Documente Academic
Documente Profesional
Documente Cultură
Institutional Reforms
Challenges/Outstanding Issues
• The contract for the Eshiem – Manso new standard line was signed in February,
2018 subject to three conditions precedent.
• Contract now effective, having met the three (3) conditions precedent:
• Ministry of Finance approval – 18th June, 2018
• PPA approval – 22nd June, 2018
• Value-for-Money (VfM) Audit - March, 2019
• Contract has been re-negotiated in line with recommendations of VfM Audit.
• Contractor already mobilized to site and works expected to be completed by August
2020 (dependent on releases from GoG).
WESTERN RAILWAY LINE
STANDARD GAUGE
• Negotiations concluded with Messrs China Railway Wuju Corporation for the
continuation of the new standard gauge line to Dunkwa.
• Discussion of Workplan ongoing
• Funding arrangements on-going with China Development Bank (CDB) for $1
billion credit facility out of which $500 million has been earmarked for the
Western Line.
• Cabinet and Parliamentary approvals to be obtained on the Loan Agreement.
• Expected commencement date is July 2019
WESTERN RAILWAY LINE
STANDARD GAUGE
Final Engineering Design
• Basic Engineering Parameters:
• Gauge – standard gauge (1,435 mm)
• Maximum design speed – 160km/hr
• Maximum axle load – 25 tons
• Detailed topographical survey from Takoradi to Kumasi has been completed
• Geotechnical & geological surveys between Takoradi – Tarkwa completed
• Alignment and final design completed between Takoradi to Tarkwa
• Detailed Design of Infrastructure (Bridges/Culverts) completed between Takoradi and Manso.
• Bill of Quantities completed up to Manso
EASTERN RAILWAY LINE
REHABILITATION OF NARROW GAUGE
ACCRA – TEMA SERVICE
• Allocation has been made in the 2019 Budget to extend the rehabilitation
works from Nsawam –Koforidua
• Budgetary allocation for 2019 is GHS 8,000,000
• Total Project Cost is estimated at GHS 134,632,915.00
• Works to be undertaken in sections from Station to Station beginning from
Nsawam
EASTERN RAILWAY LINE
REFURBISHMENT OF OLD PASSENGER COACHES
• Consultant has been engaged and assignment officially commenced on 13th March,
2019.
• Inception Report expected from Consultant on 12th April, 2019 for discussion with
stakeholders.
KUMASI – PAGA LINE (CENTRAL
SPINE)
Feasibility Studies
• Proposed route of the line is Kumasi – Aduadin – Ahenema Kokoben – Nerebehi – Mankraso –
Bechem – Duayaw Nkwanta – Sunyani – Chiraa – Techiman – Tamale – Paga)
• Construction works will commence from both terminal points in Ouagadougou and
Mpakadan.
GHANA – BURKINA FASO
INTERCONNECTIVITY PROJECT
PHASES OF PROJECT DEVELOPMENT
• Phase I - Preliminary Alignment Studies
Pre-feasibility Studies - On-going
Full Feasibility Studies - On-going
Preliminary Design (FEED) - On-going
• Phase II - Procurement Process
Expression of Interest (EOI) - Completed
Request for Qualification (RFQ) - Completed
Request for Proposals (RFP)
Negotiations and Contract Signing
GHANA – BURKINA FASO
INTERCONNECTIVITY PROJECT
PHASES OF PROJECT DEVELOPMENT
• Phase III - Analysis of Technical Studies
Review of Design
• Phase IV - Monitoring and Supervision of Construction
Review of Design
Work Supervision
Contract Administration
Budgeting and Project Accounting
Environmental, Social, Health and Safety Management
Control Tests
Training and Transfer of Technology
GHANA – BURKINA FASO
INTERCONNECTIVITY PROJECT
Status of Procurement Process
• Expression of Interest (EOI) stage of the procurement process was completed in May 2018.
• 16 firms submitted EOI proposals which were evaluated leading to the shortlisting of 12 firms
to the Request for Qualification (RFQ) stage.
• Initial deadline for submission of Qualification documents was 25th March, 2019.
• Following requests by bidders, the deadline has been extended by 30 working days ending 6th
May, 2019.
Background
• The development of the Trans-ECOWAS rail project will result in a direct rail connectivity with
the neighbouring States, Togo (on the East) and Ivory Coast (on the West) to boost trade and
facilitate economic growth and development in the West African countries affected by the
project.
• The expansion is in line with the objective of the Economic Community of West African States
(ECOWAS) to link all member states by rail.
• It will also facilitate the achievement of the broad objective of the Union of African Railways to
link member countries by rail.
TRANS-ECOWAS LINE
(AFLAO – ELUBO)
Feasibility Studies
• Greenfield project with an approximate length of 570km.
• Feasibility studies have commenced and Inception Report has been submitted and reviewed on
13th March, 2019 by the following key stakeholders:
• Ministry of Roads & Highways
• Ministry of Transport
• Ministry of Finance
• Ministry of Planning
• National Development Planning Commission
• Ghana Railway Development Authority
• Ghana Railway Company Ltd.
• Department of Urban Roads
APPROXIMATE LENGTH OF RAIL LINE
ON THE MASTER PLAN
Western Line (Takoradi – Kumasi with Branch to Awaso) – 435.4KM
• The Ministry is pursuing associated infrastructure development. In this direction, all railway
stations are to be developed as economic centers.
• Other economic infrastructure would be developed along the railway corridor and at vantage
nodes where the railway lines terminate.
• For example, at Mpakadan, where the on-going Tema – Akosombo rail terminates, Volta Rail
City would be developed.
THE RAILWAY ECONOMIC
CORRIDOR
• Other associated infrastructure which will be developed include the following:
• Hospitality
• Housing
• Free zones / Industrial Parks
• Container Terminals / Inland Ports
• Stations
• Cities
INSTITUTIONAL AND REGULATORY
REFORMS
Review of Railways Act
It is difficult to compare cost per km of railway line construction as several factors may affect the cost of the
construction of the lines. These factors include the following
• The scope of works
• The topography or terrain of the area in which the line is being constructed
• The design speed of the line,- the cost of 120km/h line would be relatively cheaper than a 160km/h line and a
high speed line of about 350km/h
• The type of signaling and communication being deployed ETCS Level 1 or 2
• The type of formation and the finish-i.e. whether the sub base has bituminous surfacing or not. (Blanketing )
• The axle load
• The Cost of Land acquisition and compensation to be paid
• The provision of rolling stock and
• The tractive power to be deployed. i.e. whether electricity or diesel
COMPARISON OF RAILWAY CONTRACTS
IN GHANA
2. Kojokrom -Eshiem Contractor: Amandi Holdings Ltd 5km (Single Scope: Construction of a Standard 4.0 Million
Track) railway Line from Kojokrom to Eshiem
Procurement Method: Single (5km) including
Source
• Station at Eshiem
Funding: GoG • Supply and installation of semi-
automatic level crossings
Type of Contract: • No Signaling
Design and Build • No Rolling Stock
(FIDIC Red Book) Design Criteria
Duration: 12 Months
3. Eshiem-Manso Contractor: Amandi Holdings Ltd 17km Scope: Construction of a railway line 4.4 Million per km
from Eshiem to Manso. Negotiated to 3.97
Procurement Method: Single Million following the
Source • Stations and Halts: Angu and Manso. completion of VfM
One Halt to be located by Employer
Funding: GoG • Supply and Installation of semi-
automatic level crossings.
Type of Contract: • 7m standard gauge formation with
Design and Build Bituminous surfacing on Subbase
(FIDIC Red Book) • No Signaling and Communication
• No Rolling Stock
Design Criteria:
Gauge: Standard Gauge (1435mm)
Speed: 120km/h
Axle Load: 21 tons
Duration: 24 Months
4. Tema-Akosombo Contractor: AFCONS 85km Scope: Construction of Single Standard gauge 4.7 Million
Infrastructure Ltd railway line from Tema-Akosombo (85km)
Less Provisional
Procurement Method: Single • Formation – subbase (blanket) 25cm Class Sums for 50% Land
Source A Acquisition and
• Signaling and Communication (ERTMS Owner’s Engineer
Funding: Indian EXIM ECTS Level I)
Type of Contract: EPC • Railhead with basic facilities at Tema and
(Silver Book) Akosombo 4.2 Million
• 5 Nos Railway Stations
• Railway Maintenance Facility
• Capacity Building
Design Criteria:
Gauge: Standard Gauge (1435mm)
Design Speed: 120km/h
Axle Load: 21 tons
5. Continuation of Western Contractor: 132km Scope: Single standard gauge railway line To be defined with new
Railway Line (Manso- China Wuju Railway Corp Group from Manso (Km 32.6) to Dunkwa (km 165) BOQ
Dunkwa) (CRWJ) with double formation on variant section
3.98 Million for the
Procurement Method: Restrictive • Formation: Single standard gauge with a Whole Line
Tendering (2012) double formation on variant sections with (2012 Tender)
Bituminous Surfacing
Funding: China Development Bank • Renovation of 19 Nos. station buildings
and facilities within the section which
Type of Contract: should be specified by the Employer in
Traditional Design and Build based the approval of Technical Documents
on Employer’s design (FIDIC Red • Supply and installation of Level Crossing
Book) systems
• Supply of Rolling Stock
• Signalling and Communication
Design Criteria:
Gauge: Standard gauge (1435mm)
Design Speed: 120km/h to Tarkwa, 160km/h
after Tarkwa to Dunkwa
Axle Load: 21 tons to Tarkwa.
COMPARISON OF RAILWAY CONTRACTS
IN GHANA
No. Name of Project Contractor and Distance Project Scope and Cost Price/Km
Procurement Method
6. Central Spine (Kumasi- Contractor: China Civil Engineering 96 km Scope: Construction of a Single track 5.2 Million
Bechem section) Construction Corporation (CCECC) Standard Gauge Railway Line from Kumasi
to Bechem Less Provisional Sums
Procurement Method: Single and Cost of Supply of
Source: Formation: Standard Gauge with Bituminous Rolling Stock
Surfacing
Funding: China Development Bank Signaling and Communication- ERTMS 4.6 million
(CDB) ETCS Level 2
Railway Maintenance Workshop at Kumasi
Type of Contract: EPC 5 No Railway Stations
Supply of Rolling Stock for Testing and
(Silver Book) Commissioning
Capacity Building
Design Criteria:
Gauge: Standard Gauge (1435mm)
Design Speed: 160km/h
Axle Load: 25 tons
Signalling and Comm: ECTS Level 2