36CT
0.64CT = 750M
CT = $1 171.875 M
The Rapid Cost method represented below was used to calculate the capital costs before
contingency. The capital cost for the plant processing 350 tonnes per hour, operating 24hrs per
day for a year having 340 days was calculated below.
Plant capacity for the year will be 2 856 000 t/yr = 2.856Mt/yr
n
S2
C2 =C1 ( )
S1
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING PLANT
Where:
C2 is capital cost of the plant with capacity S2 (Project plan)
The exponent n is typically 0.8 to 0.9 for processes that use a lot of mechanical work or gas
compression. Averaged across the whole chemical industry, n is about 0.6.
This value can be used to get a rough estimate of the capital cost if there are not sufficient data
available to calculate the index for the particular process. For mineral processing plants, the
value of 0.8 will be used.
0.8
2.856
C2 =$ 1 171.875 M ( 4 )
C 2 = $895 034 670.8 before contingency
The value usually has to be adjusted for inflation to give an estimate for the current market
capital cost of the plant. The plant cost indices as presented using Chemical Engineering Plant
Cost Index (CEPCI) to adjust the capital costs. For this case, since the Platreef plant is for the
year 2017 which is the same year for our project plan, there is no need for the value to be
adjusted.
CTI = CW + CF + CN
Where: CTI is the total investment needed for a project.
CF is the fixed capital
CN is the land and contingency costs
CW is the working capital which is estimated as 25% of fixed capital
CT = 1.25CF +CN
CT=$984 034 670.8 and CN =$984 034 67.08
Start-up
Initial catalyst charges
Raw materials and intermediates in the process
Finished product inventories
Funds to cover outstanding accounts from customers
Most of the working capital is recovered at the end of the project. The total investment needed
for a project is the sum of the fixed and working capital.
Working capital can vary from as low as 3 % of the fixed capital for a simple, single-product,
process, with little or no finished product storage; to as high as 30 % for a process producing a
diverse range of product grades for a sophisticated market, such as synthetic fibres .A typical
figure for petrochemical plants is 15 % of the fixed capital.
The total investment needed for a project is the sum of the fixed and working capital:
CT =C W +C f
day and with 3 weeks of shutdown and 1 week of holidays, the annual year will consists of
337days.
There are two groups in which the operating costs can be divided into and these are:
a) Fixed costs: These costs do not depend upon the production rate, and they must be paid even
if no chemical is produced. Examples of fixed operating costs are described below.
i. Capital charges are recovered from the project to repay the initial capital investment.
The procedure adopted depends upon the accounting practice of the company. Capital is
often recovered as a depreciation charge of 10% per annum (for example) based on a
plant operating life of IO years, although the plant is not necessarily replaced after that
time! Interest must also be paid on the capital borrowed to finance the plant[ CITATION
Ray89 \l 1033 ] . The capital may be obtained from company reserves, but it should be
repaid with interest-based upon a consideration of the alternative investments and their
return on capital, i.e. applicable market rates.
ii. Rates are payable to the local authority or shire based upon the assessed rateable value of
the site. A typical figure is l-2% of the capital cost [ CITATION Ray89 \l 1033 ].
iii. Insurance for the site, the plant and employees is usually about l-2% of the fixed capital
[ CITATION Ray89 \l 1033 ].
iv. Royalties and licence fees are payable to the company or individual responsible for
developing the process. This payment may be a lump sum or an annual fee, and is
typically either l-5% of sales price of 1% of the fixed capital [ CITATION Ray89 \l
1033 ].
b) Variable costs: These costs are dependent upon the amount of chemical produced. Examples
of these variable costs are described below.
i) Raw materials are determined from the process flowsheet and from material balances. The
ratio of the cost of raw materials to total plant cost obviously will vary considerably for different
types of plants. In chemical plants, raw-material costs are usually in the range of 10 to 50
percent of the total product cost. Due to lack of enough information readily available to us on the
processing of PGMs, to determine the cost of raw materials, costs had to be scaled from the
Sunhanko projects. The cost of the ore as the raw material was taken from the Sunhanko project
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING PLANT
because the type of ore that they are currently mining is very similar to our ore from the design
question. This value of the ore was also converted to US dollars and escalated to our current
year. From the Sunhanko Project Plant, raw materials which includes reagents and consumables
were being purchased for CAN$2.18/t milled and the ore was CAN$8.17. The total amount of
reagents and consumables purchased for the whole year are:
Total costs of the raw materials per annum in USD for the year 2012 was calculated below. The
rate at the time was 1 Can = 0.99 USD
The estimated cost price is based on the year 2012 prices. The value for raw materials need to be
adjusted to give an estimate for the current market cost of the raw materials. United States
Consumer Price Index was used to make the adjustment.
= $ 30 537 736.49
ii) Miscellaneous materials include items such as safety clothing, chart recorder paper, etc., that
are not included as raw materials or maintenance materials. These are usually calculated as 10%
of the total maintenance cost.
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING PLANT
iii) Utilities (services) include electricity, water, steam, compressed air, etc. Quantities are
determined from the flowsheet and from energy balances, current costs (and anticipated price
rises) should be obtained for these items. Utilities can be estimated roughly to about 10-20% of
the total product cost. The following factors were calculated from Coulson and Richardson
Volume 6.
iv) Shipping and packaging costs depend on factors specific to the process, the location and the
type of product. In PGMs processing, there are negligible.
v) Maintenance includes materials and labour costs. This cost is typically between 5-15% of
installed capital cost and should be estimated from data for a similar plant].
vi) Labour costs should be estimated from reasonably detailed manning estimates. The
operating labour costs may not decrease if production is reduced, however overtime payments
will be required for significant increases in production. Operating labour costs do not normally
exceed 15% of the total operating cost.
= 3.333
vii) Supervision includes the management team directly responsible for the overall plant
operation and for directing the work of the plant operators. The personnel requirements of the
management team should be determined, although an approximate figure of 20% of labour costs
can be used to provide an initial estimate.
viii) Laboratory costs for analysis associated with quality control and process monitoring. An
approximate estimate can be obtained as 20- 30% of the operating labour cost or 2-4% of the
total production cost.
ix) Plant overheads include general operating costs such as security, canteen, medical,
administration, etc. This item is often estimated as 50- 100% of item of the operating labour.
be operating at 90% efficiency, the annual production in tonnes/ year of the individual metals in
processing 350tonnes of the ore per hour is calculated as shown below:
( ( hryr )
)
operating time
g
1 000 000 ( )
t
From annual production rates, the revenue expected can thus be calculated using the formula:
6.6.1 REVENUES
The revenues for any given project are the incomes earned from sales of main products/ services
and by products. In this project the products are platinum, rhodium and palladium and the by-
products are gold, silver, copper, nickel and cobalt. Annual production rates of the products and
by products will be calculated based on information on the market price of products obtained
from literature. Table below shows the different prices obtained for each product and by-
products obtained.
6.6.2 MARGINS
The sum of product and by-products revenues minus raw material costs is known as the
gross margin (or sometimes product margin or just margin).
Gross margin = Revenues - Raw materials costs
= $539 320 310.3– $30 537 736.49
= $508 782 573.80
6.6.3 PROFITS
Gross profit = Revenues – Total Operating Costs
= $539 320 310.3- $377 320 310.3
=$162 000 000
The net profit (or cash flow after tax) is the amount left after tax deductions. In calculating cash
flows, the project is frequently considered as an isolated system and taxes on profits and the
effect of depreciation of the investment are not considered, tax rates are not stead and depend on
government policy. In recent years, corporation tax has been running at around 25% and this
figure can be used to make an estimate of the cash flow after tax. Depreciation rates depend on
government policy and on the accounting practices of the particular company [ CITATION
Ray89 \l 1033 ]. Taking the value of taxes to be 22% of the gross profit. . Depreciation rates
depend on government policy, and on the accounting practices of the particular company and for
the design 10% depreciation was assumed.
Net profit = gross profit – taxes
= $162 000 000– 0.22($162 000 000)
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING PLANT
the period before the break-even point. It is very useful in judging projects that have a short life
span with capital injected only for a short time.
Total investment
Simple payback period= + 2 yrs construction
Average annual cash flow + Annual Depreciation
984 538 137.90
Simple payback period= +2yrs
539033 029.20+70 850 496.30
𝑅𝑂� =12.83
The disadvantage of using the rate of return is that it does not take into account the change in the
cash flow pattern with time during the project installation. A better measure is the net present
value (NPV) and the discounted cash flow analysis (DCF) which takes into account the change
in the net cash flow rate pattern and time value of money.
1+i
¿
¿
¿
Future worth∈ year n
Present value of a future ∑ ¿
¿
The interest rate used in discounting future values is known as the discount rate and is chosen to
reflect the earning power of money.
1+i '
¿
¿
¿n
¿
C Fn
¿
n =t
NPV =∑ ¿
n=1
The cash flows, and whatever criteria of performance are to be used, are then calculated
assuming a range of error for each of the factors in turn; for example, an error of, say, 10 per
cent on the sales price might be assumed. This will show how sensitive the cash flows and
economic criteria are to errors in the forecast figures. It gives some idea of the degree of risk
involved in making judgements on the forecast performance of the project.
The closer the plant is to the mine the lower the cost of transportation. Hence, the plant site
should be a close to the Great Dyke where the availability of ore will be high. The PGMs
processing plant should also be as close as possible to the factories that supply the chemicals to
reduce costs on transportation of the chemicals and also ensures constant availability of the
chemicals supply.
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING PLANT
Ore: The processing plant should be as close as possible to the Mining site. This reduces the cost
of handling and transportation of ore.
Reagents: In the processing of PGMs, various chemicals or reagents will be required to enable
the extraction process such as sulphuric acid and hydrochloric acid. As such, these chemicals
must be readily available.
Water: It is needed for underground operations, processing of the gold ore through crushing,
milling, gravity concentration and leaching and also preparation of reagents.
The processing plant should be sited where there is abundant source of raw water and potable
water for drinking and food preparation.
Pumping and pipeline maintenance costs are greatly reduced if the processing plant is close to
these sources of water. Water is needed for underground operations, processing of the ore from
milling up to leaching operations. The processing plant should be sited where there is abundant
source of raw water. This reduces the pumping and pipeline maintenance costs. The most critical
raw material for mine plant is the ore.
Labour may be skilled or unskilled. Unskilled labour should be adequately available locally
while skilled labour can come from elsewhere. In addition there has to be labour suitable for
training to operate the plant. Labor will be needed for construction of the plant and its operation.
Skilled construction workers are usually brought in from outside the site area, but there should
be an adequate pool of unskilled labor available locally, and labor suitable for training to operate
the plant.
Skilled craft workers such as electricians, welders, and pipe fitters will be needed for plant
maintenance. Local labor laws, trade union customs, and restrictive practices must be considered
when assessing the availability and suitability of the local labor for recruitment and training.
Labour is needed for construction and operation of the plant. Skilled construction workers will
usually be brought in from the site are but there should be an adequate pool of unskilled labour
available locally and labour suitable for training to operate the plant. Labour can be
accommodated in the nearest town and provisional accommodation constructed on site.
Particular care must be taken when building plants on reclaimed land or in earthquake zones
because of the poor seismic character of such land. The land should be competent enough to
accommodate and support the heavy equipment used in mineral processing and extraction of the
desired minerals. The ground should also have sufficient land for future expansion. The land
location should be of relative altitude to environmentally sensitive areas like rivers, wells and
communities.
The wind direction should also be considered since the plant involves crushing and emission of
dust thus the plant should be located where the air quality for the surrounding community is not
compromised.
appropriate authorities must be consulted during the initial site survey to determine the standards
that must be met. An environmental impact assessment should be made for each new project or
major modification or addition to an existing process.
inherent risk of flooding. Thus it is worthwhile to have knowledge of such regional historical
events. Soil types, altitude, rainfall patterns and proximity to large water bodies give an
approximation of this flooding risk. It is vital that adequate fire services should be available and
the risk of fire on adjacent sites is known.
7.1.10 CLIMATE
The prevailing weather in the area to be chosen should be taken into consideration as the average
temperatures and humidity have an impact on the type of equipment used in the processing plant
and thus a location with favorable climatic conditions should be chosen.
The site of the location must also have good rainfall pattern in order to have sufficient water for
the processes involved but keeping in mind that too much rainfall also comes with negative
effects such as malaria outbreaks, cold and may result in the flooding of the tailings dams.
The natural occurrence of disaster must be taken into consideration in order to determine the
type of structures to construct and costs of insurance in case of a disaster. The ground should be
above the flood plain, flat and has good drainage.
Does any national legislation exist which creates certain prerequisites for PGMs
processing plants?
On the real level, it should be analyzed for the following:
Are there residential areas in the proximity (this should be analysed in view to the
prominent wind direction)?
Are there areas of natural or cultural importance in the proximity?
The effects of the plant on traffic flow should also be considered.
i. Sebakwe Sub-Chambers
ii. Musengezi Sub-Chambers
iii. Selukwe Sub-Chambers
iv. Darwendale Sub-Chambers;
v. Wedza Sub-Chambers
Disadvantages
the site is particularly marshy and would require an extensive and rigorous site
preparation so that good plant foundations can be laid
Disadvantages
Disadvantages
Disadvantages
Disadvantages
FACTOR Sebakwe Sub- Musengezi Sub- Selukwe Sub- Darwendale Sub- Wedza Sub-
Chambers Chambers Chambers Chambers Chambers
Rank Points Score Points Score Points Score Points Score Points Score
Raw material 10 9 90 5 50 7 70 8 80 6 60
supply
Transport 8 7 56 5 40 7 56 6 48 6 48
facilities and
communication
links
Availability of 7 6 42 6 42 4 28 5 35 4 28
labour
Availability of 9 8 72 4 36 6 54 7 56 6 54
utilities; fuel,
power
Availability of 9 7 63 5 45 5 45 7 63 4 36
suitable land
Environmental 7 6 42 4 28 5 35 4 24 6 42
impact
(Effluent
disposal)
Political and 6 5 30 4 24 4 24 5 30 4 24
other strategic
considerations
Consumer 5 4 20 3 15 2 10 4 20 3 15
markets
Fire and flood 4 3 12 2 8 2 8 3 12 3 12
protection
Total 65 427 288 330 368 319
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING PLANT
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING
PLANT
PLANT
8.0 REFERENCES
1. Stilwell, L.C. and Minnitt, R.C.A., “Is platinum paying its rent?”, International
Platinum Conference ‘Platinum Surges Ahead’, The Southern African Institute of
Mining and Metallurgy, 285-293, 2006.
2. Butler, J., “Platinum 2011 Interim Review”, Johnson Matthey plc, November 2011.
3. Liddell, K.S., McRae, L. B, and Dunne, R.C., “Process routes for the beneficiation of
noble metals from Merensky and UG-2 ores”, Extraction Metallurgy ’85, London,
U.K., Institution of Mining and Metallurgy, London, 789-816, 1985.
4. Rule, C.M. “Energy considerations in the current PGM processing flowsheet utilizing
new technologies”, J. S. Afr. Inst. Min. Metall., 109(1), 39-46, 2009.
5. Esterhuizen, L., “Power versus PGMs – Eskom wins”, Royal Bank of Canada Europe
Ltd., 11 April 2008.
6. Van Manen, P.K., “Furnace energy efficiency at Polokwane smelter”, J. S. Afr. Inst.
Min. Metall., 109(1), 47-52, 2009.
7. Jones, R.T., “An overview of southern African PGM smelting”, Nickel and Cobalt
2005: Challenges in extraction and production, 44th Annual Conference of
Metallurgists, Calgary, Alberta, Canada, 21-24 August 2005, CIM, Montreal, 147-
178, 2005.
8. Esterhuizen, L., “PGMs & South African golds trip notes – who needs what when”,
Royal Bank of Canada Europe Ltd, 19 February 2010.
9. Geldenhuys, I.J. and Jones, R.T., “Four years of DC arc smelting of PGM-containing
oxide feed materials at Mintek”, Mintek, Randburg, South Africa, 2009.
10. Liddell, K.S., “Hydrometallurgical treatment process for extraction of platinum group
metals obviating the matte smelting process”, R.S.A. Pat. 2000/6600: Appl. 19 May
1998: Acc. July 25 2001.
DESIGN OF A 350 TONNES PER HOUR PGM ORE PROCESSING
PLANT