Documente Academic
Documente Profesional
Documente Cultură
No Fire Fire
Probability of non-ignition=98/100=0.98 Probability of ignition=2/100=0.02
4. Which of the following is not a relevant source of information for RBI assessment?
1. Maintenance costs.
2. Site conditions (e.g., weather, seismic activity)
3. Incident investigation records.
4. Equipment replacement costs.
6. Which of the following statements is correct with regard to equipment items with
risk is defined acceptable by RBI analysis?
1. They normally provide an initial screening with which to rank units for
attention.
2. They are usually numeric and should be comparable.
3. They must be included in the documentation of any RBI evaluation.
4. They are more accurate than the results of qualitative analysis.
8. In RBI, residual factors for loss of containment include all of the following
except:
1. Human errors.
2. Unknown mechanisms of deterioration.
3. Inspection efforts.
4. Secondary effects from nearby units.
14. Which of the following is most important to the success of risk mitigation by
emergency isolation?
1. Operations surveillance.
2. Chain-wheel-operated gate valves.
3. Fire deluge systems.
4. Proper isolation valve locations.
1. Employed only when the risk matrix indicates that the risk is high.
2. Normally employed to determine the effects of the dominant failure
mechanisms for each part of equipment studied.
3. A review of input variables in a risk calculation to determine their influence
on the risk value.
4. based on statistical analysis that uses historical data gathered from a particular
facilities to develop a better understanding of the risk value.
16. The suitability and current condition of equipment within the current operating
envelope we determine the:
1. Consequence of failure.
2. Probability of failure.
3. Total risk.
4. Likelihood of repair.
18. Which of the following statements is correct with regard to the use of RBI for
managing inspection costs.
20. Which of the following may make it impractical to reduce some risks to an
acceptable level?
1. Labor contracts.
2. Cost constraints.
3. Regulatory requirements.
4. Production needs.
21. The risk to a given facility, process unit, system, equipment item, or component
as compared to a similar item is referred to as:-
1. Absolute risk.
2. Relative risk.
3. Qualitative risk.
4. Quantitative risk.
1. Indeterminate event.
2. External event.
3. Unassigned event.
4. Relative risk event.
1. Consequence risks.
2. Inspection risks.
3. Absolute risks.
4. Relative risks.
27. which of the following statements is correct with regard to assumption in an RBI
analysis about the nature and extent of equipment deterioration:
1-
Data to be used.
2-
Plans used by similar facilities.
3-
Person with sole responsibility for preparing the plan
4-
Person who will obtain Jurisdictional authority approval.
29. Which type of RBI typically requires the most detailed information and data for
models?
1- Quantitative.
2- Semi- quantitative.
3- Qualitative.
4- Semi- qualitative.
32. How does an iso-risk line on a risk plot help with inspection planning?
38. When risk acceptability criteria are being established, it is generally recognized
the:
39. Which of the following is a methodology that will increase the precision of an
RBI?
1- Mechanical damage.
2- Brittle fracture.
3- Material thickness.
4- Weld defect.
1- Mitigation risk.
2- Reducing uncertainty.
3- Identifying risk.
4- Identifying deterioration mechanisms.
45. The plan resulting from a detailed description of an RBI assessment for each
piece of equipment will specify:
49. If the scope of an assessment is a multi-unit facility, then the first step in the
application of RBI is:
50. In which of the following situations is there usually a potential for risk
management through inspection?
1- outcome of an event.
2- Failure of pressure equipment.
3- A negative event.
4- Occurrence of a particular set of circumstances.
53. With regard to environmental consequences, the RBI program typically focuses
on:
1- Carcinogenic agents.
2- Chronic risks.
3- Acute risks.
4- Long-term risks.
1- Loss of strength.
2- A small hole.
3- Fatigue damage.
4- Chloride stress corrosion.
56. Which of the following statements about risk mitigation activities is correct?
1- Age of equipment.
2- Failure mode.
3- Deterioration mechanisms.
4- Inspection effectiveness.
59. The time frame over which an RBI analysis is applicable should:
62. With regard to initial assumptions in an RBI analysis, which of the following
statement is correct?
- Consequence and probability estimates that are too conservative can result in
unnecessarily inflated calculated risks.
63. Risk management through inspections may have little or no effect in situation
involving:
64. One of the factors in determining the probability of failure caused by deterioration
is the:
1- An equipment re-rate.
2- Each significant change in risk.
3- Implementation of risk mitigation strategies.
4- A default maximum time period.