Your dreamhome is growing day by day, brick by brick!!

Illustration for a typical time frame of 1000 sq.ft ground floor house construction -

Week No.
List of Activities Start Week Finish Week 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52
Planning & Purchase of land, Registration 1 4 1 4
Consulting Engineer/Architect, Design Drwaings, Approval from authority 5 12 5 12
Time Schedule and Monthly Cash Outflow 10 11 10 11
Contractor Selection 10 11 10 11
Borewell 12 12 12
Excavation as per drawing 13 15 13 15
Footing/Foundations* 16 17 16 17
Pillars/Columns (Up to plinth level) 18 19 18 19
Soil filling in trenches and compaction till ground level 19 19 19
Plinth Construction* 20 21 20 21
Pillars up to lintel level* 22 23 22 23
Lintel* 24 27 24 27
Pillars up to roof level* 26 27 26 27
Soil filling and compaction till plinth level 26 27 26 27
Roof Slab* 28 32 28 32
Brick Work & Curing 28 34 28 34
Ducts for electrical wiring 35 36 35 36
Frames for doors & windows 35 35 35
Plastering & Curing 37 39 37 39
Water Treatment, Heat Treatment 40 40 40
Flooring/Tiling 41 44 41 44
Electrical Wiring 43 45 43 45
Water Supply, Sanitary & Plumbing 45 47 45 47
Doors & Windows 45 47 45 47
Painting 48 51 48 51
Connections for electricity and drainage 50 51 50 51
Inside furnishing 51 52 51 52
Completion/Occupancy Certificate 52 52 52
Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10 Month 11 Month 12
*Including reinforcement, shuttering, concreting, curing, deshuttering
Your dreamhome is grow

Illustration for a typical time frame of

Start Finish
S.No List of Activities Week Week 1 2 3 4 5 6 7 8 9 10 11
1 Planning & Purchase of land, Registration 1 4 1 4
2 Consulting Engineer/Architect, Design Drwaings, A 5 12 5
3 Time Schedule and Monthly Cash Outflow 10 11 10 11
4 Contractor Selection 10 11 10 11
5 Borewell 12 12
6 Excavation as per drawing 13 15
7 Footing/Foundations* 16 17
8 Pillars/Columns (Up to plinth level) 18 19
9 Soil filling in trenches and compaction till ground l 19 19
10 Plinth Construction* 20 21
11 Pillars up to Plintel level* 22 23
12 Lintel* 24 27
13 Pillars up to roof level* 26 27
14 Soil filling and compaction till plinth level 26 27
15 Roof Slab* 28 32
16 Brick Work & Curing 28 34
17 Ducts for electrical wiring 35 36
18 Frames for doors & windows 35 35
19 Plastering & Curing 37 39
20 Water Treatment, Heat Treatment 40 40
21 Flooring/Tiling 41 44
22 Electrical Wiring 43 45
23 Water Supply, Sanitary & Plumbing 45 47
24 Doors & Windows 45 47
25 Painting 48 51
26 Connections for electricity and drainage 50 51
27 Inside furnishing 51 52
28 Completion/Occupancy Certificate 52 52
Month 1 Month 2 Month 3
*Including reinforcement, shuttering, concreting, curing, deshuttering
amhome is growing day by day, brick by brick!!

pical time frame of 1000 sq.ft ground floor house construction -

Week No.

12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42

12

12
13 15
16 17
18 19
19
20 21
22 23
24 27
26 27
26 27
28 32
28 34
35 36
35
37 39
40
41

Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10


43 44 45 46 47 48 49 50 51 52

44
43 45
45 47
45 47
48 51
50 51
51 52
52
Month 10 Month 11 Month 12