Sunteți pe pagina 1din 105

MS PIPE RATES AS PER PH SSR 2015-16

Cost includes Earth Work excavation, Laying and Jointing, Pressure Testing, Refilling etc
complete. But, excluding Taxes and Contractor Profit.
Sl Dia Thic Working Material Loweri Siza of Earth 75% Contractor Total cost
No kne Pressure cost ng, L&J trench work Extra profit @ (Rs)
ss in Excavati 13.615%
Kg/Cm^2 on

1 500 8 27 8314 783 1.1 1.7 151.99 113.99 1274.77 10637.75


2 500 10 34 9763 802 1.1 1.7 151.99 113.99 1474.64 12305.62
3 600 8 23 9886 967 1.2 1.8 175.56 131.67 1519.47 12679.70
4 600 10 28 11610 987 1.2 1.8 175.56 131.67 1756.91 14661.14
5 700 8 20 11403 1221 1.3 1.9 200.76 150.57 1766.59 14741.92
6 700 10 24 13425 1246 1.3 1.9 200.76 150.57 2045.29 17067.62
7 800 8 17 12923 1406 1.4 2 227.58 170.69 2005.12 16732.39
8 800 10 21 15212 1433 1.4 2 227.58 170.69 2320.44 19363.71
9 800 12 26 17524 1475 1.4 2 227.58 170.69 2640.94 22038.21
10 900 8 15 14466 1707 1.5 2.1 256.03 192.02 2262.96 18884.01
11 900 10 19 16989 1737 1.5 2.1 256.03 192.02 2610.55 21784.60
12 900 12 23 19563 1788 1.5 2.1 256.03 192.02 2967.94 24766.99
13 1000 8 14 16053 1889 1.6 2.2 286.11 214.58 2510.97 20953.66
14 1000 10 17 18875 1921 1.6 2.2 286.11 214.58 2899.54 24196.23
15 1000 12 20 21717 1976 1.6 2.2 286.11 214.58 3293.97 27487.65
16 1000 14 24 24507 2002 1.6 2.2 286.11 214.58 3677.37 30687.05
17 1100 8 12 20601 1889 1.7 2.3 317.8
18 1100 10 16 20601 1982 1.7 2.3 317.8 238.35 3150.40 26289.55
19 1100 12 19 23711 2041 1.7 2.3 317.8 238.35 3581.85 29890.01
20 1100 14 22 26800 2069 1.7 2.3 317.8 238.35 4006.23 33431.38
21 1100 16 25 29920 2126 1.7 2.3 317.8 238.35 4438.78 37040.93
22 1200 8 11 23313 1661 1.8 2.4 351.13 263.35 3483.87 29072.35
23 1200 10 14 22484 2044 1.8 2.4 351.13 263.35 3423.15 28565.63
24 1200 12 17 25864 2108 1.8 2.4 351.13 263.35 3892.05 32478.53
25 1200 14 20 29178 2138 1.8 2.4 351.13 263.35 4347.33 36277.81
26 1200 16 23 32517 2199 1.8 2.4 351.13 263.35 4810.24 40140.72
27 1200 18 26 35872 2261 1.8 2.4 351.13 263.35 5275.47 44022.95
28 1300 8 11 25437 1909 1.9 2.5 386.08 289.56 3815.15 31836.79
29 1300 10 13 24256 2107 1.9 2.5 386.08 289.56 3681.31 30719.95
30 1300 12 16 27857 2177 1.9 2.5 386.08 289.56 4181.12 34890.76
31 1300 14 18 31478 2209 1.9 2.5 386.08 289.56 4678.47 39041.11
32 1300 16 21 35128 2276 1.9 2.5 386.08 289.56 5184.54 43264.18
33 1300 18 24 38751 2342 1.9 2.5 386.08 289.56 5686.80 47455.44
34 1300 20 26 42381 2431 1.9 2.5 386.08 289.56 6193.14 51680.78
35 1400 8 10 26052 2197 2 2.6 422.66 317.00 3946.81 32935.46
36 1400 10 12 26052 2316 2 2.6 422.66 317.00 3963.01 33070.66
37 1400 12 15 29965 2390 2 2.6 422.66 317.00 4505.84 37600.49
38 1400 14 17 33853 2425 2 2.6 422.66 317.00 5039.95 42057.60
39 1400 16 20 37756 2495 2 2.6 422.66 317.00 5580.88 46571.53
40 1400 18 22 41653 2568 2 2.6 422.66 317.00 6121.39 51082.05
41 1400 20 24 45595 2596 2 2.6 422.66 317.00 6661.91 55592.56
42 1400 22 27 49483 2748 2 2.6 422.66 317.00 7211.95 60182.61
43 1500 8 9 28971 2525 2.1 2.7 460.86 345.65 4397.99 36700.49
44 1500 10 11 27863 2371 2.1 2.7 460.86 345.65 4226.16 35266.67
45 1500 12 14 32048 2450 2.1 2.7 460.86 345.65 4806.71 40111.21
46 1500 14 16 36158 2488 2.1 2.7 460.86 345.65 5371.46 44823.96
47 1500 16 18 40284 2562 2.1 2.7 460.86 345.65 5943.29 49595.79
48 1500 18 20 44492 2639 2.1 2.7 460.86 345.65 6526.69 54464.20
49 1500 20 23 48647 2742 2.1 2.7 460.86 345.65 7106.42 59301.92
50 1500 22 25 52904 2770 2.1 2.7 460.86 345.65 7689.82 64170.33
51 1500 24 27 57059 2875 2.1 2.7 460.86 345.65 8269.82 69010.32
52 1600 8 9 30617 2903 2.2 2.8 500.68 375.51 4683.04 39079.23
53 1600 10 11 29712 2427 2.2 2.8 500.68 375.51 4495.02 37510.21
54 1600 12 13 34111 2511 2.2 2.8 500.68 375.51 5105.38 42603.57
55 1600 14 15 38574 2552 2.2 2.8 500.68 375.51 5718.60 47720.79
56 1600 16 17 42965 2633 2.2 2.8 500.68 375.51 6327.46 52801.65
57 1600 18 19 47393 2715 2.2 2.8 500.68 375.51 6941.50 57925.69
58 1600 20 21 51815 2820 2.2 2.8 500.68 375.51 7557.85 63069.04
59 1600 22 23 56290 2898 2.2 2.8 500.68 375.51 8177.74 68241.93
60 1600 24 26 60806 3028 2.2 2.8 500.68 375.51 8810.29 73520.48
61 1600 26 28 65290 3170 2.2 2.8 500.68 375.51 9440.12 78776.31
62 1700 8 8 32505 3336 2.3 2.9 542.14 406.61 5008.92 41798.67
63 1700 10 10 31433 2487 2.3 2.9 542.14 406.61 4747.38 39616.12
64 1700 12 12 36195 2576 2.3 2.9 542.14 406.61 5407.84 45127.59
65 1700 14 14 40883 2618 2.3 2.9 542.14 406.61 6051.83 50501.58
66 1700 16 16 45493 2703 2.3 2.9 542.14 406.61 6691.06 55835.80
67 1700 18 18 50276 2790 2.3 2.9 542.14 406.61 7354.11 61368.85
68 1700 20 20 54964 2904 2.3 2.9 542.14 406.61 8007.90 66824.64
69 1700 22 22 59652 3019 2.3 2.9 542.14 406.61 8661.83 72281.57
70 1700 24 24 64443 3146 2.3 2.9 542.14 406.61 9331.41 77869.16
71 1700 26 26 69184 3285 2.3 2.9 542.14 406.61 9995.83 83413.57
72 1700 28 28 73924 3285 2.3 2.9 542.14 406.61 10641.18 88798.92
73 1800 8 8 34409 3838 2.4 3 585.22 438.92 5346.77 44617.90
74 1800 10 9 33313 2752 2.4 3 585.22 438.92 5049.69 42138.82
75 1800 12 11 38311 2846 2.4 3 585.22 438.92 5742.96 47924.10
76 1800 14 13 43253 2891 2.4 3 585.22 438.92 6421.94 53590.08
77 1800 16 15 48173 2979 2.4 3 585.22 438.92 7103.78 59279.92
78 1800 18 17 53128 3074 2.4 3 585.22 438.92 7791.34 65017.47
79 1800 20 19 58131 3191 2.4 3 585.22 438.92 8488.43 70834.56
80 1800 22 21 63139 3314 2.4 3 585.22 438.92 9187.01 76664.15
81 1800 24 23 68094 3449 2.4 3 585.22 438.92 9880.02 82447.15
82 1800 26 25 73142 3595 2.4 3 585.22 438.92 10587.18 88348.31
83 1800 28 27 78158 3595 2.4 3 585.22 438.92 11270.11 94047.24
84 1800 30 28 94572 3595 2.4 3 585.22 438.92 13504.87 112696.01
85 1900 8 7 35005 4414 2.5 3.1 629.92 472.44 5516.98 46038.34
86 1900 10 9 35092 3151 2.5 3.1 629.92 472.44 5356.87 44702.23
87 1900 12 11 40338 3252 2.5 3.1 629.92 472.44 6084.86 50777.22
88 1900 14 13 45560 3298 2.5 3.1 629.92 472.44 6802.10 56762.46
89 1900 16 14 50732 3393 2.5 3.1 629.92 472.44 7519.21 62746.57
90 1900 18 16 55960 3492 2.5 3.1 629.92 472.44 8244.48 68798.84
91 1900 20 18 61235 3615 2.5 3.1 629.92 472.44 8979.41 74931.77
92 1900 22 20 66497 3744 2.5 3.1 629.92 472.44 9713.40 81056.76
93 1900 24 22 71725 3885 2.5 3.1 629.92 472.44 10444.39 87156.75
94 1900 26 23 77041 4038 2.5 3.1 629.92 472.44 11188.99 93370.35
95 1900 28 25 82316 4038 2.5 3.1 629.92 472.44 11907.18 99363.54
96 1900 30 27 99329 4038 2.5 3.1 629.92 472.44 14223.50 118692.86
97 1900 32 29 105824 4038 2.5 3.1 629.92 472.44 15107.80 126072.16
98 2000 8 7 36624 5078 2.6 3.2 676.25 507.19 5838.85 48724.29
99 2000 10 9 36854 3983 2.6 3.2 676.25 507.19 5721.08 47741.52
100 2000 12 10 42380 4088 2.6 3.2 676.25 507.19 6487.74 54139.18
101 2000 14 12 47864 4136 2.6 3.2 676.25 507.19 7240.93 60424.36
102 2000 16 14 53313 4235 2.6 3.2 676.25 507.19 7996.29 66727.72
103 2000 18 15 58842 4338 2.6 3.2 676.25 507.19 8763.08 73126.52
104 2000 20 17 64330 4469 2.6 3.2 676.25 507.19 9528.11 79510.55
105 2000 22 19 69865 4511 2.6 3.2 676.25 507.19 10287.42 85846.85
106 2000 24 20 75407 4658 2.6 3.2 676.25 507.19 11061.97 92310.41
107 2000 26 22 80935 4821 2.6 3.2 676.25 507.19 11836.80 98776.24
108 2000 28 24 86477 4821 2.6 3.2 676.25 507.19 12591.35 105072.79
109 2000 30 26 92067 4821 2.6 3.2 676.25 507.19 13352.43 111423.86
110 2000 32 27 108976 4821 2.6 3.2 676.25 507.19 15654.59 130635.02
111 2000 34 29 115669 4821 2.6 3.2 676.25 507.19 16565.84 138239.28
112 2100 8 7 38472 5840 2.7 3.3 724.2 543.15 6205.63 51784.98
113 2100 10 8 45245 5840 2.7 3.3 724.2 543.15 7127.77 59480.12
114 2100 12 10 44485 4591 2.7 3.3 724.2 543.15 6854.25 57197.60
115 2100 14 11 50239 4644 2.7 3.3 724.2 543.15 7644.87 63795.22
116 2100 16 13 55941 4746 2.7 3.3 724.2 543.15 8435.08 70389.43
117 2100 18 15 61704 4857 2.7 3.3 724.2 543.15 9234.83 77063.18
118 2100 20 16 67497 4993 2.7 3.3 724.2 543.15 10042.06 83799.41
119 2100 22 18 73293 5136 2.7 3.3 724.2 543.15 10850.66 90547.01
120 2100 24 20 79100 5289 2.7 3.3 724.2 543.15 11662.11 97318.46
121 2100 26 21 84904 5458 2.7 3.3 724.2 543.15 12475.34 104104.69
122 2100 28 23 90712 5458 2.7 3.3 724.2 543.15 13266.10 110703.45
123 2100 30 24 96560 5458 2.7 3.3 724.2 543.15 14062.30 117347.65
124 2100 32 26 102409 5458 2.7 3.3 724.2 543.15 14858.64 123992.99
125 2100 34 28 108278 5458 2.7 3.3 724.2 543.15 15657.71 130661.06
126 2100 36 29 128515 5458 2.7 3.3 724.2 543.15 18412.97 153653.32
127 2200 8 6 40088 6714 2.8 3.4 773.79 580.34 6556.46 54712.59
128 2200 10 8 47142 6714 2.8 3.4 773.79 580.34 7516.86 62726.99
129 2200 12 9 46529 5118 2.8 3.4 773.79 580.34 7216.10 60217.24
130 2200 14 11 52537 5173 2.8 3.4 773.79 580.34 8041.58 67105.71
131 2200 16 12 58522 5280 2.8 3.4 773.79 580.34 8871.01 74027.14
132 2200 18 14 64583 5395 2.8 3.4 773.79 580.34 9711.87 81044.00
133 2200 20 16 70645 5378 2.8 3.4 773.79 580.34 10534.90 87912.03
134 2200 22 17 76666 5528 2.8 3.4 773.79 580.34 11375.08 94923.21
135 2200 24 19 82736 5689 2.8 3.4 773.79 580.34 12223.43 102002.56
136 2200 26 20 88852 5866 2.8 3.4 773.79 580.34 13080.22 109152.35
137 2200 28 22 94873 5866 2.8 3.4 773.79 580.34 13899.98 115993.11
138 2200 30 23 100988 5866 2.8 3.4 773.79 580.34 14732.54 122940.67
139 2200 32 25 107110 5866 2.8 3.4 773.79 580.34 15566.05 129896.18
140 2200 34 26 113279 5866 2.8 3.4 773.79 580.34 16405.96 136905.09
141 2200 36 28 119353 5866 2.8 3.4 773.79 580.34 17232.93 143806.06
142 2300 10 7 49313 7721 2.9 3.5 824.99 618.74 7961.74 66439.48
143 2300 12 9 48589 5811 2.9 3.5 824.99 618.74 7603.12 63446.86
144 2300 14 10 54865 5867 2.9 3.5 824.99 618.74 8465.23 70640.96
145 2300 16 12 61148 5980 2.9 3.5 824.99 618.74 9336.04 77907.77
146 2300 18 13 67476 6101 2.9 3.5 824.99 618.74 10214.07 85234.81
147 2300 20 15 73772 6248 2.9 3.5 824.99 618.74 11091.29 92555.02
148 2300 22 16 80100 6424 2.9 3.5 824.99 618.74 11976.81 99944.54
149 2300 24 18 86429 6573 2.9 3.5 824.99 618.74 12858.79 107304.52
150 2300 26 19 92810 6757 2.9 3.5 824.99 618.74 13752.61 114763.34
151 2300 28 21 99105 6757 2.9 3.5 824.99 618.74 14609.68 121915.41
152 2300 30 22 105487 6757 2.9 3.5 824.99 618.74 15478.58 129166.32
153 2300 32 24 111869 6757 2.9 3.5 824.99 618.74 16347.49 136417.23
154 2300 34 25 118304 6757 2.9 3.5 824.99 618.74 17223.62 143728.35
155 2300 36 27 124695 6757 2.9 3.5 824.99 618.74 18093.75 150989.49
156 2400 10 7 51209 8879 3 3.6 877.82 658.37 8390.13 70014.32
157 2400 12 9 50616 6997 3 3.6 877.82 658.37 8053.16 67202.35
158 2400 14 10 57156 7055 3 3.6 877.82 658.37 8951.48 74698.66
159 2400 16 11 63664 7172 3 3.6 877.82 658.37 9853.47 82225.66
160 2400 18 13 70322 7297 3 3.6 877.82 658.37 10776.98 89932.16
161 2400 20 14 76863 7453 3 3.6 877.82 658.37 11688.77 97540.96
162 2400 22 16 83458 7614 3 3.6 877.82 658.37 12608.60 105216.79
163 2400 24 17 90115 7789 3 3.6 877.82 658.37 13538.78 112978.97
164 2400 26 18 96710 7981 3 3.6 877.82 658.37 14462.83 120690.02
165 2400 28 20 103318 7981 3 3.6 877.82 658.37 15362.51 128197.70
166 2400 30 21 109913 7981 3 3.6 877.82 658.37 16260.42 135690.60
167 2400 32 23 116569 7981 3 3.6 877.82 658.37 17166.63 143252.82
168 2400 34 24 123271 7981 3 3.6 877.82 658.37 18079.11 150867.30
169 2400 36 26 129917 7981 3 3.6 877.82 658.37 18983.96 158418.15
170 2400 40 28 142254 7981 3 3.6 877.82 658.37 20663.65 172434.83
171 2400 42 30 149268 7981 3 3.6 877.82 658.37 21618.60 180403.79
172 2500 10 7 53383 10211 3.1 3.7 932.28 699.21 8880.45 74105.94
173 2500 14 10 59544 8617 3.1 3.7 932.28 699.21 9502.25 79294.74
174 2500 16 11 66303 8738 3.1 3.7 932.28 699.21 10438.96 87111.45
175 2500 18 12 73165 8896 3.1 3.7 932.28 699.21 11394.73 95087.22
176 2500 20 14 80027 9031 3.1 3.7 932.28 699.21 12347.37 103036.86
177 2500 22 15 86950 9198 3.1 3.7 932.28 699.21 13312.68 111092.17
178 2500 24 16 93812 9379 3.1 3.7 932.28 699.21 14271.58 119094.07
179 2500 26 18 100674 9581 3.1 3.7 932.28 699.21 15233.35 127119.84
180 2500 28 19 107589 9795 3.1 3.7 932.28 699.21 16203.96 135219.45
181 2500 30 20 114416 9795 3.1 3.7 932.28 699.21 17133.46 142975.95
182 2500 32 22 121331 9795 3.1 3.7 932.28 699.21 18074.93 150832.42
183 2500 34 23 128298 9795 3.1 3.7 932.28 699.21 19023.49 158747.98
184 2500 36 25 135213 9795 3.1 3.7 932.28 699.21 19964.97 166604.46
185 2500 38 26 185170 9795 3.1 3.7 932.28 699.21 26766.61 223363.10
186 2500 46 31 193528 9795 3.1 3.7 932.28 699.21 27904.55 232859.04
187 2600 12 8 62297 11744 3.2 3.8 988.36 741.27 10316.17 86086.80
188 2600 14 9 61891 8805 3.2 3.8 988.36 741.27 9860.75 82286.38
189 2600 16 11 68915 8932 3.2 3.8 988.36 741.27 10834.36 90410.99
190 2600 18 12 75998 9069 3.2 3.8 988.36 741.27 11817.36 98613.99
191 2600 20 13 83126 9232 3.2 3.8 988.36 741.27 12810.03 106897.66
192 2600 22 14 90255 9408 3.2 3.8 988.36 741.27 13804.61 115197.24
193 2600 24 16 97437 9597 3.2 3.8 988.36 741.27 14808.17 123571.80
194 2600 26 17 104572 9805 3.2 3.8 988.36 741.27 15807.92 131914.55
195 2600 28 18 111754 10027 3.2 3.8 988.36 741.27 16815.97 140326.60
196 2600 30 20 118882 10267 3.2 3.8 988.36 741.27 17819.13 148697.76
197 2600 32 21 126062 10523 3.2 3.8 988.36 741.27 18831.54 157146.17
198 2600 34 22 133252 10795 3.2 3.8 988.36 741.27 19847.49 165624.12
199 2600 36 24 140486 11081 3.2 3.8 988.36 741.27 20871.34 174167.97
200 2600 38 25 147668 11390 3.2 3.8 988.36 741.27 21891.24 182678.87
201 2600 40 26 154902 11713 3.2 3.8 988.36 741.27 22920.12 191264.75
202 2600 42 27.56923 162145 12049 3.2 3.8 988.36 741.27 23952.00 199875.63
203 2700 18 11 78908 9147 3.3 3.9 1046.07 784.55 12237.93 102123.55
204 2700 20 13 86248 9320 3.3 3.9 1046.07 784.55 13260.82 110659.44
205 2700 22 14 93643 9500 3.3 3.9 1046.07 784.55 14292.16 119265.78
206 2700 24 15 101046 9697 3.3 3.9 1046.07 784.55 15326.90 127900.52
207 2700 26 16 108481 9913 3.3 3.9 1046.07 784.55 16368.58 136593.20
208 2700 28 17.69877 115984 10143 3.3 3.9 1046.07 784.55 17421.43 145379.05
209 2700 30 19 123430 10391 3.3 3.9 1046.07 784.55 18468.97 154120.59
210 2700 32 20 130833 10655 3.3 3.9 1046.07 784.55 19512.83 162831.45
211 2700 34 21 138282 10940 3.3 3.9 1046.07 784.55 20565.81 171618.44
212 2700 36 23 145783 11238 3.3 3.9 1046.07 784.55 21627.65 180479.27
213 2700 38 24 153239 11555 3.3 3.9 1046.07 784.55 22685.94 189310.56
214 2700 40 25.28395 160740 11887 3.3 3.9 1046.07 784.55 23752.41 198210.03
215 2700 42 26.54815 168188 12295 3.3 3.9 1046.07 784.55 24822.00 207135.62
216 2800 18 11 81732 9341 3.4 4 1105.41 829.06 12662.97 105670.43
217 2800 20 12 89401 9516 3.4 4 1105.41 829.06 13730.93 114582.39
218 2800 22 13 97062 9704 3.4 4 1105.41 829.06 14799.57 123500.04
219 2800 24 15 104725 9910 3.4 4 1105.41 829.06 15870.93 132440.40
220 2800 26 16 112386 10131 3.4 4 1105.41 829.06 16944.07 141395.53
221 2800 28 17.06667 120095 10369 3.4 4 1105.41 829.06 18026.05 150424.52
222 2800 30 18.28571 127863 10625 3.4 4 1105.41 829.06 19118.52 159540.99
223 2800 32 20 135524 10902 3.4 4 1105.41 829.06 20199.28 168559.75
224 2800 34 21 143239 11194 3.4 4 1105.41 829.06 21289.43 177656.90
225 2800 36 22 150961 11393 3.4 4 1105.41 829.06 22367.87 186656.34
226 2800 38 23 158729 11719 3.4 4 1105.41 829.06 23469.87 195852.34
227 2800 40 24 166444 12068 3.4 4 1105.41 829.06 24567.79 205014.25
228 2800 42 25.6 174253 12431 3.4 4 1105.41 829.06 25680.40 214298.87
229 2900 18 10.5931 84688 10629 3.5 4.1 1166.37 874.78 13255.31 110613.46
230 2900 20 12 92563 10814 3.5 4.1 1166.37 874.78 14352.68 119770.83
231 2900 22 13 100491 11006 3.5 4.1 1166.37 874.78 15458.22 128996.37
232 2900 24 14 108426 11218 3.5 4.1 1166.37 874.78 16567.43 138252.58
233 2900 26 15 116352 11448 3.5 4.1 1166.37 874.78 17677.87 147519.02
234 2900 28 16 124321 11696 3.5 4.1 1166.37 874.78 18796.62 156854.76
235 2900 30 17.65517 132302 11962 3.5 4.1 1166.37 874.78 19919.45 166224.59
236 2900 32 18.83218 140238 12244 3.5 4.1 1166.37 874.78 21038.33 175561.47
237 2900 34 20 148273 12547 3.5 4.1 1166.37 874.78 22173.55 185034.69
238 2900 36 21 156296 12869 3.5 4.1 1166.37 874.78 23309.72 194515.86
239 2900 38 22 164330 13206 3.5 4.1 1166.37 874.78 24449.43 204026.58
240 2900 40 24 172318 13563 3.5 4.1 1166.37 874.78 25585.60 213507.75
241 2900 42 25 180353 13938 3.5 4.1 1166.37 874.78 26730.62 223062.77
242 3000 18 10.24 87474 10715 3.6 4.2 1228.95 921.71 13661.25 114000.91
243 3000 20 11.37778 95709 10904 3.6 4.2 1228.95 921.71 14808.17 123571.84
244 3000 22 13 103858 11104 3.6 4.2 1228.95 921.71 15944.89 133057.55
245 3000 24 14 112051 11322 3.6 4.2 1228.95 921.71 17090.05 142613.71
246 3000 26 15 120246 11562 3.6 4.2 1228.95 921.71 18238.47 152197.13
247 3000 28 16 128481 11816 3.6 4.2 1228.95 921.71 19394.25 161841.91
248 3000 30 17 136737 12090 3.6 4.2 1228.95 921.71 20555.61 171533.27
249 3000 32 18.20444 144931 12385 3.6 4.2 1228.95 921.71 21711.39 181178.05
250 3000 34 19.34222 153220 12697 3.6 4.2 1228.95 921.71 22882.41 190950.07
251 3000 36 20 161522 13028 3.6 4.2 1228.95 921.71 24057.80 200758.46
252 3000 38 22 169777 13378 3.6 4.2 1228.95 921.71 25229.37 210535.03
253 3000 40 23 178078 13748 3.6 4.2 1228.95 921.71 26409.92 220386.59
254 3000 42 24 186367 14135 3.6 4.2 1228.95 921.71 27591.16 230243.82
Note:- Cost of pipe varies with Raw material cost.
Rmt Amount
60 4532307
29396 1944715896
4928 394291744
176 15366780
34560 2358906727
68255.403 Per Rmt

Nos Amount
2 1140000
10 353643.5
75 25804650
7 3242120
2 1323316
11 4576594
3 1680219
1 560073
8 6400832
3 1362055
1 611178.8
1 873112.55
36 6502212
6 1283064
1 231365
22 3642166
8 1590240
1 216302.4
40 6712120
8 1608241.2
1 218552.3
2 618940 13.70518
12 1566558
4 624096.8
28 539840
2 559000
69 4949163
74 15549279.6
2 40480
2 3066
9 161990.1
2 48880
1000cum 3667000
18631cum 75516100.8
8591cum 42530604.6
455cum 2736324.5
1300cum 10673090
100cum 669455
174cum 1098105.3
320cum 2626976
594Rmt 1483812
135 967005
22Rmt 20064
655MT 40829556
169.83cum 473706.82
6 39168882
1500cum 989700
10000cum 1941000
450Rmt 2876557.5
53 56551
53 118296
4 165641.2
1 90573
705 323292351
Month 25.07.2015 SSR 2015-16 JUNE

H2=HR Plates
(1.6&2mm
-Avg) 44500 BWSC Pipes
Rods
(5.5/6mm ) 42500 Class 300 350 400 450 500

C2=Cement 6300 12 3272 3964 4350 4804 5370


14 3272 3964 4350 4820 5435
16 3272 3964 4372 4892 5514
18 3272 3984 4435 4949 5775
20 3272 4022 4483 5188 6054
22 3316 4064 4688 5397 6344
24 3403 4166 4871 5645 6649
26 3528 4313 5057 5861 6911
28 3594 4437 5236 6096 7371
30 3783 4637 5912 6619 7842

K9-SSR Revised- K7 SSR K7


Pig iron Dia Rates K9 Rates Revised
26000 100 1062.00 1062.00 892.00 892.00
150 1569.00 1569.00 1235.00 1235.00
200 2095.00 2095.00 1722.00 1722.00
250 2749.00 2749.00 2310.00 2310.00
300 3482.00 3482.00 2967.00 2967.00
350 4340.00 4340.00 3734.00 3734.00
400 5233.00 5233.00 4532.00 4532.00
450 6261.00 6261.00 5452.00 5452.00
500 7284.00 7284.00 6498.00 6498.00
600 9607.00 9607.00 8647.00 8647.00
700 12420.00 12420.00 11189.00 11189.00
750 13938.00 13938.00 12537.00 12537.00
800 15380.00 15380.00 13855.00 13855.00
900 18758.00 18758.00 16904.00 16904.00
1000 22235.00 22235.00 20036.00 20036.00
1100 23747.00 23747.00
1200 27765.00 27765.00
HT Wire 59500 PSC Pipes
Cement 6300 Dia 6 Kg/cm2 8 Kg/cm2 10 Kg/cm2 12 Kg/cm2 14 Kg/cm2
350 2901 2911 2925 2941 3001
400 3121 3144 3179 3222 3282
450 3338 3355 3394 3461 3549
500 3613 3630 3660 3741 3819
600 4156 4188 4233 4366 4505
700 5094 5118 5201 5326 5513
800 6014 6078 6235 6385 6638
900 6977 7034 7194 7493 7783
1000 8192 8267 8501 8838 9251
1100 9307 9444 9708 10231 10680
1200 10335 10514 11052 11554 12215
1300 11724 12372 13034 13706 14859
1400 13368 14117 14900 16152 17443
1500 15575 16459 17343 18782 20219
1600 17533 18542 19552 22097 22877
1700 18461 19200 20201 22678 25066
1800 19973 21233 22406 24592 27172
1900 21328 22494 24485 25879 28114
2000 23457 24906 26232 28786 32730

Cement AC Pipes AC -Couplings


6300 Dia Class - 15 Class - 20 Class - 25 Class - 15
Fiber 80 198.00 218.00 271.00 92.00
75500 100 261.00 332.00 408.00 119.00
125 340.00 424.00 532.00 149.00
150 478.00 596.00 749.00 175.00
200 791.00 1015.00 1287.00 321.00
250 1002.00 1303.00 1631.00 376.00
300 1402.00 1830.00 2339.00 490.00
350 1708.00 2221.00 2803.00 635.00
400 2219.00 2906.00 3607.00 978.00
450 2641.00 3508.00 4391.00 1171.00
500 3255.00 4287.00 5382.00 1396.00
600 4631.00 6052.00 7711.00 1725.00
700 6085.00 8255.00 10674.00 3366.00
750 6935.00 9529.00 12213.00 2556.00
800 7935.00 10796.00 13856.00 2899.00
850 8901.00 12145.00 15602.00 3230.00
900 9923.00 13569.00 17452.00 3574.00
1000 12249.00 16658.00 21461.00 4362.00

Pig Iron CI Pipes


26000 Dia LA A B
80 834.00 904.00 972.00
100 1015.00 1115.00 1191.00
125 1279.00 1396.00 1504.00
150 1549.00 1697.00 1829.00
200 2261.00 2454.00 2656.00
250 3047.00 3318.00 3590.00
300 3929.00 4298.00 4655.00
350 5026.00 5453.00 6915.00
400 6120.00 6687.00 7217.00
450 7405.00 8136.00 8775.00
500 8758.00 9541.00 10322.00
600 11581.00 12643.00 13693.00
700 15246.00 16657.00 17996.00
750 17076.00 18670.00 20254.00
800 19114.00 20827.00 22530.00
900 23293.00 29103.00 27538.00
1000 27985.00 30568.00 33040.00

Resin HDPE-80 Grade


111770 Class PE-80 63 75 90 110 125
4 90 122 175 261 337
Resin HDPE-100 Grade
112600 Class PE-100 63 75 90 110 125
6 105 149 212 318 406
8 134 190 271 404 521
10 162 229 325 482 626
12.5 212 302 429 645 827
16 273 389 566 813 1043

Resin PVC Pipe rates


71214 Class 63 75 90 110 125
2.5
4 53 78 106 154 201
6 77 105 152 220 281
10 116 168 237 354 462

HT Wire 59500 PCCP Pipes


Cement 6300 Dia 4kg/cm2 6 Kg/cm2 8 Kg/cm2 10 Kg/cm2 12 Kg/cm2
HR coil 44500 400 5299 5299 5299 5299 5326
450 5760 5760 5760 5787 5856
500 6297 6297 6311 6401 6477
600 7490 7546 7646 7779 7902
700 8658 8795 8960 9135 9301
800 10175 10366 10596 10826 11036
900 12064 12308 12593 12880 13167
1000 13990 14317 14660 15015 15367
1100 15571 15960 16373 16745 17137
1200 17661 18115 18576 19035 19506
1300 19663 20189 20724 21260 21810
1400 21578 22176 22801 23428 24052
1500 23698 24365 25034 25692 27075
1600 26725 27468 28227 29643 30505
1700 28791 29652 30564 32187 33163
1800 31566 32470 34239 35336 36407
1900 36864 37895 39868 41033 43117
2000 39362 41316 42641 44004 46383
600 700 800 900 1000 1100 1200

7077 8534 9700 11990 13540 19402 21457


7178 8745 10462 12481 14809 19754 22098
7284 9331 11188 13416 15870 19948 22904
7701 9899 11895 14340 16931 21877 25209
8112 10464 12643 15231 18056 24046 27687
8458 11058 13616 15979 19667 25573 29898
8909 11820 14414 17601 21498 28334 32472
9316 12309 15508 18834 23002 29840 33761
9891 12906 16250 19730 24248 31800 37739
10405 13744 17286 21080 25997 34611 41561

16 Kg/cm2
3104
3332
3625
3931
4642
5671
6875
8308
9735
11179
13179
16190
18363
21265
24061
26461
28687
31475
35283

AC -Couplings
Class - 20 Class - 25
99.00 114.00
129.00 155.00
165.00 199.00
219.00 270.00
354.00 450.00
475.00 604.00
637.00 819.00
820.00 1046.00
1277.00 1632.00
1544.00 1979.00
1866.00 2381.00
2170.00 2776.00
3050.00 3966.00
3494.00 4509.00
3931.00 5087.00
4397.00 5702.00
4888.00 6347.00
5944.00 7746.00

140 160 180 200 225 250 280 315 355


416 544 687 842 1093 1352 1685 2141 2610
140 160 180 200 225 250 280 315 355
510 667 839 1037 1338 1646 2063 2615 3284
652 849 1074 1327 1711 2114 2646 3351 4201
784 1021 1293 1594 2059 2542 3178 4029 5059
1041 1356 1712 2120 2675 3302 4149 5232 6655
1321 1709 2152 2664 3357 4152 5219 6604 8417

140 160 180 200 225 250 280 315

251 331 422 513 682 793 1038 1314


362 469 604 735 985 1209 1527 1919
573 751 962 1171 1567 1907 2413 3046

14 Kg/cm2 16 Kg/cm2 18kg/cm2 20kg/cm2


5383 5479 5570 5640
5940 6061 6144 6240
6583 6682 6831 6941
8026 8216 8392 8570
9462 9665 9924 10118
11250 11512 11788 12106
13425 13773 14117 14460
15660 16067 16487 16919
17495 17942 18413 19446
19927 20449 21483 22221
22294 23529 24187 25014
25287 26053 26835 28573
27835 28983 30690 32692
31367 33513 34466 35392
34989 36634 37666 38643
38420 40175 41414 42653
44774 46395 47771 49071
47823 50049 51630 53033
400 450 500 560 630 710
3382 4300 5281 6539 8271 10510
400 450 500 560 630 710
4319 5371 6644 7759 9785 12443
5520 6893 8499 9935 12570 15931
6632 8293 10231 11889 15061 19130
8617 10894 13454 15185 18071
10844 13617 16108
Data based on 2015-16 Common SSR
MA 0%
Earthwork excavation in all soils upto SDR using 2/3 machinery and 1/3rd manual labour Common SSR 2015-16

Rate Analysis : Rate Add: LI 13% Total Sand for bedding/encasing: Rate Earth workEarth work classification : Rate/cum

1 E/W Rate -using machinery 81.28 - 81.28 Cost of sand for filling - 302.00 1 Sand or LooSand or Loose soils wet sand(8b)

2 Diff. of 20a & 20b (of 8,9,12,13) 0.00 0.00 Conveyance charges 10KM Lead 796.13 2 Loamy clayey
Loamy clayey soils like BC and OG soils (9b)

3 Cost of refilling included in e/w 0.00 Seignorage charges 40/1.13615 35.21 3 Slushy SoilsSlushy Soils (10b)

4 Cost of sand filling 1224.79 - 1224.79 Filling charges - 91.45 4 Clayey Soil Clayey Soils(11b)

5 E/W rate - manual(as per Std. data) 112.84 112.84 Deduct stacking stacking 5 Hard gravellHard gravelly soils (12b)

Add: MA on filling charges 0.00 6 Mixture of Mixture of gravel and SDR (13b)

E/w rate for 2/3rd machinery & 1/3rd manual 91.80 /cum Total: 1224.79 Total: 112.84

= 81.28 x 2/3 + 112.84 x 1/3 =

Extra Allowance for trench cutting 75% Add LA & LI at 13%

Average Manual earth work rate with LA & LI - per cum: 112.84
PVC pipes - Earth work
1 Earth work excavation in all soils upto SDR except hard rock requiring blasting for P.V.C pipes with 150 mm thick sand cushion and filling with
excavated soils including laying jointing testing of pipe line but excluding cost of materials etc. complete

Trench size 0.70m x 1.00m 0.80m x 1.10m 0.90m x 1.20m

Pipe dia in mm = 63 mm 75 mm 90 mm 110 mm 125 mm 140 mm 160 mm 180 mm 200 mm 225 mm 250 mm 280 mm 315 mm

1 Earth work 64.26 64.26 64.26 64.26 64.26 64.26 80.78 80.78 80.78 99.14 99.14 99.14 99.14

2 Extra allowance at 75% 19.75 19.75 19.75 19.75 19.75 19.75 24.82 24.82 24.82 30.47 30.47 30.47 30.47

3 Sand cushion cost 128.60 128.60 128.60 128.60 128.60 128.60 146.97 146.97 146.97 165.35 165.35 165.35 165.35

4 Refilling charges 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

5 Lowering, Laying, Jointing & HF testing 6.17 7.35 8.82 10.78 12.25 13.72 15.68 17.64 19.60 22.05 24.50 27.44 30.87

6 Add MA 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total 218.78 219.96 221.43 223.39 224.86 226.33 268.25 270.21 272.17 317.01 319.46 322.40 325.83

HDPE pipes - Earth work


2 Earth work excavation in all soils upto SDR except hard rock requiring blasting for HDPE pipes filling with excavated soils including laying jointing
testing of pipe line but excluding cost of materials etc. complete

Trench size 0.70m x 1.00m 0.80m x 1.10m 0.90m x 1.20m

Pipe dia in mm = 63 mm 75 mm 90 mm 110 mm 125 mm 140 mm 160 mm 180 mm 200 mm 225 mm 250 mm 280 mm 315 mm

1 Earth work 64.26 64.26 64.26 64.26 64.26 64.26 80.78 80.78 80.78 90.88 99.14 99.14 99.14

2 Extra allowance 19.75 19.75 19.75 19.75 19.75 19.75 24.82 24.82 24.82 30.47 30.47 30.47 30.47

3 Refilling charges 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

4 Laying, Jointing & H F Testing 37.00 41.00 46.00 53.00 64.00 67.00 72.00 80.00 87.00 96.00 102.00 112.00 183.00

5 Add MA 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total 121.01 125.01 130.01 137.01 148.01 151.01 177.60 185.60 192.60 217.35 231.61 241.61 312.61
PSC pipes - Earth work
3 Earth work excavation in all soils upto SDR except hard rock requiring blasting for PSC pipes and filling with
excavated soils including laying jointing testing of pipe line but excluding cost of materials etc. complete

Trench size 1.0m x 1.4m 1.1m x 1.6m 1.2m x 1.7m 1.3m x 1.8m 1.4m x 1.9m 1.5m x 2.0m 1.6m x 2.1m 2.0m x 2.6m

Pipe dia in mm = 350 mm 400 mm 450 mm 500 mm 600 mm 700 mm 800 mm 900 mm 1000 mm 1400 mm

1 Earth work 128.52 128.52 128.52 161.57 187.27 214.81 244.19 275.40 308.45 477.36

2 Extra allowance 39.49 39.49 39.49 49.65 57.55 66.01 75.04 84.63 94.79 146.69

3 Refilling charges 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

4 Laying, jointing, testing HFT pressure 213.00 230.00 266.00 283.00 348.00 408.00 462.00 506.00 584.00 656.00
including cost of ruuber rings, cost of
transportation of water and emptying
pipe line after completion of field testing.

5 Add MA 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

5 Total 381.01 398.01 434.01 494.22 592.82 688.82 781.23 866.03 987.24 1280.05

BWSC pipes - Earth work


4 Earth work excavation in all soils upto SDR except hard rock requiring blasting for BWSCP pipes and filling
with excavated soils including laying jointing testing of pipe line but excluding cost of materials etc. complete

Trench size 1.0m x 1.4m 1.0mx1.40m 1.1m x 1.6m 1.2m x 1.7m 1.3mx 1.8m 1.4m x 1.9m 1.5mx 2.0m 1.6mx 2.1m 1.7m x 2.2m 1.8m x 2.3m

Pipe dia in mm = 300 mm 350 mm 400 mm 450 mm 500 mm 600 mm 700 mm 800 mm 900 mm 1000 mm 1100mm 1200mm

1 Earth work 128.52 128.52 128.52 128.52 161.57 187.27 214.81 244.19 275.40 308.45 343.33 396.58

2 Extra allowance 39.49 39.49 39.49 39.49 49.65 57.55 66.01 75.04 84.63 94.79 105.51 116.79

3 Refilling charges 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0 0 0

Laying, jointing, testing HFT pressure


including cost of site welding and fixing 360.00 426.00 476.00 476.00 596.00 733.00 854.00 971.00 1142.00 1262.00 1483 1660
of Diapher cloth, cost of transportation of
Add MA
water and emptying pipe line after 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0 0
completion of field testing.
Total 528.01 594.01 644.01 644.01 807.22 977.82 1134.82 1290.23 1502.03 1665.24 1931.84 2173.37
6 AC pipes - Earth work
Earth work excavation in all soils upto SDR except hard rock requiring blasting for AC pipes and filling with excavated soils including
laying jointing testing of pipe line but excluding cost of materials etc. complete

Trench size 0.9 x 1.2 0.9 x 1.3 1.0 x 1.4 1.1 x 1.6 1.2 x 1.7 1.3x1.8

Pipe dia in mm = 80 mm 100 mm 125 mm 150 mm 200 mm 250 mm 300 mm 350 mm 400 mm 450 mm 500 mm 600 mm 700 mm

1 Earth work 99.14 99.14 99.14 99.14 107.41 107.41 107.41 128.52 128.52 128.52 161.57 187.27 214.81

2 Extra allowance 30.47 30.47 30.47 30.47 33.01 33.01 33.01 39.49 39.49 39.49 49.65 57.55 66.01

3 Sand cushion cost 165.35 165.35 165.35 165.35 165.35 165.35 165.35 183.72 183.72 183.72 202.09 220.46 238.83

4 Refilling charges 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

sub-total 294.96 294.96 294.96 294.96 305.76 305.76 305.76 351.73 351.73 351.73 413.31 465.28 519.66
Lowering, Laying, jointing, testing HFT
pressure including cost of ruuber rings, cost
5 of transportation of water and emptying pipe
line after completion of field testing.

35.00 52.00 57.00 68.00 89.00 107.00 132.00 224.00 336.00 409.00 520.00 559.00 624.00
Add MA
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total
329.96 346.96 351.96 362.96 394.76 412.76 437.76 575.73 687.73 760.73 933.31 1024.28 1143.66

RCC pipes - Earth work


Earth work excavation in all soils upto SDR except hard rock requiring blasting for RCC pipes and filling with excavated soils including laying
jointing
Trench size testing of pipe line but excluding
0.9 xcost
1.2 of materials etc. complete
0.9 x 1.3 1.0 x 1.4 1.1 x 1.6 1.2 x 1.7
80 mm 100 mm 125 mm 150 mm 200 mm 250 mm 300 mm 350 mm 400 mm 450 mm 500 mm 600 mm 700
1 Earth work 99.14 99.14 99.14 99.14 107.41 107.41 128.52 128.52 128.52 128.52 161.57 187.27
2 Extra allowance 30.47 30.47 21.66 30.47 33.01 33.01 21.66 39.49 39.49 39.49 49.65 57.55
3 Sand cushion cost 165.35 165.35 165.35 165.35 165.35 165.35 49.76 183.72 183.72 183.72 202.09 220.46
4 Refilling charges 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5 Lowering, Laying, jointing, testing HFT 46.29 57.59 73.04 86.97 113.65 120.12 134.48 149.17 164.84 191.15 224.18 292
pressure
6 Add MA including cost of ruuber rings, 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
cost of transportation of water and
emptying pipe line after completion of
field testing.
Total 341.25 352.55 286.15 368.00 392.73 419.41 320.06 486.21 500.90 516.57 604.46 689.46

PCCP pipes - Earth work


4 Earth work excavation in all soils upto SDR except hard rock requiring blasting for BWSCP pipes and filling with excavated soils including laying jointing testing of pipe line but excluding cost of materials etc
Trench size 1.0m x 1.4m 1.0mx1.40m 1.1m x 1.6m 1.2m x 1.7m 1.3mx 1.8m 1.4m x 1.9m 1.5mx 2.0m 1.6mx 2.1m 1.7m x 2.3m 1.8m x 2.4m1.9x2.5

Pipe dia in mm = 300 350 400mm 450mm 500 mm 600mm 700mm 800mm 900mm 1000mm 1100mm 1200mm 1300mm

1 Earth work 128.52 128.52 128.52 128.52 161.568 187.272 214.812 244.188 275.4 293.76 343.332 396.576 436.05
2 Extra allowance 39.49 39.49 39.49 39.49 49.65 57.55 66.01 75.04 84.63 94.79 110.3 121.87 134
3 Refilling charges 0 0 0 0 0 0 0 0 0 0 0 0 0
Laying, jointing, testing HFT pressu 306 360 449 528 575 673 767 880 992 1087 1232 1344 1439
Add MA 0 0 0 0 0 0 0 0 0 0 0 0 0
Total 474.01 528.01 617.01 696.01 786.22 917.82 1047.82 1199.23 1352.03 1475.55 1685.63 1862.45 2009.05
Loamy clayey soils like BC and OG soils (9b) 84.1

126 35.2066188

210.1

146.8

356.9

313.0702
1.0mx1.3m
355mm 400mm

119.34 119.34

36.67 36.67

165.35 165.35

0.00 0.00

1.0m x 1.40m

355 mm 400 mm 450 mm

128.52 128.52 128.52

39.49 39.49 39.49

0.00 0.00 0.00

204 227 252

0.00 0.00 0.00

372.01 395.01 420.01


1.4x2.0 1.4x2.0 1.5x2.1 1.5x2.1 1.6x2.3

750 mm 800 mm 850 mm 900 mm 1000 mm

257.04 257.04 289.17 289.17 337.82

78.99 78.99 88.86 88.86 103.81

257.21 257.21 275.58 275.58 293.95

0.00 0.00 0.00 0.00 0.00

593.24 593.24 653.61 653.61 735.58

694.00 730.00 779.00 850.00 875.00

0.00 0.00 0.00 0.00 0.00

1287.24 1323.24 1432.61 1503.61 1610.58

800 900 1000

350 420 503


including laying jointing testing of pipe line but excluding cost of materials etc. complete
2.0x2.6 2.1x2.7 2.2x2.8 2.3x2.9 2.4x3.0 2.5x3.1 2.6x3.2

1400mm 1500mm 1600mm 1700mm 1800mm 1900mm 2000mm

477.36 520.506 565.488 612.306 660.96 711.45 763.776


1218.67 1218.67 1218.67 1218.67 1218.67 1218.67 1218.67
0 0 0 0 0 0 0
1584 1758 1903 2143 2272 2478 2638
0 0 0 0 0 0 0
3280.03 3497.18 3687.16 3973.98 4151.63 4408.12 4620.45
Data based on 2015-16 Common SSR

DI pipes - Earth work


7 Earth work excavation in all soils upto SDR except hard rock requiring blasting for DI (Ductile Iron) s/s pipes and filling with excavated soils
including laying jointing testing of pipe line but excluding cost of materials etc. complete

Trench size 0.90m x 1.20m 0.90m x 1.30m 1.0m x 1.4m 1.10x 1.60 1.20 x 1.70 1.30 x 1.80 1.4x1.9m 1.4x1.9m 1.5x2.0m

Pipe dia in mm = 80 mm 100 mm 125 mm 150 mm 200 mm 250 mm 300 mm 350 mm 400 mm 450 mm 500 mm 600 mm 700 mm 750 mm 800 mm 900 mm

1 Earth work 99.14 99.14 99.14 99.14 107.41 107.41 107.41 128.52 128.52 128.52 161.57 187.27 214.81 244.19 244.19 275.40

2 Extra allowance 30.47 30.47 30.47 30.47 33.01 33.01 33.01 39.49 39.49 39.49 49.65 57.55 66.01 75.04 75.04 84.63

3 Refilling charges 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

4 Lowering 18.30 23.25 30.24 37.88 55.07 74.40 96.23 120.70 147.30 178.19 207.72 277.34 357.81 401.11 447.83 544.42

5 Jointing and Hydraulic field 23.42 31.32 38.98 46.67 55.10 62.11 85.89 106.54 116.32 127.50 165.11 194.92 249.53 272.96 354.28 421.80
testing
6 Add MA 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total 171.34 184.18 198.83 214.16 250.59 276.92 322.53 395.25 431.63 473.70 584.05 717.08 888.16 993.30 1121.34 1326.25

8 MS pipes - Earth work

Earth work excavation in all soils upto SDR except hard rock requiring blasting for MS pipes and filling with excavated soils including laying jointing testing of pipe (without earthwork)
line but excluding cost of materials etc. complete

1.3mx
Trench size 0.9 x 1.2 0.9 x 1.3 1.0 x 1.4 1.1 x 1.6 1.2 x 1.7
1.8m 1.4x1.9m 1.4x1.9m 1.5x2.0m

Pipe dia in mm = 80 mm 100 mm 125 mm 150 mm 200 mm 250 mm 300 mm 350 mm 400 mm 450 mm 500 mm 600 mm 700 mm 750 mm 800 mm 900 mm

1 Earth work 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

2 Extra allowance 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

3 Refilling charges 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Add MA 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
CI pipes - Earth work
9 Earth work excavation in all soils upto SDR except hard rock requiring blasting for CI (Cast Iron) s/s pipes and filling with excavated soils including
laying jointing testing of pipe line but excluding cost of materials etc. complete

Trench size 0.90m x 1.20m 0.90m x 1.30m 1.0m x 1.4m 1.10x 1.60 1.20 x 1.70 1.30 x 1.80 1.4x1.9m 1.4x1.9m 1.5x2.0m

Pipe dia in mm = 80 mm 100 mm 125 mm 150 mm 200 mm 250 mm 300 mm 350 mm 400 mm 450 mm 500 mm 600 mm 700 mm 750 mm 800 mm 900 mm

1 Earth work 99.14 99.14 99.14 99.14 107.41 107.41 107.41 128.52 128.52 128.52 161.57 187.27 214.81 244.19 244.19 275.40

2 Extra allowance 30.47 30.47 30.47 30.47 33.01 33.01 33.01 39.49 39.49 39.49 49.65 57.55 66.01 75.04 75.04 84.63

3 Refilling charges 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

4 Lowering 18.30 23.25 30.24 37.88 55.07 74.40 96.23 120.70 147.30 178.19 207.72 277.34 357.81 401.11 447.83 544.42

5 Jointing and Hydraulic field 23.42 31.32 38.98 46.67 55.10 62.11 85.89 106.54 116.32 127.50 165.11 194.92 249.53 272.96 354.28 421.80
testing
6 Add MA 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total 171.34 184.18 198.83 214.16 250.59 276.92 322.53 395.25 431.63 473.70 584.05 717.08 888.16 993.30 1121.34 1326.25
1.6x2.1m

1000 mm

308.45

94.79

0.00

656.55

461.94

0.00

1521.73

1.6x2.1m

1000 mm
1.6x2.1m

1000 mm

308.45

94.79

0.00

656.55

461.94

0.00

1521.73
### Data based on 2015-16 Common SSR - for PVC pipes
PVC Resin rate: Rs.71,214/MT exclusive of CED Cost of specials : 1.20 % Month 25.07.2015 JUNE

1 PVC 4 kg/cm2
Trench size 0.70m x 1.00m 0.80m x 1.10m 0.90m x 1.20m
Pipe dia in mm = 63 mm 75 mm 90 mm 110 mm 125 mm 140 mm 160 mm 180 mm 200 mm 225 mm 250 mm 280 mm 315 mm
A) Materials component
1 Cost of pipe 53.00 78.00 106.00 154.00 201.00 251.00 331.00 422.00 513.00 682.00 793.00 1038.00 1314.00

2 Cost of specials (1.20%) 0.64 0.94 1.27 1.85 2.41 3.01 3.97 5.06 6.16 8.18 9.52 12.46 15.77

3 Earth work, L/J 218.78 219.96 221.43 223.39 224.86 226.33 268.25 270.21 272.17 317.01 319.46 322.40 325.83

Total 272.42 298.90 328.70 379.24 428.27 480.34 603.22 697.27 791.33 1007.19 1121.98 1372.86 1655.60

Add Contractors profit@1 37.09 40.69 44.75 51.63 58.31 65.40 82.13 94.93 107.74 137.13 152.76 186.91 225.41

Grand Total 309.50 339.60 373.50 430.90 486.60 545.70 685.40 792.20 899.10 1144.30 1274.70 1559.80 1881.00

2 PVC Class 6 kg/cm2


Trench size 0.70m x 1.00m 0.80m x 1.10m 0.90m x 1.20m
Pipe dia in mm = 63 mm 75 mm 90 mm 110 mm 125 mm 140 mm 160 mm 180 mm 200 mm 225 mm 250 mm 280 mm 315 mm
A) Materials component
1 Cost of pipe 77.00 105.00 152.00 220.00 281.00 362.00 469.00 604.00 735.00 985.00 1209.00 1527.00 1919.00

2 Cost of specials (1.20%) 0.92 1.26 1.82 2.64 3.37 4.34 5.63 7.25 8.82 11.82 14.51 18.32 23.03

3 Earth work, L/J 218.78 219.96 221.43 223.39 224.86 226.33 268.25 270.21 272.17 317.01 319.46 322.40 325.83

Total 296.70 326.22 375.25 446.03 509.23 592.67 742.88 881.46 1015.99 1313.83 1542.97 1867.72 2267.86

Add Contractors profit@1 40.40 44.41 51.09 60.73 69.33 80.69 101.14 120.01 138.33 178.88 210.08 254.29 308.77
Grand Total 337.10 370.60 426.30 506.80 578.60 673.40 844.00 1001.50 1154.30 1492.70 1753.00 2122.00 2576.60

3 PVC Class ###


Trench size 0.70m x 1.00m 0.80m x 1.10m 0.90m x 1.20m
Pipe dia in mm = 63 mm 75 mm 90 mm 110 mm 125 mm 140 mm 160 mm 180 mm 200 mm 225 mm 250 mm 280 mm 315 mm
A) Materials component
1 Cost of pipe 116.00 168.00 237.00 354.00 462.00 573.00 751.00 962.00 1171.00 1567.00 1907.00 2413.00 3046.00

2 Cost of specials (1.20%) 1.39 2.02 2.84 4.25 5.54 6.88 9.01 11.54 14.05 18.80 22.88 28.96 36.55

3 Earth work,L/J 218.78 219.96 221.43 223.39 224.86 226.33 268.25 270.21 272.17 317.01 319.46 322.40 325.83

Total: 336.17 389.98 461.27 581.64 692.40 806.21 1028.26 1243.75 1457.22 1902.81 2249.34 2764.36 3408.38

Add Contractors profit@1 45.77 53.10 62.80 79.19 94.27 109.76 140.00 169.34 198.40 259.07 306.25 376.37 464.05
Total 381.90 443.10 524.10 660.80 786.70 916.00 1168.30 1413.10 1655.60 2161.90 2555.60 3140.70 3872.40
`
Data based on 2015-16 Common SSR - for HDPE pipes
Month 25.07.2015 JUNE
HDPE PE80 Raw material : ### (excluding CED) Cost of specials : 0.50
HDPE PE100 Raw material :### (excluding CED)
Earth work excavation in all soils upto SDR except hard rock requiring blasting for HDPE 'filling with excavated soils including laying jointing testing of pipe line including cost of materials
etc. complete

HDPE PE 80 Class 4 kg/cm2

Trench size 0.70 x 1.00m 0.80 x1.10m 0.90 x 1.20m

Pipe dia in mm = 63 mm 75 mm 90 mm 110 mm 125 mm 140 mm 160 mm 180 mm 200 mm 225 mm 250 mm 280 mm 315 mm 355mm 400mm 450mm
A) Materials component
1 Cost of pipe 90.00 122.00 175.00 261.00 337.00 416.00 544.00 687.00 842.00 1093.00 1352.00 1685.00 2141.00 2610.00 3382.00 4467.00
2 Cost of specials (0.50%) 0.45 0.61 0.88 1.31 1.69 2.08 2.72 3.44 4.21 5.47 6.76 8.43 10.71 13.05 16.91 22.34
3 Earthwork,L/J 121.01 125.01 130.01 137.01 148.01 151.01 177.60 185.60 192.60 217.35 231.61 241.61 312.61 372.01 395.01 420.01
Cost f pipe 211.46 247.62 305.89 399.32 486.70 569.09 724.32 876.04 1038.81 1315.82 1590.37 1935.04 2464.32 2995.06 3793.92 4909.35
Add Contractors profit@13 28.79 33.71 41.65 54.37 66.26 77.48 98.62 119.27 141.43 179.15 216.53 263.46 335.52 407.78 516.54 668.41
Total 240.30 281.30 347.50 453.70 553.00 646.60 822.90 995.30 1180.20 1495.00 1806.90 2198.50 2799.80 3402.80 4310.50 5577.80

HDPE PE 100 Clas 6 kg/cm2

Trench size 0.70m x 1.00m 0.80mx1.10m 0.90m x 1.20m

Pipe dia in mm = 63 mm 75 mm 90 mm 110 mm 125 mm 140 mm 160 mm 180 mm 200 mm 225 mm 250 mm 280 mm 315 mm 355mm 400mm 450mm
A) Materials component
1 Cost of pipe 105.00 149.00 212.00 318.00 406.00 510.00 667.00 839.00 1037.00 1338.00 1646.00 2063.00 2615.00 3284.00 4319.00 5565.00
2 Cost of specials (0.50%) 0.53 0.75 1.06 1.59 2.03 2.55 3.34 4.20 5.19 6.69 8.23 10.32 13.08 16.42 21.60 27.83
3 Earthwork,L/J 121.01 125.01 130.01 137.01 148.01 151.01 177.60 185.60 192.60 217.35 231.61 241.61 312.61 372.01 395.01 420.01
Cost of pipe 226.54 274.76 343.07 456.60 556.04 663.56 847.94 1028.80 1234.79 1562.04 1885.84 2314.93 2940.69 3672.43 4735.61 6012.84
Add Contractors profit@13 30.84 37.41 46.71 62.17 75.70 90.34 115.45 140.07 168.12 212.67 256.76 315.18 400.37 500.00 644.75 818.65
Total 257.38 312.16 389.78 518.77 631.74 753.90 963.38 1168.87 1402.90 1774.71 2142.60 2630.10 3341.06 4172.43 5380.36 6831.48
`
HDPE PE 100 Clas 8 kg/cm2

Trench size 0.70m x 1.00m 0.80mx1.10m 0.90m x 1.20m

Pipe dia in mm = 63 mm 75 mm 90 mm 110 mm 125 mm 140 mm 160 mm 180 mm 200 mm 225 mm 250 mm 280 mm 315 mm 355mm 400mm 450mm
A) Materials component
1 Cost of pipe 134.00 190.00 271.00 404.00 521.00 652.00 849.00 1074.00 1327.00 1711.00 2114.00 2646.00 3351.00 4201.00 5520.00 7144.00
2 Cost of specials (0.50%) 0.67 0.95 1.36 2.02 2.61 3.26 4.25 5.37 6.64 8.56 10.57 13.23 16.76 21.01 27.60 35.72
3 Earthwork,L/J 121.01 125.01 130.01 137.01 148.01 151.01 177.60 185.60 192.60 217.35 231.61 241.61 312.61 372.01 395.01 420.01
Cost of Pipe 255.68 315.96 402.37 543.03 671.62 806.27 1030.85 1264.97 1526.24 1936.91 2356.18 2900.84 3680.37 4594.02 5942.61 7599.73
Add Contractors profit@13 34.81 43.02 54.78 73.93 91.44 109.77 140.35 172.23 207.80 263.71 320.79 394.95 501.08 625.48 809.09 1034.70
Total 290.49 358.98 457.15 616.96 763.06 916.04 1171.19 1437.20 1734.03 2200.61 2676.97 3295.79 4181.45 5219.49 6751.70 8634.43

HDPE PE 100 Clas 10 kg/cm2

Trench size 0.70m x 1.00m 0.80m x 1.10m 0.90m x 1.20m

Pipe dia in mm = 63 mm 75 mm 90 mm 110 mm 125 mm 140 mm 160 mm 180 mm 200 mm 225 mm 250 mm 280 mm 315 mm 355mm 400mm 450mm
A) Materials component
1 Cost of pipe 162.00 229.00 325.00 482.00 626.00 784.00 1021.00 1293.00 1594.00 2059.00 2542.00 3178.00 4029.00 5059.00 6632.00 8597.00

2 Cost of specials (0.50%) 0.81 1.15 1.63 2.41 3.13 3.92 5.11 6.47 7.97 10.30 12.71 15.89 20.15 25.30 33.16 42.99

3 Earthwork,L/J 121.01 125.01 130.01 137.01 148.01 151.01 177.60 185.60 192.60 217.35 231.61 241.61 312.61 372.01 395.01 420.01
Cost of Pipe 283.82 355.16 456.64 621.42 777.14 938.93 1203.71 1485.07 1794.57 2286.65 2786.32 3435.50 4361.76 5456.31 7060.17 9060.00
Add Contractors profit@13 38.64 48.35 62.17 84.61 105.81 127.84 163.88 202.19 244.33 311.33 379.36 467.74 593.85 742.88 961.24 1233.52
Total 322.46 403.51 518.81 706.03 882.95 1066.77 1367.59 1687.26 2038.90 2597.97 3165.68 3903.24 4955.61 6199.18 8021.41 ###

HDPE PE 100 Clas 12.50 kg/cm2

Trench size 0.70m x 1.00m 0.80m x 1.10m 0.90m x 1.20m

Pipe dia in mm = 63 mm 75 mm 90 mm 110 mm 125 mm 140 mm 160 mm 180 mm 200 mm 225 mm 250 mm 280 mm 315 mm 355mm 400mm 450mm
A) Materials component
Cost of pipe 212.00 302.00 429.00 645.00 827.00 1041.00 1356.00 1712.00 2120.00 2675.00 3302.00 4149.00 5232.00 6655.00 8617.00 ###
Cost of specials (0.50%) 1.06 1.51 2.15 3.23 4.14 5.21 6.78 8.56 10.60 13.38 16.51 20.75 26.16 33.28 43.09 54.47
Earthwork,L/J 121.01 125.01 130.01 137.01 148.01 151.01 177.60 185.60 192.60 217.35 231.61 241.61 312.61 372.01 395.01 420.01
Cost of Pipe 334.07 428.52 561.16 785.24 979.15 1197.22 1540.38 1906.16 2323.20 2905.73 3550.12 4411.36 5570.77 7060.29 9055.10 ###
Add Contractors profit@13 45.48 58.34 76.40 106.91 133.31 163.00 209.72 259.52 316.30 395.61 483.35 600.61 758.46 961.26 1232.85 1547.82
Total 379.55 486.86 637.56 892.14 1112.46 1360.22 1750.10 2165.68 2639.50 3301.34 4033.47 5011.96 6329.23 8021.54 ### ###

HDPE PE 100 Clas 16.00 kg/cm2

Trench size 0.70m x 1.00m 0.80m x 1.10m 0.90m x 1.20m

Pipe dia in mm = 63 mm 75 mm 90 mm 110 mm 125 mm 140 mm 160 mm 180 mm 200 mm 225 mm 250 mm 280 mm 315 mm 355mm 400mm 450mm
A) Materials component
Cost of pipe 273.00 389.00 566.00 813.00 1043.00 1321.00 1709.00 2152.00 2664.00 3357.00 4152.00 5219.00 6604.00 8417.00 10844.00 13617.00
Cost of specials (0.50%) 1765.22 2515.27 3659.76 5256.86 6744.04 8541.59 11050.39 13914.83 17225.42 21706.36 26846.83 33746.05 42701.46 ### ### ###
Earthwork,L/J 121.01 428.52 561.16 785.24 979.15 1197.22 1540.38 1906.16 2323.20 2905.73 3550.12 4411.36 5570.77 7060.29 9055.10 ###
Cost of Pipe 2159.23 3332.79 4786.91 6855.09 8766.18 11059.80 14299.77 17972.99 22212.62 27969.09 34548.95 43376.41 54876.23 ### ### ###
Add Contractors profit@13 293.98 453.76 651.74 933.32 1193.52 1505.79 1946.91 2447.02 3024.25 3807.99 4703.84 5905.70 7471.40 9517.10 ### ###
Total 2453.20 3786.60 5438.60 7788.40 9959.70 12565.60 16246.70 20420.00 25236.90 31777.10 39252.80 49282.10 62347.60 ### ### ###
0.00 0.00 0.00 0.00 0.00 0.00 0.00

500mm

###
67.27
0.00
###
1840.92
###

500mm

16108.00
###
###
###
###
###
Data based on 2015-16 Common SSR - for AC pipes
Cement rate @ Rs 6300 /-& Fiber rate @ Rs 75500/- Month 25.07.2015JUNE
1 Earth work excavation in all soils except hard rock requiring blasting for AC pipes and filling with excavated soils including laying jointing testing of pipe
line including cost of materials etc. complete

AC CL-15 Kg/cm2
Pipe cost 100 mm 125 mm 150 mm 200 mm 250 mm 300 mm 350 mm 400 mm 450 mm 500 mm 600 mm 700mm
A) Materials component
1 Basic cost 261.00 340.00 478.00 791.00 1002.00 1402.00 1708.00 2219.00 2641.00 3255.00 4631.00 5729

2 Cost of specials (1.50%) 3.92 5.10 7.17 11.87 15.03 21.03 25.62 33.29 39.62 48.83 69.47 85.94

3 Transportation @10% 26.10 34.00 47.80 79.10 100.20 140.20 170.80 221.90 264.10 325.50 463.10 572.90

Pipe cost 291.02 379.10 532.97 881.97 1117.23 1563.23 1904.42 2474.19 2944.72 3629.33 5163.57 6387.84

AC couplings (100%)

5 Basic cost - each 119.00 149.00 175.00 321.00 376.00 490.00 635.00 978.00 1171.00 1396.00 1725.00 2164

6 Cost per Rmt 29.75 37.25 43.75 80.25 94.00 122.50 158.75 244.50 292.75 349.00 431.25 541.00

Rubber rings (100%)

7 Basic cost - each 83.00 108.00 136.00 142.00 164.00 164.00 186.00 228.00 267.00 309.00 350.00 727

8 Cost per Rmt 20.75 27.00 34.00 35.50 41.00 41.00 46.50 57.00 66.75 77.25 87.50 181.75

Part A Total -----------> 341.52 443.35 610.72 997.72 1252.23 1726.73 2109.67 2775.69 3304.22 4055.58 5682.32 7110.59

B) Labour component
9 Earth work excavation 346.96 351.96 362.96 394.76 412.76 437.76 575.73 687.73 760.73 933.31 1024.28 1143.66
346.96 351.96 362.96 394.76 412.76 437.76 575.73 687.73 760.73 933.31 1024.28 1143.66
Cost of Pipe 688.48 795.31 973.68 1392.48 1664.99 2164.49 2685.40 3463.41 4064.94 4988.88 6706.60 8254.24
Add contractors profit @13.61 93.74 108.28 132.57 189.59 226.69 294.70 365.62 471.54 553.44 679.24 913.10 1123.81
Total cost of pipe 782.20 903.60 1106.30 1582.10 1891.70 2459.20 3051.00 3935.00 4618.40 5668.10 7619.70 9378.10
2 AC CL-20 Kg/cm2
Pipe cost 100 mm 125 mm 150 mm 200 mm 250 mm 300 mm 350 mm 400 mm 450 mm 500 mm 600 mm 700mm
A) Materials component
1 Basic cost 332.00 424.00 596.00 1015.00 1303.00 1830.00 2221.00 2906.00 3508.00 4287.00 6052.00 7770

2 Cost of specials (1.50%) 4.98 6.36 8.94 15.23 19.55 27.45 33.32 43.59 52.62 64.31 90.78 116.55

3 Transportation @10% 33.20 42.40 59.60 101.50 130.30 183.00 222.10 290.60 350.80 428.70 605.20 777.00

4 Pipe cost 370.18 472.76 664.54 1131.73 1452.85 2040.45 2476.42 3240.19 3911.42 4780.01 6747.98 8663.55

AC couplings (100%)

5 Basic cost - each 129.00 165.00 219.00 354.00 475.00 637.00 820.00 1277.00 1544.00 1866.00 2170.00 2913

6 Cost per Rmt 32.25 41.25 54.75 88.50 118.75 159.25 205.00 319.25 386.00 466.50 542.50 728.25

Rubber rings (100%)

7 Basic cost 83.00 108.00 136.00 142.00 164.00 164.00 186.00 228.00 267.00 309.00 350.00 727

8 Cost per Rmt 20.75 27.00 34.00 35.50 41.00 41.00 46.50 57.00 66.75 77.25 87.50 181.75

Part A Total -----------> 423.18 541.01 753.29 1255.73 1612.60 2240.70 2727.92 3616.44 4364.17 5323.76 7377.98 9573.55

B) Labour component
9 Earth work excavation 346.96 351.96 362.96 394.76 412.76 437.76 575.73 687.73 760.73 933.31 1024.28 1143.66
346.96 351.96 362.96 394.76 412.76 437.76 575.73 687.73 760.73 933.31 1024.28 1143.66
Cost of Pipe 770.14 892.97 1116.25 1650.49 2025.36 2678.46 3303.64 4304.17 5124.90 6257.06 8402.26 10717.21
Add contractors profit @13.61 104.85 121.58 151.98 224.71 275.75 364.67 449.79 586.01 697.75 851.90 1143.97 1459.15
Total cost of pipe 875.00 1014.60 1268.20 1875.20 2301.10 3043.10 3753.40 4890.20 5822.60 7109.00 9546.20 12176.40
3 AC CL-25 Kg/cm2
Pipe cost 100 mm 125 mm 150 mm 200 mm 250 mm 300 mm 350 mm 400 mm 450 mm 500 mm 600 mm 700mm
A) Materials component
1 Basic cost 408.00 532.00 749.00 1287.00 1631.00 2339.00 2803.00 3607.00 4391.00 5382.00 7711.00 10047

2 Cost of specials (1.50%) 6.12 7.98 11.24 19.31 24.47 35.09 42.05 54.11 65.87 80.73 115.67 150.71

3 Transportation @10% 40.80 53.20 74.90 128.70 163.10 233.90 280.30 360.70 439.10 538.20 771.10 1004.70

4 Pipe cost 454.92 593.18 835.14 1435.01 1818.57 2607.99 3125.35 4021.81 4895.97 6000.93 8597.77 11202.41

AC couplings (100%)

5 Basic cost - each 155.00 199.00 270.00 450.00 604.00 819.00 1046.00 1632.00 1979.00 2381.00 2776.00 3788

6 Cost per Rmt 38.75 49.75 67.50 112.50 151.00 204.75 261.50 408.00 494.75 595.25 694.00 947.00

Rubber rings (100%)

7 Basic cost 83.00 108.00 136.00 142.00 164.00 164.00 186.00 228.00 267.00 309.00 350.00 727

8 Cost per Rmt 20.75 27.00 34.00 35.50 41.00 41.00 46.50 57.00 66.75 77.25 87.50 181.75

Part A Total -----------> 514.42 669.93 936.64 1583.01 2010.57 2853.74 3433.35 4486.81 5457.47 6673.43 9379.27 12331.16

B) Labour component
9 Earth work excavation 346.96 351.96 362.96 394.76 412.76 437.76 575.73 687.73 760.73 933.31 1024.28 1143.66
346.96 351.96 362.96 394.76 412.76 437.76 575.73 687.73 760.73 933.31 1024.28 1143.66
Cost of Pipe 861.38 1021.89 1299.60 1977.77 2423.33 3291.50 4009.07 5174.53 6218.19 7606.74 10403.55 13474.81
Add contractors profit @13.61 117.28 139.13 176.94 269.27 329.94 448.14 545.84 704.51 846.61 1035.66 1416.44 1834.60
Total cost of pipe 978.70 1161.00 1476.50 2247.00 2753.30 3739.60 4554.90 5879.00 7064.80 8642.40 11820.00 15309.40

RCC pipes
Earth work excavation in all soils except hard rock requiring blasting for RCC pipes and filling with excavated soils including laying jointing testing of pipe
NP2 60KMs 5km+55km
Trench size 0.9x1.3 1.0x1.4 1.2x1.7
Pipe dia in mm 300 mm 400mm 450 mm 600 mm
Cost of pipes 418.00 593.00 738.00 1197
Rubber Rings 36.80 46.80 53.20 91.20
Transportation 76.50 97.65 111.70 196.30
Cost of specials (1%) 4.18 5.93 7.38 11.97
Earthwork L/J 320.06 500.90 516.57 689.46
Add contractors profit @14% 116.48 169.41 194.27 297.61
Total 972.02 1413.69 1621.12 2483.54

2.5mts
750mm 800mm 850mm 900mm 1000mm

6528 7469 8378 9340 11530

97.92 112.04 125.67 140.10 172.95

652.80 746.90 837.80 934.00 1153.00

7278.72 8327.94 9341.47 10414.10 12855.95

2441 2769 3085 3414 4166

610.25 692.25 771.25 853.50 1041.50

755 811 904 950 1053

188.75 202.75 226.00 237.50 263.25

8077.72 9222.94 10338.72 11505.10 14160.70

1287.24 1323.24 1432.61 1503.61 1610.58


1287.24 1323.24 1432.61 1503.61 1610.58
9364.96 10546.17 11771.33 13008.71 15771.28
1275.04 1435.86 1602.67 1771.14 2147.26
10640.00 11982.00 13374.00 14779.80 17918.50
750mm 800mm 850mm 900mm 1000mm

8969 10162 11432 12772 15680

134.54 152.43 171.48 191.58 235.20

896.90 1016.20 1143.20 1277.20 1568.00

10000.44 11330.63 12746.68 14240.78 17483.20

3337 3755 4200 4669 5677

834.25 938.75 1050.00 1167.25 1419.25

755 811 904 950 1053

188.75 202.75 226.00 237.50 263.25

11023.44 12472.13 14022.68 15645.53 19165.70

1287.24 1323.24 1432.61 1503.61 1610.58


1287.24 1323.24 1432.61 1503.61 1610.58
12310.67 13795.37 15455.29 17149.14 20776.28
1676.10 1878.24 2104.24 2334.86 2828.69
13986.80 15673.60 17559.50 19484.00 23605.00
750mm 800mm 850mm 900mm 1000mm

11496 13042 14686 16427 20201

172.44 195.63 220.29 246.41 303.02

1149.60 1304.20 1468.60 1642.70 2020.10

12818.04 14541.83 16374.89 18316.11 22524.12

4307 4859 5446 6062 7399

1076.75 1214.75 1361.50 1515.50 1849.75

755 811 904 950 1053

188.75 202.75 226.00 237.50 263.25

14083.54 15959.33 17962.39 20069.11 24637.12

1287.24 1323.24 1432.61 1503.61 1610.58


1287.24 1323.24 1432.61 1503.61 1610.58
15370.78 17282.57 19395.00 21572.71 26247.70
2092.73 2353.02 2640.63 2937.12 3573.62
17463.50 19635.60 22035.60 24509.80 29821.30
Data based on 2015-16 Common SSR - for DI PIPES- 5m length/each
Pig Iron @ Rs.26000 Month 25.07.2015 JUNE 0 0
Rubber rings: 1 Transportation-Lead 600 Kms Cost of specials : 1.50 %
2015-16 #N/A Length of each pipe 5 m
Earth work excavation in all soils upto SDR except hard rock requiring blasting for 'DI s/s 'pipes and filling with excavated soils including laying jointing testing of pipe
line including cost of materials etc. complete
1 Class DI K9
Trench size 0.9m x 1.2m 0.9m x 1.3m 1.0 x 1.4m 1.1 x 1.6m 1.2 x 1.7m 1.3x1.8m 1.4x1.9m 1.4x1.9m 1.5x2.0m 1.6x2.1m

Pipe dia in mm = 100 mm 150 mm 200 mm 250 mm 300 mm 350 mm 400 mm 450 mm 500 mm 600 mm 700 mm 750 mm 800 mm 900 mm 1000 mm
1 Cost of pipe ### ### ### ### ### ### ### ### ### ### ### ### ### ### 22235.00
2 Transportation charges and
132.00 198.00 198.00 330.00 396.00 528.00 594.00 726.00 858.00 1122.00 1650.00 1980.00 3366.00 3366.00 3366.00
Loading, unloading and stacking
3 Cost of specials (1.5%) 15.93 23.54 31.43 41.24 52.23 65.10 78.50 93.92 109.26 144.11 186.30 209.07 230.70 281.37 333.53
4 Earthwork, L/J 184.18 214.16 250.59 276.92 322.53 395.25 431.63 473.70 584.05 717.08 888.16 993.30 ### ### 1521.73
Cost of pipe ### ### ### ### ### ### ### ### ### ### ### ### ### ### 27456.26
Add Contractors
5 189.81 272.94 350.59 462.52 579.01 725.45 862.80 1028.56 1202.93 1578.00 2061.92 2330.94 2736.35 3231.06 3738.17
profit@13.615%
Total ### ### ### ### ### ### ### ### ### ### ### ### ### ### 31194.42
110.17 136.51 182.12 227.24 263.62 305.69 372.83 472.26 607.34 674.07 802.11 966.22 1118.49

1 Class DI K7
Trench size 0.9m x 1.2m 0.9m x 1.3m 1.0m x 1.4m 1.1 x 1.61.2 x 1.7 1.3x1.8m 1.4x1.9m 1.4x1.9m 1.5x2.0m 1.6x2.1m

Pipe dia in mm = 100 mm 150 mm 200 mm 250 mm 300 mm 350 mm 400 mm 450 mm 500 mm 600 mm 700 mm 750mm 800 mm 900 mm 1000 mm
1 Cost of pipe 892.00 ### ### ### ### ### ### ### ### ### ### ### ### ### 20036.00
2 Transportation charges and
132.00 198.00 198.00 264.00 396.00 462.00 528.00 660.00 792.00 1122.00 1650.00 1980.00 3366.00 3366.00 3366.00
Loading, unloading and stacking
3 Cost of specials (1.50%) 13.38 18.53 25.83 34.65 44.51 56.01 67.98 81.78 97.47 129.71 167.84 188.06 207.83 253.56 300.54
4 Earthwork, L/J 184.18 214.16 250.59 276.92 322.53 395.25 431.63 473.70 584.05 717.08 888.16 993.30 ### ### 1521.73
Cost of pipe ### ### ### ### ### ### ### ### ### ### ### ### ### ### 25224.27
Add Contractors
166.32 226.78 299.04 392.87 507.84 632.72 756.94 907.78 1085.32 1445.34 1891.80 2137.33 2525.60 2974.85 3434.28
5 profit@13.615%
Total ### ### ### ### ### ### ### ### ### ### ### ### ### ### 28658.55

0
Data based on 2015-16 Common SSR - for CI PIPES
Rubber rings: 0 % Transportation 0.00% Cost of specials : 1.50 % Month 25.07.2015 JUNE
Pig Iron @ Rs. 26000 Lead 100 kms
Earth work excavation in all soils upto SDR except hard rock requiring blasting for 'CI s/s 'pipes and filling with excavated soils including laying jointing testing of pipe line including
cost of materials etc. complete
1 Class CI LA
Trench size 0.9m x 1.2m 0.9m x 1.3m 1.0 x 1.4m 1.1 x 1.6m 1.2 x 1.7m 1.3x1.8m 1.4x1.9m 1.5x2.0m

Pipe dia in mm = 80 mm 100 mm 125 mm 150 mm 200 mm 250 mm 300 mm 350 mm 400 mm 450 mm 500 mm 600 mm 700 mm 750mm 800 mm 900 mm

PART A - Materials
1 Cost of pipe 834.00 1015.00 1279.00 1549.00 2261.00 3047.00 3929.00 5026.00 6120.00 7405.00 8758.00 ### ### ### ### 23293.00
2 Transportation charges, loading,
25.00 25.00 38.00 38.00 64.00 77.00 102.00 140.00 165.00 191.00 229.00 229.00 229.00 381.00 648.00 648.00
unloading and stacking
3 Cost of specials (1.5%) 12.51 15.23 19.19 23.24 33.92 45.71 58.94 75.39 91.80 111.08 131.37 173.72 228.69 256.14 286.71 349.40

Part A Total -----------> 871.51 ### ### ### ### ### ### ### ### ### ### ### ### ### ### 24290.40

PART B - Labour component


4 Earthwork, L/J 171.34 184.18 198.83 214.16 250.59 276.92 322.53 395.25 431.63 473.70 584.05 717.08 888.16 993.30 1121.34 1326.25
Cost of pipe ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### 25616.65
Add contractors profit @ 13.6 141.98 168.74 208.99 248.39 355.28 469.26 600.76 767.43 926.97 1113.81 1320.98 1729.21 2258.98 2546.88 2882.30 3487.71
Total ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### 29104.40

2 Class CI A
Trench size 0.9m x 1.2m 0.9m x 1.3m 1.0 x 1.4m 1.1 x 1.6m 1.2 x 1.7m 1.3x1.8m 1.4x1.9m 1.5x2.0m

Pipe dia in mm = 80 mm 100 mm 125 mm 150 mm 200 mm 250 mm 300 mm 350 mm 400 mm 450 mm 500 mm 600 mm 700 mm 750mm 800 mm 900 mm

PART A - Materials
1 Cost of pipe 904.00 1115.00 1396.00 1697.00 2454.00 3318.00 4298.00 5453.00 6687.00 8136.00 9541.00 ### ### ### ### 29103.00
2 Transportation charges, loading,
25.00 25.00 38.00 38.00 64.00 77.00 114.00 140.00 165.00 204.00 242.00 242.00 242.00 406.00 648.00 648.00
unloading and stacking
3 Cost of specials (1.5%) 13.56 16.73 20.94 25.46 36.81 49.77 64.47 81.80 100.31 122.04 143.12 189.65 249.86 280.05 312.41 436.55
Part A Total -----------> 942.56 ### ### ### ### ### ### ### ### ### ### ### ### ### ### 30187.55

PART B - Labour component


4 Earthwork, L/J 171.34 184.18 198.83 214.16 250.59 276.92 322.53 395.25 431.63 473.70 584.05 717.08 888.16 993.30 1121.34 1326.25
Cost of pipe ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### 31513.80
Add contractors profit @ 13.6 151.66 182.56 225.16 268.84 381.96 506.71 653.38 826.44 1005.32 1216.60 1430.96 1877.74 2455.74 2770.56 3119.03 4290.60
Total ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### 35804.40

3 Class CI B
Trench size 0.9m x 1.2m 0.9m x 1.3m 1.0 x 1.4m 1.1 x 1.6m 1.2 x 1.7m 1.3x1.8m 1.4x1.9m 1.5x2.0m

Pipe dia in mm = 80 mm 100 mm 125 mm 150 mm 200 mm 250 mm 300 mm 350 mm 400 mm 450 mm 500 mm 600 mm 700 mm 750mm 800 mm 900 mm

PART A - Materials
1 Cost of pipe 972.00 1191.00 1504.00 1829.00 2656.00 3590.00 4655.00 6915.00 7217.00 8775.00 ### ### ### ### ### 27538.00
2 Transportation charges, loading,
25.00 25.00 38.00 38.00 64.00 77.00 114.00 152.00 177.00 216.00 254.00 254.00 254.00 432.00 648.00 648.00
unloading and stacking
3 Cost of specials (1.5%) 14.58 17.87 22.56 27.44 39.84 53.85 69.83 103.73 108.26 131.63 154.83 205.40 269.94 303.81 337.95 413.07
Part A Total -----------> ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### 28599.07

PART B - Labour component


4 Earthwork, L/J 171.34 184.18 198.83 214.16 250.59 276.92 322.53 395.25 431.63 473.70 584.05 717.08 888.16 993.30 1121.34 1326.25
Cost of pipe 1182.92 1418.05 1763.39 2108.60 3010.43 3997.77 5161.36 7565.98 7933.89 9596.33 ### ### ### ### ### 29925.32
Add contractors profit @ 13.6 161.05 193.07 240.09 287.09 409.87 544.30 702.72 1030.11 1080.20 1306.54 1540.52 2024.48 2642.41 2993.00 3354.37 4074.33
Total ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### 33999.65

`
1.6x2.1m

1000 mm

27985.00 ph ssr 61

648.00

419.78

29052.78

1521.73
30574.51
4162.72
34737.20

1.6x2.1m

1000 mm

30568.00

648.00

458.52
31674.52

1521.73
33196.25
4519.67
37715.92

1.6x2.1m

1000 mm

33040.00

648.00

495.60
34183.60

1521.73
35705.33
4861.28
40566.61
Data based on 2015-16 Common SSR - for GRP pipes
Hoop Glass 82 Choop Glass 78 Resin 110 SSR Rates
1 Earth work excavation in all soils upto SDR except hard rock requiring blasting for GRP with 300 mm thick sand encasing
filling with excavated soils including laying jointing testing of pipe line including cost of materials etc. complete

The rate of GRP pipes conforming to IS 12709-1994 is including transportation, cost of Jointing materials, Specials etc., complete

GRP pipes PN : 3 bar


Trench size 0.95 x 1.55m 1.00 x 1.60m 1.05 x 1.65m 1.10 x 1.70m 1.20 x 1.80m 1.30 x 1.90m 1.40 x 2.00m 1.50 x 2.10m 1.60 x 2.20m

Pipe dia in mm = GRP 350 mm 400 mm 450 mm 500 mm 600 mm 700 mm 800 mm 900 mm 1000 mm
A) Materials component
1 Cost of pipes 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

B) Labour component
2 Earth work, Laying, jointing, testing to HFT 1324.25 1502.90 1656.45 1838.92 2075.61 2346.96 2652.97 2939.62 3274.94
pressure including cost of transportation of water
and emptying pipe line after completion of field
testing.

Add contractors profit @ 14% 185.39 210.41 231.90 257.45 290.59 328.57 371.42 411.55 458.49
Total 1509.64 1713.31 1888.35 2096.37 2366.20 2675.53 3024.39 3351.17 3733.43

2 GRP pipes PN : 6 bar


Trench size 0.95 x 1.55m 1.0 x 1.6m 1.05 x 1.65m 1.1 x 1.7m 1.2 x 1.8m 1.3 x 1.9m 1.4 x 2.0m 1.5 x 2.1m 1.6 x 2.2m

Pipe dia in mm = GRP 350 mm 400 mm 450 mm 500 mm 600 mm 700 mm 800 mm 900 mm 1000 mm
A) Materials component
1 Cost of pipes 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

B) Labour component
2 Earth work, Laying, jointing, testing to HFT 1324.25 1502.90 1656.45 1838.92 2075.61 2346.96 2652.97 2939.62 3274.94
pressure including cost of transportation of water
and emptying pipe line after completion of field
testing.

Add contractors profit @ 14% 185.39 210.41 231.90 257.45 290.59 328.57 371.42 411.55 458.49
Total 1509.64 1713.31 1888.35 2096.37 2366.20 2675.53 3024.39 3351.17 3733.43
3 GRP pipes PN : 9 bar
Trench size 0.95 x 1.55m 1.0 x 1.6m 1.05 x 1.65m 1.1 x 1.7m 1.2 x 1.8m 1.3 x 1.9m 1.4 x 2.0m 1.5 x 2.1m 1.6 x 2.2m

Pipe dia in mm = GRP 350 mm 400 mm 450 mm 500 mm 600 mm 700 mm 800 mm 900 mm 1000 mm
A) Materials component
1 Cost of pipes 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

B) Labour component
2 Earth work, Laying, jointing, testing to HFT 1324.25 1502.90 1656.45 1838.92 2075.61 2346.96 2652.97 2939.62 3274.94
pressure including cost of transportation of water
and emptying pipe line after completion of field
testing.

Add contractors profit @ 14% 185.39 210.41 231.90 257.45 290.59 328.57 371.42 411.55 458.49
Total 1509.64 1713.31 1888.35 2096.37 2366.20 2675.53 3024.39 3351.17 3733.43

4 GRP pipes PN : 12 bar


Trench size 0.95 x 1.55m 1.0 x 1.6m 1.05 x 1.65m 1.1 x 1.7m 1.2 x 1.8m 1.3 x 1.9m 1.4 x 2.0m 1.5 x 2.1m 1.6 x 2.2m

Pipe dia in mm = GRP 350 mm 400 mm 450 mm 500 mm 600 mm 700 mm 800 mm 900 mm 1000 mm
A) Materials component
1 Cost of pipes 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

B) Labour component
2 Earth work, Laying, jointing, testing to HFT 1324.25 1502.90 1656.45 1838.92 2075.61 2346.96 2652.97 2939.62 3274.94
pressure including cost of transportation of water
and emptying pipe line after completion of field
testing.

Add contractors profit @ 14% 185.39 210.41 231.90 257.45 290.59 328.57 371.42 411.55 458.49
Total 1509.64 1713.31 1888.35 2096.37 2366.20 2675.53 3024.39 3351.17 3733.43

5 GRP pipes PN : 15 bar


Trench size 0.95 x 1.55m 1.0 x 1.6m 1.05 x 1.65m 1.1 x 1.7m 1.2 x 1.8m 1.3 x 1.9m 1.4 x 2.0m 1.5 x 2.1m 1.6 x 2.2m

Pipe dia in mm = GRP 350 mm 400 mm 450 mm 500 mm 600 mm 700 mm 800 mm 900 mm 1000 mm
A) Materials component
1 Cost of pipes 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
B) Labour component
2 Earth work, Laying, jointing, testing to HFT 1324.25 1502.90 1656.45 1838.92 2075.61 2346.96 2652.97 2939.62 3274.94
pressure including cost of transportation of water
and emptying pipe line after completion of field
testing.
Add contractors profit @ 14% 185.39 210.41 231.90 257.45 290.59 328.57 371.42 411.55 458.49
Total 1509.64 1713.31 1888.35 2096.37 2366.20 2675.53 3024.39 3351.17 3733.43
Data based on 2015-16 Common SSR - for BWSC pipes
H2=HR Plates (1.6&2mm -Avg) 44500 W2=Wire Rods (5.5/6mm
42500 ) C2=Cement 6300 Month 25.07.201 JUNE
Conveyance 100 Km from Patancheru, Hyd.
Cost of specials 0.50
1 Earth work excavation in all soils except hard rock requiring blasting for BWSC pipes and filling with excavated soils including laying jointing testing of pipe line
including cost of materials etc. complete

BWSC Class 12 Kg/cm2


1.0m x 1.40m 1.1m x 1.60m 1.2m x 1.7m 1.3m x 1.8m 1.4m x 1.9m 1.5m x 2m 1.6m x 2.1m1.7m x 2.3m
1.8m x 2.4m
Trench size
Pipe dia in mm BWSC 300 mm 350 mm 400 mm 450 mm 500 mm 600 mm 700 mm 800 mm 900 mm 1000 mm 1100mm 1200mm
A) material component
1 Cost of pipes 3272.00 3964.00 4350.00 4804.00 5370.00 7077.00 8534.00 9700.00 11990.00 13540.00 19402.00 21457.00
2 Transportation charges, including loading at factory, un- As per SSR 63.00 84.00 105.00 137.00 168.00 179.00 200.00 263.00 284.00 326.00 728.00 1016.00
Page 330
loading at site and stacking.

3 Cost of specials (0.50%) 0.00 16.36 19.82 21.75 24.02 26.85 35.39 42.67 48.50 59.95 67.70 97.01 107.29
Part A Total ---------- 3351.36 4067.82 4476.75 4965.02 5564.85 7291.39 8776.67 10011.50 12333.95 13933.70 20227.01 22580.29
B) Labour component
4 Earthwork excavation & Refilling 528.01 594.01 644.01 644.01 807.22 977.82 1134.82 1290.23 1502.03 1665.24 1931.84 2173.37

PartB Total ----------- 528.01 594.01 644.01 644.01 807.22 977.82 1134.82 1290.23 1502.03 1665.24 1931.84 2173.37

Cost of pipe 3879.37 4661.83 5120.76 5609.03 6372.07 8269.21 9911.49 11301.73 13835.98 15598.94 22158.85 24753.66
6 Add contractors profit @ 13.615% 528.18 634.71 697.19 763.67 867.56 1125.85 1349.45 1538.73 1883.77 2123.80 3016.93 3370.21

Grand Total 4407.55 5296.54 5817.95 6372.70 7239.63 9395.06 ### 12840.46 15719.75 17722.74 25175.78 28123.87

2 BWSC Class 14 Kg/cm2


1.0m x 1.40m 1.1m x 1.60m 1.2m x 1.7m 1.3m x 1.8m 1.4m x 1.9m 1.5m x 2m 1.6m x 2.1m1.7m x 2.2m
1.8m x 2.3m
Trench size
Pipe dia in mm BWSC 300 mm 350 mm 400 mm 450 mm 500 mm 600 mm 700 mm 800 mm 900 mm 1000 mm 1100mm 1200mm
A) material component
1 Cost of pipes 3272.00 3964.00 4350.00 4820.00 5435.00 7178.00 8745.00 10462.00 12481.00 14809.00 19754.00 22098.00
2 Transportation charges, including loading at factory, un- As per SSR 63.00 84.00 105.00 137.00 168.00 179.00 200.00 263.00 284.00 326.00 728.00 1016.00
loading at site and stacking. Page 330

3 Cost of specials (0.50%) 0.00 16.36 19.82 21.75 24.10 27.18 35.89 43.73 52.31 62.41 74.05 98.77 110.49
Part A Total ---------- 3351.36 4067.82 4476.75 4981.10 5630.18 7392.89 8988.73 10777.31 12827.41 15209.05 20580.77 23224.49
B) Labour component
4 Earthwork excavation & Refilling 528.01 594.01 644.01 644.01 807.22 977.82 1134.82 1290.23 1502.03 1665.24 1931.84 2173.37
PartB Total ----------- 528.01 594.01 644.01 644.01 807.22 977.82 1134.82 1290.23 1502.03 1665.24 1931.84 2173.37

Cost of pipe 3879.37 4661.83 5120.76 5625.11 6437.40 8370.71 ### 12067.54 14329.44 16874.29 22512.61 25397.86
6 Add contractors profit @ 13.615% 528.18 634.71 697.19 765.86 876.45 1139.67 1378.32 1643.00 1950.95 2297.43 3065.09 3457.92

Grand Total 4407.55 5296.54 5817.95 6390.97 7313.85 9510.38 ### 13710.54 16280.39 19171.72 25577.70 28855.78
3 BWSC Class 16 Kg/cm2
Trench size 1.0m x 1.4m 1.1 x 1.6m 1.2 x 1.7m1.3 x 1.8m1.4 x 1.9m1.5 x 2.0m1.6 x 2.1m 1.7m x 2. 1.8m x 2.4m
Pipe dia in mm BWSC 300 mm 350 mm 400 mm 450 mm 500 mm 600 mm 700 mm 800 mm 900 mm 1000 mm 1100mm 1200mm
A) material component
1 Cost of pipes 3272.00 3964.00 4372.00 4892.00 5514.00 7284.00 9331.00 11188.00 13416.00 15870.00 19948.00 22904.00

2 Cost of specials (0.50%) 0.00 16.36 19.82 21.86 24.46 27.57 36.42 46.66 55.94 67.08 79.35 99.74 114.52
3 Transportation charges, including loading at factory, un- As per SSR 63.00 84.00 105.00 137.00 168.00 179.00 200.00 263.00 284.00 326.00 728.00 1016.00
loading at site and stacking. Page 330

Part A Total ---------- 3351.36 4067.82 4498.86 5053.46 5709.57 7499.42 9577.66 11506.94 13767.08 16275.35 20775.74 24034.52
B) Labour component
4 Earthwork excavation & Refilling 528.01 594.01 644.01 644.01 807.22 977.82 1134.82 1290.23 1502.03 1665.24 1931.84 2173.37
PartB Total ----------- 528.01 594.01 644.01 644.01 807.22 977.82 1134.82 1290.23 1502.03 1665.24 1931.84 2173.37

Cost of pipe 3879.37 4661.83 5142.87 5697.47 6516.79 8477.24 ### 12797.17 15269.11 17940.59 22707.58 26207.89
6 Add contractors profit @ 13.615% 528.18 634.71 700.20 775.71 887.26 1154.18 1458.50 1742.33 2078.89 2442.61 3091.64 3568.20

Grand Total 4407.55 5296.54 5843.07 6473.18 7404.05 9631.42 ### 14539.50 17348.00 20383.20 25799.22 29776.09

4 BWSC Class 18 Kg/cm2


Trench size 1.0 x 1.4 1.1 x 1.6 1.2 x 1.7 1.3 x 1.8 1.4 x 1.9 1.5 x 2 1.6 x 2.1 1.7m x 2. 1.8m x 2.4m
Pipe dia in mm BWSC 300 mm 350 mm 400 mm 450 mm 500 mm 600 mm 700 mm 800 mm 900 mm 1000 mm 1100mm 1200mm
A) material component
1 Cost of pipes 3272.00 3984.00 4435.00 4949.00 5775.00 7701.00 9899.00 11895.00 14340.00 16931.00 21877.00 25209.00
2 Cost of specials (0.50%) 0.00 16.36 19.92 22.18 24.75 28.88 38.51 49.50 59.48 71.70 84.66 109.39 126.05
3 Transportation charges, including loading at factory, un- As per SSR 63.00 84.00 105.00 137.00 168.00 179.00 200.00 263.00 284.00 326.00 728.00 1016.00
loading at site and stacking. Page 330

Part A Total ---------- 3351.36 4087.92 4562.18 5110.75 5971.88 7918.51 10148.50 12217.48 14695.70 17341.66 22714.39 26351.05
B) Labour component
4 Earthwork excavation & Refilling 528.01 594.01 644.01 644.01 807.22 977.82 1134.82 1290.23 1502.03 1665.24 1931.84 2173.37
PartB Total ----------- 528.01 594.01 644.01 644.01 807.22 977.82 1134.82 1290.23 1502.03 1665.24 1931.84 2173.37

Cost of pipe 3879.37 4681.93 5206.19 5754.76 6779.10 8896.33 11283.32 13507.71 16197.73 19006.90 24646.23 28524.42
6 Add contractors profit @ 13.615% 528.18 637.44 708.82 783.51 922.97 1211.23 1536.22 1839.07 2205.32 2587.79 3355.58 3883.60

Grand Total 4407.55 5319.37 5915.01 6538.27 7702.07 10107.56 ### 15346.78 18403.05 21594.69 28001.81 32408.02
5 BWSC Class 20 Kg/cm2
Trench size 1.0 x 1.4 1.1 x 1.6 1.2 x 1.7 1.3 x 1.8 1.4 x 1.9 1.5 x 2 1.6 x 2.1 1.7m x 2. 1.8m x 2.4m
Pipe dia in mm BWSC 300 mm 350 mm 400 mm 450 mm 500 mm 600 mm 700 mm 800 mm 900 mm 1000 mm 1100mm 1200mm
A) material component
1 Cost of pipes 3272.00 4022.00 4483.00 5188.00 6054.00 8112.00 ### 12643.00 15231.00 18056.00 24046.00 27687.00
2 Cost of specials (0.50%) 0.00 16.36 20.11 22.42 25.94 30.27 40.56 52.32 63.22 76.16 90.28 120.23 138.44
3 Transportation charges, including loading at factory, un- As per SSR 63.00 84.00 105.00 137.00 168.00 179.00 200.00 263.00 284.00 326.00 728.00 1016.00
Page 330
loading at site and stacking.
Part A Total ---------- 3351.36 4126.11 4610.42 5350.94 6252.27 8331.56 10716.32 12969.22 15591.16 18472.28 24894.23 28841.44
B) Labour component
4 Earthwork excavation & Refilling 528.01 594.01 644.01 644.01 807.22 977.82 1134.82 1290.23 1502.03 1665.24 1931.84 2173.37
PartB Total ----------- 528.01 594.01 644.01 644.01 807.22 977.82 1134.82 1290.23 1502.03 1665.24 1931.84 2173.37

Cost of pipe 3879.37 4720.12 5254.43 5994.95 7059.49 9309.38 ### 14259.45 17093.19 20137.52 26826.07 31014.81
6 Add contractors profit @ 13.615% 528.18 642.64 715.39 816.21 961.15 1267.47 1613.53 1941.42 2327.24 2741.72 3652.37 4222.67

Grand Total 4407.55 5362.76 5969.82 6811.16 8020.64 10576.85 ### 16200.87 19420.43 22879.24 30478.44 35237.48

6 BWSC Class 22 Kg/cm2


Trench size 1.0 x 1.4m 1.1 x 1.6m 1.2 x 1.7m 1.3 x 1.8m 1.4 x 1.9m 1.5 x 2m 1.6 x 2.1m 1.7m x 2. 1.8m x 2.4m
Pipe dia in mm BWSC 300 mm 350 mm 400 mm 450 mm 500 mm 600 mm 700 mm 800 mm 900 mm 1000 mm 1100mm 1200mm
A) material component
1 Cost of pipes 3316.00 4064.00 4688.00 5397.00 6344.00 8458.00 ### 13616.00 15979.00 19667.00 25573.00 29898.00
2 Cost of specials (0.50%) 0.00 16.58 20.32 23.44 26.99 31.72 42.29 55.29 68.08 79.90 98.34 127.87 149.49
3 Transportation charges, including loading at factory, un- As per SSR 63.00 84.00 105.00 137.00 168.00 179.00 200.00 263.00 284.00 326.00 728.00 1016.00
loading at site and stacking. Page 330
Part A Total ---------- 3395.58 4168.32 4816.44 5560.99 6543.72 8679.29 11313.29 13947.08 16342.90 20091.34 26428.87 31063.49
B) Labour component
4 Earthwork excavation & Refilling 528.01 594.01 644.01 644.01 807.22 977.82 1134.82 1290.23 1502.03 1665.24 1931.84 2173.37
PartB Total ----------- 528.01 594.01 644.01 644.01 807.22 977.82 1134.82 1290.23 1502.03 1665.24 1931.84 2173.37

Cost of pipes 3923.59 4762.33 5460.45 6205.00 7350.94 9657.11 ### 15237.31 17844.93 21756.58 28360.71 33236.86
6 Add contractors profit @ 13.615% 534.20 648.39 743.44 844.81 1000.83 1314.82 1694.81 2074.56 2429.59 2962.16 3861.31 4525.20

Grand Total 4457.79 5410.72 6203.89 7049.81 8351.77 10971.93 ### 17311.87 20274.52 24718.74 32222.02 37762.06
7 BWSC Class 24 Kg/cm2
Trench size 1.0 x 1.4m 1.1 x 1.6m 1.2 x 1.7m 1.3 x 1.8m 1.4 x 1.9m 1.5 x 2m 1.6 x 2.1m 1.7m x 2. 1.8m x 2.4m
Pipe dia in mm BWSC 300 mm 350 mm 400 mm 450 mm 500 mm 600 mm 700 mm 800 mm 900 mm 1000 mm 1100mm 1200mm
A) material component
1 Cost of pipes 3403.00 4166.00 4871.00 5645.00 6649.00 8909.00 ### 14414.00 17601.00 21498.00 28334.00 32472.00
2 Cost of specials (0.50%) 0.00 17.02 20.83 24.36 28.23 33.25 44.55 59.10 72.07 88.01 107.49 141.67 162.36
3 Transportation charges, including loading at factory, un- As per SSR 63.00 84.00 105.00 137.00 168.00 179.00 200.00 263.00 284.00 326.00 728.00 1016.00
loading at site and stacking. Page 330
Part A Total ---------- 3483.02 4270.83 5000.36 5810.23 6850.25 9132.55 12079.10 14749.07 17973.01 21931.49 29203.67 33650.36
B) Labour component
4 Earthwork excavation & Refilling 528.01 594.01 644.01 644.01 807.22 977.82 1134.82 1290.23 1502.03 1665.24 1931.84 2173.37
PartB Total ----------- 528.01 594.01 644.01 644.01 807.22 977.82 1134.82 1290.23 1502.03 1665.24 1931.84 2173.37

Cost of pipes 4011.03 4864.84 5644.37 6454.24 7657.47 10110.37 ### 16039.30 19475.04 23596.73 31135.51 35823.73
6 Add contractors profit @ 13.615% 546.10 662.35 768.48 878.74 1042.56 1376.53 1799.08 2183.75 2651.53 3212.69 4239.10 4877.40

Grand Total 4557.13 5527.19 6412.85 7332.98 8700.03 11486.90 ### 18223.05 22126.57 26809.42 35374.61 40701.13
8m x 2.4m

8m x 2.4m
8m x 2.4m

8m x 2.4m

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
8m x 2.4m
Data based on 2015-16 Common SSR - for PSCpipes
HT Wire Cement 6300 Month 25.07.2015
Earth work excavation in all soils upto SDR except hard rock requiring blasting for PSC pipes 'filling with excavated soils including laying jointing testing of pipe
line including cost of materials etc. complete
Cost of specials : 1.50
Conveyance: ### (Min Distance of 100 Km should be considered)
PCC Pipes Class : 4 Kg/cm2
Trench size 1.0 x 1.4m 1.05 x 1.65m 1.1 x 1.7m 1.2 x 1.7m 1.3 x 1.8m 1.4 x 1.9m 1.5 x 2.0m 1.6 x 2.1m
Pipe dia in mm = PCCP 400 mm 450 mm 500 mm 600 mm 700 mm 800 mm 900 mm 1000 mm

1 Cost of pipes 5299.00 5760.00 6297.00 7490.00 8658.00 10175.00 12064.00 13990.00
Transportation charges, including loading at factory, un-
2 120.00 120.00 170.00 190.00 300.00 300.00 300.00 480.00
loading at site and stacking.
3 Cost of specials (1.50%) 79.49 86.40 94.46 112.35 129.87 152.63 180.96 209.85
Part A Total -----------> 5498.49 5966.40 6561.46 7792.35 9087.87 10627.63 12544.96 14679.85

4 Earth work, Laying, jointing, testing HFT pressure


including cost of site welding and fixing of polypropylene
617.01 696.01 786.22 917.82 1047.82 1199.23 1352.03 1475.55
diapher cloth,, cost of transportation of water and
emptying pipe line after completion of field testing.
Add contractors profit @ 13.615% 832.62 907.09 1000.39 1185.89 1379.97 1610.23 1892.08 2199.56
Total 6948.12 7569.50 8348.07 9896.06 11515.66 13437.09 15789.07 18354.96

PCC Pipes Class : 6 Kg/cm2


Trench size 1.0 x 1.4m 1.05 x 1.65m 1.1 x 1.7m 1.2 x 1.7m 1.3 x 1.8m 1.4 x 1.9m 1.5 x 2.0m 1.6 x 2.1m
Pipe dia in mm = PCCP 400 mm 450 mm 500 mm 600 mm 700 mm 800 mm 900 mm 1000 mm

1 Cost of pipes 5299.00 5760.00 6297.00 7546.00 8795.00 10366.00 12064.00 14317.00
Transportation charges, including loading at factory, un-
2 120.00 120.00 170.00 190.00 300.00 300.00 300.00 480.00
loading at site and stacking.
3 Cost of specials (1.50%) 79.49 86.40 94.46 113.19 131.93 155.49 180.96 214.76
Part A Total -----------> 5498.49 5966.40 6561.46 7849.19 9226.93 10821.49 12544.96 15011.76

4 Earth work, Laying, jointing, testing HFT pressure


including cost of site welding and fixing of polypropylene
617.01 696.01 786.22 917.82 1047.82 1199.23 1352.03 1475.55
diapher cloth,, cost of transportation of water and
emptying pipe line after completion of field testing.
Add contractors profit @ 13.615% 832.62 907.09 1000.39 1193.63 1398.91 1636.62 1892.08 2244.75
Total 6948.12 7569.50 8348.07 9960.64 ### 13657.34 15789.07 18732.06
PCC Pipes Class : 8 Kg/cm2
Trench size 1.0 x 1.4m 1.05 x 1.65m 1.1 x 1.7m 1.2 x 1.7m 1.3 x 1.8m 1.4 x 1.9m 1.5 x 2.0m 1.6 x 2.1m
Pipe dia in mm = PCCP 400 mm 450 mm 500 mm 600 mm 700 mm 800 mm 900 mm 1000 mm

Cost of pipes 5299.00 5760.00 6311.00 7646.00 8960.00 10596.00 12593.00 14660.00

Transportation charges, including loading at factory, un-


120.00 120.00 170.00 190.00 300.00 300.00 300.00 480.00
loading at site and stacking.

Cost of specials (1.50%) 79.49 86.40 94.67 114.69 134.40 158.94 188.90 219.90
Part A Total -----------> 5498.49 5966.40 6575.67 7950.69 9394.40 11054.94 13081.90 15359.90

Earth work, Laying, jointing, testing HFT pressure


including cost of site welding and fixing of polypropylene
617.01 696.01 786.22 917.82 1047.82 1199.23 1352.03 1475.55
diapher cloth,, cost of transportation of water and
emptying pipe line after completion of field testing.
Add contractors profit @ 13.615% 832.62 907.09 1002.32 1207.45 1421.71 1668.41 1965.18 2292.15
Total 6948.12 7569.50 8364.21 10075.96 11863.93 13922.58 16399.11 19127.60

PCC Pipes Class : 10 Kg/cm2


Trench size 1.0 x 1.4m 1.05 x 1.65m 1.1 x 1.7m 1.2 x 1.7m 1.3 x 1.8m 1.4 x 1.9m 1.5 x 2.0m 1.6 x 2.1m
Pipe dia in mm = PCCP 400 mm 450 mm 500 mm 600 mm 700 mm 800 mm 900 mm 1000 mm

Cost of pipes 5299.00 5787.00 6401.00 7779.00 9135.00 10826.00 12880.00 15015.00
Transportation charges, including loading at factory, un-
120.00 120.00 170.00 190.00 300.00 300.00 300.00 300.00
loading at site and stacking.
Cost of specials (1.50%) 79.49 86.81 96.02 116.69 137.03 162.39 193.20 225.23
Part A Total -----------> 5498.49 5993.81 6667.02 8085.69 9572.03 11288.39 13373.20 15540.23

Earth work, Laying, jointing, testing HFT pressure


including cost of site welding and fixing of polypropylene
617.01 696.01 786.22 917.82 1047.82 1199.23 1352.03 1475.55
diapher cloth,, cost of transportation of water and
emptying pipe line after completion of field testing.
Add contractors profit @ 13.615% 832.62 910.82 1014.76 1225.83 1445.89 1700.19 2004.84 2316.70
Total 6948.12 7600.64 8468.00 10229.34 12065.74 14187.81 16730.07 19332.48

PCC Pipes Class : 12 Kg/cm2


Trench size 1.0 x 1.4m 1.05 x 1.65m 1.1 x 1.7m 1.2 x 1.7m 1.3 x 1.8m 1.4 x 1.9m 1.5 x 2.0m 1.6 x 2.1m
Pipe dia in mm = PCCP 400 mm 450 mm 500 mm 600 mm 700 mm 800 mm 900 mm 1000 mm

Cost of pipes 5326.00 5856.00 6477.00 7902.00 9301.00 11036.00 13167.00 15367.00
Transportation charges, including loading at factory, un-
120.00 120.00 170.00 190.00 300.00 300.00 300.00 300.00
loading at site and stacking.
Cost of specials (1.50%) 79.89 87.84 97.16 118.53 139.52 165.54 197.51 230.51
Part A Total -----------> 5525.89 6063.84 6744.16 8210.53 9740.52 11501.54 13664.51 15897.51

including cost of site welding and fixing of polypropylene


617.01 696.01 786.22 917.82 1047.82 1199.23 1352.03 1475.55
diapher cloth,, cost of transportation of water and
Add contractors profit @ 13.615% 836.36 920.35 1025.26 1242.82 1468.83 1729.21 2044.50 2365.34
Total 6979.26 7680.20 8555.64 10371.17 12257.17 14429.98 17061.04 19738.40
PCC Pipes Class : 14 Kg/cm2
Trench size 1.0 x 1.4m 1.05 x 1.65m 1.1 x 1.7m 1.2 x 1.7m 1.3 x 1.8m 1.4 x 1.9m 1.5 x 2.0m 1.6 x 2.1m
Pipe dia in mm = PCCP 400 mm 450 mm 500 mm 600 mm 700 mm 800 mm 900 mm 1000 mm

Cost of pipes 5383.00 5940.00 6583.00 8026.00 9462.00 11250.00 13425.00 15660.00
Transportation charges, including loading at factory, un-
120.00 120.00 170.00 190.00 300.00 300.00 300.00 300.00
loading at site and stacking.
Cost of specials (1.50%) 80.75 89.10 98.75 120.39 141.93 168.75 201.38 234.90
Part A Total -----------> 5583.75 6149.10 6851.75 8336.39 9903.93 11718.75 13926.38 16194.90

including cost of site welding and fixing of polypropylene


617.01 696.01 786.22 917.82 1047.82 1199.23 1352.03 1475.55
diapher cloth,, cost of transportation of water and
Add contractors profit @ 13.615% 844.23 931.96 1039.91 1259.96 1491.08 1758.78 2080.15 2405.83
Total 7044.99 7777.07 8677.88 10514.17 12442.83 14676.76 17358.56 20076.28

PCC Pipes Class : 16 Kg/cm2


Trench size 1.0 x 1.4m 1.05 x 1.65m 1.1 x 1.7m 1.2 x 1.7m 1.3 x 1.8m 1.4 x 1.9m 1.5 x 2.0m 1.6 x 2.1m
Pipe dia in mm = PCCP 400 mm 450 mm 500 mm 600 mm 700 mm 800 mm 900 mm 1000 mm

Cost of pipes 5479.00 6061.00 6682.00 8216.00 9665.00 11512.00 13773.00 16067.00
Transportation charges, including loading at factory, un-
120.00 120.00 170.00 190.00 300.00 300.00 300.00 300.00
loading at site and stacking.
Cost of specials (1.50%) 82.19 90.92 100.23 123.24 144.98 172.68 206.60 241.01
Part A Total -----------> 5681.19 6271.92 6952.23 8529.24 10109.98 11984.68 14279.60 16608.01

including cost of site welding and fixing of polypropylene


844.23 931.96 1039.91 1259.96 1491.08 1758.78 2080.15 2405.83
diapher cloth,, cost of transportation of water and
Add contractors profit @ 13.615% 888.44 980.81 1088.13 1332.80 1579.48 1871.17 2227.38 2588.73
Total 7413.86 8184.69 9080.27 11122.00 13180.54 15614.63 18587.13 21602.57

PCC Pipes Class : 18 Kg/cm2


Trench size 1.0 x 1.4m 1.05 x 1.65m 1.1 x 1.7m 1.2 x 1.7m 1.3 x 1.8m 1.4 x 1.9m 1.5 x 2.0m 1.6 x 2.1m
Pipe dia in mm = PCCP 400 mm 450 mm 500 mm 600 mm 700 mm 800 mm 900 mm 1000 mm

Cost of pipes 5570.00 6144.00 6831.00 8392.00 9924.00 11788.00 14117.00 16487.00
Transportation charges, including loading at factory, un-
120.00 120.00 170.00 190.00 300.00 300.00 300.00 300.00
loading at site and stacking.
Cost of specials (1.50%) 83.55 92.16 102.47 125.88 148.86 176.82 211.76 247.31
Part A Total -----------> 5773.55 6356.16 7103.47 8707.88 10372.86 12264.82 14628.76 17034.31

including cost of site welding and fixing of polypropylene


844.23 931.96 1039.91 1259.96 1491.08 1758.78 2080.15 2405.83
diapher cloth,, cost of transportation of water and
Add contractors profit @ 13.615% 901.01 992.28 1108.72 1357.12 1615.28 1909.31 2274.92 2646.77
Total 7518.79 8280.40 9252.10 11324.96 13479.22 15932.91 18983.83 22086.91

PCC Pipes Class : 20 Kg/cm2


Trench size 1.0 x 1.4m 1.05 x 1.65m 1.1 x 1.7m 1.2 x 1.7m 1.3 x 1.8m 1.4 x 1.9m 1.5 x 2.0m 1.6 x 2.1m
Pipe dia in mm = PCCP 400 mm 450 mm 500 mm 600 mm 700 mm 800 mm 900 mm 1000 mm

Cost of pipes 5640.00 6240.00 6941.00 8570.00 10118.00 12106.00 14460.00 16919.00
Transportation charges, including loading at factory, un-
120.00 120.00 170.00 190.00 300.00 300.00 300.00 300.00
loading at site and stacking.
Cost of specials (1.50%) 84.60 93.60 104.12 128.55 151.77 181.59 216.90 253.79
Part A Total -----------> 5844.60 6453.60 7215.12 8888.55 10569.77 12587.59 14976.90 17472.79
including cost of site welding and fixing of polypropylene
844.23 931.96 1039.91 1259.96 1491.08 1758.78 2080.15 2405.83
diapher cloth,, cost of transportation of water and
Add contractors profit @ 13.615% 910.68 1005.54 1123.92 1381.72 1642.08 1953.26 2322.32 2706.47
Total 7599.51 8391.10 9378.95 11530.23 13702.93 16299.63 19379.37 22585.09
(Min Distance of 100 Km should be considered)

1.7 x 2.3m 1.8m x 2.4m 1.9x2.5 2.0x2.6 2.1x2.7 2.2x2.8 2.3x2.9 2.4x3.0 2.5x3.1 2.6x3.2
1100 mm 1200mm 1300mm 1400mm 1500mm 1600mm 1700mm 1800mm 1900mm 2000mm

15571.00 17661 19663 21578 23698 26725 28791 31566 36864 39362

480.00 950.00 950.00 950.00 950.00 950.00 1140.00 1140.00 1140.00 1210.00

233.57 264.92 294.95 323.67 355.47 400.88 431.87 473.49 552.96 590.43
16284.57 18875.92 20907.95 22851.67 25003.47 28075.88 30362.87 33179.49 38556.96 41162.43

1685.63 1862.45 2009.05 3280.03 3497.18 3687.16 3973.98 4151.63 4408.12 4620.45

2446.64 2823.53 3120.15 3557.83 3880.36 4324.54 4674.96 5082.63 5849.70 6233.34
20416.84 23561.90 26037.15 29689.53 32381.01 36087.58 39011.81 42413.75 48814.78 52016.22

1.7 x 2.3m 1.8m x 2.4m 1.9x2.5 2.0x2.6 2.1x2.7 2.2x2.8 2.3x2.9 2.4x3.0 2.5x3.1 2.6x3.2
1100 mm 1200 mm 1300 mm 1400 mm 1500 mm 1600 mm 1700 mm 1800 mm 1900 mm 2000 mm

15571.00 18115 20189 22176 24365 27468 29652 32470 37895 41316

480.00 950.00 950.00 950.00 950.00 950.00 1140.00 1140.00 1140.00 1210.00

233.57 271.73 302.84 332.64 365.48 412.02 444.78 487.05 568.43 619.74
16284.57 19336.73 21441.84 23458.64 25680.48 28830.02 31236.78 34097.05 39603.43 43145.74

1685.63 1862.45 2009.05 3280.03 3497.18 3687.16 3973.98 4151.63 4408.12 4620.45

2446.64 2886.27 3192.84 3640.47 3972.54 4427.21 4793.94 5207.56 5992.17 6503.37
20416.84 24085.45 26643.73 30379.14 33150.20 36944.39 40004.70 43456.24 50003.72 54269.56
1.7 x 2.3m 1.8m x 2.4m 1.9x2.5 2.0x2.6 2.1x2.7 2.2x2.8 2.3x2.9 2.4x3.0 2.5x3.1 2.6x3.2
1100 mm 1200 mm 1300 mm 1400 mm 1500 mm 1600 mm 1700 mm 1800 mm 1900 mm 2000 mm

16373.00 18576.00 20724.00 22801.00 25034.00 28227.00 30564.00 34239.00 39868.00 42641.00

480.00 950.00 950.00 950.00 950.00 950.00 1140.00 1140.00 1140.00 1210.00

245.60 278.64 310.86 342.02 375.51 423.41 458.46 513.59 598.02 639.62
17098.60 19804.64 21984.86 24093.02 26359.51 29600.41 32162.46 35892.59 41606.02 44490.62

1685.63 1862.45 2009.05 3280.03 3497.18 3687.16 3973.98 4151.63 4408.12 4620.45

2557.47 2949.97 3266.77 3726.84 4064.99 4532.10 4919.98 5452.02 6264.83 6686.47
21341.70 24617.06 27260.68 31099.89 33921.68 37819.67 41056.42 45496.24 52278.97 55797.54

1.7 x 2.3m 1.8m x 2.4m 1.9x2.5 2.0x2.6 2.1x2.7 2.2x2.8 2.3x2.9 2.4x3.0 2.5x3.1 2.6x3.2
1100 mm 1200 mm 1300 mm 1400 mm 1500 mm 1600 mm 1700 mm 1800 mm 1900 mm 2000 mm

16745.00 19035.00 21260.00 23428.00 25692.00 29643.00 32187.00 35336.00 41033.00 44004.00

480.00 950.00 950.00 950.00 950.00 950.00 1140.00 1140.00 1140.00 1210.00

251.18 285.53 318.90 351.42 385.38 444.65 482.81 530.04 615.50 660.06
17476.18 20270.53 22528.90 24729.42 27027.38 31037.65 33809.81 37006.04 42788.50 45874.06

1685.63 1862.45 2009.05 3280.03 3497.18 3687.16 3973.98 4151.63 4408.12 4620.45

2608.88 3013.40 3340.84 3813.49 4155.92 4727.78 5144.26 5603.62 6425.82 6874.83
21770.69 25146.38 27878.79 31822.94 34680.48 39452.59 42928.05 46761.29 53622.44 57369.34

1.7 x 2.3m 1.8m x 2.4m 1.9x2.5 2.0x2.6 2.1x2.7 2.2x2.8 2.3x2.9 2.4x3.0 2.5x3.1 2.6x3.2
1100 mm 1200 mm 1300 mm 1400 mm 1500 mm 1600 mm 1700 mm 1800 mm 1900 mm 2000 mm

17137.00 19506.00 21810.00 24052.00 27075.00 30505.00 33163.00 36407.00 43117.00 46383.00
480.00 950.00 950.00 950.00 950.00 950.00 1140.00 1140.00 1140.00 1210.00
257.06 292.59 327.15 360.78 406.13 457.58 497.45 546.11 646.76 695.75
17874.06 20748.59 23087.15 25362.78 28431.13 31912.58 34800.45 38093.11 44903.76 48288.75

1685.63 1862.45 2009.05 3280.03 3497.18 3687.16 3973.98 4151.63 4408.12 4620.45
2663.05 3078.49 3416.85 3899.72 4347.04 4846.90 5279.14 5751.62 6713.81 7203.59
22222.74 25689.53 28513.05 32542.53 36275.35 40446.64 44053.57 47996.36 56025.69 60112.79
1.7 x 2.3m 1.8m x 2.4m 1.9x2.5 2.0x2.6 2.1x2.7 2.2x2.8 2.3x2.9 2.4x3.0 2.5x3.1 2.6x3.2
1100 mm 1200 mm 1300 mm 1400 mm 1500 mm 1600 mm 1700 mm 1800 mm 1900 mm 2000 mm

17495.00 19927.00 22294.00 25287.00 27835.00 31367.00 34989.00 38420.00 44774.00 47823.00
480.00 950.00 950.00 950.00 950.00 950.00 1140.00 1140.00 1140.00 1210.00
262.43 298.91 334.41 379.31 417.53 470.51 524.84 576.30 671.61 717.35
18237.43 21175.91 23578.41 26616.31 29202.53 32787.51 36653.84 40136.30 46585.61 49750.35

1685.63 1862.45 2009.05 3280.03 3497.18 3687.16 3973.98 4151.63 4408.12 4620.45
2712.52 3136.67 3483.73 4070.39 4452.06 4966.03 5531.48 6029.80 6942.80 7402.58
22635.58 26175.03 29071.19 33966.73 37151.77 41440.70 46159.30 50317.73 57936.53 61773.38

1.7 x 2.3m 1.8m x 2.4m 1.9x2.5 2.0x2.6 2.1x2.7 2.2x2.8 2.3x2.9 2.4x3.0 2.5x3.1 2.6x3.2
1100 mm 1200 mm 1300 mm 1400 mm 1500 mm 1600 mm 1700 mm 1800 mm 1900 mm 2000 mm

17942.00 20449.00 23529.00 26053.00 28983.00 33513.00 36634.00 40175.00 46395.00 50049.00
480.00 950.00 950.00 950.00 950.00 950.00 1140.00 1140.00 1140.00 1210.00
269.13 306.74 352.94 390.80 434.75 502.70 549.51 602.63 695.93 750.74
18691.13 21705.74 24831.94 27393.80 30367.75 34965.70 38323.51 41917.63 48230.93 52009.74

2712.52 3136.67 3483.73 4070.39 4452.06 4966.03 5531.48 6029.80 6942.80 7402.58
2914.11 3382.29 3855.18 4283.85 4740.72 5436.70 5970.86 6528.04 7511.90 8088.99
24317.76 28224.70 32170.85 35748.04 39560.53 45368.43 49825.85 54475.47 62685.63 67501.31

1.7 x 2.3m 1.8m x 2.4m 1.9x2.5 2.0x2.6 2.1x2.7 2.2x2.8 2.3x2.9 2.4x3.0 2.5x3.1 2.6x3.2
1100 mm 1200 mm 1300 mm 1400 mm 1500 mm 1600 mm 1700 mm 1800 mm 1900 mm 2000 mm

18413.00 21483.00 24187.00 26835.00 30690.00 34466.00 37666.00 41414.00 47771.00 51630.00
480.00 950.00 950.00 950.00 950.00 950.00 1140.00 1140.00 1140.00 1210.00
276.20 322.25 362.81 402.53 460.35 516.99 564.99 621.21 716.57 774.45
19169.20 22755.25 25499.81 28187.53 32100.35 35932.99 39370.99 43175.21 49627.57 53614.45

2712.52 3136.67 3483.73 4070.39 4452.06 4966.03 5531.48 6029.80 6942.80 7402.58
2979.20 3525.18 3946.11 4391.92 4976.61 5568.40 6113.47 6699.26 7702.06 8307.47
24860.92 29417.10 32929.65 36649.84 41529.02 46467.42 51015.94 55904.27 64272.43 69324.50

1.7 x 2.3m 1.8m x 2.4m 1.9x2.5 2.0x2.6 2.1x2.7 2.2x2.8 2.3x2.9 2.4x3.0 2.5x3.1 2.6x3.2
1100 mm 1200 mm 1300 mm 1400 mm 1500 mm 1600 mm 1700 mm 1800 mm 1900 mm 2000 mm

19446.00 22221.00 25014.00 28573.00 32692.00 35392.00 38643.00 42653.00 49071.00 53033.00
480.00 950.00 950.00 950.00 950.00 950.00 1140.00 1140.00 1140.00 1210.00
291.69 333.32 375.21 428.60 490.38 530.88 579.65 639.80 736.07 795.50
20217.69 23504.32 26339.21 29951.60 34132.38 36872.88 40362.65 44432.80 50947.07 55038.50
2712.52 3136.67 3483.73 4070.39 4452.06 4966.03 5531.48 6029.80 6942.80 7402.58
3121.95 3627.17 4060.39 4632.09 5253.27 5696.37 6248.49 6870.48 7881.71 8501.35
26052.16 30268.16 33883.33 38654.08 43837.71 47535.28 52142.62 57333.08 65771.58 70942.43
Data based on 2015-16 Common SSR - for PSCpipes
HT Wire 59500 Cement 6300 Month 25.07.2015
Earth work excavation in all soils upto SDR except hard rock requiring blasting for PSC pipes 'filling with excavated soils including laying jointing testing of pipe line including
cost of materials etc. complete
Cost of specials : 1.50 %
Conveyance: ###
PSC Pipes Class : 6 Kg/cm2
Trench size 0.95 x 1.55m 1.0 x 1.6m 1.05 x 1.65m 1.1 x 1.7m 1.2 x 1.8m 1.3 x 1.9m 1.4 x 2.0m 1.5 x 2.1m 1.6 x 2.2m
Pipe dia in mm = PSC 350 mm 400 mm 450 mm 500 mm 600 mm 700 mm 800 mm 900 mm 1000 mm

1 Cost of pipes 2925.00 3179.00 3394.00 3660.00 4233.00 5201.00 6235.00 7194.00 8501.00
Transportation charges, including loading at factory, un-loading at site
2 210.00 210.00 255.00 270.00 300.00 495.00 495.00 495.00 795.00
and stacking.
3 Cost of specials (1.50%) 43.88 47.69 50.91 54.90 63.50 78.02 93.53 107.91 127.52
Part A Total -----------> 3178.88 3436.69 3699.91 3984.90 4596.50 5774.02 6823.53 7796.91 9423.52

4
Earth work, Laying, jointing, testing HFT pressure including cost of ruuber
rings, cost of transportation of water and emptying pipe line after 381.01 398.01 434.01 494.22 592.82 688.82 781.23 866.03 987.24
completion of field testing.

Add contractors profit @ 13.615% 484.68 522.09 562.83 609.83 706.53 879.91 1035.39 1179.46 1417.42
Total 4044.57 4356.79 4696.75 5088.95 5895.85 7342.75 8640.15 9842.40 11828.18

PSC Pipes Class : 12 Kg/cm2


Trench size 0.95 x 1.55m 1.0 x 1.6m 1.05 x 1.65m 1.1 x 1.7m 1.2 x 1.8m 1.3 x 1.9m 1.4 x 2.0m 1.5 x 2.1m 1.6 x 2.2m
Pipe dia in mm = PSC 350 mm 400 mm 450 mm 500 mm 600 mm 700 mm 800 mm 900 mm 1000 mm

1 Cost of pipes 2941.00 3222.00 3461.00 3741.00 4366.00 5326.00 6385.00 7493.00 8838.00
2 Transportation charges, including loading at factory, un-loading at site 210.00 210.00 255.00 270.00 300.00 495.00 495.00 495.00 795.00
and stacking.
3 Cost of specials (1.50%) 44.12 48.33 51.92 56.12 65.49 79.89 95.78 112.40 132.57
Part A Total -----------> 3195.12 3480.33 3767.92 4067.12 4731.49 5900.89 6975.78 8100.40 9765.57

4 381.01 398.01 434.01 494.22 592.82 688.82 781.23 866.03 987.24


Earth work, Laying, jointing, testing HFT pressure including cost of ruuber
rings, cost of transportation of water and emptying pipe line after
completion of field testing.
Add contractors profit @ 13.615% 486.89 528.04 572.09 621.03 724.90 897.19 1056.12 1220.78 1464.00
Total 4063.02 4406.38 4774.02 5182.37 6049.21 7486.90 8813.13 10187.21 12216.81
PSC Pipes Class : 14 Kg/cm2
Trench size 0.95 x 1.55m 1.0 x 1.6m 1.05 x 1.65m 1.1 x 1.7m 1.2 x 1.8m 1.3 x 1.9m 1.4 x 2.0m 1.5 x 2.1m 1.6 x 2.2m
Pipe dia in mm = PSC 350 mm 400 mm 450 mm 500 mm 600 mm 700 mm 800 mm 900 mm 1000 mm

1 Cost of pipes 3001.00 3282.00 3549.00 3819.00 4505.00 5513.00 6638.00 7783.00 9251.00

Transportation charges, including loading at factory, un-loading at site


2 210.00 210.00 255.00 270.00 300.00 495.00 495.00 495.00 795.00
and stacking.

3 Cost of specials (1.50%) 45.02 49.23 53.24 57.29 67.58 82.70 99.57 116.75 138.77
Part A Total -----------> 3256.02 3541.23 3857.24 4146.29 4872.58 6090.70 7232.57 8394.75 10184.77

4
Earth work, Laying, jointing, testing HFT pressure including cost of ruuber
rings, cost of transportation of water and emptying pipe line after 381.01 398.01 434.01 494.22 592.82 688.82 781.23 866.03 987.24
completion of field testing.

Add contractors profit @ 13.615% 495.18 536.33 584.25 631.80 744.11 923.03 1091.08 1260.85 1521.07
Total 4132.21 4475.57 4875.50 5272.31 6209.51 7702.55 9104.88 10521.63 12693.08

PSC Pipes Class : 16 Kg/cm2


Trench size 0.95 x 1.55m 1.0 x 1.6m 1.05 x 1.65m 1.1 x 1.7m 1.2 x 1.8m 1.3 x 1.9m 1.4 x 2.0m 1.5 x 2.1m 1.6 x 2.2m
Pipe dia in mm = PSC 350 mm 400 mm 450 mm 500 mm 600 mm 700 mm 800 mm 900 mm 1000 mm

1 Cost of pipes 3104.00 3332.00 3625.00 3931.00 4642.00 5671.00 6875.00 8308.00 9735.00
2 Transportation charges, including loading at factory, un- 210.00 210.00 255.00 270.00 300.00 495.00 495.00 495.00 795.00
loading at site and stacking.

3 Cost of specials (1.50%) 46.56 49.98 54.38 58.97 69.63 85.07 103.13 124.62 146.03
Part A Total -----------> 3360.56 3591.98 3934.38 4259.97 5011.63 6251.07 7473.13 8927.62 10676.03

4 Earth work, Laying, jointing, testing HFT pressure including 381.01 398.01 434.01 494.22 592.82 688.82 781.23 866.03 987.24
cost of ruuber rings, cost of transportation of water and
emptying pipe line after completion of field testing.

Add contractors profit @ 13.615% 509.41 543.24 594.76 647.28 763.05 944.87 1123.83 1333.41 1587.95
Total 4250.98 4533.23 4963.15 5401.47 6367.50 7884.76 9378.19 11127.06 13251.22
2.0 x 2.6m
1400 mm

11984.00

1530.00

179.76
13693.76

1280.05

2038.68
17012.49 2.9E+07 3.7E+07

1.6 x 2.2m
1000 mm

8838.00
1530.00

132.57
10500.57

1280.05
1603.93
13384.55
1.6 x 2.2m
1000 mm

9251.00

1530.00

138.77
10919.77

1280.05

1661.00
13860.82

1.6 x 2.2m
1000 mm

9735.00
1530.00

146.03

11411.03

1280.05

1727.89
14418.97
DATA BASED ON 2015-16 AS PER COMMON SSR

1 Earth work excavation in all soils upto SDR except hard rock
requiring blasting for 'MS 'pipes and refilling with excavated soils
including laying jointing testing of pipe line including cost of
materialsm CED and other taxes, etc complete

Cost of steel plate per MT Rs: ### including all taxes 33300 feb
a Fabrication charges Rs: 11.00 /kg as per SSR 2015-16
b Rate of Apoxy paint Rs: 1070.00 /10 sqm 33300
c Rate for Jointing of pipes Rs: 10.34 /kg
d Transportation charges Rs: 702.20 /MT

Trench size 0.90 x 1.20 m 0.90 x 1.30 m 1.00 x 1.40 m 1.1 x 1.6m 1.2 x 1.7m 1.3 x 1.8m 1.4 x 1.9m 1.50 x 2.0m

Pipe dia in mm = 80 mm 100 mm 125 mm 150 mm 200 mm 250 mm 300 mm 350 mm 400 mm 450 mm 500 mm 600 mm 700 mm 800 mm 900 mm 1000 mm 1100 mm 1200 mm 1300 mm 1400 mm 1500 mm 1600 mm 1800 mm 1800 mm
Thickness in mm 14 mm 14 mm 14 mm 14 mm 14 mm 14 mm 14 mm 14 mm 14 mm 14 mm 14 mm 14 mm 14 mm 14 mm 14 mm 14 mm 14 mm 14 mm 14 mm 14 mm 14 mm 14 mm 14 mm 25 mm
Pressure rating (m)

1 Wt of pipe 32.455 39.360 47.991 56.623 73.886 91.149 108.412 125.675 142.938 160.201 177.464 211.990 246.516 281.042 315.569 350.095 384.621 419.147 453.673 488.199 522.725 557.251 626.304 1125.181
2 Wastage (5%) 1.62 1.97 2.40 2.83 3.69 4.56 5.42 6.28 7.15 8.01 8.87 10.60 12.33 14.05 15.78 17.50 19.23 20.96 22.68 24.41 26.14 27.86 31.32 56.26
Total weight 34.07 41.33 50.39 59.45 77.58 95.71 113.83 131.96 150.09 168.21 186.33 222.59 258.85 295.09 331.35 367.59 403.85 440.11 476.35 512.61 548.87 585.11 657.62 1181.44

A) Materials component
1 Cost of pipe per RMT 1396.87 1694.53 2065.99 2437.45 3180.78 3924.11 4667.03 5410.36 6153.69 6896.61 7639.53 9126.19 10612.85 12098.69 13585.35 15071.19 16557.85 18044.51 19530.35 21017.01 22503.67 23989.51 26962.42 48439.04

2 Cost of specials (1.50% of basic cost) 20.95 25.42 30.99 36.56 47.71 58.86 70.01 81.16 92.31 103.45 114.59 136.89 159.19 181.48 203.78 226.07 248.37 270.67 292.96 315.26 337.56 359.84 404.44 726.59

3 Transportation charges, loading, 23.92 29.02 35.38 41.75 54.48 67.21 79.93 92.66 105.39 118.12 130.84 156.30 181.76 207.21 232.67 258.12 283.58 309.05 334.49 359.95 385.42 410.86 461.78 829.61
unloading and stacking
1441.70 1749.00 2132.40 2515.80 3283.00 4050.20 4817.00 5584.20 6351.40 7118.20 7885.00 9419.40 ### ### ### ### ### 18624.20 ### ### ### 24760.20 27828.60 49995.20

B) Labour component
4 fabrication 374.77 454.63 554.29 653.95 853.38 1052.81 1252.13 1451.56 1650.99 1850.31 2049.63 2448.49 2847.35 3245.99 3644.85 4043.49 4442.35 4841.21 5239.85 5638.71 6037.57 6436.21 7233.82 12995.84

5 Epoxy paint Out side 63.20 76.64 93.45 110.26 143.87 177.49 211.10 244.72 278.33 311.95 345.56 412.79 480.02 547.25 614.48 681.71 748.94 816.17 883.40 950.63 1017.86 1085.09 1219.55 1226.95

6 Epoxy paint Inside 53.78 67.23 84.04 100.85 134.46 168.08 201.69 235.31 268.92 302.54 336.15 403.38 470.61 537.84 605.07 672.30 739.53 806.76 873.99 941.22 1008.45 1075.68 1210.14 1210.14

8 Jointing of pipes (Rs:10.34 / kg) 352.28 427.35 521.03 614.71 802.18 989.64 1177.00 1364.47 1551.93 1739.29 802.00 987.00 1246.00 1475.00 1788.00 2002.00 2069.00 2138.00 2209.00 2425.00 2488.00 2552.00 2891.00 2891.00

844.00 1025.80 1252.80 1479.70 1933.80 2388.00 2841.90 3296.00 3750.10 4204.00 3533.30 4251.60 5043.90 5806.00 6652.40 7399.50 7999.80 8602.10 9206.20 9955.50 ### 11148.90 12554.50 18323.90
Total 2285.70 2774.80 3385.20 3995.50 5216.80 6438.20 7658.90 8880.20 ### ### ### ### ### ### ### ### ### 27226.30 ### ### ### 35909.10 40383.10 68319.10
Contractor Profit @13.615% 311.20 377.79 460.89 543.99 710.27 876.56 1042.76 1209.04 1375.32 1541.52 1554.60 1861.31 2178.09 2490.65 2814.79 3125.31 3415.95 3706.86 3997.91 4308.83 4598.93 4889.02 5498.16 9301.65
Final Rate 2596.90 3152.59 3846.09 4539.49 5927.07 7314.76 8701.66 ### ### ### ### ### ### ### ### ### ### 30933.16 ### ### ### 40798.12 45881.26 77620.75
DATA BASED ON 2014-15 AS PER COMMON SSR

1 Earth work excavation in all soils upto SDR except hard rock
requiring blasting for 'MS 'pipes and refilling with excavated soils
including laying jointing testing of pipe line including cost of
materialsm CED and other taxes, etc complete

Cost of steel plate per MT Rs: ### including all taxes 33300 feb
a Fabrication charges Rs: 11.00 /kg as per SSR 2014-15
b Rate of Apoxy paint Rs: 1070.00 /10 sqm 33300
c Rate for Jointing of pipes Rs: 10.34 /kg
d Transportation charges Rs: 702.20 /MT

Trench size 0.90 x 1.20 m 0.90 x 1.30 m 1.00 x 1.40 m 1.1 x 1.6m 1.2 x 1.7m 1.3 x 1.8m 1.4 x 1.9m 1.50 x 2.0m

Pipe dia in mm = 80 mm 100 mm 125 mm 150 mm 200 mm 250 mm 300 mm 350 mm 400 mm 450 mm 500 mm 600 mm 700 mm 800 mm 900 mm 1000 mm 1100 mm 1200 mm 1300 mm 1400 mm 1500 mm 1600 mm 1800 mm 1800 mm
Thickness in mm 14 mm 14 mm 14 mm 14 mm 14 mm 14 mm 14 mm 14 mm 14 mm 14 mm 14 mm 14 mm 14 mm 14 mm 14 mm 14 mm 14 mm 14 mm 14 mm 14 mm 14 mm 14 mm 14 mm 25 mm
Pressure rating (m)

1 Wt of pipe 32.455 39.360 47.991 56.623 73.886 91.149 108.412 125.675 142.938 160.201 177.464 211.990 246.516 281.042 315.569 350.095 384.621 419.147 453.673 488.199 522.725 557.251 626.304 1125.181
2 Wastage (5%) 1.62 1.97 2.40 2.83 3.69 4.56 5.42 6.28 7.15 8.01 8.87 10.60 12.33 14.05 15.78 17.50 19.23 20.96 22.68 24.41 26.14 27.86 31.32 56.26
Total weight 34.07 41.33 50.39 59.45 77.58 95.71 113.83 131.96 150.09 168.21 186.33 222.59 258.85 295.09 331.35 367.59 403.85 440.11 476.35 512.61 548.87 585.11 657.62 1181.44

A) Materials component
1 Cost of pipe per RMT 1379.84 1673.87 2040.80 2407.73 3141.99 3876.26 4610.12 5344.38 6078.65 6812.51 7546.37 9014.90 10483.43 11951.15 13419.68 14887.40 16355.93 17824.46 19292.18 20760.71 22229.24 23696.96 26633.61 47848.32

2 Cost of specials (1.50% of basic cost) 20.70 25.11 30.61 36.12 47.13 58.14 69.15 80.17 91.18 102.19 113.20 135.22 157.25 179.27 201.30 223.31 245.34 267.37 289.38 311.41 333.44 355.45 399.50 717.72

3 Transportation charges, loading, 23.92 29.02 35.38 41.75 54.48 67.21 79.93 92.66 105.39 118.12 130.84 156.30 181.76 207.21 232.67 258.12 283.58 309.05 334.49 359.95 385.42 410.86 461.78 829.61
unloading and stacking
1424.50 1728.00 2106.80 2485.60 3243.60 4001.60 4759.20 5517.20 6275.20 7032.80 7790.40 9306.40 ### ### ### ### ### 18400.90 ### ### ### 24463.30 27494.90 49395.60

B) Labour component
4 fabrication 374.77 454.63 554.29 653.95 853.38 1052.81 1252.13 1451.56 1650.99 1850.31 2049.63 2448.49 2847.35 3245.99 3644.85 4043.49 4442.35 4841.21 5239.85 5638.71 6037.57 6436.21 7233.82 12995.84

5 Epoxy paint Out side 63.20 76.64 93.45 110.26 143.87 177.49 211.10 244.72 278.33 311.95 345.56 412.79 480.02 547.25 614.48 681.71 748.94 816.17 883.40 950.63 1017.86 1085.09 1219.55 1226.95

6 Epoxy paint Inside 53.78 67.23 84.04 100.85 134.46 168.08 201.69 235.31 268.92 302.54 336.15 403.38 470.61 537.84 605.07 672.30 739.53 806.76 873.99 941.22 1008.45 1075.68 1210.14 1210.14

8 Jointing of pipes (Rs:10.34 / kg) 352.28 427.35 521.03 614.71 802.18 989.64 1177.00 1364.47 1551.93 1739.29 802.00 987.00 1246.00 1475.00 1788.00 2002.00 2069.00 2138.00 2209.00 2425.00 2488.00 2552.00 2891.00 2891.00

844.00 1025.80 1252.80 1479.70 1933.80 2388.00 2841.90 3296.00 3750.10 4204.00 3533.30 4251.60 5043.90 5806.00 6652.40 7399.50 7999.80 8602.10 9206.20 9955.50 ### 11148.90 12554.50 18323.90
Total 2268.50 2753.80 3359.60 3965.30 5177.40 6389.60 7601.10 8813.20 ### ### ### ### ### ### ### ### ### 27003.00 ### ### ### 35612.20 40049.40 67719.50
Contractor Profit @13.615% 317.59 385.53 470.34 555.14 724.84 894.54 1064.15 1233.85 1403.54 1573.15 1585.32 1898.12 2221.28 2540.10 2870.85 3187.56 3483.86 3780.42 4077.12 4394.26 4689.99 4985.71 5606.92 9480.73
Final Rate 2586.09 3139.33 3829.94 4520.44 5902.24 7284.14 8665.25 ### ### ### ### ### ### ### ### ### ### 30783.42 ### ### ### 40597.91 45656.32 77200.23
DATA BASED ON 2015-16 AS PER COMMON SSR

1 Earth work excavation in all soils upto SDR except hard rock
requiring blasting for 'MS 'pipes and refilling with excavated soils
including laying jointing testing of pipe line including cost of
materialsm CED and other taxes, etc complete

Cost of steel plate per MT Rs: ### including all taxes 33300 feb
a Fabrication charges Rs: 11.00 /kg as per SSR 2015-16
b Rate of Apoxy paint Rs: 1070.00 /10 sqm 33300
c Rate for Jointing of pipes Rs: 10.34 /kg
d Transportation charges Rs: 702.20 /MT

Trench size 0.90 x 1.20 m 0.90 x 1.30 m 1.00 x 1.40 m 1.1 x 1.6m 1.2 x 1.7m 1.3 x 1.8m 1.4 x 1.9m 1.50 x 2.0m

Pipe dia in mm = 80 mm 100 mm 125 mm 150 mm 200 mm 250 mm 300 mm 350 mm 400 mm 450 mm 500 mm 600 mm 700 mm 800 mm 900 mm 1000 mm 1100 mm 1200 mm 1300 mm 1400 mm 1500 mm 1600 mm 1800 mm 1800 mm
Thickness in mm 12 mm 12 mm 12 mm 12 mm 12 mm 12 mm 12 mm 12 mm 12 mm 12 mm 12 mm 12 mm 12 mm 12 mm 12 mm 12 mm 12 mm 12 mm 12 mm 12 mm 12 mm 12 mm 12 mm 25 mm
Pressure rating (m)

1 Wt of pipe 27.226 33.145 40.544 47.942 62.739 77.536 92.333 107.130 121.926 136.723 151.520 181.114 210.708 240.302 269.895 299.489 329.083 358.677 388.271 417.864 447.458 477.052 536.240 1125.181
2 Wastage (5%) 1.36 1.66 2.03 2.40 3.14 3.88 4.62 5.36 6.10 6.84 7.58 9.06 10.54 12.02 13.49 14.97 16.45 17.93 19.41 20.89 22.37 23.85 26.81 56.26
Total weight 28.59 34.81 42.57 50.34 65.88 81.42 96.95 112.49 128.03 143.56 159.10 190.17 221.25 252.32 283.39 314.46 345.53 376.61 407.68 438.75 469.83 500.90 563.05 1181.44

A) Materials component
1 Cost of pipe per RMT 1172.19 1427.21 1745.37 2063.94 2701.08 3338.22 3974.95 4612.09 5249.23 5885.96 6523.10 7796.97 9071.25 10345.12 11618.99 12892.86 14166.73 15441.01 16714.88 17988.75 19263.03 20536.90 23085.05 48439.04

2 Cost of specials (1.50% of basic cost) 17.58 21.41 26.18 30.96 40.52 50.07 59.62 69.18 78.74 88.29 97.85 116.95 136.07 155.18 174.28 193.39 212.50 231.62 250.72 269.83 288.95 308.05 346.28 726.59

3 Transportation charges, loading, 20.08 24.44 29.89 35.35 46.26 57.17 68.08 78.99 89.90 100.81 111.72 133.54 155.36 177.18 199.00 220.81 242.63 264.46 286.27 308.09 329.91 351.73 395.37 829.61
unloading and stacking
1209.80 1473.10 1801.40 2130.20 2787.90 3445.50 4102.60 4760.30 5417.90 6075.10 6732.70 8047.50 9362.70 ### ### ### ### 15937.10 ### ### ### 21196.70 23826.70 49995.20

B) Labour component
4 fabrication 314.49 382.91 468.27 553.74 724.68 895.62 1066.45 1237.39 1408.33 1579.16 1750.10 2091.87 2433.75 2775.52 3117.29 3459.06 3800.83 4142.71 4484.48 4826.25 5168.13 5509.90 6193.55 12995.84

5 Epoxy paint Out side 61.85 75.30 92.11 108.91 142.53 176.14 209.76 243.37 276.99 310.60 344.22 411.45 478.68 545.91 613.14 680.37 747.60 814.83 882.06 949.29 1016.52 1083.75 1218.21 1226.95

6 Epoxy paint Inside 53.78 67.23 84.04 100.85 134.46 168.08 201.69 235.31 268.92 302.54 336.15 403.38 470.61 537.84 605.07 672.30 739.53 806.76 873.99 941.22 1008.45 1075.68 1210.14 1210.14

8 Jointing of pipes (Rs:10.34 / kg) 295.62 359.94 440.17 520.52 681.20 841.88 1002.46 1163.15 1323.83 1484.41 802.00 987.00 1246.00 1475.00 1788.00 1976.00 2041.00 2106.00 2177.00 2390.00 2450.00 2511.00 2846.00 3449.00

725.70 885.30 1084.50 1284.00 1682.80 2081.70 2480.30 2879.20 3278.00 3676.70 3232.40 3893.70 4629.00 5334.20 6123.50 6787.70 7328.90 7870.30 8417.50 9106.70 9643.10 10180.30 11467.90 18881.90
Total 1935.50 2358.40 2885.90 3414.20 4470.70 5527.20 6582.90 7639.50 8695.90 9751.80 9965.10 ### ### ### ### ### ### 23807.40 ### ### ### 31377.00 35294.60 68877.10
263.52 321.10 392.92 464.84 608.69 752.53 896.26 1040.12 1183.95 1327.71 1356.75 1625.79 1904.97 2179.99 2466.47 2735.91 2988.60 3241.38 3494.89 3767.73 4019.83 4271.98 4805.36 9377.62
2199.02 2679.50 3278.82 3879.04 5079.39 6279.73 7479.16 8679.62 9879.85 11079.51 ### 13566.99 15896.67 18191.69 20582.27 22830.71 24939.40 27048.78 29164.29 31441.13 33544.83 35648.98 40099.96 78254.72
DATA BASED ON 2015-16 AS PER COMMON SSR

1 Earth work excavation in all soils upto SDR except hard rock
requiring blasting for 'MS 'pipes and refilling with excavated soils
including laying jointing testing of pipe line including cost of
materialsm CED and other taxes, etc complete

Cost of steel plate per MT Rs: ### including all taxes 33300 feb
a Fabrication charges Rs: 11.00 /kg as per SSR 2015-16
b Rate of Apoxy paint Rs: 1070.00 /10 sqm 33300
c Rate for Jointing of pipes Rs: 10.34 /kg
d Transportation charges Rs: 702.20 /MT

Trench size 0.90 x 1.20 m 0.90 x 1.30 m 1.00 x 1.40 m 1.1 x 1.6m 1.2 x 1.7m 1.3 x 1.8m 1.4 x 1.9m 1.50 x 2.0m

Pipe dia in mm = 80 mm 100 mm 125 mm 150 mm 200 mm 250 mm 300 mm 350 mm 400 mm 450 mm 500 mm 600 mm 700 mm 800 mm 900 mm 1000 mm 1100 mm 1200 mm 1300 mm 1400 mm 1500 mm 1600 mm 1800 mm
Thickness in mm 10 mm 10 mm 10 mm 10 mm 10 mm 10 mm 10 mm 10 mm 10 mm 10 mm 10 mm 10 mm 10 mm 10 mm 10 mm 10 mm 10 mm 10 mm 10 mm 10 mm 10 mm 10 mm 10 mm
Pressure rating (m)

1 Wt of pipe 22.195 27.128 33.293 39.458 51.789 64.120 76.451 88.781 101.112 113.443 125.774 150.435 175.097 199.758 224.420 249.081 273.743 298.404 323.066 347.727 372.389 397.050 446.373
2 Wastage (5%) 1.11 1.36 1.66 1.97 2.59 3.21 3.82 4.44 5.06 5.67 6.29 7.52 8.75 9.99 11.22 12.45 13.69 14.92 16.15 17.39 18.62 19.85 22.32
Total weight 23.31 28.49 34.95 41.43 54.38 67.33 80.27 93.22 106.17 119.11 132.06 157.96 183.85 209.75 235.64 261.53 287.43 313.32 339.22 365.12 391.01 416.90 468.69

A) Materials component
1 Cost of pipe per RMT 955.71 1168.09 1432.95 1698.63 2229.58 2760.53 3291.07 3822.02 4352.97 4883.51 5414.46 6476.36 7537.85 8599.75 9661.24 10722.73 11784.63 12846.12 13908.02 14969.92 16031.41 17092.90 19216.29

2 Cost of specials (1.50% of basic cost) 14.34 17.52 21.49 25.48 33.44 41.41 49.37 57.33 65.29 73.25 81.22 97.15 113.07 129.00 144.92 160.84 176.77 192.69 208.62 224.55 240.47 256.39 288.24

3 Transportation charges, loading, 16.37 20.01 24.54 29.09 38.19 47.28 56.37 65.46 74.55 83.64 92.73 110.92 129.10 147.29 165.47 183.65 201.83 220.01 238.20 256.39 274.57 292.75 329.11
unloading and stacking
986.40 ### 1479.00 1753.20 2301.20 2849.20 3396.80 3944.80 4492.80 5040.40 5588.40 6684.40 7780.00 8876.00 9971.60 ### ### 13258.80 ### ### ### 17642.00 19833.60

B) Labour component
4 fabrication 256.41 313.39 384.45 455.73 598.18 740.63 882.97 1025.42 1167.87 1310.21 1452.66 1737.56 2022.35 2307.25 2592.04 2876.83 3161.73 3446.52 3731.42 4016.32 4301.11 4585.90 5155.59

5 Epoxy paint Out side 60.51 73.95 90.76 107.57 141.18 174.80 208.41 242.03 275.64 309.26 342.87 410.10 477.33 544.56 611.79 679.02 746.25 813.48 880.71 947.94 1015.17 1082.40 1216.86

6 Epoxy paint Inside 53.78 67.23 84.04 100.85 134.46 168.08 201.69 235.31 268.92 302.54 336.15 403.38 470.61 537.84 605.07 672.30 739.53 806.76 873.99 941.22 1008.45 1075.68 1210.14

8 Jointing of pipes (Rs:10.34 / kg) 241.03 294.59 361.38 428.39 562.29 696.19 829.99 963.89 1097.80 1231.60 802.00 987.00 1246.00 1433.00 1737.00 1921.00 1982.00 2044.00 2107.00 2316.00 2371.00 2427.00 2752.00

611.70 749.10 920.60 1092.50 1436.10 1779.70 2123.00 2466.60 2810.20 3153.60 2933.60 3538.00 4216.20 4822.60 5545.90 6149.10 6629.50 7110.70 7593.10 8221.40 8695.70 9170.90 10334.50
Total ### ### 2399.60 2845.70 3737.30 4628.90 5519.80 6411.40 7303.00 8194.00 8522.00 ### ### ### ### ### ### 20369.50 ### ### ### 26812.90 30168.10
217.58 266.13 326.71 387.44 508.83 630.22 751.52 872.91 994.30 1115.61 1160.27 1391.78 1633.28 1865.06 2112.71 2344.00 2558.63 2773.31 2988.21 3222.98 3436.71 3650.58 4107.39
1815.68 2220.83 2726.31 3233.14 4246.13 5259.12 6271.32 7284.31 8297.30 9309.61 9682.27 11614.18 13629.48 15563.66 17630.21 19560.30 21351.33 23142.81 24936.11 26895.28 28678.81 30463.48 34275.49
DATA BASED ON 2015-16 AS PER COMMON SSR

1 Earth work excavation in all soils upto SDR except hard rock
requiring blasting for 'MS 'pipes and refilling with excavated soils
including laying jointing testing of pipe line including cost of
materialsm CED and other taxes, etc complete

Cost of steel plate per MT Rs: ### including all taxes 33300 feb
a Fabrication charges Rs: 11.00 /kg as per SSR 2015-16
b Rate of Apoxy paint Rs: 1070.00 /10 sqm 33300
c Rate for Jointing of pipes Rs: 10.34 /kg
d Transportation charges Rs: 702.20 /MT

Trench size 0.90 x 1.20 m 0.90 x 1.30 m 1.00 x 1.40 m 1.1 x 1.6m 1.2 x 1.7m 1.3 x 1.8m 1.4 x 1.9m 1.50 x 2.0m

Pipe dia in mm = 80 mm 100 mm 125 mm 150 mm 200 mm 250 mm 300 mm 350 mm 400 mm 450 mm 500 mm 600 mm 700 mm 800 mm 900 mm 1000 mm 1100 mm 1200 mm 1300 mm 1400 mm 1500 mm 1600 mm 1800 mm
Thickness in mm 8 mm 8 mm 8 mm 8 mm 8 mm 8 mm 8 mm 8 mm 8 mm 8 mm 8 mm 8 mm 8 mm 8 mm 8 mm 8 mm 8 mm 8 mm 8 mm 8 mm 8 mm 8 mm 8 mm
Pressure rating (m)

1 Wt of pipe 17.362 21.308 26.240 31.172 41.037 50.901 60.766 70.631 80.495 90.360 100.224 119.954 139.683 159.412 179.141 198.870 218.600 238.329 258.058 277.787 297.516 317.246 356.704
2 Wastage (5%) 0.87 1.07 1.31 1.56 2.05 2.55 3.04 3.53 4.02 4.52 5.01 6.00 6.98 7.97 8.96 9.94 10.93 11.92 12.90 13.89 14.88 15.86 17.84
Total weight 18.23 22.38 27.55 32.73 43.09 53.45 63.81 74.16 84.52 94.88 105.23 125.95 146.66 167.38 188.10 208.81 229.53 250.25 270.96 291.68 312.40 333.11 374.54

A) Materials component
1 Cost of pipe per RMT 747.43 917.58 1129.55 1341.93 1766.69 2191.45 2616.21 3040.56 3465.32 3890.08 4314.43 5163.95 6013.06 6862.58 7712.10 8561.21 9410.73 10260.25 11109.36 11958.88 12808.40 13657.51 15356.14

2 Cost of specials (1.50% of basic cost) 11.21 13.76 16.94 20.13 26.50 32.87 39.24 45.61 51.98 58.35 64.72 77.46 90.20 102.94 115.68 128.42 141.16 153.90 166.64 179.38 192.13 204.86 230.34

3 Transportation charges, loading, 12.80 15.72 19.35 22.98 30.26 37.53 44.81 52.08 59.35 66.62 73.89 88.44 102.98 117.53 132.08 146.63 161.18 175.73 190.27 204.82 219.37 233.91 263.00
unloading and stacking
771.40 947.10 1165.80 1385.00 1823.40 2261.90 2700.30 3138.20 3576.60 4015.10 4453.00 5329.90 6206.20 7083.10 7959.90 8836.30 9713.10 10589.90 ### ### ### 14096.30 15849.50

B) Labour component
4 fabrication 200.53 246.18 303.05 360.03 473.99 587.95 701.91 815.76 929.72 1043.68 1157.53 1385.45 1613.26 1841.18 2069.10 2296.91 2524.83 2752.75 2980.56 3208.48 3436.40 3664.21 4119.94

5 Epoxy paint Out side 59.16 72.61 89.42 106.22 139.84 173.45 207.07 240.68 274.30 307.91 341.53 408.76 475.99 543.22 610.45 677.68 744.91 812.14 879.37 946.60 1013.83 1081.06 1215.52

6 Epoxy paint Inside 53.78 67.23 84.04 100.85 134.46 168.08 201.69 235.31 268.92 302.54 336.15 403.38 470.61 537.84 605.07 672.30 739.53 806.76 873.99 941.22 1008.45 1075.68 1210.14

8 Jointing of pipes (Rs:10.34 / kg) 188.50 231.41 284.87 338.43 445.55 552.67 659.80 766.81 873.94 981.06 783.00 967.00 1221.00 1406.00 1707.00 1889.00 1889.00 1661.00 1909.00 2197.00 2197.00 2197.00 3872.74

501.90 617.40 761.30 905.50 1193.80 1482.10 1770.40 2058.50 2346.80 2635.10 2618.20 3164.50 3780.80 4328.20 4991.60 5535.80 5898.20 6032.60 6642.90 7293.30 7655.60 8017.90 10418.30
Total ### ### 1927.10 2290.50 3017.20 3744.00 4470.70 5196.70 5923.40 6650.20 7071.20 8494.40 9987.00 ### ### ### ### 16622.50 ### ### ### 22114.20 26267.80
173.36 213.01 262.37 311.85 410.79 509.75 608.69 707.53 806.47 905.42 962.74 1156.51 1359.73 1553.65 1763.35 1956.76 2125.48 2263.15 2465.57 2673.50 2842.20 3010.85 3576.36
1446.66 1777.51 2189.47 2602.35 3427.99 4253.75 5079.39 5904.23 6729.87 7555.62 8033.94 9650.91 11346.73 12964.95 14714.85 16328.86 17736.78 18885.65 20574.77 22309.90 23717.70 25125.05 29844.16
DATA BASED ON 2015-16 AS PER COMMON SSR

1 Earth work excavation in all soils upto SDR except hard rock
requiring blasting for 'MS 'pipes and refilling with excavated soils
including laying jointing testing of pipe line including cost of
materialsm CED and other taxes, etc complete

Cost of steel plate per MT Rs: ### including all taxes 33300 feb
a Fabrication charges Rs: 11.00 /kg as per SSR 2015-16
b Rate of Apoxy paint Rs: 1070.00 /10 sqm 33300
c Rate for Jointing of pipes Rs: 10.34 /kg
d Transportation charges Rs: 702.20 /MT

Trench size 0.90 x 1.20 m 0.90 x 1.30 m 1.00 x 1.40 m 1.1 x 1.6m 1.2 x 1.7m 1.3 x 1.8m 1.4 x 1.9m 1.50 x 2.0m 1.6 x 2.1m

Pipe dia in mm = 80 mm 100 mm 125 mm 150 mm 200 mm 250 mm 300 mm 350 mm 400 mm 450 mm 500 mm 600 mm 700 mm 800 mm 900 mm 1000 mm 1000 mm 1100 mm 1200 mm 1300 mm 1400 mm 1500 mm 1600 mm 1800 mm 1800 mm
Thickness in mm 6 mm 6 mm 6 mm 6 mm 6 mm 6 mm 6 mm 6 mm 6 mm 6 mm 6 mm 6 mm 6 mm 6 mm 6 mm 6 mm 6 mm 6 mm 6 mm 6 mm 6 mm 6 mm 6 mm 6 mm 6 mm
Pressure rating (m)

1 Wt of pipe 12.725 15.685 19.384 23.083 30.482 37.880 45.279 52.677 60.075 67.474 74.872 89.669 104.466 119.263 134.060 148.857 148.857 163.654 178.451 193.248 208.044 222.841 237.638 267.232 267.232
2 Wastage (5%) 0.64 0.78 0.97 1.15 1.52 1.89 2.26 2.63 3.00 3.37 3.74 4.48 5.22 5.96 6.70 7.44 7.44 8.18 8.92 9.66 10.40 11.14 11.88 13.36 13.36
Total weight 13.37 16.46 20.35 24.23 32.00 39.77 47.54 55.31 63.08 70.84 78.61 94.15 109.69 125.22 140.76 156.30 156.30 171.83 187.37 202.91 218.44 233.98 249.52 280.59 280.59

A) Materials component
1 Cost of pipe per RMT 548.17 674.86 834.35 993.43 1312.00 1630.57 1949.14 2267.71 2586.28 2904.44 3223.01 3860.15 4497.29 5134.02 5771.16 6408.30 6408.30 7045.03 7682.17 8319.31 8956.04 9593.18 10230.32 11504.19 11504.19

2 Cost of specials (1.50% of basic cost) 8.22 10.12 12.52 14.90 19.68 24.46 29.24 34.02 38.79 43.57 48.35 57.90 67.46 77.01 86.57 96.12 96.12 105.68 115.23 124.79 134.34 143.90 153.45 172.56 172.56

3 Transportation charges, loading, 9.39 11.56 14.29 17.01 22.47 27.93 33.38 38.84 44.29 49.74 55.20 66.11 77.02 87.93 98.84 109.75 109.75 120.66 131.57 142.48 153.39 164.30 175.21 197.03 197.03
unloading and stacking
565.80 696.50 861.20 1025.30 1354.20 1683.00 2011.80 2340.60 2669.40 2997.80 3326.60 3984.20 4641.80 5299.00 5956.60 6614.20 6614.20 7271.40 7929.00 8586.60 9243.80 9901.40 10559.00 11873.80 11873.80

B) Labour component
4 fabrication 147.07 181.06 223.85 266.53 352.00 437.47 522.94 608.41 693.88 779.24 864.71 1035.65 1206.59 1377.42 1548.36 1719.30 1719.30 1890.13 2061.07 2232.01 2402.84 2573.78 2744.72 3086.49 3086.49

5 Epoxy paint Out side 57.82 71.26 88.07 104.88 138.49 172.11 205.72 239.34 272.95 306.57 340.18 407.41 474.64 541.87 609.10 676.33 676.33 743.56 810.79 878.02 945.25 1012.49 1079.72 1214.18 1214.18

6 Epoxy paint Inside 53.78 67.23 84.04 100.85 134.46 168.08 201.69 235.31 268.92 302.54 336.15 403.38 470.61 537.84 605.07 672.30 672.30 739.53 806.76 873.99 941.22 1008.45 1075.68 1210.14 1210.14

8 Jointing of pipes (Rs:10.34 / kg) 138.25 170.20 210.42 250.54 330.88 411.22 491.56 571.91 652.25 732.49 812.83 973.51 1134.19 1294.77 1455.46 1616.14 1616.14 1776.72 1937.41 2098.09 2258.67 2419.35 2580.04 2901.30 2901.30

396.90 489.70 606.30 722.80 955.80 1188.80 1421.90 1654.90 1888.00 2120.80 2353.80 2819.90 3286.00 3751.90 4217.90 4684.00 4684.00 5149.90 5616.00 6082.10 6547.90 7014.00 7480.10 8412.10 8412.10
Total 962.70 1186.20 1467.50 1748.10 2310.00 2871.80 3433.70 3995.50 4557.40 5118.60 5680.40 6804.10 7927.80 9050.90 ### ### 11298.20 ### 13545.00 ### ### ### 18039.10 20285.90 20285.90
Add Contractor
131.07 161.50 199.80 238.00 314.51 391.00 467.50 543.99 620.49 696.90 773.39 926.38 1079.37 1232.28 1385.26 1538.25 1538.25 1691.16 1844.15 1997.14 2150.04 2303.03 2456.02 2761.93 2761.93
Profit@13.615%
Total Cost 1093.77 1347.70 1667.30 1986.10 2624.51 3262.80 3901.20 4539.49 5177.89 5815.50 6453.79 7730.48 9007.17 10283.18 11559.76 12836.45 12836.45 14112.46 15389.15 16665.84 17941.74 19218.43 20495.12 23047.83 23047.83
DATA FOR MS PIPE RATES
SSR 2015-16
Sl. No. Description Quantity Unit Rate Per Amount

1 Transportation charges for a lead of 100 KMs

First 5Km's 5 Km's 52.20 5Km's 52.20

From 5km to 30 km 25 Km's 7.80 /Km 195.00

From 30Km's to 100 KM 70 Km's 6.50 /Km 455.00

0 Km's /Km 0.00

0 Km's /Km 0.00

0 Km's /Km 0.00

Total 100 702.20 /1 MT

II Apoxy coating
Painting two coats to New MS Pipes in Anti corrosive Bitumen Paint (Black) Gr - I
including cost and conveyance of all materials to site, incidental, operational and
all labour charges etc., complete for finished item of work.

Cost of Anti corrosive 1.10 liters 569.00 Litre 625.90


Bitumen Paint (Black) Gr - I
Bld.SSR item. No.204

1st Class Painter 0.33 Nos 480.00 each 158.40

2nd Class Painter 0.77 Nos 370.00 each 284.90

0.00 0.00

Sundries
Total r per 10 Sqmt 1070.00 /10Sqm
Cement Mortor lining data for MS pipes
SSR 2009-10
Cement Mortar (1:2)
720.50 Kgs Cost of Cement ### 1 Ton 2593.80
1.00 Cum Cost of sand for mortar 376.71 1 Cum 376.71
1.00 Cum Mixing charges by Machine 34.00 1 Cum 34.00

3004.51

Cement Mortar (1:3)


480.00 Kgs Cost of Cement ### 1 Ton 1728.00
1.00 Cum Cost of sand for mortar 376.71 1 Cum 376.71
1.00 Cum Mixing charges by Machine 34.00 1 Cum 34.00

2138.71
Data
1 Diameter of MS pipe 5000 mm MS rods rate 36000.00 /MT
2 Thickness of MS pipe 10 mm
3 Inlining thickness 12 mm
4 Out Coating thickness 25 mm

Sno Description NO L B D Qty Unit Rate Amount

Cost of CM (1:2) prop.


1 Inlining 12mm thick in CM (1:2) prop 3.142 5.012 0.012 0.189 Cum.
required for 1 Rmt.
2 Add 5% for wastage 0.009 Cum.
0.198 Cum. 3004.51 596.16

Cost of CM (1:3) prop.


3 Outcoating with CM (1:3) prop. 3.142 5.069 0.025 0.398 Cum.
required for 1 Rmt.
4 Add 5% for wastage 0.020 Cum.
0.418 Cum. 2138.71 894.15

Cost of MS rods inclg. Fabrication


5 MS rods 6mm dia at 4 Nos. each side 3.142 5.044 8 ### mtrs
5.58 Kgs/5 36000.00 40.17
Cost of wire mesh Mt
6 Wire mesh of size 50mm x 50mm x
3mm.
Area of mesh: 3.142 5.044 1 15.848 Sqm 77.80 1232.99

Guniting Charges:
7 Inlining: 3.142 5.012 1 15.748 Sqm.
8 Outcoating: 3.142 5.069 1 15.927 Sqm.
31.67 Sqm. 70.00 2217.22

Total: Rate per Rmt length 4981.00


Data
1 Diameter of MS pipe 900 mm
2 Thickness of MS pipe 10 mm
3 Inlining thickness 12 mm
4 Out Coating thickness 25 mm

Sno Description NO L B D Qty Unit Rate Amount

Cost of CM (1:2) prop.


1 Inlining 12mm thick in CM (1:2) prop 3.142 0.912 0.012 0.034 Cum.
required for 1 Rmt.
2 Add 5% for wastage 0.002 Cum.
0.036 Cum. 3004.51 108.48

Cost of CM (1:3) prop.


3 Outcoating with CM (1:3) prop. 3.142 0.969 0.025 0.076 Cum.
required for 1 Rmt.
4 Add 5% for wastage 0.004 Cum.
0.080 Cum. 2138.71 170.93

Cost of MS rods inclg. Fabrication


5 MS rods 6mm dia at 4 Nos. each side 3.142 0.944 8 23.728 mtrs
1.04 Kgs/5 36000.00 7.52
Cost of wire mesh Mt
6 Wire mesh of size 50mm x 50mm x
3mm.
Area of mesh: 3.142 0.944 1 2.966 Sqm 77.80 230.76

Guniting Charges:
7 Inlining: 3.142 0.912 1 2.866 Sqm.
8 Outcoating: 3.142 0.969 1 3.045 Sqm.
5.91 Sqm. 70.00 413.71

Total: Rate per Rmt length 931.00


Data
1 Diameter of MS pipe 800 mm
2 Thickness of MS pipe 10 mm
3 Inlining thickness 12 mm
4 Out Coating thickness 25 mm

Sno Description NO L B D Qty Unit Rate Amount

Cost of CM (1:2) prop.


1 Inlining 12mm thick in CM (1:2) prop 3.142 0.812 0.012 0.031 Cum.
required for 1 Rmt.
2 Add 5% for wastage 0.002 Cum.
0.032 Cum. 3004.51 96.58

Cost of CM (1:3) prop.


3 Outcoating with CM (1:3) prop. 3.142 0.869 0.025 0.068 Cum.
required for 1 Rmt.
4 Add 5% for wastage 0.003 Cum.
0.072 Cum. 2138.71 153.29

Cost of MS rods inclg. Fabrication


5 MS rods 6mm dia at 4 Nos. each side 3.142 0.844 8 21.215 mtrs
0.93 Kgs/5 36000.00 6.72
Cost of wire mesh Mt
6 Wire mesh of size 50mm x 50mm x
3mm.
Area of mesh: 3.142 0.844 1 2.652 Sqm 77.80 206.31

Guniting Charges:
7 Inlining: 3.142 0.812 1 2.551 Sqm.
8 Outcoating: 3.142 0.869 1 2.730 Sqm.
5.28 Sqm. 70.00 369.72

Total: Rate per Rmt length 833.00


Data
1 Diameter of MS pipe 700 mm
2 Thickness of MS pipe 10 mm
3 Inlining thickness 12 mm
4 Out Coating thickness 25 mm

Sno Description NO L B D Qty Unit Rate Amount

Cost of CM (1:2) prop.


1 Inlining 12mm thick in CM (1:2) prop 3.142 0.712 0.012 0.027 Cum.
required for 1 Rmt.
2 Add 5% for wastage 0.001 Cum.
0.028 Cum. 3004.51 84.69

Cost of CM (1:3) prop.


3 Outcoating with CM (1:3) prop. 3.142 0.769 0.025 0.060 Cum.
required for 1 Rmt.
4 Add 5% for wastage 0.003 Cum.
0.063 Cum. 2138.71 135.65

Cost of MS rods inclg. Fabrication


5 MS rods 6mm dia at 4 Nos. each side 3.142 0.744 8 18.701 mtrs
0.82 Kgs/5 36000.00 5.92
Cost of wire mesh Mt
6 Wire mesh of size 50mm x 50mm x
3mm.
Area of mesh: 3.142 0.744 1 2.338 Sqm 77.80 181.87

Guniting Charges:
7 Inlining: 3.142 0.712 1 2.237 Sqm.
8 Outcoating: 3.142 0.769 1 2.416 Sqm.
4.65 Sqm. 70.00 325.73

Total: Rate per Rmt length 734.00


Data
1 Diameter of MS pipe 600 mm
2 Thickness of MS pipe 10 mm
3 Inlining thickness 12 mm
4 Out Coating thickness 25 mm

Sno Description NO L B D Qty Unit Rate Amount

Cost of CM (1:2) prop.


1 Inlining 12mm thick in CM (1:2) prop 3.142 0.612 0.012 0.023 Cum.
required for 1 Rmt.
2 Add 5% for wastage 0.001 Cum.
0.024 Cum. 3004.51 72.80

Cost of CM (1:3) prop.


3 Outcoating with CM (1:3) prop. 3.142 0.669 0.025 0.053 Cum.
required for 1 Rmt.
4 Add 5% for wastage 0.003 Cum.
0.055 Cum. 2138.71 118.01

Cost of MS rods inclg. Fabrication


5 MS rods 6mm dia at 4 Nos. each side 3.142 0.644 8 16.188 mtrs
0.71 Kgs/5 36000.00 5.13
Cost of wire mesh Mt
6 Wire mesh of size 50mm x 50mm x
3mm.
Area of mesh: 3.142 0.644 1 2.023 Sqm 77.80 157.42

Guniting Charges:
7 Inlining: 3.142 0.612 1 1.923 Sqm.
8 Outcoating: 3.142 0.669 1 2.102 Sqm.
4.02 Sqm. 70.00 281.74

Total: Rate per Rmt length 635.00


Data
1 Diameter of MS pipe 500 mm
2 Thickness of MS pipe 10 mm
3 Inlining thickness 12 mm
4 Out Coating thickness 25 mm

Sno Description NO L B D Qty Unit Rate Amount

Cost of CM (1:2) prop.


1 Inlining 12mm thick in CM (1:2) prop 3.142 0.512 0.012 0.019 Cum.
required for 1 Rmt.
2 Add 5% for wastage 0.001 Cum.
0.020 Cum. 3004.51 60.90

Cost of CM (1:3) prop.


3 Outcoating with CM (1:3) prop. 3.142 0.569 0.025 0.045 Cum.
required for 1 Rmt.
4 Add 5% for wastage 0.002 Cum.
0.047 Cum. 2138.71 100.37

Cost of MS rods inclg. Fabrication


5 MS rods 6mm dia at 4 Nos. each side 3.142 0.544 8 13.674 mtrs
0.60 Kgs/5 36000.00 4.33
Cost of wire mesh Mt
6 Wire mesh of size 50mm x 50mm x
3mm.
Area of mesh: 3.142 0.544 1 1.709 Sqm 77.80 132.98

Guniting Charges:
7 Inlining: 3.142 0.512 1 1.609 Sqm.
8 Outcoating: 3.142 0.569 1 1.788 Sqm.
3.40 Sqm. 70.00 237.76

Total: Rate per Rmt length 536.00


Data
1 Diameter of MS pipe 1000 mm
2 Thickness of MS pipe 8 mm
3 Inlining thickness 12 mm
4 Out Coating thickness 25 mm

Sno Description NO L B D Qty Unit Rate Amount

Cost of CM (1:2) prop.


1 Inlining 12mm thick in CM (1:2) prop 3.142 1.012 0.012 0.038 Cum.
required for 1 Rmt.
2 Add 5% for wastage 0.002 Cum.
0.040 Cum. 3004.51 120.37

Cost of CM (1:3) prop.


3 Outcoating with CM (1:3) prop. 3.142 1.065 0.025 0.084 Cum.
required for 1 Rmt.
4 Add 5% for wastage 0.004 Cum.
0.088 Cum. 2138.71 187.86

Cost of MS rods inclg. Fabrication


5 MS rods 6mm dia at 4 Nos. each side 3.142 1.040 8 26.141 mtrs
1.15 Kgs/5 36000.00 8.28
Cost of wire mesh Mt
6 Wire mesh of size 50mm x 50mm x
3mm.
Area of mesh: 3.142 1.040 1 3.268 Sqm 77.80 254.23

Guniting Charges:
7 Inlining: 3.142 1.012 1 3.180 Sqm.
8 Outcoating: 3.142 1.065 1 3.346 Sqm.
6.53 Sqm. 70.00 456.82

Total: Rate per Rmt length 1028.00


Data
1 Diameter of MS pipe 900 mm
2 Thickness of MS pipe 8 mm
3 Inlining thickness 12 mm
4 Out Coating thickness 25 mm

Sno Description NO L B D Qty Unit Rate Amount

Cost of CM (1:2) prop.


1 Inlining 12mm thick in CM (1:2) prop 3.142 0.912 0.012 0.034 Cum.
required for 1 Rmt.
2 Add 5% for wastage 0.002 Cum.
0.036 Cum. 3004.51 108.48

Cost of CM (1:3) prop.


3 Outcoating with CM (1:3) prop. 3.142 0.965 0.025 0.076 Cum.
required for 1 Rmt.
4 Add 5% for wastage 0.004 Cum.
0.080 Cum. 2138.71 170.22

Cost of MS rods inclg. Fabrication


5 MS rods 6mm dia at 4 Nos. each side 3.142 0.940 8 23.628 mtrs
1.04 Kgs/5 36000.00 7.49
Cost of wire mesh Mt
6 Wire mesh of size 50mm x 50mm x
3mm.
Area of mesh: 3.142 0.940 1 2.953 Sqm 77.80 229.78

Guniting Charges:
7 Inlining: 3.142 0.912 1 2.866 Sqm.
8 Outcoating: 3.142 0.965 1 3.032 Sqm.
5.90 Sqm. 70.00 412.83

Total: Rate per Rmt length 929.00


Data
1 Diameter of MS pipe 800 mm
2 Thickness of MS pipe 8 mm
3 Inlining thickness 12 mm
4 Out Coating thickness 25 mm

Sno Description NO L B D Qty Unit Rate Amount

Cost of CM (1:2) prop.


1 Inlining 12mm thick in CM (1:2) prop 3.142 0.812 0.012 0.031 Cum.
required for 1 Rmt.
2 Add 5% for wastage 0.002 Cum.
0.032 Cum. 3004.51 96.58

Cost of CM (1:3) prop.


3 Outcoating with CM (1:3) prop. 3.142 0.865 0.025 0.068 Cum.
required for 1 Rmt.
4 Add 5% for wastage 0.003 Cum.
0.071 Cum. 2138.71 152.58

Cost of MS rods inclg. Fabrication


5 MS rods 6mm dia at 4 Nos. each side 3.142 0.840 8 21.114 mtrs
0.93 Kgs/5 36000.00 6.69
Cost of wire mesh Mt
6 Wire mesh of size 50mm x 50mm x
3mm.
Area of mesh: 3.142 0.840 1 2.639 Sqm 77.80 205.34

Guniting Charges:
7 Inlining: 3.142 0.812 1 2.551 Sqm.
8 Outcoating: 3.142 0.865 1 2.718 Sqm.
5.27 Sqm. 70.00 368.84

Total: Rate per Rmt length 830.00


Data
1 Diameter of MS pipe 700 mm
2 Thickness of MS pipe 8 mm
3 Inlining thickness 12 mm
4 Out Coating thickness 25 mm

Sno Description NO L B D Qty Unit Rate Amount

Cost of CM (1:2) prop.


1 Inlining 12mm thick in CM (1:2) prop 3.142 0.712 0.012 0.027 Cum.
required for 1 Rmt.
2 Add 5% for wastage 0.001 Cum.
0.028 Cum. 3004.51 84.69

Cost of CM (1:3) prop.


3 Outcoating with CM (1:3) prop. 3.142 0.765 0.025 0.060 Cum.
required for 1 Rmt.
4 Add 5% for wastage 0.003 Cum.
0.063 Cum. 2138.71 134.94

Cost of MS rods inclg. Fabrication


5 MS rods 6mm dia at 4 Nos. each side 3.142 0.740 8 18.601 mtrs
0.82 Kgs/5 36000.00 5.89
Cost of wire mesh Mt
6 Wire mesh of size 50mm x 50mm x
3mm.
Area of mesh: 3.142 0.740 1 2.325 Sqm 77.80 180.89

Guniting Charges:
7 Inlining: 3.142 0.712 1 2.237 Sqm.
8 Outcoating: 3.142 0.765 1 2.404 Sqm.
4.64 Sqm. 70.00 324.85

Total: Rate per Rmt length 731.00


Data
1 Diameter of MS pipe 600 mm
2 Thickness of MS pipe 8 mm
3 Inlining thickness 12 mm
4 Out Coating thickness 25 mm

Sno Description NO L B D Qty Unit Rate Amount

Cost of CM (1:2) prop.


1 Inlining 12mm thick in CM (1:2) prop 3.142 0.612 0.012 0.023 Cum.
required for 1 Rmt.
2 Add 5% for wastage 0.001 Cum.
0.024 Cum. 3004.51 72.80

Cost of CM (1:3) prop.


3 Outcoating with CM (1:3) prop. 3.142 0.665 0.025 0.052 Cum.
required for 1 Rmt.
4 Add 5% for wastage 0.003 Cum.
0.055 Cum. 2138.71 117.30

Cost of MS rods inclg. Fabrication


5 MS rods 6mm dia at 4 Nos. each side 3.142 0.640 8 16.087 mtrs
0.71 Kgs/5 36000.00 5.10
Cost of wire mesh Mt
6 Wire mesh of size 50mm x 50mm x
3mm.
Area of mesh: 3.142 0.640 1 2.011 Sqm 77.80 156.45

Guniting Charges:
7 Inlining: 3.142 0.612 1 1.923 Sqm.
8 Outcoating: 3.142 0.665 1 2.089 Sqm.
4.01 Sqm. 70.00 280.86

Total: Rate per Rmt length 633.00


Data
1 Diameter of MS pipe 500 mm
2 Thickness of MS pipe 8 mm
3 Inlining thickness 12 mm
4 Out Coating thickness 25 mm

Sno Description NO L B D Qty Unit Rate Amount

Cost of CM (1:2) prop.


1 Inlining 12mm thick in CM (1:2) prop 3.142 0.512 0.012 0.019 Cum.
required for 1 Rmt.
2 Add 5% for wastage 0.001 Cum.
0.020 Cum. 3004.51 60.90

Cost of CM (1:3) prop.


3 Outcoating with CM (1:3) prop. 3.142 0.565 0.025 0.044 Cum.
required for 1 Rmt.
4 Add 5% for wastage 0.002 Cum.
0.047 Cum. 2138.71 99.66

Cost of MS rods inclg. Fabrication


5 MS rods 6mm dia at 4 Nos. each side 3.142 0.540 8 13.573 mtrs
0.60 Kgs/5 36000.00 4.30
Cost of wire mesh Mt
6 Wire mesh of size 50mm x 50mm x
3mm.
Area of mesh: 3.142 0.540 1 1.697 Sqm 77.80 132.00

Guniting Charges:
7 Inlining: 3.142 0.512 1 1.609 Sqm.
8 Outcoating: 3.142 0.565 1 1.775 Sqm.
3.38 Sqm. 70.00 236.88

Total: Rate per Rmt length 534.00


Data
1 Diameter of MS pipe 1000 mm
2 Thickness of MS pipe 6 mm
3 Inlining thickness 12 mm
4 Out Coating thickness 25 mm

Sno Description NO L B D Qty Unit Rate Amount

Cost of CM (1:2) prop.


1 Inlining 12mm thick in CM (1:2) prop 3.142 1.012 0.012 0.038 Cum.
required for 1 Rmt.
2 Add 5% for wastage 0.002 Cum.
0.040 Cum. 3004.51 120.37

Cost of CM (1:3) prop.


3 Outcoating with CM (1:3) prop. 3.142 1.061 0.025 0.083 Cum.
required for 1 Rmt.
4 Add 5% for wastage 0.004 Cum.
0.088 Cum. 2138.71 187.16

Cost of MS rods inclg. Fabrication


5 MS rods 6mm dia at 4 Nos. each side 3.142 1.036 8 26.041 mtrs
1.15 Kgs/5 36000.00 8.25
Cost of wire mesh Mt
6 Wire mesh of size 50mm x 50mm x
3mm.
Area of mesh: 3.142 1.036 1 3.255 Sqm 77.80 253.25

Guniting Charges:
7 Inlining: 3.142 1.012 1 3.180 Sqm.
8 Outcoating: 3.142 1.061 1 3.334 Sqm.
6.51 Sqm. 70.00 455.94

Total: Rate per Rmt length 1025.00


Data
1 Diameter of MS pipe 900 mm
2 Thickness of MS pipe 6 mm
3 Inlining thickness 12 mm
4 Out Coating thickness 25 mm

Sno Description NO L B D Qty Unit Rate Amount

Cost of CM (1:2) prop.


1 Inlining 12mm thick in CM (1:2) prop 3.142 0.912 0.012 0.034 Cum.
required for 1 Rmt.
2 Add 5% for wastage 0.002 Cum.
0.036 Cum. 3004.51 108.48

Cost of CM (1:3) prop.


3 Outcoating with CM (1:3) prop. 3.142 0.961 0.025 0.075 Cum.
required for 1 Rmt.
4 Add 5% for wastage 0.004 Cum.
0.079 Cum. 2138.71 169.52

Cost of MS rods inclg. Fabrication


5 MS rods 6mm dia at 4 Nos. each side 3.142 0.936 8 23.527 mtrs
1.04 Kgs/5 36000.00 7.45
Cost of wire mesh Mt
6 Wire mesh of size 50mm x 50mm x
3mm.
Area of mesh: 3.142 0.936 1 2.941 Sqm 77.80 228.80

Guniting Charges:
7 Inlining: 3.142 0.912 1 2.866 Sqm.
8 Outcoating: 3.142 0.961 1 3.019 Sqm.
5.88 Sqm. 70.00 411.95

Total: Rate per Rmt length 926.00


Data
1 Diameter of MS pipe 800 mm
2 Thickness of MS pipe 6 mm
3 Inlining thickness 12 mm
4 Out Coating thickness 25 mm

Sno Description NO L B D Qty Unit Rate Amount

Cost of CM (1:2) prop.


1 Inlining 12mm thick in CM (1:2) prop 3.142 0.812 0.012 0.031 Cum.
required for 1 Rmt.
2 Add 5% for wastage 0.002 Cum.
0.032 Cum. 3004.51 96.58

Cost of CM (1:3) prop.


3 Outcoating with CM (1:3) prop. 3.142 0.861 0.025 0.068 Cum.
required for 1 Rmt.
4 Add 5% for wastage 0.003 Cum.
0.071 Cum. 2138.71 151.88

Cost of MS rods inclg. Fabrication


5 MS rods 6mm dia at 4 Nos. each side 3.142 0.836 8 21.014 mtrs
0.92 Kgs/5 36000.00 6.66
Cost of wire mesh Mt
6 Wire mesh of size 50mm x 50mm x
3mm.
Area of mesh: 3.142 0.836 1 2.627 Sqm 77.80 204.36

Guniting Charges:
7 Inlining: 3.142 0.812 1 2.551 Sqm.
8 Outcoating: 3.142 0.861 1 2.705 Sqm.
5.26 Sqm. 70.00 367.96

Total: Rate per Rmt length 827.00


Data
1 Diameter of MS pipe 700 mm
2 Thickness of MS pipe 6 mm
3 Inlining thickness 12 mm
4 Out Coating thickness 25 mm

Sno Description NO L B D Qty Unit Rate Amount

Cost of CM (1:2) prop.


1 Inlining 12mm thick in CM (1:2) prop 3.142 0.712 0.012 0.027 Cum.
required for 1 Rmt.
2 Add 5% for wastage 0.001 Cum.
0.028 Cum. 3004.51 84.69

Cost of CM (1:3) prop.


3 Outcoating with CM (1:3) prop. 3.142 0.761 0.025 0.060 Cum.
required for 1 Rmt.
4 Add 5% for wastage 0.003 Cum.
0.063 Cum. 2138.71 134.24

Cost of MS rods inclg. Fabrication


5 MS rods 6mm dia at 4 Nos. each side 3.142 0.736 8 18.500 mtrs
0.81 Kgs/5 36000.00 5.86
Cost of wire mesh Mt
6 Wire mesh of size 50mm x 50mm x
3mm.
Area of mesh: 3.142 0.736 1 2.313 Sqm 77.80 179.91

Guniting Charges:
7 Inlining: 3.142 0.712 1 2.237 Sqm.
8 Outcoating: 3.142 0.761 1 2.391 Sqm.
4.63 Sqm. 70.00 323.97

Total: Rate per Rmt length 729.00


Data
1 Diameter of MS pipe 600 mm
2 Thickness of MS pipe 6 mm
3 Inlining thickness 12 mm
4 Out Coating thickness 25 mm

Sno Description NO L B D Qty Unit Rate Amount

Cost of CM (1:2) prop.


1 Inlining 12mm thick in CM (1:2) prop 3.142 0.612 0.012 0.023 Cum.
required for 1 Rmt.
2 Add 5% for wastage 0.001 Cum.
0.024 Cum. 3004.51 72.80

Cost of CM (1:3) prop.


3 Outcoating with CM (1:3) prop. 3.142 0.661 0.025 0.052 Cum.
required for 1 Rmt.
4 Add 5% for wastage 0.003 Cum.
0.055 Cum. 2138.71 116.60

Cost of MS rods inclg. Fabrication


5 MS rods 6mm dia at 4 Nos. each side 3.142 0.636 8 15.986 mtrs
0.70 Kgs/5 36000.00 5.06
Cost of wire mesh Mt
6 Wire mesh of size 50mm x 50mm x
3mm.
Area of mesh: 3.142 0.636 1 1.998 Sqm 77.80 155.47

Guniting Charges:
7 Inlining: 3.142 0.612 1 1.923 Sqm.
8 Outcoating: 3.142 0.661 1 2.077 Sqm.
4.00 Sqm. 70.00 279.98

Total: Rate per Rmt length 630.00


Data
1 Diameter of MS pipe 500 mm
2 Thickness of MS pipe 6 mm
3 Inlining thickness 12 mm
4 Out Coating thickness 25 mm

Sno Description NO L B D Qty Unit Rate Amount

Cost of CM (1:2) prop.


1 Inlining 12mm thick in CM (1:2) prop 3.142 0.512 0.012 0.019 Cum.
required for 1 Rmt.
2 Add 5% for wastage 0.001 Cum.
0.020 Cum. 3004.51 60.90

Cost of CM (1:3) prop.


3 Outcoating with CM (1:3) prop. 3.142 0.561 0.025 0.044 Cum.
required for 1 Rmt.
4 Add 5% for wastage 0.002 Cum.
0.046 Cum. 2138.71 98.96

Cost of MS rods inclg. Fabrication


5 MS rods 6mm dia at 4 Nos. each side 3.142 0.536 8 13.473 mtrs
0.59 Kgs/5 36000.00 4.27
Cost of wire mesh Mt
6 Wire mesh of size 50mm x 50mm x
3mm.
Area of mesh: 3.142 0.536 1 1.684 Sqm 77.80 131.02

Guniting Charges:
7 Inlining: 3.142 0.512 1 1.609 Sqm.
8 Outcoating: 3.142 0.561 1 1.763 Sqm.
3.37 Sqm. 70.00 236.00

Total: Rate per Rmt length 531.00


code Dia thick Rate
100010 ### 10 mm 4981.00
90010 900 mm 10 mm 931.00
80010 800 mm 10 mm 833.00
70010 700 mm 10 mm 734.00
60010 600 mm 10 mm 635.00
50010 500 mm 10 mm 536.00
10008 ### 8 mm 1028.00
9008 900 mm 8 mm 929.00
8008 800 mm 8 mm 830.00
7008 700 mm 8 mm 731.00
6008 600 mm 8 mm 633.00
5008 500 mm 8 mm 534.00
10006 ### 6 mm 1025.00
9006 900 mm 6 mm 926.00
8006 800 mm 6 mm 827.00
7006 700 mm 6 mm 729.00
6006 600 mm 6 mm 630.00
5006 500 mm 6 mm 531.00
PVC/HDPE

Trench size 0.70 x 1.00m

Pipe dia in mm = 63 mm 75 mm 90 mm 110 mm 125 mm

DI pipes

Trench size 0.9m x 1.2m 0.9m x 1.3m

Pipe dia in mm = 100 mm 150 mm 200 mm 250 mm

Above 1000mm Dia

Width of the trench Dia of pipe/1000+0.3+0.3

Depth of the trench Dia of pipe/1000+0.6+0.6


0.80 x1.10m 0.90 x 1.20m

140 mm 160 mm 180 mm 200 mm 225 mm 250 mm 280 mm 315 mm

0.9m x 1.3m 1.0 x 1.4m 1.1 x 1.6m 1.2 x 1.7m 1.3x1.8m 1.4x1.9m 1.4x1.9m

300 mm 350 mm 400 mm 450 mm 500 mm 600 mm 700 mm 750 mm 800 mm


1.5x2.0m 1.6x2.1m

900 mm 1000 mm

S-ar putea să vă placă și