Sunteți pe pagina 1din 4

Conplast F292 constructive solutions

Foam cement admixture


considered and trials performed to ensure
Uses compliance.
For the production of foamed low density mortars.
Typical application include trench filling for road
reinstatement, lightweight roofing screeds and the Typical Properties
filling of undesirable voids such as old sewers and
Appearance : Clear liquid
solvent tanks.
Specific Gravity : Typically 1.10 at 20oC
Compatibility with other admixtures
Advantages
Conplast F292 should not be mixed with other
• When used with approved foam generating admixture. The Fosroc Technical Service
equipment, produces a consistent pre-foam, Department can give advice on the use of other
which is stable under the alkaline conditions of admixtures in the same finished mortar.
cement mortars.
Compatibility with cements
• Easily controlled addition of pre-foam to pre-
batched mortar allows close control of finished Conplast F292 is compatible with Portland cement.
product density. Consult the Fosroc Technical service Department for
advice on use with special cements or cement
• Suitable for production of a wide range of replacement materials.
finished densities.
• Foamed mortar provides an easily placed
lightweight product at an economic price. Limitations
Conplast F292 should not be diluted with water
which is bellow 10oC are encountered; the water can
Description be warmed to above 10oC by means such as the
use of immersion heater. Dilution of Conplast F292
Conplast F292 is a concentrated solution of selected
should not be allowed to cool to bellow10oC.
surfactant materials, which is diluted with water
before use. Low temperatures significantly reduce the foaming
effectiveness of the product. If it is not possible to
Used with approved Fosroc Foam Generator,
avoid such low temperatures then the use of
Conplast F292 produces a consistent pre-foam that
Conplast F294 is recommended.
is stable under alkaline conditions and therefore
suitable for use in the production of foamed mortars. Dilutions should not be made with concrete wash
water or water from other sources containing high
Foamed mortar has many uses, including trench
levels of calcium ions.
filling during road reinstatement, lightweight roofing
screeds and void filling.
The material is highly mobile, being able to flow for Dosage
long distances under its own hydrostatic head, and
is therefore particularly suitable for filling old sewers The dosage of Conplast F292 required will vary,
and solvent tanks. depending on the desired final mortar density and
the original starting material. Further details on a
By controlled variation of the amount of pre-foamed suitable procedure for determining the required
added to a premixed mortar, the production of a quantities are given later in this sheet. Typical
desired density finished product can be achieved, dosages are in the range 0.6 to 1.0 litres of undiluted
the minimum attainable density will vary for material per cubic metre of finished mortar over a
particular mix designs and performance density range of 1500 to 800 kg/m3. The use of
requirements. Typical finished densities of down to dosages outside this range may be suitable in
1000 kg/m3 can be obtained with 2:1 sand: cement certain circumstances, in these cases the Fosroc
mortars and down to 600 kg/m3 with 1:1 sand: Technical Service Department should be contacted
cement mortars. Local materials may give values for advice.
above or bellow these values. It is important that the
specific requirements of a particular mix are

Page 1
Technical report

Application instructions

Foam addition procedure


Conplast F292 should be diluted with potable water After production, foamed mortar will be of a fluid
and used to produce a pre-foam that is mixed into a self-levelling consistency and therefore it is not
pre-batched mortar. Varying the amount of foam usually practical to transport it from plant to site. It
added to a mortar allows the production of a range will normally be most convenient for the pre-foam to
of densities of finished product. be added on site to a mortar delivered in a readymix
Complast F292 is not intended for direct addition to truck. If foamed mortar is transported for long
mortar and use in this manner will not produce distances in the truck drum, or if there are significant
foamed systems. time delays between the addition of the pre-foamed
and the placement of the foamed mortar, some
The Fosroc Foam Generator has been designed to breakdown of the foam may occur. This will increase
produce a pre-foam system. This equipment is density and reduced yield.
recommended for use with Conplast foam
admixtures. All information in this data sheet is When foam production is required, the valve on the
based on the use of this equipment. delivery unit is turned from the recirculation to the
delivery position and a pre-foam will be produced.
The pre-foam is added into the back of the readymix
Dilution and Preparation drum with the drum on fast spin. The rotation of the
drum blends the pre-foam and mortar together to
Dilute Conplast F292 by taking 4 litres of admixture
produce the finished foamed mortar. Fast spin
and diluting to 100 litres with water, this can easily
should be maintained for 2 – 4 minutes after the
be done in the holding tank of the Fosroc Foam
addition of the pre-foam to ensure complete
Generator, using the volume graduation marks.
blending.
Dilutions should be made using potable water at a
Foam generation can be stopped at any time by
temperature above 10oC. Concrete wash water is
returning the valve at the delivery unit to
not suitable. If the locally available water has a high
recirculation position.
hardness it is recommended that the diluted material
produced be used immediately. When blending of the pre-foam and mortar is
complete, the foamed material is ready for
With the system set to recirculation, the pump on the
placement. The mortar is self-levelling and can be
generator can be switched on. The pump can
flowed into place directly, or down trenches, gullies
remain switched on even when foam is not
or pipes. The foamed mortar can also be pumped
immediately required but if this is done the valve at
using standard concrete pumping equipment.
the delivery unit should be kept in the recirculation
Contact the Fosroc Technical Service Department
position until foam is required.
for further information.
If more than the initial 100 litres of diluted material
are required, the generator holding tank can be
topped up at any time. The volume graduation Initial mortar mix proportions
marks on the level tube provide a useful means of A sand: cement mortar should be pre-batched into
measurement for this purpose. Adding litre of the readymix truck. Best results will be obtained with
Conplast F292 diluted to 25 litres with potable water finer sands with a high proportion of material
each time should do topping up. During topping up, passing a 300µm sieve. The use of sands containing
the valve at the delivery unit should be switched to large amounts of coarse material, larger than 2 mm
the recirculation position for two minutes to ensure in diameter, may lead to a less stable foamed
an even mixing. product, particularly at the lower density.

constructive solutions Page 2


Technical report

If densities down to 1000 kg / m3 are required, it is Figure 1 shows, on the horizontal axis, typical foam
recommended that the batched mortar should be 2:1 addition times that will be required to produce a
sand: cement mix. If densities bellow 1000 kg / m3 finished foamed material of the target wet density,
are desired it is recommended that a 1: 1 sand read off the left hand axis, for each cubic metre of an
cement mortar should be used. Trials should be original mortar of 2200 kg/m3 density. In practice this
performed to check that the combination of strength can be used for most mortar mix designs without
and density desired are obtained. Mortar mix major variation.
proportion may be varied from the suggested
Figure 1 should be used as follows:
starting values above if so indicated by the results
obtained in the trials. 1. Determine the desired finished density and the
amount of original mortar batched in the readymix
truck. The amount batched can most easily be
Initial mortar workability obtained from the batch ticket.
The delivered mortar should be batched to have a 2. For the first truck of a pour, read off the lower
workability equivalent to a collapsed slump prior to curve on Figure 1 the suggested addition time for
the addition of the foam; the water content to give the finished density required. The value obtained is
this will typically result in a water: cement ratio on the addition time for each cubic metre of original
the range 0.5 to 0.6 but may vary depending on the mortar. Add the pre-foam required and measure the
sand grading. Where appropriate to the needs of a density produced (a suitable method of density
particular job or necessary due to the water demand measurement is detailed below).
of local materials, values outside these limits may be
3. If the density obtained is higher than that desired
used.
then more pre-foam could be added. To estimate the
An alternative method of assessing a suitable additional amount required, determine where on the
workability for the starting mortar is to observe it in figure the measured density and actual addition time
the readymix truck prior to the addition of the foam. meet and then move parallel to the existing lines
With truck drum on slow spin, a suitable mortar until the final desired density is reached. This point
should appear to virtually self-level in the drum and will then indicate the total pre-foam addition time
should flow freely over the back blade. required, again for each cubic metre of starting
mortar and the extra time needed can be calculated
The workability of the delivered mix is particularly
by the difference between this value and the addition
critical to the amount of foam required for a desired
time so far.
final density. Mixes of lower workability than that
suggested above may cause difficulties in blending 4. For subsequent trucks of the same pour and
the pre-foam into the mortar and, therefore, using the same materials, the addition time per cubic
extended mixing periods may be required. If the pre- metre of original mortar should be the same as for
foam does not blend into the mortar after three to the first truck. If the volume of original mortar varies
four minutes fast spin, a further 10 to 20 litres of between trucks the total pre-foam addition time must
water should be added into the back of the truck and be modified to allow for this. It is recommended that
the fast spin period repeated. the foamed density should be checked for each
truck individually to ensure compliance with
requirements.
Calculation of required foam quantity
The Fosroc Foam Generator produces a pre-foam at
a consistent expansion and output rate. The most
convenient means of measurement of addition is to
time the process.

constructive solutions Page 3


Certain factors may also lead to changes in density
Density Measurement
and therefore reduced yield. Losses will not always
The density of the foamed material can be occur but their possibility should be taken into
measured by using a spring balance and a container account. Possible causes include; delays in
of known volume (approximately 5 litres is suitable). discharge from a truck, transport of foamed mortar
The weight of foamed material to fill the container over long distances such as may occur if pre-foam is
will allow the calculation of a wet density. The dry added at a readymix plant instead of on site, and
density of the foamed material will typically be 50 – pumping.
100 kg / m3 lower than the wet density. It is
If foamed concrete is placed against a dry substrate
recommended that the wet density measurement is
there is the possibility of foamed collapse due to the
always used as a routine quality control check.
suction of moisture out of the foamed mortar. If this
situation exists, the substrate should be wetted
Yield before placing the foamed mortar to reduce the
likelihood of the problem.
Unless extremely tight control is exercised, which
will require extra time, the density of a foamed
mortar is likely vary by ± 100 kg / m3. This variability Cleaning and Disposal
should be allowed for in estimating the possible
Spillages of Conplast F292
volume of material required.

PT.FOSROC
Indonesia
Jl.Akasia II Blok A8 No.1
Delta Silicon Industrial Park
Lippo Cikarang telephone: fax: email:
Bekasi 17550 +62 21 897 2103 +62 21 897 2107 indonesia@fosroc.co.id
Indonesia +62 22 520 1308 +62 22 522 2713
www.fosroc.com +62 31 502 9142 +62 31 502 2711

Page 4

S-ar putea să vă placă și