Documente Academic
Documente Profesional
Documente Cultură
PAGE
2 OF 10 REV. 0A
1.0 PURPOSE
To ensure that all materials required for construction work conform to Project Material
0A Specification, and by applying certain control procedures from Supplier/Vendor to
prevent the undesirable use and to set up the traceability of the materials and equipment.
2.0 SCOPE
3.0 DEFINITION
None
4.0 RESPONSIBILITIES
Monitoring the control of the materials received & required for construction work.
Claiming to the insurance company for the damage to and/or loss of materials.
0A 4.3 QC Inspector
To Inspect and test of arriving Materials and Equipment’s are as per project
construction requirements.
4.4.1 Managing and tracing for the overage, shortage and/or damage of
materials required for construction work.
4.4.2 Preparing the documents for the claim of damage and/or loss of
materials required for construction work.
0A 4.4.3 Identify and confirm to the requirements of the purchase documents and
make sure that procured materials, equipment’s are sourced from
SAMAC No: N-00-PQ-5-11-PR
MATERIAL RECEIVING CTCI No: XA95-0000-N511
PROCEDURE PAGE DATE 01-Dec-2014
3 OF 10 REV. 0A
Company Approved Supplier and that all Materials & equipment
received are controlled in accordance with this procedure, ITB &
applicable standards.
Procurement Construction
Prepare Purchase Order Representative Supervisor
Vendor’s Construction
Fabricate & Prepare Quality Documents Representative Supervisor
Site Warehouse
Prepare Receiving Inspection & Testing Plan Supervisor
Site Material
Site Warehouse Control Engineer/
Supervisor/ Site Control
Inspection Inspection Engineer Manager
Unaccepted
Accepted
Professional
Testing (If Required) Inspector/ Responsible Party
Unaccepted Construction Inspection
Engineer
Accepted
Site Warehouse
Fill out Inspection Record Supervisor
Inspection Engineer
Site Warehouse
Receiving & Storing Supervisor
4 OF 10 REV. 0A
5.1 Receiving Plan
5.1.2 Upon delivery, Site Warehouse Supervisor shall fill out the
Equipment/Material Inspection Record and notify the QC Inspector to
proceed with the inspection/testing.
A. Visual Inspection
B. Report Review
C. Miscellaneous
5 OF 10 REV. 0A
5.2.2 Results of Inspection / Testing
E. When the required inspection and testing have been completed, the
Site Warehouse Supervisor may proceed with the receiving and
recording of materials required for construction work.
5.3 The materials required for construction work shall not be released for use
provided that it has not been inspected or otherwise verified. But, if urgent case
occurs, the use of the un-inspected product shall be approved by Project Site
Manager and shall be specifically marked as individual case.
5.4 For the materials supplied by subcontractor (i.e. directly used in field construction
work), QC Inspector shall check for the associated mill sheets, heat numbers or
test reports. And construction engineer (supervisor) shall verify the quantity and
trace the use of the supplied materials
5.5 Unless otherwise specified by the project, all inspection/testing records shall be
kept in file for at least one year after project completion.
5.6 Receiving/Storage/Custody/Maintenance
6 OF 10 REV. 0A
6.0 RELEVANT PROCEDURES
7.0 ATTACHMENTS
7 OF 10 REV. 0A
Attachment-1 Material Inspection Record (MIR)
ITP-MIR-1
MATERIAL INSPECTION RECORD RECORD NO.
DATE
Material Description:
Remarks
Warehouse Received
CTCI PMT
By
Name
Signature
Date
Attachment-2 Sample of Over/Shortage/Damage (OSD) Report (Page 1/2)
Attachment-2 Sample of Over/Shortage/Damage (OSD) Report (Page 2/2)