Documente Academic
Documente Profesional
Documente Cultură
Description
1 Concrete Demolition
1.2.1 Demolition at Lower Ground Level (+96.05m) (With Diamond Saw Cutting)
1.2.2 Demolition at Upper Ground Level (+102.05m) (With Diamond Saw Cutting)
1.2.3 Demolition at First Floor Level (+107.95m) (With Diamond Saw Cutting)
Providing & erecting sturdy H frames, other structural steel members for temporary
nature back propping / scaffolding as specified in the structural drawings or any other
level as required for a specified period. Providing & fixing steel props with steel section
or wooden runners, (4”x 3”) if approved and planks & bracings to support beam, slab &
adjacent areas of column etc. as per instruction and as directed by consultant etc.
1.3 complete. The scope shall also include covering entire building portion to be dismantled
safety including providing necessary horizontal supports etc. with column or beam and
maintaining the same for the entire duration of the works including dismantling & taking
away on completion of work from the site etc. complete. The contractor under specif
cases shall submit the design for shuttering, staging, supporting etc for Consultants
review & comments.
3 Structural Strenghtening
Providing / supplying, fabricating, transporting structural steel members, hoisting using
crane, lifting, erecting and placement in its final position of grade E 250 Mpa and
required size comprising of built up sections, readily available sections, welded frame
works, etc with necessary castellations, bolting provisions, slots, nitches, bearing plates,
connection plates, extension plates, splices, etc for proper execution of works.
Cost to include straightening, cutting, welding, bending to shape and size, provisions for
bolting, primer application, and approved factory finish including stamping, packing,
transportation and storage after necessary submission and approval of designs,
development drawings, GA drawings, shop drawings, fabrication drawings from the
principle consultant.
Fabricated structural steel members shall be provided with 2 coat of rusticide till final
erection is carried out, at site.
The rate to include the cost of all materials, labour, tools, tackles, cranes, devices and
plants, wastage etc., as per specification and drawings complete
The structural steel work shall include welded / bolted and built up sections, trusses,
purlins, frame work welded and / or bolted, girders, gusset plates, base plates, cleats,
3.10 installing inserts, bearing plates etc., as per drawings. Cost to include fabricating
necessary Gusset Plates, welding Stiffener plates, Brackets, Bolts, Cleats, seating
angles, bolts, washers, and grouting for bolts etc., to the required size, shape, alignment
etc, as per the drawings .
The rate to include the cost of all materials, labour, tools, tackles, cranes, devices and
plants, wastage etc., as per specification and drawings complete
The structural steel work shall include welded / bolted and built up sections, trusses,
purlins, frame work welded and / or bolted, girders, gusset plates, base plates, cleats,
installing inserts, bearing plates etc., as per drawings. Cost to include fabricating
necessary Gusset Plates, welding Stiffener plates, Brackets, Bolts, Cleats, seating
angles, bolts, washers, and grouting for bolts etc., to the required size, shape, alignment
etc, as per the drawings .
cum 368 -
cum 324 -
cum 724 -
cum 198 -
Sqm 14,762 -
-
MT 235 -
mt 40 -
-
mt 113 -
mt 90 -
mt 120 -
sqm 3,850 -
-
-