Documente Academic
Documente Profesional
Documente Cultură
I
n the summer of 2009, the developer Jeddah Economic opened in Dubai, United Arab Emirates (UAE); but to create a
Company invited a limited number of competing design unique architectural identity for what would be the next
teams to submit proposals for a 1 km (0.6 mile) tall tower world’s tallest building.
to be located in Jeddah, along the Red Sea in the Kingdom of Not only were a handful of design teams in competition
Saudi Arabia (KSA). A previous concept for a mile-high tower for the commission, but four internationally recognized
had been considered to be economically unfeasible and general contractors were also vying for the project at the
unbuildable from a technical standpoint. The participants in same time. Of the several judging criteria, roughly half the
the design competition were provided detailed instructions to total weight would be given to construction viability and
build upon the success of the Burj Khalifa, then recently structural/architectural efficiency. It wasn’t until March of
2010 that the team of Adrian Smith + Gordon Gill
Architecture and Thornton Tomasetti structural engineers
were notified that they had been awarded the design contract,
and that the Saudi Binladen Group would be the builder. The
winning proposal was a powerful, linearly tapering, three-
legged tower form (Fig. 1).1,2
This article traces the key structural engineering analysis
and design considerations for the Jeddah Tower, which will be
the first man-made structure to reach 1 km in height.
Descriptions of the most critical aspects of the technical
solutions for the foundation system, the wind engineering and
testing program used to develop the concrete bearing wall
system resisting wind and seismic lateral loads, and the key
analytical design considerations are included. The tower
design is presented as a logical historical step in the continued
development and advancement of tall and ultra-tall tower
structures. Upon completion in 2019, Jeddah Tower will take
its place alongside the tallest and most recognizable towers in
the world (Fig. 2).
Planning Considerations
The bearing wall formulation is a very powerful system
with the potential to reach even greater heights for future
towers. It is best employed for towers of primarily residential
use, such as Jeddah Tower, as the walls tend to compartmentalize
the plan into discrete, limited areas rather than open floor
spaces typical of office towers. For Jeddah Tower, there is a
distinct hierarchy in the arrangement of the walls (Fig. 3) and
their primary importance to the overall system performance is
described:
•• Core walls form the triangular, torsional “hub” of the
Fig. 4: A 4 m (13 ft) thick “sky raft” transfers loads from the spire silo tower. Organized around the central core of vertical
to the bearing wall system below transportation shafts and exit stairs, these walls are
Tower Concrete
Tower piling installation commenced in June 2013 after Experience with the construction of other supertall towers
extensive in-place pile load testing was conducted exclusively has shown that the most economical designs specify
with Osterberg load cells. The raft foundation was constructed maximum concrete strengths based on what can reasonably be
in the spring of 2014, with four separate massive concrete supplied and delivered to specific height limits. For this
placements (three wings and final central area placement) project, Thornton Tomasetti recommended to the owner and
without significant incident. Prior to construction of the mat, a the contractor that 100 MPa (14,500 psi) concrete be supplied
4.5 m (15 ft) test cube was constructed on-site and up to the 300 m (984 ft) level, as this would reduce the
instrumented to verify the concrete temperatures through the amount of reinforcement in the bearing wall system and
thickness of the mat. Self-consolidating concrete was chosen minimize overall costs. However, without adequate local
for the raft foundation placements, which were achieved experience with the necessary concrete mixtures, the final
through pumping and using several simultaneous deposit decision was to specify a maximum concrete cylinder strength
points through placing booms (shown in Fig. 8). As is of 85 MPa (12,330 psi) and an average static modulus of
routinely done in the KSA, ice was used in the mixture, and elasticity (MOE) of 43 GPa (6.2 × 106 psi) at 90 days for the
approximately 50% of the portland cement was replaced by lower tower walls and coupling beams. High-strength (520
fly ash to control the in-place concrete temperatures during MPa [75,000 psi]) reinforcement is used in the walls over the
the hydration process. The resulting temperatures during the bottom 300 m of the tower to control congestion. The tower
hydration process were less than 155°F (68°C) and maximum bearing walls are being constructed with flowable mixtures
temperature differentials were less than 40°F (22°C). using high-quality coarse aggregate from nearby quarries, and
the mixtures have consistently produced strengths well above
Structural Analysis 100 MPa. Specified concrete strengths are reduced to 75 MPa
Several comprehensive analysis models were developed (10,880 psi) in the middle third and 65 MPa (9430 psi) in the
for evaluating various design aspects and at various times upper third of the tower.
during the design process (Fig. 9). Tower dynamic behavior
and member load demands were corroborated across different Construction Well Underway
FEA software platforms such as ETABS, Midas Gen, and The tower superstructure is moving along nicely and has
Strand7. Furthermore, SAP2000 was used to study elastic reached an elevation of 178 m (584 ft) above the raft
buckling behavior and confirm global stability. Abaqus was foundation, with the central triangular core extending 10 to 12
employed to study with high fidelity the tower’s inherent stories above the following wing walls. Floor slabs are
nonlinear behavior. In addition to corroborating the ETABS following the wall construction (Fig. 10). As the tower tapers,
results, Midas Gen was used to conduct comprehensive it is expected that the construction progress will begin to
evaluations of construction sequencing, including nonlinear significantly accelerate as less concrete and reinforcement is
time-dependent concrete modulus, creep, and shrinkage inputs. required to be placed for each cycle.
As the structural system is very much standardized and The tower structure is expected to be completed in 2019. A
repetitive, the technically intensive design process was complete long-term structural health monitoring (SHM)
nevertheless fundamentally quite manageable. The program is being implemented to verify the behavior and
fundamental translation periods of the tower are approximately performance of the tower both during construction and over
12 seconds with a torsional period of 6 seconds. These periods the life of the building. Elements of the piling, raft foundation,
testify to the underlying high stiffness for such an ultra-tall, tower walls, and upper levels of the spire are included in the