2 Radars 2 x independently operated radars. (one X-band and 1 S-band)
3 Gyro Compass Minimum one gyrocompass
4 Echo Sounder One echo sounder with a repeater at the aft maneuvering control panel.
5 Portable Transistorized Loud Hailer Minimum One unit
6 VHF Radio (Portable) Minimum 3 units for deck crew with sufficient spare batteries
Shall have ability to communicate via satellite communication (Voice) and data (E-
mail) within 24 hr/day.
7 Communication System/ E-mail
Minimum available dedicated bandwidth of 256 Kbps.
Not allowed for International Call routing.
8 Public Address System Required, 1 loudspeaker fwd, 1 loudspeaker aft, 1 galley / cabin
Compliance to SOLAS.
1 SOLAS Compliance
All life saving appliances to comply with SOLAS 1974 & latest amendments.
Each side of the vessel (mid-ship) marked with - RESCUE ZONE - which is painted
4 Rescue Zone in bright yellow with diagonal black stripes.
The area minimum 1 meters wide and open from the main deck to the waterline.
Page 2 of 21
Clear area 5 m x 5 m square as dedicated PTD landing zone, c/w perimeter
Personnel Transfer Device (PTD) Landing
5 marking in bright yellow with diagonal black stripes & red/ white bulls eye center
Zone
marking. Area must be clear of materials at all times
One mounted at each "RESCUE ZONE". A nylon net long enough to reach the
6 Scrambling Net waterline and should be rolled up & ready to launch. The net should be 2 meters
wide, made of 8 mm circ. Nylon and 200 mm x 200 mm netting.
Shall have one portable aluminium gangway or similar c/w hand rail & safety
7 Gangway netting capable of providing safe access to & from vessel when alongside wharf or
jetty.
All hatch covers located on deck, accommodation or engine room shall be fitted
8 Hatch Cover
with securing arrangement (i.e. chain, steel holder, etc) and safety pin.
All machinery spaces including enclosed spaces containing diesel or gas fired
engines shall be provided with a permanently installed CO 2 Fire Protection System.
Halon Fixed Smothering system is strictly prohibited. System must be so designed
1 Engine Room CO2 System as to sound an alarm for a period of approximately one minute before discharge of
the extinguishing medium occurs for personnel to evacuate area. The system shall
also have provision outside the area for being manually operated, the time delay
safeguard must also be provided on the manual facility.
Automatic/ centrally controlled smoke & heat detection system in accom & engine
2 Fire Alarm & Smoke Detection System room spaces indicating zone/location (audible & visual) of fire/ smoke & capable of
identifying system faults at central panel
10 Main Engine Emergency Stop To be fitted in wheel house on the navigation control console
Page 3 of 21
Minimum 2 x main generators of 440 V/ 220 V, 50/60 Hz. driven by independent
11 Generators
engine with sufficient capacity to support electrical load of vessel and cargo.
14 Oily Water Separator @ 15 ppm Minimum 1 unit required and fitted with auto shut off and alarm system
For vessels with deep draft (over 4 meters) the water cooler suction to be located
19 Engine cooling system
at vessel's side. Bottom suction is not acceptable.
To advise the last date of the general overhaul with report attached and latest
20 Main engines last general overhaul
running hours
G. DECK EQUIPMENT
Minimum 2 sets recessed bow anchors meeting Classification Society
1 Anchor and Windlass requirements.
Each windlass fitted with a warping head for mooring rope handling.
Page 4 of 21
2 Anchor chain diameter & length Minimum chain length of 12 shackles (330 meter), on each side
3 Main Deck Crash Rails Continuous crash rails of at least 1.2 m on both sides of vessel main deck
H. WHEELHOUSE/ ACCOMMODATION
Shall be of design and built with as near as possible 360° un-obstructed visibility.
1 Wheel House Full remote control of main engine (s) and bow thruster shall be provided at both
fwd and aft maneuvering stations.
2 Clear View Screen Minimum 1 unit clear view screen fwd and aft of wheel house or wind shield wiper
Lodging, laundry & catering facilities must be of adequate size & numbers to
accommodate the proposed number of project personnel comfortably over a 24-
3 Accomodation General Requirement hour p/d continuous operation. All crew shall have individually assigned beds, in
well equipped rooms of good standard & quality, free of vermin.
Note: Hot bunking’ is not acceptable.
"Permanent Steel Constructed Module Design", fitted out with fire resistant
4 Accommodation Construction materials & asbestos free. The vessel shall be capable of fully accommodating
vessel crew and Company personnel.
Noise levels shall not be more than recognised industry standards and at all times
5 Insulation and Noise Level and in all locations less than the limits as laid down in the IMO Resolution A468
(Xii) (Code of noise level on board ships). All insulation shall contain no asbestos.
Each sleeping space for each occupant without deducting any equipment used by
the occupants shall be:
7 Sleeping Space
3 m2 of deck area & 6 m3 of volume, head room 1.91 meters length.
Each berth must have bedside shelf & light in good order/ condition with sufficient
light for reading & a readily accessible locker. All bunks shall be provided with
8 Berths curtains & no more than one berth may be over another.
Safety Guard/ Rails shalll be fitted on the upper bunk to prevent from falling down
whilst asleep.
Page 5 of 21
Quantity and construction shall in accordance with Indonesian Health Minister
Decree (Kepmenkes) 715-2003
10 Communal Toilet/ Shower room 1 – 10 persons = 1
11 – 25 persons = 2
26 – 50 persons = 3
12 Cooking Facilities Electric cooking facility, open flame stoves are not permitted.
Owner shall provide catering service / food standard that meet requirements of
6 Food Standard (Catering Service) GOI (KEPUTUSAN MENTERI KESEHATAN REPUBLIK INDONESIA NOMOR
715/MENKES/SK/V/2003) and PHE ONWJ OH/IH Department.
13 Pest Control Program Prior to On Hire and minimum semi - annual pest control program.
14 Dedicated Smoking Room Indoor c/w electric lighter, asthray and exhaust
Minimum 1 set CMOS Infra Red outdoor camera, Marine standard, stand alone
15 CCTV DVR with storage capacity minimum 7 days continous recording.
Camera installation viewing vessel forward, Aft working deck, and Engine Room.
I. MEDICAL
Medical supplies as prescribed by company (First Aid Level 3), refers to
1 Medical Supplies
Attached List
2 First Aid Kit First Aid Kits shall be available in the wheel house, mess room and engine room.
Page 6 of 21
Minimum 1 unit stretcher capable of immediate deployment and securely loaded to
3 Stretcher
Rigid-Type "Personnel Transfer Device".
4 Eye Wash Stations Eye Wash Stations shall be provided on the main deck and in the engine room.
J. MANNING / COMPETENCY
K. PERSONNEL CERTIFICATIONS
Required for all crews prior to entering COMPANY's facilities & shall be submitted
1 Sea Survival Certificate for approval by COMPANY's Marine Dept. BST validity maximum 5 years, BOSIET 3
years
Required for all crews prior to entering COMPANY's facilities & MCU shall be
2 Medical Check Up
submitted for approval by COMPANY's Medical section, maximum 1 year
Mandatory Additional Training for Captain Captain and All Deck Officers shall ATTEND and PASS the Offshore Navigation
3
and Deck Officers Training at COMPANY's approved Training provider.
Mandatory Additional Training for Chief Chief Engineer and All Watchkeeping Engineers shall ATTEND and PASS the
4
Engineer and Watchkeeping Engineers Marine Machinery Training at COMPANY's approved Training provider.
Required for minimum One (1) Crane Operator, certificate to be made available
6 MIGAS Certified Crane Operator
onboard for assessment by PHE Lifting Team
Page 7 of 21
Detail Required.
Slow Speed Hourly Fuel Usage
6 Slow Speed Fuel Usage is the sum of main engines fuel consumption at
(liters/hour)
3 knots added with one generator fuel consumptions at 80% load.
Detail Required.
Maneuvering is defined as the main engines are ON but the VESSEL is
Maneuvering Hourly Fuel Usage not underway (e.g. station keeping or at the platform or rig for transfer of
7
(liters/hour) personnel or cargo).
Maneuvering Fuel Usage is the sum of Slow Speed Fuel Usage added
with Bow Thruster and / or additional generator consumption at 80% load.
Detail Required.
8 Standby Hourly Fuel Usage (liters/hour)
Standby Fuel Usage is consumption of one generator at 80% load.
Detail Required.
Towing is defined as the main engines are ON and the VESSEL is
engaged in towing activities.
9 Towing Hourly Fuel Usage (liters/hour)
Towing Fuel Usage is the sum of main engines fuel consumption at
100% of maximum RPM added with two generators consumption at 80%
load and/or diesel-driven winch fuel consumption.
Detail Required.
Anchor Handling is defined as the main engines are ON and the VESSEL
Anchor Handling Hourly Fuel Usage is performing Anchor Handling.
10
(liters/hour) Anchor Handling Fuel Usage is the sum of Normal Speed Fuel Usage
added with additional generator fuel consumption at 80% load and/or
diesel-driven winch fuel consumption.
Bidder to provide a Speed, Engine performance and Fuel Consumption
Vessel Speed, Engine performance and
11 Report that is issued or endorsed by Classification or Independent Marine
Fuel Consumption Evidence
Surveying Company.
12 Endurance time without Refueling & Water Minimum 20 days (based on 12 hours/day operation)
Page 8 of 21
B. MACHINERY & POLLUTION PREVENTION
Maximum 3,000 bhp
1 Certified Total Horse Power (BHP@...RPM)
Note: BHP figure shall match with class certificate
2 Engine Rating To state maximum duration of engine's MCR (i.e. 8 hours out of 12 hours)
C. DECK EQUIPMENT
4 Safety Devices for Deck Crane Anti Two Block, Safe Load Indicator, Boom Limit Switch, Emergency Shut Down
6 Vessel fenders Fully fendered (Tyres) with internal laced securing chains
7 Main Deck Crash Rails Continuous crash rails of at least 1.2 m on both sides of vessel main deck
8 Mini platform Located on Port / Stb Stern complete with steps, handrails & non slip grating
Minimum 200 m2
Note :
- Clear deck space includes aft main deck area which can be used for the required
1 Clear deck space (m2)
scope of work (e.g. Cargo stowage, Working Area, etc.)
- Excluding areas occupied by winches, capstans, crane, mini jumping platform,
hatches and other obstructions; deck area above main deck also excluded
5 Reefer points Minimum 2 (two) points of 440V / 220V 50 / 60 Hz 3 phase; explosion proof type
6 Refrigerated Cargo Cold storage room - Minimum 8 m3 (able to maintain 4degC temperature)
Sea Fastening / Lashing equipment /
7 Min 4 sets Certified lashing equipment
ratchet
8 Fuel Tank capacity (m3) Sufficient for 20 days (12 hr/ day) operation plus reserve without refueling.
Fuel Transfer Pump Rate (m3/hour @ mtr Minimum 50 m3/hr @ 50m head
9
head) (Sufficient capabilty to transfer Fuel to Flow Stations)
10 Fuel Transfer Metering System Minimum 1 set complete with annual calibration
Page 9 of 21
11 Potable Water Tank Capacity (m3) Sufficient for 20 days operation plus reserve without top up water.
E. WHEELHOUSE/ ACCOMMODATION
1 Accomodation Capacity Total minimum berths for Company personnel are 30 berths
F. SPECIAL FEATURES
Preferred to have External Fire Fighting Capability
1 External Fire Fighting Capability
Detail Required
Fast Rescue Boat (Rigid or Rubber) with minimum 6 Person Capacity and Minimum
Power 25 bhp.
2 Rescue Capability
This boat shall also be capable to be deployed to assist mooring operation near
offshore installations.
3 Bow Bumper Large tractor tyres or other types of rubber fender (W, M or Key Hole)
G. PERMITS
Permit for Company's personnel onboard
1 (as per applicable regulation) Required for Company Personnel who stay onboard as passenger
Permit for transporting Fuel (Ijin Required for transporting fuel to PHE ONWJ Stations / Jack-Up Rigs and Support
2
Pengangkutan BBM) Vessels
Page 10 of 21
NNAIRE
ENT
BIDDER'S RESPONSE
COMPANY CRITERIA
Yes / No / Detail
To be complied prior to
delivery and renewed timely
to enable vessel Yes, comply
uninterupted service during
charter period
2013
48,55 meter
11,80 meter
4,60 meter
767 ton
To be complied prior to
Yes, to be complied prior to delivery
delivery including proper
including proper closure of findings
closure of findings
Intermediate Docking : August 2016
16-Jul-18
Page 11 of 21
yes, 2 unit (x band and s band)
yes, 1 unit Toyko keiki 11 ES
yes, Furuno FCV 627
yes, 1 unit
yes, 3 unit Icom IC M-34
yes, 79 set
yes, 12 set
Page 12 of 21
yes, 5 mx 5 m, each side as
dedicated PTD landing zone, c/w
perimeter marking in bright
yellow with diagonal black
stripes & red/ white bulls eye
center marking. Area must be
clear of materials at all times
800 Rpm
1900 Rpm
800 Rpm
1900 Rpm
Page 13 of 21
yes, 2 unit main generator
400V/3ph/50Hz
yes, comply
yes, approximately 5 m3
Page 14 of 21
To be complied prior to yes, diam. 30mm, length 385m,
delivery each side
yes, available, height from main
deck 1,8 m, length. 25 m
yes, comply
Page 15 of 21
yes, comply;
- main deck 3 unit,
- fore castle 3 unit
To be complied prior to
yes,
delivery
Page 16 of 21
will supplied prior delivery
To be complied by each
will fulfilled requirement prior
personnel prior to working in
delivery
PHE ONWJ field
To be complied by each
will fulfilled requirement prior
personnel prior to working in
delivery
PHE ONWJ field
To be complied by each
will fulfilled requirement prior
personnel prior to working in
delivery
PHE ONWJ field
To be complied by each
will fulfilled requirement prior
personnel prior to working in
delivery
PHE ONWJ field
To be complied by each
will fulfilled requirement prior
personnel prior to working in
delivery
PHE ONWJ field
IREMENT
REMARKS BIDDER'S RESPONSE
Page 17 of 21
yes, comply 168 ltr/hr of slow speed
hourly fuel usage
yes, comply
Page 18 of 21
MANDATORY Maximum power is 2800 HP
Rating B.
engine rating is 12 hour on MCR
yes, bow thruster capacity is about
MANDATORY
2,8 ton
To be complied prior to
To be complied prior to delivery
delivery
not available
To be complied prior to yes, deck crane is SWL 3,3 ton,
delivery with 12 meter boom radius
yes, complete with Anti Two
To be complied prior to Block, Safe Load Indicator, Boom
delivery Limit Switch, Emergency Shut
Down
To be complied prior to
yes, comply
delivery
yes, comply
Page 19 of 21
yes, comply volume potable water
362,293 M3
yes, comply. Flow rate 65 m3/hr @
32 m head
yes, comply
yes, comply
To be complied prior to
yes, comply
deivery
To be complied prior to
yes, comply
delivery
To be complied prior to
yes, comply
delivery
Page 20 of 21
TYPE A - UTILITY (ACCOMMODATION) BOAT
COMPLETE FIRST AID BAG