Documente Academic
Documente Profesional
Documente Cultură
Cellier Activity
Issued by Department Revision Page
FRFRA/PA A 1 / 29
Customer Plant ABB Contract No. Customer Contract No.
CHEVRON PAKISTAN KARACHI PLANT B09166 PO 001 01 37199
FLUSHING PROCEDURE
Ce document est la propriété exclusive d’ABB Cellier. Il est interdit d’en faire usage ou de le communiquer sans autorisation préalable.
This document belongs to ABB Cellier. It is prohibited to use or transmit it without our prior consent.
1 A 60 119
2 A 61 120
3 A 62 121
4 A 63 122
5 A 64 123
6 A 65 124
7 A 66 125
8 A 67 126
9 A 68 127
10 A 69 128
11 A 70 129
12 A 71 130
13 A 72 131
14 A 73 132
15 A 74 133
16 A 75 134
17 A 76 135
18 A 77 136
19 A 78 137
20 A 79 138
21 A 80 139
22 A 81 140
23 A 82 141
24 A 83 142
25 A 84 143
26 A 85 144
27 A 86 145
28 A 87 146
29 A 88 147
30 89 148
31 90 149
32 91 150
33 92 151
34 93 152
35 94 153
36 95 154
37 96 155
38 97 156
39 98 157
40 99 158
41 100 159
42 101 160
43 102 161
44 103 162
45 104 163
46 105 164
47 106 165
48 107 166
49 108 167
50 109 168
51 110 169
52 111 170
53 112 171
54 113 172
55 114 173
56 115 174
57 116 175
58 117 176
59 118 178
¨ Seules les pages révisées font l’objet de l’émission de référence. Only the revised pages are sent with the last issue to date.
CONTENTS
1. PURPOSE ....................................................................................................................... 4
5. FLUSHING ACTIVITIES.................................................................................................. 7
5.1 PRINCIPLE ................................................................................................................................ 7
5.2 PROCESS & INSTRUMENT AIR LINES UPSTREAM TO ABB SUPPLY ................................. 7
5.3 TANKS ....................................................................................................................................... 7
5.4 SUCTION PIPES UPSTREAM PUMP ........................................................................................ 8
5.5 PROCESS PIPES DOWSTREAM PUMP ................................................................................... 8
5.6 ABB EQUIPMENT (SKID).......................................................................................................... 8
5.7 PIGGED LINES ( NOT RELATED TO MANIFOLD) ................................................................... 8
5.8 PIGGABLE MANIFOLD ........................................................................................................... 10
5.9 PIGGED LINES ( UPSTREAM AND DOWNSTREAM OF MANIFOLD) ................................... 10
5.10 STEAM & CONDENSATE LINES ............................................................................................ 11
5.11 DRAINING OF PIPELINES ...................................................................................................... 11
5.12 COMPANY'S REPORT ............................................................................................................ 11
1. PURPOSE
The purpose of this document is to establish the flushing procedure between the piping installation
of Lube Oil Blending Plant and the ABB equipment.
This procedure has to be followed carefully in view to protect sensitive equipment such as pumps,
flow meters, air regulators, steam traps, pigged valves and others which will be installed on pipes
lines and also to obtain, from the very first batch, a good level of produced oil in terms of clearness.
A part of this document is also dedicated to pressure tests done after construction completion
because this activity is relatively close and linked to flushing activity.
2. DOCUMENTS OF REFERENCE
Documents of reference are all last revisions of deliverable documents sent by ABB in Transmittals
from project B09166.
- Prior to flush, pipes & accessories network will need to be mechanically receipted and therefore
pressure tested.
- The flushing of the plant shall be carried out by an experienced test engineer who shall have no
other duties during that task. The test engineer shall be mobilised sufficiently early to familiarize
himself with the specific job in hand. Flushing schedule will have to be issued a month before
flushing starts to make sure that site co-activities will be coordinated in a safe manner.
- The process lines and hot oil heating circuits have to be exclusively flushed with rinsing oil.
- The utilities lines like process water, service, fire, steam and condensates have to be water or
steam flushed.
- Instrument air and process air lines shall be cleaned with compressed air.
- For liquid media, the minimal amount of flushing fluid have to be at least 3 times the volume of
the pipeline to be flushed if recirculation is not possible (minimum indicative value).
- The use of temporarily hoses, spool pipes, blind flanges, iso-container or strainer (250µ) will be
needed for this operation.
- The drainage of the flushing fluid from the pipe network shall be by gravity when possible, or air
blowing or pigging.
- Each ABB Cellier’s equipment (case of skid) is already tested, flushed and cleaned in
workshop, and has to be disconnected from the rest of the plant during flushing activities.
- A follow-up document is recommended to know the cleanliness of the pipes and their status.
- Attention: Flushing activity is not intend to remove rust into pipe. The rust has to be removed
before construction.
4.1 PRINCIPLE
Pressure test has to be completed before flushing of the pipelines, latest during flushing. Anyhow
for flushing using liquid media, it must be done before liquid recirculation.
As a general rules, pressure tests are done at 1.5 times the max operating pressure of each line
and are performed in accordance with Customer or local contractor procedure and rules.
A special attention has to be given to the pigged lines. Indeed the pigged line has to be tested
at 3 different phases of the construction:
- Phase 1:
At the time of prefabrication, before mounting in the rack and without pigged equipment.
Accordingly, the pressure for tests can be as per normal pipe.
- Phase 2 Optional:
At the end of pipe construction and without pigged equipment installed. Accordingly, the
pressure for tests can be as per normal pipe. (Using spool replacing pigged equipment).
Phase 3:
At the end of the complete construction of the pigged line including pigged equipment
mounting.
Important note: Phase 3 has to be done only after flushing of the pigged line. The
flushing procedure of one pigged line is described in section 5.7:
To practice this test, pigged equipment shall be connected to air instrument with a minimum
pressure of 5 barg, in order to avoid being free of movement.
During the elaboration of the "test systems", some equipment will be an integral part of the system
to be tested (if in conformity with the specification of the piping class).
- Perform a complete verification in order to be sure of the definition and conformity with the
drawings and engineering documents (piping class, rating of flanges, quality of seals, etc. ...)
- Disassemble safety valves, control or regulating valves (replaced by spool pipes) and other
regulation units as well as reassembling after cleanings and/or tests.
- Protect electric and pneumatic sensitive equipment in case of any liquid projection.
The COMPANY will be responsible for all failures which may occur, either during the tests, or due
to the fact that they have not taken all necessary steps to empty completely the circuits after the
tests (in particular in case of frost).
A test report has to be issued by Company and has to be available at the request of ABB Cellier.
5. FLUSHING ACTIVITIES
5.1 PRINCIPLE
Flushing principle:
Cleaning of the system by flushing with fluid (liquid or gas) until total elimination of internal waste.
Fluid media:
- For Instrument air and process air lines: Compressed air ( Dry air / 25 µm max)
- For the process lines and hot oil heating circuits: Oil ( 175 µm max)
- For utilities lines like process water, service, fire, steam and condensates: water or steam
flushed.
Draining:
The evacuation of flushing fluid will be carried out at the pipe extremity, as near as possible to the
connections of the equipment which will be temporarily protected. Equipment which may suffer
from blocking or damage must be disconnected (pumps, compressors, exchanger…)
As process & instrument air lines are needed for others flushing works, it is strongly advised to
proceed of flushing of air networks as first step.
Blowing of the upstream side to ABB equipment should be carried out. All air regulators shall be
disconnected and protected from the dust or foreign matters.
Note: Air lines from ABB equipment shall not be flushed because they are considered clean when
installed.
5.3 TANKS
In a first time, all base oil storages tanks, additives storages tanks, minibulks tanks, holding tanks
and dedicated tanks will have to be cleaned manually by entering in the tanks itself (if possible)
and removing all dust, steel or other materials. Bases and walls of tanks will have to be brushed by
tissues or blooms containing base oil. Surfaces states must be perfect after this operation.
In some case, tanks can be delivered with special rustproof oil to prevent rust until final use of the
tanks. In case of rustproof oil isn’t compatible with fluid which will be allocated in the tank, it should
be cleaned taking into recommendation of rustproof oil supplier, then rinse with Base oil.
Suction pipes from tanks to pumps or others facilities to pumps will have to be cleaned manually
before mounting by removing all dust, steel or other materials to ensure that pumps will be fully
protected of damage caused by impurities.
Process pipes from pumps to blenders, kettles, Drum Decanting System, ILB, SMB or piggable
manifold will have be flushed with base oil using 3 times the volume of the length of the pipes.
Each ABB Cellier’s equipment is already tested, flushed and cleaned in workshop, and has
to be disconnected from the rest of the plant during flushing activities.
If some modifications are done after start-up or during production, each existing ABB
Cellier’s equipment would be probably already cleaned in production or will be cleaned
separately, then shall be disconnected during flushing procedure.
Before proceed to the flush of one pigged line, the following requirements have to be completed:
- The pigged line construction has to be completed and pressure tests as defined in
section 4.1 have to be done (phase 1 and phase 2 optional).
- Then, pigged equipment have to be mounted on the line including pigged stations and
In-line equipment like twin valves, distribution valves or others
- They have to be connected to instrument air (5 barg min)
- They have to be connected to process air (set at 2 barg min)
- One pig has to be available (the one in spare dedicated for flushing and usually
provided by ABB)
- Pigged line has to be in rest position: pigged equipment in close position (pig passing
through the line) and no pressure into the pigged line.
- One special blind flange in Stainless Steel has to be separately constructed (usually
not supplied by ABB) to proceed to flushing
Refer to below picture
Special blind flange for pigged line flushing
- Some amount of base Oil has to be introduced in the pigged line using product inlet
valve from launching station or nozzle available on the pipe (e.g. PI or PS).
Note: Recommended volume is using 1 m3 of Base Oil equivalent to one IBC.
- When targeted quantity is introduced into the pigged line, a pigging operation has to
be started. Air has to be injected go through air injection from pigged launching station
in order to push the pig. If needed air injection can be manually introduced by forcing
the solenoid valve (s).
- Then pig pushes the base oil and flush the line. When pig is closed to pigged receiving
station, base oil goes out from pigged line though the special blind flange.
- Pig stops against the special blind flange. The special blind flange is in stainless steel
and allow to check if pig is against flange by helping of one pig detector.
- Finally, the line can be depressurized and special flange dismantled to recover pig.
The shape of the special flange allows extracting easily the pig.
Attention: Before dismantling this special flange, operators have to take care that
there is no pressure anymore in the pigged line.
- If cleanliness is considered acceptable, flushing is finished, otherwise procedure has
to be repeated again until acceptable.
For additional information, refer to specification 3BFR4 ST000 J000014 – Start-up and
maintenance instructions for a pigged line.
ABB doesn’t allow any flushing or air blowing passing through the manifold during
flushing period. Lots of sensitive gaskets and internal parts can be damaged quickly.
Inlet pigged or dedicated lines and outlet pigged lines have to be disconnected from the
manifold to be flushed using removable spool pieces (usually not supplied by ABB).
Then for piggable lines only, an additional flushing has to be done with pig, as per described in
section 5.7.
Depending to the location of pig introduction system (on Manifold or at the opposite end), it is
strongly advised to push pig from Manifold toward end of the line in order to avoid bring back
waste into Manifold.
Then an additional flushing has to be done with pig, as per described in section 5.7.
Depending to the location of pig introduction system (on Manifold or at the opposite end), it is
strongly advised to push pig from Manifold toward end of the line in order to avoid bring back
waste into Manifold.
The steam lines must be flushed by steam or water to clear the carbon from the pipe internal.
ABB equipment should be disconnected and by-passed. For the rest of the plant, the sensitive
equipment on those lines are steam traps and piston valves seats that could be jammed or
damaged by foreign matters. They have to be removed and replaced by spool pipes or protected
before flushing.
After flushing, all pipelines except air circuits and pigged lines (special procedure) will be drained
and blown with compressed air to be completely emptied.
A flushing report has to be issued by Company and has to be available at the request of ABB
Cellier.
Solution 2:
- 1 line flushed at time
- Tank source used to introduce flushing oil, transfer pump used
- ILB disconnected and end of flushed line connected to one tank, truck, IBC, or
others
- No special cleaning system required
Solution 3:
- 2 lines flushed at the same time
- Only one tank source A used to inject flushing oil (can be the same tank used
for all lines flushing), transfer pump A used
- Both connections on ILB disconnected and both feeding lines connected
together with flexible
- End of second flushed line connected to one tank, truck, IBC, or others
- No special cleaning system required
Solution 2:
- 1 line flushed at time
- Tank source used to introduce flushing oil, transfer pump used
- SMB disconnected and end of flushed line connected to one tank, truck, IBC, or
others
- No special cleaning system required
Solution 3:
- 2 lines flushed at the same time
- Only one tank source A used to inject flushing oil (can be the same tank used for all
lines flushing), transfer pump A used
- Both connections on SMB disconnected and both feeding lines connected together
with flexible
- End of second flushed line connected to one tank, truck, IBC, or others
- No special cleaning system required
Solution 2:
- 1 line flushed at time
- Tank source used to introduce flushing oil, transfer pump used
- DDS disconnected and end of flushed line connected to one tank, truck, IBC, or others
- No special cleaning system required
Solution 3:
- 2 lines flushed at the same time
- Only one tank source A used to inject flushing oil (can be the same tank used for all
lines flushing), transfer pump A used
- Both connections on DDS disconnected and both feeding lines connected together
with flexible
- End of second flushed line connected to one tank, truck, IBC, or others
- No special cleaning system required
Important note:
If it is not possible to bypass the Blenders, washing nozzles (if any) have to be dismantled and
discharge pump has to be protected with a strainer (175 µm)
Solution 2:
- 1 line flushed at time
- Tank source used to introduce flushing oil, transfer pump used
- ABB / CT / VII disconnected and end of flushed line connected to one tank, truck, IBC,
or others
- No special cleaning system required
Solution 3:
- 2 lines flushed at the same time
- Only one tank source A used to inject flushing oil (can be the same tank used for all
lines flushing), transfer pump A used
- Both connections on ABB / CT / VII disconnected and both feeding lines connected
together with flexible
- End of second flushed line connected to one tank, truck, IBC, or others
- No special cleaning system required
Note :
- Procedure is suitable for dedicated and pigged lines.
§ For pigged lines, an additional flushing has to be done with pig, as per
described in section 5.7.
Depending to the location of pig introduction system (on Manifold or at the
opposite end), it is strongly advised to push pig from Manifold toward end of
the line in order to avoid bring back waste into Manifold.
Solution 2:
- 1 inlet line flushed at time
- Tank source used to introduce flushing oil, transfer pump used.
- Manifold disconnected and connected to one tank, truck, IBC, or others
- No special cleaning system required
Note :
- Procedure is suitable for dedicated and pigged lines.
§ For pigged lines, an additional flushing has to be done with pig, as per
described in section 5.7.
Depending to the location of pig introduction system (on Manifold or at the
opposite end), it is strongly advised to push pig from Manifold toward end of
the line in order to avoid bring back waste into Manifold.
Solution 3:
- 2 inlet lines flushed at the same time
- Only one tank source A used to inject flushing oil (can be the same tank used for all
inlet lines flushing), transfer pump A used
- Both connections on Manifold disconnected and both inlet lines connected
together with a flexible
- End of second flushed lines connected to one tank, truck, IBC, or others
- No special cleaning system required
Note :
- Procedure is suitable for dedicated and pigged lines.
§ For pigged lines, an additional flushing has to be done with pig, as per
described in section 5.7.
Depending to the location of pig introduction system (on Manifold or at the
opposite end), it is strongly advised to push pig from Manifold toward end of
the line in order to avoid bring back waste into Manifold.
Note :
Further to this flushing, an additional flushing has to be done with pig, as per described in
section 5.7.
Depending to the location of pig introduction system (on Manifold or at the opposite end), it
is strongly advised to push pig from Manifold toward end of the line in order to avoid bring
back waste into Manifold.
Solution 2:
- 1 outlet line flushed at time
- One tank source (from inlet line) used to introduce flushing oil, transfer pump used
- Inlet and outlet removable spools from manifold disconnected, then lines connected
together with a flexible
- End of the outlet line connected to one tank, truck, IBC, or others
- No special cleaning system required
Note : Further to this flushing, an additional flushing has to be done with pig, as per
described in section 5.7.
Depending to the location of pig introduction system (on Manifold or at the opposite end), it
is strongly advised to push pig from Manifold toward end of the line in order to avoid bring
back waste into Manifold.
Warning notices reading “keep away – pipeline under test” shall be placed at appropriate locations
while testing. Notice shall be in both English and the local/working language.
The customer or local contractor shall prepare an emergency plan which shall describe actions to
be taken in case of leaks or burst. The emergency plan should include, but not limited to the
following:
Protective clothing, gloves and goggles shall be worn when handling chemicals. A safety shower
and eyes-bath shall be available at appropriate location.
Any leaking flanges visually inspected should be tightened only after the pressure in the test
section is reduced to a safe level (static head + 1 bar)
The tests on site shall be left in a clean condition and free of debris. The waste, chemicals, dyes
etc. shall be disposed of as per the customer disposal requirements.
End of document