DBR for DESIGN AND CONSTRUCTION OF ELEVATED VIADUCT OF LENGTH 6.

305 KMS
FROM CH: 796.983 TO CH: 5691.7, CH: 6202.5 TO CH: 7100 AND CH: 7187 TO CH:
7700 BETWEEN PRAJAPATI NAGAR TO SITABURDI

NAGPUR METRO RAIL CORPORATION LIMITED

DESIGN AND CONSTRUCTION OF ELEVATED VIADUCT OF LENGTH


6.305 KMS FROM CH: 796.983 TO CH: 5691.7, CH: 6202.5 TO CH:
7100 AND CH: 7187 TO CH: 7700 BETWEEN PRAJAPATI NAGAR
TO SITABURDI
GEOTECHNICAL INTERPRETATIVE REPORT
(R0)
FEB 2019

ITD Cementation India Limited STUP Consultants Pvt. Ltd.

Document No: 71568/E/GIR/DN-01


DBR for DESIGN AND CONSTRUCTION OF ELEVATED VIADUCT OF LENGTH 6.305 KMS
FROM CH: 796.983 TO CH: 5691.7, CH: 6202.5 TO CH: 7100 AND CH: 7187 TO CH:
7700 BETWEEN PRAJAPATI NAGAR TO SITABURDI

CONTRACTOR CLIENT

GIR for DESIGN AND CONSTRUCTION OF ELEVATED VIADUCT OF LENGTH 6.305 KMS
FROM CH: 796.983 TO CH: 5691.7, CH: 6202.5 TO CH: 7100 AND CH: 7187 TO CH: 7700
BETWEEN PRAJAPATI NAGAR TO SITABURDI

REVISION: R0

DATED: 15th February, 2019

NAME DESIGNATION SIGNATURE DATE

ITD Cementation
India Limited

Page 1
DBR for DESIGN AND CONSTRUCTION OF ELEVATED VIADUCT OF LENGTH 6.305 KMS
FROM CH: 796.983 TO CH: 5691.7, CH: 6202.5 TO CH: 7100 AND CH: 7187 TO CH:
7700 BETWEEN PRAJAPATI NAGAR TO SITABURDI

GENERAL CONSULTANT

GIR for DESIGN AND CONSTRUCTION OF ELEVATED VIADUCT OF LENGTH 6.305 KMS
FROM CH: 796.983 TO CH: 5691.7, CH: 6202.5 TO CH: 7100 AND CH: 7187 TO CH: 7700
BETWEEN PRAJAPATI NAGAR TO SITABURDI

REVISION: R0

DATED: 15th February, 2019

NAME DESIGNATION SIGNATURE DATE

Page 2
DBR for DESIGN AND CONSTRUCTION OF ELEVATED VIADUCT OF LENGTH 6.305 KMS
FROM CH: 796.983 TO CH: 5691.7, CH: 6202.5 TO CH: 7100 AND CH: 7187 TO CH:
7700 BETWEEN PRAJAPATI NAGAR TO SITABURDI

DESIGN CONSULTANT

GIR for DESIGN AND CONSTRUCTION OF ELEVATED VIADUCT OF LENGTH 6.305


KMS FROM CH: 796.983 TO CH: 5691.7, CH: 6202.5 TO CH: 7100 AND CH: 7187 TO
CH: 7700 BETWEEN PRAJAPATI NAGAR TO SITABURDI

REVISION: R0

DATED: 15th May, 2017

NAME DESIGNATION SIGNATURE DATE

STUP Amit Kumar Joint Vice 15.02.2019


Consultants Chakraborty President
Senior Design
Pvt. Ltd. Sumit Ghose
Manager
Principal
Probal Kundu Design 15.02.2019
Engineer

Page 3
DBR for DESIGN AND CONSTRUCTION OF ELEVATED VIADUCT OF LENGTH 6.305 KMS
FROM CH: 796.983 TO CH: 5691.7, CH: 6202.5 TO CH: 7100 AND CH: 7187 TO CH:
7700 BETWEEN PRAJAPATI NAGAR TO SITABURDI

Contents

1.0 Introduction ................................................................................................................................6


2.0 Report – Objectives and Scope .................................................................................................6
3.0 Geology and Background...........................................................................................................6
4.0 Seismic Conditions.....................................................................................................................7
5.0 Geotechnical Investigations .......................................................................................................8
6.0 Interpretations General ..............................................................................................................9
6.1 Interpretation of Field Results .................................................................................................. 14
6.1.1 Standard Penetration Test (SPT) ................................................................................14
6.2 Interpretation of Laboratory Test Results................................................................................. 14
6.3 Ground water table................................................................................................................... 14
7.0 Description of Soil Strata..........................................................................................................14
8.0 References ...............................................................................................................................26

List of Tables:
Table 1: Summary of boreholes: ...................................................................................................... 9
Table 2: Engineering Properties of Soil : ..................................................................................... .15

List of Annexure:
Annexure – 1: Borehole Location Plan………………………………………………………………............27
Annexure - 2: Subsurface Profile …………………………………………………………………………....31
Annexure – 3: Reference Charts and Tables and Minutes of Meetings……….………………………....46
Annexure – 4: Soil Stratification from Factual Geotechnical Report………………………………………53

Page 4
DBR for DESIGN AND CONSTRUCTION OF ELEVATED VIADUCT OF LENGTH 6.305 KMS
FROM CH: 796.983 TO CH: 5691.7, CH: 6202.5 TO CH: 7100 AND CH: 7187 TO CH:
7700 BETWEEN PRAJAPATI NAGAR TO SITABURDI

1 Introduction

STUP Consultants Pvt. Ltd. has been appointed by M/s ITD CEMENTATION INDIA LTD.
as Detailed Design structural consultant for design and construction of elevated viaduct of
length 6.305 kms from chainage 796.983 to ch: chainage 5691.700, chainage 6202.500 to
chainage 7100 and chainage 7187.000 to chainage 7700.000 between Prajapati Nagar to
Sitaburdi.
According to the Employer’s Requirements, the Geotechnical Interpretative Report is one
of the documents to be submitted to the Employer.

2 Report – Objectives and Scope

Purpose and requirements are defined under supporting documents as follows:

A geotechnical engineering study comprising of field investigation and laboratory tests has
been carried out along the proposed alignment. This Geotechnical Interpretative Report
presents the findings of the geotechnical engineering study.

This Geotechnical Interpretive Report includes review of Site Investigation results,


Geotechnical Interpretation of site investigation work and selection of engineering
parameters required for the design of structures etc.

The purpose of the study is to interpret subsurface ground conditions of the site and to
present an evaluation and summary of the soil properties for the design of the temporary
and permanent structures along the alignment.

This report refers to the interpretation of geotechnical data from Final Factual Soil
Investigation Report provided by soil investigation agency C.E. Testing Company Pvt. Ltd.,
Anandjiwala Technical Consultancy, and Constell Consultants Pvt. Ltd. appointed by M/s
ITD Cementation India Ltd.

3 Geology and Background

The region forms part of Deccan Plateau having flat topped and terraced features.
Eastward and northeastwards the landscape changes due to the change in the underlying
rocks. The rocks of Gondwana series present a low rolling topography with a poor soil

Page 5
DBR for DESIGN AND CONSTRUCTION OF ELEVATED VIADUCT OF LENGTH 6.305 KMS
FROM CH: 796.983 TO CH: 5691.7, CH: 6202.5 TO CH: 7100 AND CH: 7187 TO CH:
7700 BETWEEN PRAJAPATI NAGAR TO SITABURDI

cover and vegetation. On the north the upland ranges are the extension of Satpuras which
gradually narrows down towards west. South of these upland range stretches the Ambegad
hills, the western extremity of which is the Nagpur district. The Ramtek temple is on the
spur of this range. The Girad hill range extends along the southeast and separates the
valley of the Kar from that of Jamb upto Kondhali. Another main hill range runs northwards
through Katol taluka from Kondhali to Kelod separating the Wardha and Wainganga valleys.
The northeastern and east central parts of the district is drained by the Wainganga and its
tributaries. The central and western portion is drained by the Wena which is a tributary of
Wardha River.

4 Seismic Conditions

The seismic hazard map of India was updated in 2002 by the Bereau of Indian Standards
(BIS). The new map includes the central districts of Beed (Bir), Dharashiv (Osmanabad) and
Latur, along the eastern sections of Ahmednagar, Pune, Satara and Sangli districts in Zone
III. All of these areas lay in Zone I or II in the BIS 1984 map. The zones in the rest of the
state are the same as in the previous map. The districts of Raigad, Ratnagiri and Satara are
the only districts to lie in Zone IV. The remaining western and north-western districts all lie in
Zone III. The central and eastern districts lie in Zone II. It must be noted that BIS estimates
the hazard, based in part, on previous known earthquakes. Since the earthquake database
in India is still incomplete, especially with regards to earthquakes prior to the historical
period ( before 180 AD.), these zones offer a rough guide to the earthquake hazard in any
particular region and needs to be regularly updated.

Page 6
DBR for DESIGN AND CONSTRUCTION OF ELEVATED VIADUCT OF LENGTH 6.305 KMS
FROM CH: 796.983 TO CH: 5691.7, CH: 6202.5 TO CH: 7100 AND CH: 7187 TO CH:
7700 BETWEEN PRAJAPATI NAGAR TO SITABURDI

The area under study (Nagpur) falls in Seismic Zone II.

5 Geotechnical Investigations

Boreholes were executed along the alignment to determine the ground condition and
engineering parameters of soil for the design works more precisely.

The Investigation is summarized below –

1. Boreholes – 129 nos.

2. Standard Penetration Tests : at 1.50 m intervals in each borehole

3. Ground Water Table Location

The logs of the boring and the test results are given in Factual Geotechnical Investigation
Report, ITDCEM/NMRCL/R4/PN/2017/153, ITDCEM/NMRCL/R4/PN/2017/204,

Page 7
DBR for DESIGN AND CONSTRUCTION OF ELEVATED VIADUCT OF LENGTH 6.305 KMS
FROM CH: 796.983 TO CH: 5691.7, CH: 6202.5 TO CH: 7100 AND CH: 7187 TO CH:
7700 BETWEEN PRAJAPATI NAGAR TO SITABURDI

ITDCEM/NMRCL/R4/PN/2017/205 and ITDCEM/NMRCL/R4/PN/2017/211 respectively


submitted to NMRCL by ITDC and some relevant data is included in Annexure A-4.

6 Interpretations General
In general the sub surface strata present at the project site can be described predominantly as
moderately weathered to completely weathered /weathered granite gneiss overlain by Silty
Clay/Clayey silt with bands of Silty sand/ Sandy silt at a number of locations.

For selection of design engineering parameters of soil, the boreholes conducted at the location
are grouped and discussed separately as following –

Table 1: Summary of boreholes:


Standing
Borehole Co-ordinates Termination Water
Sr. No Bore Hole No. Chain.age (m) R..L. Depth (mt.) Level
B.G.L
North East
(m.)
MPP-01 (BH- CH (-287.I
1 2339984.354 307902.772 286.878 22.42 8.1
01) 23)
MPP-02 {BH-
2 CH (-256.856) 2339965.772 307879.86 286.815 20.53 8.0
04)
3 MP-09 (BH-05) CH (-225.844) 2339958.451 307849.344 286.987 22.36 7.1
MP- 11 {BH-
4 CH (-178.837) 2339924.519 307816.093 286.577 17.81 8.0
06)
5 PJ-02 (BH-7) CH (-138.328) 2339897.078 307788.364 286.104 !8.63 7.3
CH (-
6 PJ-04 (BH-8) 2339876.213 307767.158 286.339 18.37 7.3
J07.32B)
7 PJ-06 (BH-9) CH (-76.328) 2339855.656 307744.955 286.504 19.93 7.3
8 MP-13 (BH-10) CH (-23.876) 2339819.769 307702.73 287.152 21.02 7.0
9 MP-15 (BH-11) CH-32.124 2339786.052 307657.87 287.99 20.5 7.5
MP- 17 (BH-
10 CH-91.124 2339751.981 307609.702 288.807 21.83 7.0
12)
11 MP-18 CH-127.1 24 2339731.241 307580.276 288.465 22.22 7.0
12 MP-19 (BR-13) CH-158.26 2339714.138 307554.425 288.149 21 .54 8.3
13 MP-21 (BH-14) CH-208.135 2339690.64 307510.371 287.311 19.72 6.1
14 MP-23 (BH-15) CH-252.557 2339674 .426 307469.181 287325 19.51 4.0
MPP-03 (BH-
15 CH-296.979 233965.5.052 307426.301 287.313 19.23 5.4
16)
MPP-04 (BH-
16 CH-321.979 2339654.532 307401.65 287.524 18.03 5.5
18)
MPP-05 (BH-
17 CH-346.979 2339656.122 307378.769 287.468 17.66 4.9
20)
MPP-06 (BH-
18 CH-371.979 2339655.633 307355.5 287255 22.38 4.7
21)
19 P-2 CH-863.190 2339653 306868.864 290.722 25.56 9.8

Page 8
DBR for DESIGN AND CONSTRUCTION OF ELEVATED VIADUCT OF LENGTH 6.305 KMS
FROM CH: 796.983 TO CH: 5691.7, CH: 6202.5 TO CH: 7100 AND CH: 7187 TO CH:
7700 BETWEEN PRAJAPATI NAGAR TO SITABURDI

20 P-4 CH-928.190 2339653.933 306787.043 291.367 22.35 8.7


21 P-6 CH-993.190 2339653.826 306722.132 291.893 23.6 8.6
22 P-8 CH-1055.1 90 2339653.503 306645.81 O 292.141 23.87 10.2
23 P-9 CH-1089.000 2339655.202 306610.975 292.267 26.76 8.2
24 SP-12 CH-1192.460 2339661.1S1 306508.486 292.657 24.23 8.1
25 SP-17 CH-1269.960 2339665.495 306435.405 293.038 25.7 8.1
26 P-19 CH-1327.210 2339664.633 306380.063 293.33 23.33 8.9

Standing
Termination Water
Bore Hole Chainage Borehole Coordinates R.L.
SL.No Location Depth (m) Level
No. B.G.L (m.)
(m) Easting Northing (m) (m) (m)
Near Pier
27 BH-P172 6341.12 301700.364 2339981.235 307.091 14.76 2.00
172
Near Pier
28 BH-P174 6409.12 301690.784 2339914.083 306.890 16.30 1.90
174
Near Pier
29 BH-P176 6477.12 301681.472 2339845.881 307.134 17.90 1.95
176
Near Pier
30 BH-P178 6545.12 301673.963 2339795.334 307.260 16.10 2.15
178
Near Pier
31 BH-P180 6613.12 301664.308 2339726.099 306.712 14.70 1.80
180
Near Pier
32 BH-CP182 6678.19 301655.126 2339659.998 305.816 14.80 1.65
182
Near Pier
33 BH-P184 6740.12 301648.037 2339587.869 304.965 14.75 2.20
184
Near Pier
34 BH-SP186 6792.36 301640.842 2339536.87 304.155 14.50 2.35
186
Near Pier
35 BH-SP189 6834.36 301635.672 2339499.805 303.633 14.56 2.10
189
Near Pier
36 BH-SP191 6869.86 301629.673 2339457.764 303.245 14.84 2.25
191
Near Pier
37 BH-CP193 6929.73 301622.931 2339410.123 303.083 14.75 2.40
193
BH- Near Pier
38 7100.73 301532.426 2339295.993 300.980 15.32 2.70
P199(New) 199
Near Pier
39 BH-P200 7187.73 301445.736 2339211.044 301.956 15.74 3.10
200
Near Pier
40 BH-P202 7231.73 301419.254 2339186.111 300.253 18.70 2.95
202
Near Pier
41 BH-P204 7281.73 301374.266 2339152.675 299.940 20.50 1.54
204
Near Pier
42 BH-P206 7328.73 301329.834 2339138.354 300.068 18.58 1.65
206
Near Pier
43 BH-P208 7393.73 301267.879 2339118.794 299.947 20.10 1.68
208
Near Pier
44 BH-P210 7461.73 301202.927 2339098.668 299.826 17.70 1.70
210
Near Pier
45 BH-P212 7529.73 301136.836 2339081.442 299.646 20.03 1.75
212
Near Pier
46 BH-P214 7600.73 301071.125 2339056.263 298.995 17.54 1.65
214

Page 9
DBR for DESIGN AND CONSTRUCTION OF ELEVATED VIADUCT OF LENGTH 6.305 KMS
FROM CH: 796.983 TO CH: 5691.7, CH: 6202.5 TO CH: 7100 AND CH: 7187 TO CH:
7700 BETWEEN PRAJAPATI NAGAR TO SITABURDI

Near Pier
47 BH-P216 7668.73 301011.771 2339039.139 298.370 17.82 1.60
216

Standing
Borehole Coordinates Water
Bore Hole Chainage Termination
SL.No Location R.L.(m) Level
No. (m) Depth (m)
Easting Northing B.G.L
(m.)
Near Pier
48 BH-SP14 1231.93 306483.626 2339663.341 292.785 23.22 2.85
14
Near Pier
49 BH-P21 1389.21 306320.623 2339672.158 293.753 22.32 3.40
21
Near Pier
50 BH-P23 1451.21 306290.855 2339673.478 293.980 21.78 3.60
23
Near Pier
51 BH-P25 1525.21 306198.833 2339680.709 294.564 22.24 2.70
25
Near Pier
52 BH-P27 1593.21 306131.166 2339684.643 294.787 22.43 3.50
27
Near Pier
53 BH-P29 1661.21 306063.400 2339688.262 294.999 21.84 3.50
29
Near Pier
54 BH-P31 1726.21 305998.940 2339691.771 294.105 21.72 3.20
31
Near Pier
55 BH-P33 1788.21 305930.940 2339697.105 293.940 21.53 3.35
33
Near Pier
56 BH-P35 1850.21 305813.398 2339698.570 294.770 21.73 3.30
35
Near Pier
57 BH-P37 1908.57 305813.930 2339701.816 295.083 21.31 3.15
37
Near Pier
58 BH-SP40 1947.63 305772.442 2339704.160 295.537 21.53 3.00
40
Near Pier
59 BH-SP42 1979.28 305740.807 2339705.998 295.736 23.63 3.20
42
Near Pier
60 BH-P44 2019.84 305717.347 2339707.258 296.018 23.33 2.90
44
Near Pier
61 BH-P45 2056.20 305667.379 2339710.000 296.496 19.74 2.85
45
Near Pier
62 BH-P47 2121.20 305604.124 2339714.534 296.645 21.83 3.05
47
Near Pier
63 BH-P49 2189.20 305535.052 2339718.834 297.121 20.92 2.90
49
Near Pier
64 BH-P51 2251.20 305474.226 2339723.009 297.500 19.63 2.70
51
Near Pier
65 BH-P53 2316.20 305412.684 2339725.000 297.861 20.72 2.80
53
Near Pier
66 BH-P55 2375.20 305353.124 2339728.238 298.267 19.53 3.00
55
Near Pier
67 BH-P57 2446.20 305287.363 2339732.259 298.670 20.93 3.20
57
Near Pier
68 BH-P59 2520.20 305207.713 2339736.598 299.283 18.83 3.40
59
Near Pier
69 BH-P61 2588.20 305139.773 2339740.954 299.517 16.73 3.35
61
Near Pier
70 BH-P63 2650.20 305077.597 2339744.700 299.625 17.23 3.25
63
Near Pier
71 BH-P65 2715.20 305015.740 2339748.323 299.406 16.79 3.40
65

Page 10
DBR for DESIGN AND CONSTRUCTION OF ELEVATED VIADUCT OF LENGTH 6.305 KMS
FROM CH: 796.983 TO CH: 5691.7, CH: 6202.5 TO CH: 7100 AND CH: 7187 TO CH:
7700 BETWEEN PRAJAPATI NAGAR TO SITABURDI

Near Pier
72 BH-P67 2783.20 304946.811 2339752.378 299.080 16.56 3.50
67
Near Pier
73 BH-P69 2851.20 304879.773 2339756.238 298.862 18.18 3.20
69
Near Pier
74 BH-P71 2925.20 304813.372 2339760.189 298.648 17.47 3.15
71
Near Pier
75 BH-P74 3030.20 304720.678 2339765.736 298.620 17.58 3.60
74
Near Pier
76 BH-SP76 3090.45 304660.732 2339769.431 298.659 15.66 3.00
76
Near Pier
77 BH-SP78 3118.45 304624.082 2339771.759 298.725 16.04 3.40
78
Near Pier
78 BH-SP81 3167.95 304580.787 2339774.414 299.090 17.13 3.20
81
BH- Near Pier
79 3229.51 304520.678 2339777.920 300.053 14.85 2.70
P83(R2) 83
Near Pier
80 BH-P85 3297.51 304462.826 2339781.374 300.875 14.60 2.80
85
BH- Near Pier
81 3365.51 304394.113 2339787.225 300.796 15.40 3.00
P87(R2) 87
Near Pier
82 BH-P89 3436.51 304301.113 2339801.231 300.932 18.00 3.15
89
Near Pier
83 BH-P91 3510.51 304228.491 2339809.021 300.229 16.00 3.10
91
Near Pier
84 BH-P93 3584.51 304150.602 2339809.021 300.330 18.54 3.20
93
BH- Near Pier
85 3652.51 304084.424 2339834.805 300.149 19.73 3.10
P95(R2) 95
BH- Near Pier
86 3720.51 304015.136 2339849.340 299.520 17.02 3.25
P97(R2) 97
BH- Near Pier
87 3785.51 303938.630 2339864.721 298.779 18.73 3.00
P99R2) 99
Near Pier
88 BH-P101 3850.51 303898.323 2339868.025 298.564 17.23 3.20
101
Near Pier
89 BH-SP106 3952.76 303782.121 2339876.641 298.903 24.24 2.80
106
Near Pier
90 BH-SP133 4762.25 302995.997 2340042.112 306.611 17.25 2.65
133
Near Pier
91 BH-P142 5047.00 302715.480 2340100.650 307.600 16.01 3.80
142
Near Pier
92 BH-P146 5183.00 302585.420 2340137.530 306.900 30.00 3.80
146
Near Pier
93 BH-P148 5251.00 302525.870 2340154.870 306.620 30.00 3.60
148
Near Pier
94 BH-P149 5288.00 302484.320 2340167.520 306.650 30.08 3.60
149
Near Pier
95 BH-P151 5353.00 302423.950 2340190.700 307.110 13.70 3.20
151
Near Pier
96 BH-P153 5415.00 302363.340 2340213.190 307.670 13.70 3.50
153
Near Pier
97 BH-P155 5480.00 302300.410 2340230.170 308.110 15.70 3.70
155

Near Pier
98 BH-P156 5517.00 302258.580 2340240.850 308.590 15.40 3.40
156
Near Pier
99 BH-P158 5567.00 302213.560 2340253.250 309.030 16.00 3.30
158

Page 11
DBR for DESIGN AND CONSTRUCTION OF ELEVATED VIADUCT OF LENGTH 6.305 KMS
FROM CH: 796.983 TO CH: 5691.7, CH: 6202.5 TO CH: 7100 AND CH: 7187 TO CH:
7700 BETWEEN PRAJAPATI NAGAR TO SITABURDI

Near Pier
100 BH-SP161 5611.35 302187.853 2340259.907 309.233 17.60 3.20
161
BH- Near
101 5644.05 302159.980 2340268.770 309.560 16.60 3.70
P164(R2) SP164
BH-
102 - 5691.75 302114.780 2340280.500 309.710 16.90 3.90
P164A(R2)

Borehole Coordinates Standing


Bore Hole Termination
SL.No Chainage (m) R.L.(m) Water Level
No. Depth (m)
Easting Northing B.G.L (m.)
BH-
103 3910.76 2339873.100 303836.300 298.700 15.67 2.90
P102/103
BH-
104 3988.26 2339876.700 303759.400 298.900 17.75 2.90
SP107/108
BH-
105 4048.76 2339878.300 303693.900 299.200 17.50 2.90
P109/110
BH-
106 4082.58 2339888.200 303643.600 299.500 18.36 3.15
P110/111
BH-
107 4156.58 2339900.200 303590.700 300.000 18.10 3.20
P112/113
BH-
108 4193.58 2339909.200 303552.100 299.800 30.10 2.95
P113/114
BH-
109 4264.58 2339926.400 303488.900 300.000 30.00 2.95
P115/116
BH-
110 4329.58 2339942.900 303428.400 300.600 30.00 3.40
P117/118
BH-
111 4391.58 2339959.300 303369.200 301.500 30.00 2.90
P119/120
BH-
112 4428.58 2339975.200 303309.400 302.400 16.20 3.00
P120/121
113 BH-P121 4473.36 2339981.700 303284.800 302.700 30.10 2.80
BH-
114 4496.58 2339987.600 303253.900 303.600 14.50 2.85
P122/123
115 BH-P123 4530.58 2339999.400 303217.500 303.600 30.00 2.80
116 BH-P125 4564.58 2340006.100 303182.500 304.000 15.20 2.60
117 BH-P126 4609.36 2340013.400 303151.900 304.400 30.00 2.80
118 BH-P127 4638.58 2340019.400 303127.900 304.700 15.40 2.60
119 BH-P128 4675.58 2340032.800 303061.000 306.000 15.30 2.80
BH-
120 4720.25 2340037.200 303029.700 306.400 14.60 3.00
SP129/130
121 BH-P135 4797.75 2340049.000 302954.100 307.100 16.20 2.80
122 BH-P136 4824.00 2340053.400 302923.600 307.400 16.25 2.82
123 BH-P137 4874.16 2340058.000 302893.800 307.700 16.00 3.08
124 BH-P138 4886.00 2340061.500 302870.400 307.800 13.90 2.70
125 BH-P140 4954.00 - - 307.800 14.60 2.70
BH-
126 4985.58 2340084.600 302772.500 307.900 13.50 2.90
P140/141
BH-P143
127 5094.16 2340111.100 302678.200 307.400 15.10 2.90
(DCPT)

Page 12
DBR for DESIGN AND CONSTRUCTION OF ELEVATED VIADUCT OF LENGTH 6.305 KMS
FROM CH: 796.983 TO CH: 5691.7, CH: 6202.5 TO CH: 7100 AND CH: 7187 TO CH:
7700 BETWEEN PRAJAPATI NAGAR TO SITABURDI

BH-
128 5115.00 2340120.000 302646.700 307.200 18.00 2.85
P144/145
BH-
129 6986.58 2339351.500 301597.100 302.200 18.06 2.80
P200/197

The design parameter of a particular strata is considered as the average representative value of
the strata obtained from in-situ given in GFR. Wherever the results are not available or found
erratic the design parameters are derived from the standards, codes, books as well as
literatures based on the type of soil. The various charts and tables referred are attached as
Annexure A-3.

6.1 Interpretation of Field Results

6.1.1 Standard Penetration Test (SPT)

Field SPT Value (Observed N) along the depth has been primarily used for interpretation of
other engineering properties of the various soil and rock strata. The soil can be identified
predominantly as Silty Clay/Clayey silt/ Clay with bands of Silty sand/ Sandy silt at a
number of locations. The rock is mainly moderately weathered to completely weathered
/weathered granite gneiss. The consistency of soil and rock is determined from the SPT N
values.

6.2 Interpretation of Laboratory Test Results

Laboratory Tests were performed rarely on very few samples and hence ignored. SPT N values
has been predominantly used for determination of engineering properties of the soil and rock.

6.3 Ground water table

Ground water table is maximum 10.20m BGL at P-8 and minimum 2.60m BGL at BH-P127/125
(Refer Factual Geotechnical Investigation Report (GFR No: ITDCEM/NMRCL/R4/PN/2017/153,
ITDCEM/NMRCL/R4/PN/2017/204, ITDCEM/NMRCL/R4/PN/2017/205 and
ITDCEM/NMRCL/R4/PN/2017/211 respectively.

7 Description of Soil Strata

The stratification and engineering properties of soil is discussed in following session. The top
layer along most of the alignment consists of a bitumen layer mixed with stone

Page 13
DBR for DESIGN AND CONSTRUCTION OF ELEVATED VIADUCT OF LENGTH 6.305 KMS
FROM CH: 796.983 TO CH: 5691.7, CH: 6202.5 TO CH: 7100 AND CH: 7187 TO CH:
7700 BETWEEN PRAJAPATI NAGAR TO SITABURDI

chips/pebbles/gravels/silty clay with thickness varying from 0.8m to 4.1m. The average
thickness of soil underlying bitumen layer, consisting predominantly of silty clay/ clayey silt/clay
with bands of Silty sand/ Sandy silt at a number of locations overlying the rock strata varies in
thickness from 2.3m to 14.3m. The SPT N value of the soil varies from 13 to 73.

The rock strata encountered below the soil layer consists mainly of moderately weathered to
completely weathered /weathered granite gneiss. The moderately weathered rock has SPT N
value greater than 200 (all SPT values more than 200 has been restricted to 200) whereas the
completely weathered rock has SPT N value ranging from 125 to 170.

*Note: As per the meeting dated 22nd June, 2017 between GC and ITD/STUP, it was decided
that any SPT value less than 100 is to be ignored while evaluation of pile capacity. Minutes of
the meeting is attached in Annexure A-3.

Engineering properties of soil stratum are summarized below for this location grouping together
Boreholes having similar strata.
Table 2: Engineering Properties of Soil :
BH- BH-P109/ BH- BH- BH- BH-
BH.NO:
SP107/108 110 P110/111 P112/113 P113/114 P115/116

Undrained
Layer Average SPT N
Description Cohesion *
No. Depth (m) Value
Mpa
Fill consisting of bitumen, stone chips/ silty clay
— 1.9 16 -
with sand gravels pebbles, brick pieces etc.
Silty clay / clayey silt /sandy silty clay with
I 2.8 20 -
kankars, calcareous nodules etc.
Completely weathered rock/Highly weathered
II 17.3 >200 1.30
rock (granite gneiss) /weathered granite gneiss

BH-P117/118 BH-P119/120 BH-P120/121 BH-P121 BH-P122/123

Page 14
DBR for DESIGN AND CONSTRUCTION OF ELEVATED VIADUCT OF LENGTH 6.305 KMS
FROM CH: 796.983 TO CH: 5691.7, CH: 6202.5 TO CH: 7100 AND CH: 7187 TO CH:
7700 BETWEEN PRAJAPATI NAGAR TO SITABURDI

Undrained
Layer Average SPT N
Description Cohesion *
No. Depth (m) Value
Mpa
Fill consisting of bitumen, stone chips/ silty clay
— 1.0 10 -
with sand gravels pebbles, brick pieces etc.
Silty clay / clayey silt / sandy silty clay with
I 2.3 65 -
kankars, calcareous nodules etc.
II Moderately/Highly Weathered Rock. 20.9 >200 1.3

BH-P123 BH-P125 BH-P126 BH-P127 BH-P128

Undrained
Layer Average SPT N
Description Cohesion *
No. Depth (m) Value
Mpa
Fill consisting of bitumen, stone chips/ silty clay
— 1.4 - -
with sand gravels pebbles, brick pieces etc.
Silty clay / clayey silt / sandy silty clay with
I 2.3 28 -
kankars, calcareous nodules etc.
II Moderately/Highly Weathered Rock. 17.9 >200 1.3

BH-SP129/130 BH-P133 BH-P135 BH-P136 BH-P137 BH-P138

Undrained
Layer Average SPT N
Description Cohesion *
No. Depth (m) Value
Mpa
Fill consisting of bitumen, stone chips/ silty clay
— 1.0 11 -
with sand gravels pebbles, brick pieces etc.
Silty clay / clayey silt / sandy silty clay with
I 3.0 14 -
kankars, calcareous nodules etc.
II Moderately/Highly Weathered Rock. 11.7 >200 1.3

BH-P140 BH-P142 BH-P143 BH-P144/145

Undrained
Layer Average SPT N
Description Cohesion *
No. Depth (m) Value
Mpa
Fill consisting of bitumen, stone chips/ silty clay
— 1.0 - -
with sand gravels pebbles, brick pieces etc.
Silty clay / clayey silt / sandy silty clay with
I 2.8 36 -
kankars, calcareous nodules etc.
II Moderately/Highly Weathered Rock. 11.2 >200 1.3

BH-P200/197

Page 15
DBR for DESIGN AND CONSTRUCTION OF ELEVATED VIADUCT OF LENGTH 6.305 KMS
FROM CH: 796.983 TO CH: 5691.7, CH: 6202.5 TO CH: 7100 AND CH: 7187 TO CH:
7700 BETWEEN PRAJAPATI NAGAR TO SITABURDI

Undrained
Layer Average SPT N
Description Cohesion *
No. Depth (m) Value
Mpa
Fill consisting of bitumen, stone chips/ silty clay
- 3.5 10 -
with sand gravels pebbles, brick pieces etc.
Completely weathered rock / weathered granite
II 12.0 83 -
gneiss
III Moderately / Slightly weathered granite gneiss 1.0 >200 1.3

BH- P172 BH-P174 BH-P176 BH-P178 BH-P180

Average Layer Undrained


Layer Thickness(m) SPT N
Description Cohesion *
No. Value
Mpa
Filled up soil consists of bitumen,
- 0.9 10 -
concrete slab, silty sand, gravel etc.
Stiff to very stiff/hard, clayey silt / Silty
I 4.7 13 -
Clay
Medium dense/Dense/Very dense, silty
II 2.0 60 -
sand with rock particles.
III Moderately/Highly Weathered Rock. 10.2 >200 1.3

BH-CP182 BH-P184 BH-SP186 BH-SP189 BH-P191 BH-CP193

Average Layer Undrained


Layer SPT N
Description Thickness(m) Cohesion *
No. Value
Mpa
Filled up soil consists of bitumen, stone
- 0.8 39 -
chips, concrete slab, gravel, pebbles etc.
I Stiff to very stiff/hard clayey silt / Silty Clay 1.0 50 -
Medium dense/Dense/Very dense, silty
II 2.7 79 -
sand with rock particles.
III Moderately/Highly Weathered Rock. 11.3 >200 1.3

Page 16
DBR for DESIGN AND CONSTRUCTION OF ELEVATED VIADUCT OF LENGTH 6.305 KMS
FROM CH: 796.983 TO CH: 5691.7, CH: 6202.5 TO CH: 7100 AND CH: 7187 TO CH:
7700 BETWEEN PRAJAPATI NAGAR TO SITABURDI

BH-P200 BH-P202 BH-P204 BH-P206

Average Layer Undrained


Layer Thickness (m) SPT N
Description Cohesion *
No. Value
Mpa
Filled up soil consists of silty sand / silty clay
- 1.2 17 -
with kankar, gravel, boulders etc.
I Stiff to very stiff/hard clayey silt / Silty Clay 4.4 33 -
Medium dense/Dense/Very dense, silty sand
II 3.5 72 -
with rock particles/dust.
III Moderately/Highly Weathered Rock. 10.3 >200 1.3

BH-P208 BH-P210 BH-P212 BH-P214 BH-P216

Average Layer Undrained


Layer SPT N
Description Thickness (m) Cohesion *
No. Value
Mpa
Filled up soil consists of bitumen,
- 0.9 10 -
concrete slab, silty sand, boulders etc.
Stiff to very stiff/dense/ hard clayey silt /
I 7.8 23 -
Silty Clay
Dense to Very dense, silty sand with clay
II 2.7 41 -
binder.
III Moderately/Highly Weathered Rock. 10.3 >200 1.3

BH-P55 BH-P57 BH-P61 BH-P65

Average Layer Undrained


Layer Thickness(m) SPT N
Description Cohesion *
No. Value
Mpa
Filled up soil consists of bitumen, stone
- 1.1 13 -
chips, concrete slab, boulder etc.
Stiff to very stiff/hard Silty clay with
I 6.0 27 -
traces of kankar,rock particles & sand.
Dense to very dense, silty sand with rock
II 1.6 52 -
particles.
III Moderately/Highly Weathered Rock. 10.3 >200 1.30

Page 17
DBR for DESIGN AND CONSTRUCTION OF ELEVATED VIADUCT OF LENGTH 6.305 KMS
FROM CH: 796.983 TO CH: 5691.7, CH: 6202.5 TO CH: 7100 AND CH: 7187 TO CH:
7700 BETWEEN PRAJAPATI NAGAR TO SITABURDI

BH-P93 BH-P95 BH-P97 BH-P99 BH-P101

Average Layer
Thickness(m) Undrained
Layer SPT N
Description Cohesion *
No. Value
Mpa
Filled up soil consists of bitumen,
- stone chips, concrete slab, sand, 1.8 16 -
boulders etc.
Stiff to very stiff/hard Silty clay
I with traces of kankar,rock 2.4 -
particles & sand. 40
Dense to very dense, silty sand
II 4.7 -
with rock particles. 50
Moderately/Highly Weathered
III 10.3 1.3
Rock. >200

BH-P146 BH-P155 BH-P156 BH-P164 BH-P164A

Average Layer
Thickness(m) Undrained
Layer SPT N
Description Cohesion *
No. Value
Mpa
Filled up soil consists of bitumen,
- stone chips, concrete slab, brick 1.2 - -
bats & boulder.
Stiff to very stiff/hard Silty
I clay/clayey silt with traces of 3.7 31 -
kankar.
II Dense to very dense, silty sand. 1.6 59 -
Moderately/Highly Weathered
III 13.0 >200 1.3
Rock.

BH-SP14 BH-P21 BH-P23 BH-P25

Average Layer
Thickness(m) Undrained
Layer SPT N
Description Cohesion *
No. Value
Mpa
Filled up soil consists of bitumen,
- stone chips, brick bats, kankar, 1.1 12 -
boulders etc.
I Stiff to very stiff/hard Silty clay 9.5 23 -
Very dense, silty sand with
II 2.0 54 -
Kankar.
Moderately/Highly Weathered
III 7.2 >200 >200
Rock.

BH-P27 BH-P29 BH-P31 BH-P33 BH-P35

Page 18
DBR for DESIGN AND CONSTRUCTION OF ELEVATED VIADUCT OF LENGTH 6.305 KMS
FROM CH: 796.983 TO CH: 5691.7, CH: 6202.5 TO CH: 7100 AND CH: 7187 TO CH:
7700 BETWEEN PRAJAPATI NAGAR TO SITABURDI

Average Layer
Thickness(m) Undrained
Layer SPT N
Description Cohesion *
No. Value
Mpa

Filled up soil consists of bitumen, stone


-- 1.1 12 -
chips, boulders etc.
I Stiff to very stiff/hard Silty clay 12.5 29 -
II Very dense, silty sand. Obs. Kankar. 1.8 73 -
III Moderately/Highly Weathered Rock. 10.2 >200 1.3

BH-P37 BH-SP40 BH-SP42 BH-P44

Average Layer Undrained


Layer Thickness (m) SPT N
Description Cohesion *
No. Value
Mpa
Filled up soil consists of bitumen, stone
- 1.2 11 -
chips, boulders etc.
Stiff to very stiff/hard, silty clay with
I 6.8 25 -
Kankar.
Dense to Very dense, silty sand. Obs.
II 4.2 56 -
Kankar.
III Moderately/Highly Weathered Rock. 10.3 >200 1.30

BH-P47 BH-P49 BH-P51 BH-P53

Average Layer Undrained Angle of Internal


Layer Thickness(m) SPT N
Description Cohesion * Friction
No. Value
Mpa (degrees)
Filled up soil consists of
- bitumen, stone chips, 1.0 11 - -
boulders etc.
Stiff to very stiff/hard silty
I clay. Obs. Kankar & gravel & 7.3 25 - -
sand
Dense to Very dense, silty
II 2.2 66 - -
sand with rock particles.
Moderately/Highly
III 10.3 1.3 -
Weathered Rock. >200

BH-P67 BH-P69 BH-P71 BH-P74 BH-SP76 BH-SP78

Page 19
DBR for DESIGN AND CONSTRUCTION OF ELEVATED VIADUCT OF LENGTH 6.305 KMS
FROM CH: 796.983 TO CH: 5691.7, CH: 6202.5 TO CH: 7100 AND CH: 7187 TO CH:
7700 BETWEEN PRAJAPATI NAGAR TO SITABURDI

Average Layer
Thickness(m) Undrained
Layer SPT N
Description Cohesion *
No. Value
Mpa
Filled up soil consists of bitumen, stone
- 1.4 13 -
chips, boulders, sand mixture etc.
I Stiff to very stiff/hard silty clay 4.0 35 -
Dense to Very dense, silty sand with rock
1 1.1 56 -
particles.
III Moderately/Highly Weathered Rock. 10.2 >200 1.30

BH-SP81 BH-P83(R2) BH-P85 BH-P87(R2) BH-P89 BH-P91

Average Layer
Thickness(m) Undrained
Layer SPT N
Description Cohesion *
No. Value
Mpa

Filled up soil consists of bitumen, stone


- 1.1 10 -
chips, concrete slab, boulders, sand etc.
I Stiff to very stiff/hard silty clay / clayey silt. 2.9 17 -
II Dense to Very dense, silty sand. 1.9 47 -
III Moderately/Highly Weathered Rock. 10.3 >200 1.3

BH-SP106

Average Layer Undrained


Layer Thickness(m) SPT N
Description Cohesion *
No. Value
Mpa
Filled up soil consists of bitumen, stone
- 1.2 13 -
chips, boulders etc.
Stiff to very stiff/hard silty clay / clayey
I 5.0 14 0.07
silt.
II Dense to Very dense, silty sand. 4.8 35 -
IA Very stiff/hard silty clay / clayey silt. 3.0 28 -
III Moderately/Highly Weathered Rock. 10.3 >200 1.3

BH-SP133 BH-P142

Page 20
DBR for DESIGN AND CONSTRUCTION OF ELEVATED VIADUCT OF LENGTH 6.305 KMS
FROM CH: 796.983 TO CH: 5691.7, CH: 6202.5 TO CH: 7100 AND CH: 7187 TO CH:
7700 BETWEEN PRAJAPATI NAGAR TO SITABURDI

Average Layer
Thickness(m) Undrained
Layer SPT N
Description Cohesion *
No. Value
Mpa

Filled up soil consists of brick bats, stone


- 1.1 11 -
chips, concrete slab, boulders, sand etc.
I Stiff to very stiff/hard silty clay / clayey silt. 2.2 35 -
II Dense to Very dense, silty sand. 3.1 47 -
III Moderately/Highly Weathered Rock. 10.3 >200 1.3

BH-P158

Average Layer
Undrained
Layer Thickness(m) SPT N
Description Cohesion *
No. Value
Mpa
Filled up soil consists of bitumen, stone
- 1.2 - -
chips, brick bats, concrete slab, boulder etc.
I Hard, silty clay. 2.6 75 -
II Dense to Very dense, silty sand. 2.0 70 -
III Moderately/Highly Weathered Rock. 10.2 >200 1.3

BH-P199

Average
Undrained Angle of Internal
Layer Layer SPT N
Description Cohesion * Friction
No. Thickness(m) Value
Mpa (degrees)
Filled up soil consists of
- bitumen, stone chips, boulders 1.1 - - -
etc.
I Medium dense, silty sand. 4.4 63 - 33
II Completely Weathered rock 1.5 170 0.95 -
Moderately/Highly Weathered
III 8.3 >200 1.3 -
Rock.

PJ-04 (BH-
MP-13 (BH-10) PJ-02 (BH-07) MP-11 (BH-06) MP-09 (BH-05)
08)

Page 21
DBR for DESIGN AND CONSTRUCTION OF ELEVATED VIADUCT OF LENGTH 6.305 KMS
FROM CH: 796.983 TO CH: 5691.7, CH: 6202.5 TO CH: 7100 AND CH: 7187 TO CH:
7700 BETWEEN PRAJAPATI NAGAR TO SITABURDI

Average Layer
Thickness(m) Undrained
SPT N
Sl.No Description Cohesion *
Value
Mpa
Filling consisting of bitumen, stone chips / silty
- clay with sand gravel pebbles, brick pieces 1.9 19 -
etc.
Silty clay / clayey silty / sandy silty clay with
I 6.6 31 -
kankars, calcareous nodules etc.
II Moderately/Highly Weathered Rock. 11.1 >200 1.3

MPP-01 (BH-01) MP-17 (BH-12) MP-18 MP-19 (BH-13)

Average Layer
Undrained
Thickness(m) SPT N
Sl.No Description Cohesion *
Value
Mpa
Filling consisting of bitumen, stone chips / silty
- clay with sand gravel pebbles, brick pieces 4.1 21 -
etc.
Silty clay / clayey silty / sandy silty clay with
I 7.1 39 -
kankars, calcareous nodules etc.
II Moderately/Highly Weathered Rock. 10.8 >200 1.3

MP-23 (BH- MPP-03 (BH- MPP-03 (BH- MPP-04 (BH- MPP-04 (BH-
15) 16) 17) 19) 18)

Average Layer
Thickness(m) Undrained
SPT N
Sl.No Description Cohesion *
Value
Mpa

Filling consisting of bitumen, stone chips / silty


- clay with sand gravel pebbles, brick pieces 2.4 17 -
etc.
Silty clay / clayey silty / sandy silty clay with
I 6.2 29 -
kankars, calcareous nodules etc.
II Moderately/Highly Weathered Rock. 10.3 >200 1.3

MPP-06 P-2 P-4 SP-12

Page 22
DBR for DESIGN AND CONSTRUCTION OF ELEVATED VIADUCT OF LENGTH 6.305 KMS
FROM CH: 796.983 TO CH: 5691.7, CH: 6202.5 TO CH: 7100 AND CH: 7187 TO CH:
7700 BETWEEN PRAJAPATI NAGAR TO SITABURDI

Average Layer Undrained


SPT N
Sl.No Description Thickness(m) Cohesion *
Value
Mpa

Filling consisting of bitumen, stone chips / silty


- clay with sand gravel pebbles, brick pieces 1.5 19 -
etc.
Silty clay / clayey silty / sandy silty clay with
I 9.9 32 -
kankars, calcareous nodules etc.
II Moderately/Highly Weathered Rock. 11.0 >200 1.3

BH-
BH-
P140/ PJ-06 MPP-02 P-6 P-8 P-9 P-19
P102/103
P141

Undrained
Layer Average SPT N
Description Cohesion *
No. Depth (m) Value
Mpa
Fill consisting of bitumen, stone chips/ silty clay
- 1.4 21 -
with sand gravels pebbles, brick pieces etc.
Silty clay / clayey silt /sandy silty clay with
I 8.1 41 -
kankars, calcareous nodules etc.
II Completely weathered /weathered granite gneiss 4.3 170 0.95
III Moderately/Highly Weathered Rock. 10.1 >200 1.30

BH-P59 BH-P63 BH-P151 BH- P45

Undrained
Layer Average SPT N
Description Cohesion *
No. Depth (m) Value
Mpa
Filled up soil consists of bitumen, stone chips,
- 1.1 15.0 -
concrete slab, boulder etc.
Stiff to very stiff/hard Silty clay with traces of
I 5.7 24.3 -
kankar, rock particles & sand.
Completely weathered /weathered granite
II 1.7 170.0 1.0
gneiss
III Moderately/Highly Weathered Rock. 8.7 >200 1.3

BH-P153 BH-SP161 MP-15 (BH-11) MP-21 (BH-14) SP-135

Page 23
DBR for DESIGN AND CONSTRUCTION OF ELEVATED VIADUCT OF LENGTH 6.305 KMS
FROM CH: 796.983 TO CH: 5691.7, CH: 6202.5 TO CH: 7100 AND CH: 7187 TO CH:
7700 BETWEEN PRAJAPATI NAGAR TO SITABURDI

Undrained
Layer Average SPT N
Description Cohesion *
No. Depth (m) Value
Mpa
Filled up soil consists of bitumen, stone chips,
- 1.6 21 -
concrete slab, brick bats & boulder.
Stiff to very stiff/hard Silty clay/clayey silt with
I 5.2 21 -
traces of kankar.
II Dense to very dense, silty sand. 6.1 59 -
Completely weathered /weathered granite
III 1.5 125 0.75
gneiss
IV Moderately/Highly Weathered Rock. 9.1 >200 1.3

Note:
1. Extrapolated SPT (N) values has been incorporated following proceedings of the
meeting dated 22nd June, 2017 between GC and ITD/STUP regarding method for
determination of vertical pile capacity as per Method 2 of IRC 78-2014. Minutes of
Meeting has been included in Annexure- A-3.

2. Suggested values of undrained cohesion are as per IRC 78-2014, Method 2, Pg-79.
As per the above stated meeting extrapolated SPT (N) values <100 are to be ignored
during pile capacity determination. As such, undrained cohesion and angle of friction
values have not been suggested for N<100.

3. SPT N value and thickness of various strata have been derived by taking average
value of that particular strata in the various Boreholes considered.

Page 24
DBR for DESIGN AND CONSTRUCTION OF ELEVATED VIADUCT OF LENGTH 6.305 KMS
FROM CH: 796.983 TO CH: 5691.7, CH: 6202.5 TO CH: 7100 AND CH: 7187 TO CH:
7700 BETWEEN PRAJAPATI NAGAR TO SITABURDI

8 References

1. The Standard Penetration Test (SPT): Methods and Use. CIRIA Report 143 1995

2. IS: 6403 – 1981 Code of Practice for Determination of Bearing Capacity of Shallow
Foundation

3. FHWA-IF-02-034 Evaluation of Soil and Rock Properties.

4. FHWA NHI-01-031 Sub-Surface Investigation - Geotechnical Site Characterization.

5. J. E. Bowles, Foundation Analysis and Design-Fifth Edition.

6. Factual Geotechnical Investigation Report No: ITDCEM/NMRCL/R4/PN/2017/153,


ITDCEM/NMRCL/R4/PN/2017/204, ITDCEM/NMRCL/R4/PN/2017/205 and
ITDCEM/NMRCL/R4/PN/2017/211 respectively submitted to NMRCL by ITDC

7. N. V. Nayak, Foundation Design Manual

8. Samsher Prakash, Soil Dynamics

9. Nitin Som and Das Theory and Practice of Foundation Design

10. NMRCL TENDER NO. N1C-09/2016(ICB): PART 2- Work Requirement & Appendices

Page 25
DBR for DESIGN AND CONSTRUCTION OF ELEVATED VIADUCT OF LENGTH 6.305 KMS
FROM CH: 796.983 TO CH: 5691.7, CH: 6202.5 TO CH: 7100 AND CH: 7187 TO CH:
7700 BETWEEN PRAJAPATI NAGAR TO SITABURDI

Annexure A – 1
Borehole Location Plan

Page 26
Page 27
Page 28
Page 29
Page 30
DBR for DESIGN AND CONSTRUCTION OF ELEVATED VIADUCT OF LENGTH 6.305 KMS
FROM CH: 796.983 TO CH: 5691.7, CH: 6202.5 TO CH: 7100 AND CH: 7187 TO CH:
7700 BETWEEN PRAJAPATI NAGAR TO SITABURDI

Annexure A – 2
Sub-surface Profile

Page 31
Page 32
Page 33
Page 34
Page 35
Page 36
Page 37
Page 38
Page 39
Page 40
Page 41
Page 42
Page 43
Page 44
Page 45
DBR for DESIGN AND CONSTRUCTION OF ELEVATED VIADUCT OF LENGTH 6.305 KMS
FROM CH: 796.983 TO CH: 5691.7, CH: 6202.5 TO CH: 7100 AND CH: 7187 TO CH:
7700 BETWEEN PRAJAPATI NAGAR TO SITABURDI

Annexure A – 3
Reference Charts and Tables and Minutes of
Meetings

Page 46
DBR for DESIGN AND CONSTRUCTION OF ELEVATED VIADUCT OF LENGTH 6.305 KMS
FROM CH: 796.983 TO CH: 5691.7, CH: 6202.5 TO CH: 7100 AND CH: 7187 TO CH:
7700 BETWEEN PRAJAPATI NAGAR TO SITABURDI

REFERENCE CHARTS AND TABLES

1. Soil Consistency and SPT N Resistance

As per Table 8 of CIRIA Report 143, the consistency of soil can be classified as –

For Cohesionless Soil

Corrected SPT Values N” Classification

0–3 Very loose

3–8 Loose

8 – 25 Medium

25 – 42 Dense

42 – 58 Very Dense

For Cohesive Soil

SPT Values N Classification

0–4 Very Soft

4–8 Soft

8 – 15 Firm

15 – 30 Stiff

30 – 60 Very Stiff

> 60 Hard

Page 47
DBR for DESIGN AND CONSTRUCTION OF ELEVATED VIADUCT OF LENGTH 6.305 KMS
FROM CH: 796.983 TO CH: 5691.7, CH: 6202.5 TO CH: 7100 AND CH: 7187 TO CH:
7700 BETWEEN PRAJAPATI NAGAR TO SITABURDI

2. Permeability of soil

As per clause 4.3.1.5, the general values of permeability for different type of cohesionless
soil are –

Coefficient of Permeability (k) in 10¯4


Type of Sand cm/sec

Very Fine Sand 1– 50

Fine Sand 51– 200

Fine to Medium Sand 201 – 500

Medium Sand 501– 1000

Medium to Coarse Sand 1001 – 1500

Gravel and Coarse Sand 1501 – 3000

3. Poisson’s Ratio

In absence of data for Poisson’s ratio the values are considered from section 2.6.6 of
Foundation Design and Construction by M J Tomlinson and same are as below –

Type of Soil Poisson’s Ratio

Clays (undrained) 0.50

Clays (Stiff, undrained) 0.10 – 0.20

Silt 0.30

Sands 0.10 – 0.30

Rocks 0.20

Page 48
DBR for DESIGN AND CONSTRUCTION OF ELEVATED VIADUCT OF LENGTH 6.305 KMS
FROM CH: 796.983 TO CH: 5691.7, CH: 6202.5 TO CH: 7100 AND CH: 7187 TO CH:
7700 BETWEEN PRAJAPATI NAGAR TO SITABURDI

4. Angle of Internal Friction and Field SPT N value

IS 6403 gives the values for Angle of Shearing resistance corresponding to Field SPT N
value (Ref: 03)

Page 49
DBR for DESIGN AND CONSTRUCTION OF ELEVATED VIADUCT OF LENGTH 6.305 KMS
FROM CH: 796.983 TO CH: 5691.7, CH: 6202.5 TO CH: 7100 AND CH: 7187 TO CH:
7700 BETWEEN PRAJAPATI NAGAR TO SITABURDI

5. Shear Strength of cohesive soil and Field SPT N value

Terzaghi and Peck gave the values for undrained shear strength corresponding to Field
SPT N value (Ref: 16)

Page 50
DBR for DESIGN AND CONSTRUCTION OF ELEVATED VIADUCT OF LENGTH 6.305 KMS
FROM CH: 796.983 TO CH: 5691.7, CH: 6202.5 TO CH: 7100 AND CH: 7187 TO CH:
7700 BETWEEN PRAJAPATI NAGAR TO SITABURDI

Page 51
DBR for DESIGN AND CONSTRUCTION OF ELEVATED VIADUCT OF LENGTH 6.305 KMS
FROM CH: 796.983 TO CH: 5691.7, CH: 6202.5 TO CH: 7100 AND CH: 7187 TO CH:
7700 BETWEEN PRAJAPATI NAGAR TO SITABURDI

Page 52
DBR for DESIGN AND CONSTRUCTION OF ELEVATED VIADUCT OF LENGTH 6.305 KMS
FROM CH: 796.983 TO CH: 5691.7, CH: 6202.5 TO CH: 7100 AND CH: 7187 TO CH:
7700 BETWEEN PRAJAPATI NAGAR TO SITABURDI

Annexure A – 4

Soil Stratification from Factual Geotechnical


Report

Page 53
DBR for DESIGN AND CONSTRUCTION OF ELEVATED VIADUCT OF LENGTH 6.305 KMS
FROM CH: 796.983 TO CH: 5691.7, CH: 6202.5 TO CH: 7100 AND CH: 7187 TO CH:
7700 BETWEEN PRAJAPATI NAGAR TO SITABURDI

Page 54
DBR for DESIGN AND CONSTRUCTION OF ELEVATED VIADUCT OF LENGTH 6.305 KMS
FROM CH: 796.983 TO CH: 5691.7, CH: 6202.5 TO CH: 7100 AND CH: 7187 TO CH:
7700 BETWEEN PRAJAPATI NAGAR TO SITABURDI

Page 55
DBR for DESIGN AND CONSTRUCTION OF ELEVATED VIADUCT OF LENGTH 6.305 KMS
FROM CH: 796.983 TO CH: 5691.7, CH: 6202.5 TO CH: 7100 AND CH: 7187 TO CH:
7700 BETWEEN PRAJAPATI NAGAR TO SITABURDI

Page 56
DBR for DESIGN AND CONSTRUCTION OF ELEVATED VIADUCT OF LENGTH 6.305 KMS
FROM CH: 796.983 TO CH: 5691.7, CH: 6202.5 TO CH: 7100 AND CH: 7187 TO CH:
7700 BETWEEN PRAJAPATI NAGAR TO SITABURDI

Page 57
DBR for DESIGN AND CONSTRUCTION OF ELEVATED VIADUCT OF LENGTH 6.305 KMS
FROM CH: 796.983 TO CH: 5691.7, CH: 6202.5 TO CH: 7100 AND CH: 7187 TO CH:
7700 BETWEEN PRAJAPATI NAGAR TO SITABURDI

Page 58
DBR for DESIGN AND CONSTRUCTION OF ELEVATED VIADUCT OF LENGTH 6.305 KMS
FROM CH: 796.983 TO CH: 5691.7, CH: 6202.5 TO CH: 7100 AND CH: 7187 TO CH:
7700 BETWEEN PRAJAPATI NAGAR TO SITABURDI

Page 59
DBR for DESIGN AND CONSTRUCTION OF ELEVATED VIADUCT OF LENGTH 6.305 KMS
FROM CH: 796.983 TO CH: 5691.7, CH: 6202.5 TO CH: 7100 AND CH: 7187 TO CH:
7700 BETWEEN PRAJAPATI NAGAR TO SITABURDI

Page 60
DBR for DESIGN AND CONSTRUCTION OF ELEVATED VIADUCT OF LENGTH 6.305 KMS
FROM CH: 796.983 TO CH: 5691.7, CH: 6202.5 TO CH: 7100 AND CH: 7187 TO CH:
7700 BETWEEN PRAJAPATI NAGAR TO SITABURDI

Page 61
DBR for DESIGN AND CONSTRUCTION OF ELEVATED VIADUCT OF LENGTH 6.305 KMS
FROM CH: 796.983 TO CH: 5691.7, CH: 6202.5 TO CH: 7100 AND CH: 7187 TO CH:
7700 BETWEEN PRAJAPATI NAGAR TO SITABURDI

Page 62
DBR for DESIGN AND CONSTRUCTION OF ELEVATED VIADUCT OF LENGTH 6.305 KMS
FROM CH: 796.983 TO CH: 5691.7, CH: 6202.5 TO CH: 7100 AND CH: 7187 TO CH:
7700 BETWEEN PRAJAPATI NAGAR TO SITABURDI

Page 63
DBR for DESIGN AND CONSTRUCTION OF ELEVATED VIADUCT OF LENGTH 6.305 KMS
FROM CH: 796.983 TO CH: 5691.7, CH: 6202.5 TO CH: 7100 AND CH: 7187 TO CH:
7700 BETWEEN PRAJAPATI NAGAR TO SITABURDI

Page 64
DBR for DESIGN AND CONSTRUCTION OF ELEVATED VIADUCT OF LENGTH 6.305 KMS
FROM CH: 796.983 TO CH: 5691.7, CH: 6202.5 TO CH: 7100 AND CH: 7187 TO CH:
7700 BETWEEN PRAJAPATI NAGAR TO SITABURDI

Page 65
DBR for DESIGN AND CONSTRUCTION OF ELEVATED VIADUCT OF LENGTH 6.305 KMS
FROM CH: 796.983 TO CH: 5691.7, CH: 6202.5 TO CH: 7100 AND CH: 7187 TO CH:
7700 BETWEEN PRAJAPATI NAGAR TO SITABURDI

Page 66
DBR for DESIGN AND CONSTRUCTION OF ELEVATED VIADUCT OF LENGTH 6.305 KMS
FROM CH: 796.983 TO CH: 5691.7, CH: 6202.5 TO CH: 7100 AND CH: 7187 TO CH:
7700 BETWEEN PRAJAPATI NAGAR TO SITABURDI

Page 67
DBR for DESIGN AND CONSTRUCTION OF ELEVATED VIADUCT OF LENGTH 6.305 KMS
FROM CH: 796.983 TO CH: 5691.7, CH: 6202.5 TO CH: 7100 AND CH: 7187 TO CH:
7700 BETWEEN PRAJAPATI NAGAR TO SITABURDI

Page 68
DBR for DESIGN AND CONSTRUCTION OF ELEVATED VIADUCT OF LENGTH 6.305 KMS
FROM CH: 796.983 TO CH: 5691.7, CH: 6202.5 TO CH: 7100 AND CH: 7187 TO CH:
7700 BETWEEN PRAJAPATI NAGAR TO SITABURDI

Page 69
DBR for DESIGN AND CONSTRUCTION OF ELEVATED VIADUCT OF LENGTH 6.305 KMS
FROM CH: 796.983 TO CH: 5691.7, CH: 6202.5 TO CH: 7100 AND CH: 7187 TO CH:
7700 BETWEEN PRAJAPATI NAGAR TO SITABURDI

Page 70