ENGINEERPNG DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH QUALITY ASSASMENT
NEEDS MODIFICATION / RECONSTRUCTION ON NATIONAL WATERWAY-5 IN PLAN
ODISHA.
Contents
Chapter 1 - Introduction ............................................................................................................ 2
i|Page
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED
ENGINEERPNG DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH QUALITY ASSASMENT
NEEDS MODIFICATION / RECONSTRUCTION ON NATIONAL WATERWAY-5 IN PLAN
ODISHA.
Chapter 1 - Introduction
1.1 General
Government of India had declared the National waterway NW-5 in Mahanadi / Brahmani delta,
Matai River & East Coast Canal (ECC) in November 2008 for total length of about 600 km. The IWAI
has taken up action for implementing phase 1 development of 212 Km National Water way no 5
between Pankapal to Paradeep and Dhamra and therefore intend to examine the cross-drainage
structures such as bridges (except railway bridges) for adequacy of required horizontal and vertical
clearance for class-III waterway and suggest modification/reconstruction plan including detail
engineering report.
Details of the existing bridge
The bridge at jokadia is located over river Kharasrota connecting the roads between Jokadia and
Kanhupur in the district of Jajpur. The bridge is located at distance of 11.700 km from Pankapal
(considering Pankapal as 0.000 km at NH-5 A). The existing bridge of 7 spans of 41.5 m c/c with 5.5 m
carriageway width was constructed in the year 2006,. All the foundations are of well foundation
having 7 m dia well for abutments and 6.0 m dia. well for piers.
The existing bridge is of wall type substructure for pier shafts and abutments, with Roller
rocker bearing & RCC box type Girder with RCC deck superstructure. The wearing coat of the bridge
is of cement concrete wearing coat with surface reinforcement.
2|Page
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED
ENGINEERPNG DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH QUALITY ASSASMENT
NEEDS MODIFICATION / RECONSTRUCTION ON NATIONAL WATERWAY-5 IN PLAN
ODISHA.
Senior Material
Engineer
QC/Asst. QC
QC/Asst. QC
Engineer (Eartwork,
Engineer
Concrete and Misc.
(Pavement courses)
works)
3|Page
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED
ENGINEERPNG DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH QUALITY ASSASMENT
NEEDS MODIFICATION / RECONSTRUCTION ON NATIONAL WATERWAY-5 IN PLAN
ODISHA.
4|Page
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED
ENGINEERPNG DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH QUALITY ASSASMENT
NEEDS MODIFICATION / RECONSTRUCTION ON NATIONAL WATERWAY-5 IN PLAN
ODISHA.
viii. Preparation of JMF for flexible pavement & concrete mix design.
ix. Calculation of test results from test observations carried out by Lab Technician.
x. Selecting borrow areas.
xi. Periodical checking of calibration of WMM Plant, Hot mix plant, Batching plan
xii. Preparation of summary test results for monthly progress report.
5|Page
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED
ENGINEERPNG DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH QUALITY ASSASMENT
NEEDS MODIFICATION / RECONSTRUCTION ON NATIONAL WATERWAY-5 IN PLAN
ODISHA.
6|Page
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED
ENGINEERPNG DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH QUALITY ASSASMENT
NEEDS MODIFICATION / RECONSTRUCTION ON NATIONAL WATERWAY-5 IN PLAN
ODISHA.
xiii) If the contractor do not have own laboratories, they shall arrange to conduct the tests in the
laboratories of reputed academic institutions or in accredited third party laboratories.
xiv) During construction, the contractor shall conduct tests on every materials which shall be used in
the project including raw materials, processed materials, manufactured materials, proprietory
materials, etc.
7|Page
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED
ENGINEERPNG DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH QUALITY ASSASMENT
NEEDS MODIFICATION / RECONSTRUCTION ON NATIONAL WATERWAY-5 IN PLAN
ODISHA.
i.Electrically operated
b Oven ii. Thermo statically controlled (including thermometer)
Iii. Stainless steel interior from 0o C to 220o C
200 mm internal dia (brass frame and steel/or brass
c IS Sieve wire cloth mesh) consisting of sieve sets of required
sieve sizes complete with lid.
Capable of shaking 200mm dia sieves- electrically
d Sieve shaker
operated with time switch.
e top Watches 1/5 Sec Accuracy
i. Compressing Beakers
f Glass Ware ii. Pipettes
Iii. Dishes
Iv. Measuring cylinders (100 to 1000 cc)
i. 600 mm x 450 mm x 5 mm
g Enamel trays ii. 450 mm x 300 mm x 40 mm
Iii. 300 mm x 250 mm x 40 mm
Liquid limit devise with ASTM
h as per IS:2720(Part 5)
grooving tools
Sampling pipettes fitted with
i 10 ml. capacity
pressure and suction inlets
Compaction apparatus
j (Proctor) complete with collar, as per IS:2720 (Part 7)
base plate and hammer and all
other accessories.
Modified AASHTO compaction
k apparatus or heavy as per IS:2720 (Part 8)
compaction
Sand pouring cylinder with
l conical funnel and tap as per IS:2720 (Part 28)
including modern equipment.
Natural sand passes through 1
m
mm and retained on 600 mm as per IS: 2720 Part 28.
8|Page
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED
ENGINEERPNG DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH QUALITY ASSASMENT
NEEDS MODIFICATION / RECONSTRUCTION ON NATIONAL WATERWAY-5 IN PLAN
ODISHA.
Sl
no Equipments Remarks
Sampling tins with lids 100 mm
dia x 75 mm ht. 1/2 kg capacity
n and miscellaneous items like
moisture tins with lid 50 gm
etc.
9|Page
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED
ENGINEERPNG DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH QUALITY ASSASMENT
NEEDS MODIFICATION / RECONSTRUCTION ON NATIONAL WATERWAY-5 IN PLAN
ODISHA.
Sl
no Equipments Remarks
Apparatus for determination of
g specific gravity of fine and
coarse aggregate as per IS:2386(Part 3)
3 liter,15 liter and 30 liter
cylinder for checking bulk
h as per IS:2386 Part 3
density of aggregate with
tamping rod.
i Electronic balance 500 gm,2.0 kg,5.kg and 10.0 kg sensitive to 0.1 gm
Cement and Cement Testing
3
Equipment
High frequency mortar cube Cement motor moulds (70.6 mm W x 70.6 mm Lx 70.6
a
vibrator for cement testing mm H)
Vicat needle apparatus for
b as per IS:269
setting time with plungers
Soundness testing apparatus
c
for cement (Le Chattlier)
i. 5 -20 kg capacity electronic type - accuracy 1 gm
d Weigh Balances ii. 500 gm capacity electronic type - accuracy 0.01 gm
iii. Electronic 5 kg capacity accuracy 0.5 gm
iv. 50 kg capacity electronic type - accuracy 2 gm
Concrete mixer power driven,
e
1 cft capacity
10 | P a g e
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED
ENGINEERPNG DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH QUALITY ASSASMENT
NEEDS MODIFICATION / RECONSTRUCTION ON NATIONAL WATERWAY-5 IN PLAN
ODISHA.
Sl
no Equipments Remarks
Constant temperature bath for
accommodating bitumen test
specimen, electrically operated
a
and thermostatically controlled
(to accommodate minimum six
specimens)
Penetrometer automatic type,
b including adjustable weight as per IS: 1203
arrangement and needles
Bitumen laboratory mixer
c including required accessories
(20 Itrs.)
d Ductility meter
e Furol Viscometer
11 | P a g e
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED
ENGINEERPNG DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH QUALITY ASSASMENT
NEEDS MODIFICATION / RECONSTRUCTION ON NATIONAL WATERWAY-5 IN PLAN
ODISHA.
Sl
no Equipments Remarks
Oven-electrically operated,
thermostatically
q controlled(including
thermometer), stainless steel
interior from O°C to 220°C
Cannon Manning Viscometer
for determination of Absolute
r viscosity and Cannon Fenske
Viscometer for determination
of Kinematic viscosity.
a Direct shear test apparatus having 12 variable speed and 2 KN proving ring with all
the accessories given in IS:2720 Part 13.
12 | P a g e
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED
ENGINEERPNG DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH QUALITY ASSASMENT
NEEDS MODIFICATION / RECONSTRUCTION ON NATIONAL WATERWAY-5 IN PLAN
ODISHA.
13 | P a g e
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED
ENGINEERPNG DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH QUALITY ASSASMENT
NEEDS MODIFICATION / RECONSTRUCTION ON NATIONAL WATERWAY-5 IN PLAN
ODISHA.
Sl
no Equipments Remarks
k Sand Equivalent test apparatus
l Thermometers
m Gas Stove and Cylinder
Soxhlet extraction or
centrifuge type apparatus
n complete with extraction
thimbles with solvent and filter
paper
compressing beakers, pipettes, dishes, measuring
o Glassware cylinders (100 to 1000 cc and metallic thermometers
range up to 300°C)
Hot plates 200 mm dia (1500
p
watt)
electrically operated, thermostatically controlled
q Oven (including thermometer), stainless steel interior from
O°C to 220°C
3 Concrete Batching Plant
i. b. 150 mm x 300 mm ht. cylinder with capping
a Moulds component along with the capping set.
Ii. Cube 150 mm and 100 mm (each size)
b Apparatus for slump test
High frequency mortar cube Cement motor moulds (70.6 mm W x 70.6 mm Lx 70.6
c
vibrator for cement testing mm H
Vicat needle apparatus for
d as per IS:269-1967
setting time with plungers
Soundness testing apparatus
e
for cement(Le Chattlier)
i. 5 -20 kg capacity Electronic type - Accuracy 1 gm
f Weigh Balances ii. 500 gm capacity Electronic type - Accuracy 0.01 gm
iii. Electronic 5 kg capacity - Accuracy 0.5 gm
iv. 50 kg capacity Electronic type - Accuracy 2 gm
Variable frequency and
g size 1 m x 1 m as per the relevant British standard
amplitude vibrating table
Compression and Flexural
strength testing machine of
h 2000 KN capacity with
additional dial for flexural
testing
i Lechatelier flask
14 | P a g e
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED
ENGINEERPNG DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH QUALITY ASSASMENT
NEEDS MODIFICATION / RECONSTRUCTION ON NATIONAL WATERWAY-5 IN PLAN
ODISHA.
in order to ensure that material used in construction is of high quality and meets the codal
requirements of BIS, IRC or MORTH as applicable, a series of tests may have to be carried out at
regular frequencies. The testing has to be done first at the level of the supplier/manufacture or the
contractor. This forms the first level check. The testing may be done jointly with the client or his
consultants in the site laboratory. This forms the second level check. The material may sometimes
be tested at reputed Govt. approved independent laboratories. This forms third level check.
The required test for the various materials as well as the frequency of such testing and
acceptance is listed below:-
15 | P a g e
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED
ENGINEERPNG DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH QUALITY ASSASMENT
NEEDS MODIFICATION / RECONSTRUCTION ON NATIONAL WATERWAY-5 IN PLAN
ODISHA.
Tensile strength ,
10mm to 16 1 Every 45 T or IS:1786 -2008 is:1599,&
16 | P a g e
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED
ENGINEERPNG DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH QUALITY ASSASMENT
NEEDS MODIFICATION / RECONSTRUCTION ON NATIONAL WATERWAY-5 IN PLAN
ODISHA.
7 Concrete cubes, Compressive 6 nos Every 5 cum or IS: 456 & CPWD spec.
(150x150x150) strength part thereof Vol.-1,2009
in case of
column.
Concrete cubes, Compressive 6 nos Every 20 cum IS: 456 & CPWD spec.
(150x150x150) strength or part thereof Vol.-1,2009
in case of slab
and beam.
17 | P a g e
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED
ENGINEERPNG DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH QUALITY ASSASMENT
NEEDS MODIFICATION / RECONSTRUCTION ON NATIONAL WATERWAY-5 IN PLAN
ODISHA.
aggregates
e. Stability of Mix For each 400 tonnes mix
produced, a set of 3 marshall
specimens to be prepared &
tested for stability, flow value,
density & void content subject to
a minimum of two sets being
tested per plant per day.
4. BC a. Agg. Impact value/Los 1 test per 50 m3 of aggregate
angeles abrasion value
b. Flakiness Index & 1 test per 50 m3 of aggregate
Elongation Index
d. Water absorption of Initially one set of 3
aggregate representative specimens for
each source of supply.
Subsequently when warranted
by changes in the quality of
aggregates
18 | P a g e
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED
ENGINEERPNG DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH QUALITY ASSASMENT
NEEDS MODIFICATION / RECONSTRUCTION ON NATIONAL WATERWAY-5 IN PLAN
ODISHA.
a. The contractor shall submit the RFI (Request For Inspection) in approved format prior to 24
hours for the item of works he intends inspection by the Consultancy team.
b. The RFI should contain the Sl.No of Book and to be maintained with serial No of pages with
triplicate copy of different colours.
c. The 1st copy of RFI is to be submitted by the agency to the Consultancy team before
concealing any item of works.
d. The concerned field officer shall attend the work for supervision/checking of the work with
RFI.
e. The concerned Field officer shall check the work and put his signature as token of approval
of the work.
f. In case not approved, the reasons for non-approval are to be mentioned in the RFI and
agency is to be informed.
g. The RFI for the same work shall be submitted by the agency again for checking after
rectification as required.
h. The passed RFIs are to be enclosed with RA Bills by the agency, for recommendation of the
consultant for Payment.
4.2. Documentation:
The supervision Consultant shall maintain following documents and Registers in their office.
a. Contract documents
b. Execution of work.
19 | P a g e
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED
ENGINEERPNG DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH QUALITY ASSASMENT
NEEDS MODIFICATION / RECONSTRUCTION ON NATIONAL WATERWAY-5 IN PLAN
ODISHA.
c. Quality control.
20 | P a g e
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED
ENGINEERPNG DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH QUALITY ASSASMENT
NEEDS MODIFICATION / RECONSTRUCTION ON NATIONAL WATERWAY-5 IN PLAN
ODISHA.
d. Progress Report.
(Submitted to the client in each week is to be kept in hard copy in proper manner)
e. Bills.
i. Others.
21 | P a g e
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED
ENGINEERPNG DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH QUALITY ASSASMENT
NEEDS MODIFICATION / RECONSTRUCTION ON NATIONAL WATERWAY-5 IN PLAN
ODISHA.
Chapter 5 - Conclusion:
The QAP shall be adhered for carrying out the work and cases such as Non-Conforming Tests,
additional tests, emergency works etc shall be dealt separately. The supervision methodology shall
be revisited in case of multiple shift works and from case to case basis. The Contractor shall maintain
all testing records in his office and each test should be signed by the Consultant/Client.
22 | P a g e
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED
ENGINEERPNG DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH QUALITY ASSASMENT
NEEDS MODIFICATION / RECONSTRUCTION ON NATIONAL WATERWAY-5 IN PLAN
ODISHA.
SAMPLE FORMATS
23 | P a g e
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED
ENGINEERPNG DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH QUALITY ASSASMENT
NEEDS MODIFICATION / RECONSTRUCTION ON NATIONAL WATERWAY-5 IN PLAN
ODISHA.
24 | P a g e
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED
ENGINEERPNG DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH QUALITY ASSASMENT
NEEDS MODIFICATION / RECONSTRUCTION ON NATIONAL WATERWAY-5 IN PLAN
ODISHA.
Format
Sl no Material Description ID
Un Confined Compressive Strength D-15
Field Density Test Core Cutter Method D-16
Determination of Dry Density of Soil in place (Sand
Replacement Method) D-17
Aggregate Impact Value- AIV E-1
Flakiness Index & Elongation Index E-2
Individual Gradation of Coarse Aggregate E-3
Sieve Analysis of Fine Aggregate E-4
9 Aggregate Deleterious material and Organic Impurities E-5
Point Load Test E-6
Soundness test by using Sodium Sulphate E-7
Specific Garvity & Water absrption of Fine Aggregate E-8
Specific Gravity & Water absorption of Coarse Aggregate E-9
Penetration Value of Bitumen F-1
Bitumen Specific Gravity F-2
Determination of Softening Point F-3
Determination of Viscosity F-4
10 Bitumen
Gradation aggregate Sector Binder Content Paving
Mixtures Centrifuge Method BC/DBM/BM F-5
Flash & Fire Point F-6
Marshall Test Result F-7
11 Calibration chart for batching plant for aggregate gauge G-1
12 Calibration chart for Batching plant for water meter G-2
13 Calibration chart Batching Plant for Cement Gauge G-3
14 Calibration Report (Cube Testing Machine) G-4
15 Record of Calibration Equipments G-5
16 Daily Progress Report G-6
17 Request for Inspection.
25 | P a g e
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED ENGINEERPNG DESIGN & DRAWING OF BRIDGES QUALITY ASSASMENT
FOR EXISTING BRIDGES WHICH NEEDS MODIFICATION / RECONSTRUCTION ON NATIONAL WATERWAY-5 IN ODISHA. PLAN
Signed Signed
Date Date
Prepared by Approved by
(For Contractor) (For QA Engineer)
26 | P a g e
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED
ENGINEERPNG DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH QUALITY ASSASMENT
NEEDS MODIFICATION / RECONSTRUCTION ON NATIONAL WATERWAY-5 IN PLAN
ODISHA.
S.
DESCRIPTION YES NO N.A.
NO.
1 Formwork design/drawing/sketch approved including
de-shuttering arrangements
2 Trial panel approved(if required)
3 Formwork alignment correct
4 Formwork levels correct, including screeds
5 Formwork dimensions correct ,
27 | P a g e
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED
ENGINEERPNG DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH QUALITY ASSASMENT
NEEDS MODIFICATION / RECONSTRUCTION ON NATIONAL WATERWAY-5 IN PLAN
ODISHA.
SL.
DESCRIPTION YES NO N.A.
NO.
25 Chamfers/fillets sizes, straightness, fixing acceptable
26 Form work clean
27 Form work release oil material approved
28 Form work release oil applied correctly
29 Construction joint preparation satisfactory
30 Contraction/expansion joint preparation satisfactory
31 Safe access constructed
32 Adequate workspace provided for labour, equipment
33 Shutter vibrators (ifrequired) location and fixing arrangements
approved
28 | P a g e
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED
ENGINEERPNG DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH QUALITY ASSASMENT
NEEDS MODIFICATION / RECONSTRUCTION ON NATIONAL WATERWAY-5 IN PLAN
ODISHA.
LOCATION: DATED:
CONTRACTORS INSPECTION REQUEST NO.:
REF DRG NO.:
29 | P a g e
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED
ENGINEERPNG DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH QUALITY ASSASMENT
NEEDS MODIFICATION / RECONSTRUCTION ON NATIONAL WATERWAY-5 IN PLAN
ODISHA.
LOCATION: DATED:
30 | P a g e
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED
ENGINEERPNG DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH QUALITY ASSASMENT
NEEDS MODIFICATION / RECONSTRUCTION ON NATIONAL WATERWAY-5 IN PLAN
ODISHA.
Admixture :
Placement temperature of
Concrete :
Ambient temp :
Weather condition :
31 | P a g e
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED
ENGINEERPNG DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH QUALITY ASSASMENT
NEEDS MODIFICATION / RECONSTRUCTION ON NATIONAL WATERWAY-5 IN PLAN
ODISHA.
S or NS*
Type of remark
S.No Observation
{S or NS*}
Remarks:
In case of NS report in item (1) to (5), it should be examined by competent authority before
approval or non-approval. If required, a separate non-conformance report (including sketches,
photographs, etc.,) shall be prepared for further action.
*S= Satisfactory, NS= Not satisfactory
32 | P a g e
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED
ENGINEERPNG DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH QUALITY ASSASMENT
NEEDS MODIFICATION / RECONSTRUCTION ON NATIONAL WATERWAY-5 IN PLAN
ODISHA.
(IS:4031 PART-V)
Section/Location of Lab
Remarks:
33 | P a g e
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED
ENGINEERPNG DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH QUALITY ASSASMENT
NEEDS MODIFICATION / RECONSTRUCTION ON NATIONAL WATERWAY-5 IN PLAN
ODISHA.
FINENESS OF CEMENT
(IS:4031 PART-1)
Section/Location of Lab
OBSERVATIONS:
SPECIFIED
AVERAGE LIMITS AS
S.No. DESCRIPTION 1 2 3
(%) PER
IS: 8112
1 Wt. of Sample taken (W 1) gm
2 Wt. of residue on 901J sieve (W 2) gm Max. 10%
3 Fineness (%) (W/W 1) X100
Remarks:
34 | P a g e
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED
ENGINEERPNG DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH QUALITY ASSASMENT
NEEDS MODIFICATION / RECONSTRUCTION ON NATIONAL WATERWAY-5 IN PLAN
ODISHA.
Acceptance Criteria:
Remarks:
.
35 | P a g e
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED
ENGINEERPNG DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH QUALITY ASSASMENT
NEEDS MODIFICATION / RECONSTRUCTION ON NATIONAL WATERWAY-5 IN PLAN
ODISHA.
Remarks:
36 | P a g e
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED
ENGINEERPNG DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH QUALITY ASSASMENT
NEEDS MODIFICATION / RECONSTRUCTION ON NATIONAL WATERWAY-5 IN PLAN
ODISHA.
Week No. :
Trial No.
Determination
1 2 3 Average
Weight of bottle (w1)
Remarks:
37 | P a g e
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED
ENGINEERPNG DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH QUALITY ASSASMENT
NEEDS MODIFICATION / RECONSTRUCTION ON NATIONAL WATERWAY-5 IN PLAN
ODISHA.
Section/Location of Lab
Remarks:
38 | P a g e
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED
ENGINEERPNG DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH QUALITY ASSASMENT
NEEDS MODIFICATION / RECONSTRUCTION ON NATIONAL WATERWAY-5 IN PLAN
ODISHA.
. :
39 | P a g e
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED
ENGINEERPNG DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH QUALITY ASSASMENT
NEEDS MODIFICATION / RECONSTRUCTION ON NATIONAL WATERWAY-5 IN PLAN
ODISHA.
19.000
10.000
4.750
2.000
Sand =
1.180
0.425
0.075
Pan Silt &Clay =
40 | P a g e
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED
ENGINEERPNG DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH QUALITY ASSASMENT
NEEDS MODIFICATION / RECONSTRUCTION ON NATIONAL WATERWAY-5 IN PLAN
ODISHA.
Remarks:
Type of Soil:
Prepared by Checked by Approved by
41 | P a g e
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED
ENGINEERPNG DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH QUALITY ASSASMENT
NEEDS MODIFICATION / RECONSTRUCTION ON NATIONAL WATERWAY-5 IN PLAN
ODISHA.
• Observations Calculations
Corre Parti
Hydr
Menis Compo cted cle
omet Temp
Elapsed cus site Readi Heigh Value( Factor size
% Finer (N’)=
s. er erat R=R % Finer based on whole
time(t) corre Corre ng(R t (He) n) in (M)=V30n 100*G/(Ms*
NO min
Read
ction
ure
ction h’+C D=(MV weight N=N’*(w’/w)
ing( (t) h)=R cm poise /g(G-1) (G-1))*R
Cm (C) h1+C He/t)
Rh1) mm
m
1 2 3 4 5 6 7 8 9 10 11 12 13
42 | P a g e
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED
ENGINEERPNG DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH QUALITY ASSASMENT
NEEDS MODIFICATION / RECONSTRUCTION ON NATIONAL WATERWAY-5 IN PLAN
ODISHA.
Determination no. 1 2 3 4 5 1 2 3
No. of Blows
Container no.
TestResults
Liquid Limit(LL%):
Plastic Limit(PL%):
Plasticity Index(LL-PL):
Remarks:
Type of Soil:
Prepared by Checked by Approved by
43 | P a g e
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED
ENGINEERPNG DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH QUALITY ASSASMENT
NEEDS MODIFICATION / RECONSTRUCTION ON NATIONAL WATERWAY-5 IN PLAN
ODISHA.
Remarks:
44 | P a g e
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED
ENGINEERPNG DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH QUALITY ASSASMENT
NEEDS MODIFICATION / RECONSTRUCTION ON NATIONAL WATERWAY-5 IN PLAN
ODISHA.
S.
Description Trial 1 Trial 2 Trial 3 Average
No.
1 Wt. of Density Bottle with Lid (W 1)
Remarks:
.
Prepared by Checked by Approved by
45 | P a g e
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED
ENGINEERPNG DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH QUALITY ASSASMENT
NEEDS MODIFICATION / RECONSTRUCTION ON NATIONAL WATERWAY-5 IN PLAN
ODISHA.
Test Results:
Maximum dry density (MOD) glcc =
Optimum moisture content (OMC) % =
Remarks: I-
46 | P a g e
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED ENGINEERPNG DESIGN & DRAWING OF BRIDGES QUALITY ASSASMENT
FOR EXISTING BRIDGES WHICH NEEDS MODIFICATION / RECONSTRUCTION ON NATIONAL WATERWAY-5 IN ODISHA. PLAN
Mould No 10 30 65
No of Blows
Penetration Proving Ring Load CBRValue Proving Ring Load CBRValue Proving Ring Load (Kg) CBRValue
(mm) Reading (div) (Kg) (%) Reading (div) (Kg) (%) Reading (div) (%)
0.00
0.50
1.00
1.50
2.00
2.50
3.00
4.00
5.00
.
7.50
10.00
-
12.50
47 | P a g e
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED ENGINEERPNG DESIGN & DRAWING OF BRIDGES QUALITY ASSASMENT
FOR EXISTING BRIDGES WHICH NEEDS MODIFICATION / RECONSTRUCTION ON NATIONAL WATERWAY-5 IN ODISHA. PLAN
CBR Graphs for 10 Blows CBR Graphs for 30 Blows CBR Graphs for 65 Blows
Remarks:
48 | P a g e
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED QUALITY
ENGINEERPNG DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH NEEDS ASSASMENT
MODIFICATION / RECONSTRUCTION ON NATIONAL WATERWAY-5 IN ODISHA. PLAN
On Remoulded and
Un-Soakedl Soaked Sample
10
CBR Graph
30
65
49 | P a g e
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED ENGINEERPNG DESIGN & DRAWING OF BRIDGES QUALITY ASSASMENT
FOR EXISTING BRIDGES WHICH NEEDS MODIFICATION / RECONSTRUCTION ON NATIONAL WATERWAY-5 IN ODISHA. PLAN
Sl. Horizontal Corrected Area Normal Stress (kg/cm') =0.5 Normal Stress (kg/cm') =1.0 Normal Stress (kg/cm') =1.5
No. Displacement (A-dx6)cm'
(d)cm Shear Load from Shear Load from Shear Load from
Proving Ring Shear Stress Proving Ring Shear Stress Proving Ring Shear Stress
1 kg/cm' kg/cm' kg/cm'
Divisions kg Divisions kg Divisions kg
50 | P a g e
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED ENGINEERPNG DESIGN & DRAWING OF BRIDGES QUALITY ASSASMENT
FOR EXISTING BRIDGES WHICH NEEDS MODIFICATION / RECONSTRUCTION ON NATIONAL WATERWAY-5 IN ODISHA. PLAN
SI. No Max. Normal Stress Max. Shear Stress (kg/cm2) Normal Stress Versus Shear Stress Graph
(kg/cm2)
1 0.50
2 1.00
3 1.50
Remarks:
51 | P a g e
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED ENGINEERPNG QUALITY
DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH NEEDS MODIFICATION / ASSASMENT
RECONSTRUCTION ON NATIONAL WATERWAY-5 IN ODISHA. PLAN
1 2 3 4 5 6 7 8 9 10 11 12 13 14
1 0.0
2 0.2
3 0.4
4 0.6
5 0.8
,
6 1.0
7 1.2
8 1.4
9 1.6
10 1.8
11 2.0
12 2.2
13 2.4
14 2.6
15 2.8
16 3.0
17 3.2
18 3.4
19 3.6
20 3.8
52 | P a g e
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED ENGINEERPNG QUALITY
DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH NEEDS MODIFICATION / ASSASMENT
RECONSTRUCTION ON NATIONAL WATERWAY-5 IN ODISHA. PLAN
21 4.0
22 4.2
23 4.4
24 4.6
25 4.8
26 5.0
27 5.2
28 5.4
29 5.6
30 5.8
31 6.0
32 6.2
33 6.4
34 6.6
35 6.8
36 7.0
37 7.2
38 7.4
39 7.6
40 7.8
41 8.0
42 8.2
43 8.4
44 8.6
45 8.8
46 9.0
47 9.2
48 9.4
49 9.6
50 9.8
51 10.0
53 | P a g e
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED ENGINEERPNG QUALITY
DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH NEEDS MODIFICATION / ASSASMENT
RECONSTRUCTION ON NATIONAL WATERWAY-5 IN ODISHA. PLAN
Mohr's Envelop
Remarks: .
54 | P a g e
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED ENGINEERPNG QUALITY
DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH NEEDS MODIFICATION / ASSASMENT
RECONSTRUCTION ON NATIONAL WATERWAY-5 IN ODISHA. PLAN
55 | P a g e
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED ENGINEERPNG QUALITY
DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH NEEDS MODIFICATION / ASSASMENT
RECONSTRUCTION ON NATIONAL WATERWAY-5 IN ODISHA. PLAN
Remarks:
.
-
56 | P a g e
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED ENGINEERPNG QUALITY
DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH NEEDS MODIFICATION / ASSASMENT
RECONSTRUCTION ON NATIONAL WATERWAY-5 IN ODISHA. PLAN
Remarks:
.
Prepared by Checked by Approved by
57 | P a g e
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED ENGINEERPNG QUALITY
DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH NEEDS MODIFICATION / ASSASMENT
RECONSTRUCTION ON NATIONAL WATERWAY-5 IN ODISHA. PLAN
(IS:2720 PART-17)
Section Lab location : Sampled Location/Chainage :
Date of Testing : Weight of Sample Taken :
NMC or OMC : Depth :
Diameter of mould(D) : FDD or MOD :
Length of mould (L) : Dia of Stand Pipe (d) :
Area of mould (A) : Area of stand pipe (a) :
S. Initial Head Final Head Initial Time Final Time Net Time Coefficient
No (h1) (h2) (t1 ) (t2) (t) of
permeability
(K)
1
2 .
3
Calculation:
Remarks:
58 | P a g e
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED ENGINEERPNG QUALITY
DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH NEEDS MODIFICATION / ASSASMENT
RECONSTRUCTION ON NATIONAL WATERWAY-5 IN ODISHA. PLAN
Remarks:
.
Prepared by Checked by Approved by
59 | P a g e
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED ENGINEERPNG QUALITY
DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH NEEDS MODIFICATION / ASSASMENT
RECONSTRUCTION ON NATIONAL WATERWAY-5 IN ODISHA. PLAN
(IS:2720 PART-10)
Section/Location of Lab : Date of Testing :
Initial Height of Sample : Rate of Strain :
Initial Dia. of Sample : Sample Code :
OMC% : MDD(g/cc) :
Sample Vol. of Weight of Container Container Wt. of Wt. M.C% gdry
No. Sample Sample No Wt Container Container glcc
+ Wet Soil + Dry Soil
60 | P a g e
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED ENGINEERPNG QUALITY
DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH NEEDS MODIFICATION / ASSASMENT
RECONSTRUCTION ON NATIONAL WATERWAY-5 IN ODISHA. PLAN
17 3.2
18 3.4
19 3.6
20 3.8
21 4.0
22 4.2
23 4.4
24 4.6
25 4.8
26 5.0
27 5.2
28 5.4
29 5.6
30 5.8
Remarks:
61 | P a g e
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED ENGINEERPNG QUALITY
DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH NEEDS MODIFICATION / ASSASMENT
RECONSTRUCTION ON NATIONAL WATERWAY-5 IN ODISHA. PLAN
Standard Deviation :
REMARKS:
62 | P a g e
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED ENGINEERPNG QUALITY
DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH NEEDS MODIFICATION / ASSASMENT
RECONSTRUCTION ON NATIONAL WATERWAY-5 IN ODISHA. PLAN
63 | P a g e
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED ENGINEERPNG QUALITY
DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH NEEDS MODIFICATION / ASSASMENT
RECONSTRUCTION ON NATIONAL WATERWAY-5 IN ODISHA. PLAN
Remarks:
64 | P a g e
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED ENGINEERPNG QUALITY
DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH NEEDS MODIFICATION / ASSASMENT
RECONSTRUCTION ON NATIONAL WATERWAY-5 IN ODISHA. PLAN
63 50
50 40 .
40 31.5
31.5 25
25 20
20 16
16 12.5
12.5 10
10 6.3
Total (gm) A= B= C=
. 0=
Remarks:
65 | P a g e
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED ENGINEERPNG QUALITY
DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH NEEDS MODIFICATION / ASSASMENT
RECONSTRUCTION ON NATIONAL WATERWAY-5 IN ODISHA. PLAN
(IS:383)
Location of Lab : Date of Sampling :
. = (g)
63mm 100 - - -
40mm 85-100 100 - -
20mm 0-20 85-100 - -
16mm - - 100 -
2.36mm - - - 0-5
Remarks:
66 | P a g e
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED ENGINEERPNG QUALITY
DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH NEEDS MODIFICATION / ASSASMENT
RECONSTRUCTION ON NATIONAL WATERWAY-5 IN ODISHA. PLAN
FINENESS MODULUS
Remarks:
67 | P a g e
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED ENGINEERPNG QUALITY
DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH NEEDS MODIFICATION / ASSASMENT
RECONSTRUCTION ON NATIONAL WATERWAY-5 IN ODISHA. PLAN
Description of material :
.
5. NO DETERMINATION NO. 1 2 AVERAGE
68 | P a g e
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED ENGINEERPNG QUALITY
DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH NEEDS MODIFICATION / ASSASMENT
RECONSTRUCTION ON NATIONAL WATERWAY-5 IN ODISHA. PLAN
Sample No : Depth :
Remarks:
.
Prepared by Checked by Approved by
69 | P a g e
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED ENGINEERPNG QUALITY
DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH NEEDS MODIFICATION / ASSASMENT
RECONSTRUCTION ON NATIONAL WATERWAY-5 IN ODISHA. PLAN
COARSE AGGREGATE
Passing Retained Grading Weight Weight Percentage Weighted
sieve size sieve of of Test of Test Passing Average
size Orignal Fraction Fraction Finer Sieve (Corrected
Sample Before Test After Test After Test Percent
Percent (gm) (gm) (Actual Loss)
Percentage
Loss)
63mm 40mm
40mm 20mm
20mm 10mm
10mm 4.75mm
Total
Remarks:
70 | P a g e
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED ENGINEERPNG QUALITY
DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH NEEDS MODIFICATION / ASSASMENT
RECONSTRUCTION ON NATIONAL WATERWAY-5 IN ODISHA. PLAN
Proposed Use
BY PYCNOMETER METHOD
Description 1 2 3
Pycnometer Bottle Number
71 | P a g e
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED ENGINEERPNG QUALITY
DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH NEEDS MODIFICATION / ASSASMENT
RECONSTRUCTION ON NATIONAL WATERWAY-5 IN ODISHA. PLAN
Remarks:
72 | P a g e
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED ENGINEERPNG QUALITY
DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH NEEDS MODIFICATION / ASSASMENT
RECONSTRUCTION ON NATIONAL WATERWAY-5 IN ODISHA. PLAN
Average .
Remarks:
.
Prepared by Checked by Approved by
73 | P a g e
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED ENGINEERPNG QUALITY
DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH NEEDS MODIFICATION / ASSASMENT
RECONSTRUCTION ON NATIONAL WATERWAY-5 IN ODISHA. PLAN
Proposed Use
S.
Description Trial 1 Trial 2 Trial 3
No.
1 Weight of Pycnometer (W 1) g
2 Weight of Pycnometer + Sample (W 2) g
3 Weight of Pycnometer + Sample + Water (W 3) g
4 Weight of Pycnometer + Water (W 4) g
5 Weight of Sample (W2 - W 1) g
6 Specific Gravity of Sample =
(W2 -W1)/(W4 - W 1) - (W3 - W 2)
Average
Remarks:
.
.
Prepared by Checked by Approved by
74 | P a g e
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED ENGINEERPNG QUALITY
DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH NEEDS MODIFICATION / ASSASMENT
RECONSTRUCTION ON NATIONAL WATERWAY-5 IN ODISHA. PLAN
Remarks:
75 | P a g e
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED ENGINEERPNG QUALITY
DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH NEEDS MODIFICATION / ASSASMENT
RECONSTRUCTION ON NATIONAL WATERWAY-5 IN ODISHA. PLAN
Bitumen Grade
Observations
Pouring Temperature, °C
Test Temperature, °C
Viscosity in (see)
Viscosity in (Cst)
76 | P a g e
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED ENGINEERPNG QUALITY
DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH NEEDS MODIFICATION / ASSASMENT
RECONSTRUCTION ON NATIONAL WATERWAY-5 IN ODISHA. PLAN
. 1 2
1 Weight of Mix :W 1g
2 Initial weight of filter paper
3 Weight of Aggregate after :W 2g
extraction
4 Weight of filter paper after :W 3g
extraction with fine materials
5 Increased weight of filter : W 4g
6 Weight of Binder :W 5g
W 1-(W 2+W 4)
7 Binder Content (BC) :BC%
= W 5/W 1X100
GRADATION OF AGGREGATE FRACTION (BC - MoRT&H Table 500-18),
(DBM - MoRT&H Table 500-10)&(BM - MoRT&H Table 500-4)
Sieve Wt. Cumulative % % JMF Grading 1 Grading 2
size retained Wt. Retained Passing LIMITS
Nominal Size
Nominal Size
(mm) (g) retained (g)
Aggregate = Aggregate =
Layer thickness = Layer thickness =
Remarks:
77 | P a g e
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED ENGINEERPNG DESIGN & DRAWING OF BRIDGES FOR QUALITY
EXISTING BRIDGES WHICH NEEDS MODIFICATION / RECONSTRUCTION ON NATIONAL WATERWAY-5 IN ODISHA. ASSASMENT PLAN
Average
Average
Average
78 | P a g e
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED ENGINEERPNG DESIGN & DRAWING OF BRIDGES FOR QUALITY
EXISTING BRIDGES WHICH NEEDS MODIFICATION / RECONSTRUCTION ON NATIONAL WATERWAY-5 IN ODISHA. ASSASMENT PLAN
Average
Average
MARSHALL CURVES
79 | P a g e
PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED ENGINEERPNG DESIGN & DRAWING OF BRIDGES FOR QUALITY
EXISTING BRIDGES WHICH NEEDS MODIFICATION / RECONSTRUCTION ON NATIONAL WATERWAY-5 IN ODISHA. ASSASMENT PLAN
Bitumen % @ Max Stability = Properties of Mix at Average Bitumen Content of % Specific Limit
Bitumen % @ Max Density = Stability (Kg) =
Density (g/cc) =
Bitumen % @ 4% voids = Air Voids (%) =
V.F.B (%) =
V.M.A (%) =
Average (%) = Flow (mm) =
Remarks :
80 | P a g e
`PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED ENGINEERPNG QUALITY
DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH NEEDS MODIFICATION / ASSASMENT
RECONSTRUCTION ON NATIONAL WATERWAY-5 IN ODISHA. PLAN
REMARKS:
81 | P a g e
`PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED ENGINEERPNG QUALITY
DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH NEEDS MODIFICATION / ASSASMENT
RECONSTRUCTION ON NATIONAL WATERWAY-5 IN ODISHA. PLAN
REMARKS:
82 | P a g e
`PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED ENGINEERPNG QUALITY
DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH NEEDS MODIFICATION / ASSASMENT
RECONSTRUCTION ON NATIONAL WATERWAY-5 IN ODISHA. PLAN
CALIBRATED DATE:
DIAL GUAGE READINGS
LOAD TRIAL-1 TRIAL·2 TRAIL·3 AVERAGE
APPLIED
(KG) LOADING UNLOADING LOADING UNLOADING LOADING UNLOADING
0
50
100
150
200
250
300
350
400
450
500 p
550
600
650
700
750 ~
800
850
900
950
1000
1050
1100
1150
REMARKS:
.
For Contractor For Engineer
83 | P a g e
`PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED ENGINEERPNG QUALITY
DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH NEEDS MODIFICATION / ASSASMENT
RECONSTRUCTION ON NATIONAL WATERWAY-5 IN ODISHA. PLAN
CALIBRATION REPORT .
(CUBE TESTING MACHINE)
DATE OF CALIBRATION: TEMP. :
EQUIPMENT: MODEL:
SL.
.
DEFLECTION IN DIAL GAUGE ACTUAL LOAD
REF:
AVERAGE OF INDICATED LOAD
NO. IN PROVING RING APPLIED THREE READING IN GAUGE ERROR
1
2
3
4 .
5
6
7
8
·9
10
NOTE: To obtain correct result positive (+) error to be subtracted, negative (-) error to be
84 | P a g e
`PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED ENGINEERPNG QUALITY
DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH NEEDS MODIFICATION / ASSASMENT
RECONSTRUCTION ON NATIONAL WATERWAY-5 IN ODISHA. PLAN
Name of Work:
Name of Contractor:
ITEM DATE *DATE OF NEXT DATE OF RESULT OF
CALIBRATED CALIBRATION INSPECTION INSPECTIONS
&PERSON &PERSON
CERTIFYING(FOR APPROVING (FOR
VENDOR OR DEPARTMENT)
CONTRACTOR)
Name: Name:
Signed: Signed:
Date: Date:
85 | P a g e
`PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED ENGINEERPNG QUALITY
DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH NEEDS MODIFICATION / ASSASMENT
RECONSTRUCTION ON NATIONAL WATERWAY-5 IN ODISHA. PLAN
Name of Contractor:
.,
Name: Name:
Signed: Signed:
Date: Date:
86 | P a g e
`PREPARATION OF DETAILED ENGINEERNG REPORT (DER) INCLUDING DETAILED ENGINEERPNG QUALITY
DESIGN & DRAWING OF BRIDGES FOR EXISTING BRIDGES WHICH NEEDS MODIFICATION / ASSASMENT
RECONSTRUCTION ON NATIONAL WATERWAY-5 IN ODISHA. PLAN
Chainage from……………To…………..
Approved /Disapproved.
Signature
87 | P a g e