NAWARA PIPELINE PROJECT NAWARA PIPELINE PROJECT  

L3 schedule 07/11/2018
Activity ID Activity Name Original Remaining Start Finish Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019
Duration Duration Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
1868d 336d 18-Aug-2014 09-Oct-2019 09-Oct-2019 16:00
NAWARA PIPELINE PROJECT
08:00 A 16:00
MILESTONES 336d 336d 08-Nov-2018 08:00
09-Oct-2019 16:00 09-Oct-2019 16:00

CONTRACTUAL MILESTONES 336d 336d 08-Nov-2018 08:00


09-Oct-2019 16:00 09-Oct-2019 16:00
N.M.CTR.40 Mechanical Completion 0d 0d 08-Nov-2018 08:00
N.M.CTR.50 Ready for Start Up 0d 0d 31-Dec-2018 15:00
N.M.CTR.30 Engineering Completed 0d 0d 31-Jan-2019 14:00
N.M.CTR.61 Anticipated PAC (Gas from LVS2) 0d 0d 15-Mar-2019 13:00
N.M.CTR.60 Provisional Acceptance 0d 0d 10-Sep-2019 08:00
N.M.CTR.70 All final document issued 0d 0d 09-Oct-2019 16:00
N.M.CTR.80 Project Finish 0d 0d 09-Oct-2019 16:00
PROJECT MILESTONES 268d 268d 26-Nov-2018 08:00
21-Aug-2019 08:00 21-Aug-2019 08:00
N.M.PRJ.51 Power supply by Company (SNDP, STEG) 0d 0d 26-Nov-2018 08:00* 26-Nov-2018 08:00*
N.M.PRJ.42 Assumption GTP Ready for Gas 0d 0d 28-Feb-2019 07:00* 28-Feb-2019 07:00*
N.M.PRJ.41 HC availability for PPL commisioning (Assumption) from LVS 2 0d 0d 28-Feb-2019 15:00* 28-Feb-2019 15:00*
N.M.PRJ.52 Power supply by Company (CPF) 0d 0d 01-May-2019 07:00* 01-May-2019 07:00*
N.M.PRJ.40 Assumption of Hydrocarbon supply by Company (CPF for 24" and condensate) 0d 0d 01-Aug-2019 08:00* 01-Aug-2019 08:00*
N.M.PRJ.70 MFL (Intellegent Pig) Completion 0d 0d 21-Aug-2019 08:00* 21-Aug-2019 08:00*
N.M.PRJ.80 Hot functional test Completion with Hydrocarbon 0d 0d 21-Aug-2019 08:00 21-Aug-2019 08:00
Vender Mobilization Millstones (comm'g) 23d 23d 10-Nov-2018 08:00
03-Dec-2018 08:00 03-Dec-2018 08:00
A3330 ROTORK 0d 0d 10-Nov-2018 08:00* 10-Nov-2018 08:00*
A3320 SAMIA ITALIA 0d 0d 30-Nov-2018 08:00* 30-Nov-2018 08:00*
A3340 VALVITALIA 0d 0d 03-Dec-2018 08:00* 03-Dec-2018 08:00*
INTERFACE MILESTONES 232d 232d 31-Dec-2018 15:00
21-Aug-2019 08:00 21-Aug-2019 08:00
CPF (release by OMV) 0d 0d 21-Aug-2019 08:00
21-Aug-2019 08:00 21-Aug-2019 08:00
N.1.2.IM.CPF.50 Gas & Condensate Available at Pig Traps inlets "Assumption" 0d 0d 21-Aug-2019 08:00* 21-Aug-2019 08:00*
GTP (release by OMV) 88d 88d 31-Dec-2018 15:00
29-Mar-2019 17:00 29-Mar-2019 17:00
N.3.2.IM.GTP.40 Utilities available to Pipeline Contractor for precommissionning of the pigging system(FPL) 0d 0d 31-Dec-2018 15:00
N.3.2.IM.GTP.50 GTP ready to export gas and liquid available at Pig Launcher battery limit(FPL) 0d 0d 29-Mar-2019 17:00
FREE ISSUE 371 KM X 24" PIPELINE 1839d 306d 18-Aug-2014 08:00
10-Sep-2019
A 08:00 10-Sep-2019 08:00

SP1 1718d 306d 16-Dec-2014 12:00


10-Sep-2019
A 08:00 10-Sep-2019 08:00
HOME OFFICE 1496d 84d 16-Dec-2014 12:00
30-Jan-2019
A 14:00 30-Jan-2019 14:00
DETAILED ENGINEERING 1496d 84d 16-Dec-2014 12:00
30-Jan-2019
A 14:00 30-Jan-2019 14:00
GENERAL 19d 19d 03-Jan-2019 16:00
30-Jan-2019 14:00 30-Jan-2019 14:00
N.1.1.H.E.GE.30 Submission of All Engineering Documents 0d 0d 03-Jan-2019 16:00
N.1.1.H.E.GE.35 Client Review 6d 6d 08-Jan-2019 12:00
16-Jan-2019 14:00
N.1.1.H.E.GE.40 Comment Implementation & Final Revision 9d 9d 18-Jan-2019 08:00
30-Jan-2019 14:00
MAINTENANCE 1044d 27d 16-Dec-2014 12:00
14-Dec-2018
A 16:00 14-Dec-2018 16:00
N.1.1.H.E.MA.25 O&M Manual 34d 27d 16-Dec-2014 12:00
14-Dec-2018
A 16:00
N.1.1.H.E.MA.40 CMMS 11d 27d 09-Feb-2015 12:00
14-Dec-2018
A 16:00
N.1.1.H.E.MA.35 Maintenance Plan and SPIR 30d 27d 21-Aug-2015 08:00
14-Dec-2018
A 16:00
N.1.1.H.E.MA.45 Submission of MNT Documentation 0d 0d 14-Dec-2018 16:00
AS BUILT 1d 1d 14-Dec-2018 16:00
15-Dec-2018 16:00 15-Dec-2018 16:00
N.1.1.H.E.MA.46 As Built submission 1d 1d 14-Dec-2018 16:00
15-Dec-2018 16:00
CONSTRUCTION 256d 188d 01-Sep-2018 07:00
14-May-2019
A 17:00 14-May-2019 17:00
CONSTRUCTION (Without Temporary Facilities) 256d 188d 01-Sep-2018 07:00
14-May-2019
A 17:00 14-May-2019 17:00
VALVE STATIONS 105d 24d 01-Sep-2018 07:00
01-Dec-2018
A 17:00 01-Dec-2018 17:00
VALVE STATION 1 KP18.234 30d 8d 01-Sep-2018 07:00
15-Nov-2018
A 17:00 15-Nov-2018 17:00
ELECTRICAL & INSTRUMENTATION 30d 8d 01-Sep-2018 07:00
15-Nov-2018
A 17:00 15-Nov-2018 17:00

Doc Number : NAWPPL-BIMS-NPPL-000-PL-SCH-00005 Date Revision Checked Approved


Actual Work Critical Remaining Work summary
Remaining Work Milestone Page 1 of 11
NAWARA PIPELINE PROJECT NAWARA PIPELINE PROJECT  
L3 schedule 07/11/2018
Activity ID Activity Name Original Remaining Start Finish Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019
Duration Duration Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
A66410 Punch List Clearance 30d 8d 01-Sep-2018 07:00
15-Nov-2018
A 17:00
VALVE STATION 2 KP50.301 30d 8d 01-Sep-2018 07:00
15-Nov-2018
A 17:00 15-Nov-2018 17:00
ELECTRICAL & INSTRUMENTATION 30d 8d 01-Sep-2018 07:00
15-Nov-2018
A 17:00 15-Nov-2018 17:00
A66420 Punch List Clearance 30d 8d 01-Sep-2018 07:00
15-Nov-2018
A 17:00
VALVE STATION 3 KP79.586 30d 8d 01-Sep-2018 07:00
15-Nov-2018
A 17:00 15-Nov-2018 17:00
ELECTRICAL & INSTRUMENTATION 30d 8d 01-Sep-2018 07:00
15-Nov-2018
A 17:00 15-Nov-2018 17:00
A66430 Punch List Clearance 30d 8d 01-Sep-2018 07:00
15-Nov-2018
A 17:00
VALVE STATION 4 KP111.447 30d 8d 01-Sep-2018 07:00
15-Nov-2018
A 17:00 15-Nov-2018 17:00
ELECTRICAL & INSTRUMENTATION 30d 8d 01-Sep-2018 07:00
15-Nov-2018
A 17:00 15-Nov-2018 17:00
A66440 Punch List Clearance 30d 8d 01-Sep-2018 07:00
15-Nov-2018
A 17:00
VALVE STATION 5 KP143.427 30d 8d 01-Sep-2018 07:00
15-Nov-2018
A 17:00 15-Nov-2018 17:00
ELECTRICAL & INSTRUMENTATION 30d 8d 01-Sep-2018 07:00
15-Nov-2018
A 17:00 15-Nov-2018 17:00
A66450 Punch List Clearance 30d 8d 01-Sep-2018 07:00
15-Nov-2018
A 17:00
VALVE STATION 6 KP175.572 105d 22d 01-Sep-2018 07:00
29-Nov-2018
A 17:00 29-Nov-2018 17:00
MECHANICAL 2d 2d 28-Nov-2018 07:00
29-Nov-2018 17:00 29-Nov-2018 17:00
A17420 Leak test 2d 2d 28-Nov-2018 07:00*
29-Nov-2018 17:00
ELECTRICAL & INSTRUMENTATION 30d 8d 01-Sep-2018 07:00
15-Nov-2018
A 17:00 15-Nov-2018 17:00
A66460 Punch List Clearance 30d 8d 01-Sep-2018 07:00
15-Nov-2018
A 17:00
INTERMEDIATE PIG TRAPS 30d 8d 01-Sep-2018 07:00
15-Nov-2018
A 17:00 15-Nov-2018 17:00
A66470 Punch List Clearance 30d 8d 01-Sep-2018 07:00
15-Nov-2018
A 17:00
VALVE STATION 7 KP207.856 2d 2d 30-Nov-2018 07:00
01-Dec-2018 17:00 01-Dec-2018 17:00
CIVIL & STRUCTURE 2d 2d 30-Nov-2018 07:00
01-Dec-2018 17:00 01-Dec-2018 17:00
A5600 Road completion - 2d 2d 30-Nov-2018 07:00*
01-Dec-2018 17:00
LAUNCHING FACILITIES @ NAWARA CPF 14d 14d 01-May-2019 07:00
14-May-2019 17:00 14-May-2019 17:00
SUB-CLASS 14d 14d 01-May-2019 07:00
14-May-2019 17:00 14-May-2019 17:00
DIVISION 14d 14d 01-May-2019 07:00
14-May-2019 17:00 14-May-2019 17:00
SUB-DIVISION 14d 14d 01-May-2019 07:00
14-May-2019 17:00 14-May-2019 17:00
TELECOMMUNICATIONS 14d 14d 01-May-2019 07:00
14-May-2019 17:00 14-May-2019 17:00
N.1.1.C.LF.TL.10 Telecommunication & Security System completion 14d 14d 01-May-2019 07:00*
14-May-2019 17:00
A68830 Control building ready by others 0d 0d 01-May-2019 07:00* 01-May-2019 07:00*
RECEIVING FACILITIES @ GABES GTP 76d 8d 01-Sep-2018 07:00
15-Nov-2018
A 17:00 15-Nov-2018 17:00
SUB-CLASS 76d 8d 01-Sep-2018 07:00
15-Nov-2018
A 17:00 15-Nov-2018 17:00
DIVISION 76d 8d 01-Sep-2018 07:00
15-Nov-2018
A 17:00 15-Nov-2018 17:00
SUB-DIVISION 76d 8d 01-Sep-2018 07:00
15-Nov-2018
A 17:00 15-Nov-2018 17:00
CIVIL 76d 8d 01-Sep-2018 07:00
15-Nov-2018
A 17:00 15-Nov-2018 17:00
N.1.1.C.RF.CV.25 Reinstatement 3d 8d 01-Sep-2018 07:00
15-Nov-2018
A 17:00
N.1.1.C.RF.CV.15 Asphalt Road 20d 5d 27-Oct-2018 07:00
15-Nov-2018
A 17:00
Mechanical Completion 26d 26d 08-Nov-2018 07:00
03-Dec-2018 17:00 03-Dec-2018 17:00
A1- LVS1 2d 2d 30-Nov-2018 07:00
01-Dec-2018 17:00 01-Dec-2018 17:00
MC-LVS1-140 Nitrogen System 2d 2d 30-Nov-2018 07:00*
01-Dec-2018 17:00
A2- LVS2 2d 2d 28-Nov-2018 07:00
29-Nov-2018 17:00 29-Nov-2018 17:00
MC-LVS2-40 Nitrogen System 2d 2d 28-Nov-2018 07:00*
29-Nov-2018 17:00
A3- LVS3 2d 2d 26-Nov-2018 07:00
27-Nov-2018 17:00 27-Nov-2018 17:00
MC-LVS3-180 Nitrogen System 2d 2d 26-Nov-2018 07:00*
27-Nov-2018 17:00
A4- LVS4 2d 2d 24-Nov-2018 07:00
25-Nov-2018 17:00 25-Nov-2018 17:00
MC-LVS4-190 Nitrogen System 2d 2d 24-Nov-2018 07:00*
25-Nov-2018 17:00
A5- LVS5 2d 2d 22-Nov-2018 07:00
23-Nov-2018 17:00 23-Nov-2018 17:00
MC-LVS5-180 Nitrogen System 2d 2d 22-Nov-2018 07:00*
23-Nov-2018 17:00
A6- LVS6 9d 9d 20-Nov-2018 07:00
28-Nov-2018 15:00 28-Nov-2018 15:00

Doc Number : NAWPPL-BIMS-NPPL-000-PL-SCH-00005 Date Revision Checked Approved


Actual Work Critical Remaining Work summary
Remaining Work Milestone Page 2 of 11
NAWARA PIPELINE PROJECT NAWARA PIPELINE PROJECT  
L3 schedule 07/11/2018
Activity ID Activity Name Original Remaining Start Finish Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019
Duration Duration Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
MC-LVS6-1160 Nitrogen System 2d 2d 20-Nov-2018 07:00*
21-Nov-2018 17:00
MC-LVS6-1190 Instrument System 0d 0d 28-Nov-2018 15:00
A7- LVS7 2d 19-Nov-2018 17:00 19-Nov-2018 17:00
2d 18-Nov-2018 07:00
MC-LVS7-940 Nitrogen System 2d 2d 18-Nov-2018 07:00*
19-Nov-2018 17:00
A8- LVS8 2d 17-Nov-2018 17:00 17-Nov-2018 17:00
2d 16-Nov-2018 07:00
MC-LVS8-720 Nitrogen System 2d 2d 16-Nov-2018 07:00*
17-Nov-2018 17:00
A9- LVS9 2d 15-Nov-2018 17:00 15-Nov-2018 17:00
2d 14-Nov-2018 07:00
MC-LVS9-500 Nitrogen System 2d 2d 14-Nov-2018 07:00*
15-Nov-2018 17:00
A10- LVS10 2d 13-Nov-2018 17:0013-Nov-2018 17:00
2d 12-Nov-2018 07:00
MC-LVS10-280 Nitrogen System 2d 2d 12-Nov-2018 07:00*
13-Nov-2018 17:00
A11- LVS11 2d 11-Nov-2018 17:0011-Nov-2018 17:00
2d 10-Nov-2018 07:00
MC-LVS11-60 Nitrogen System 2d 2d 10-Nov-2018 07:00*
11-Nov-2018 17:00
A12- LVS12 2d 2d 08-Nov-2018 07:00 09-Nov-2018 17:00
09-Nov-2018 17:00
MC-LVS12-60 Nitrogen System 2d 2d 08-Nov-2018 07:00*
09-Nov-2018 17:00
A0- CPF 3d 3d 01-Dec-2018 07:00
03-Dec-2018 17:00 03-Dec-2018 17:00
MC-CPF-320 Instrument System 1d 1d 01-Dec-2018 07:00*
01-Dec-2018 15:00
MC-CPF-290 Nitrogen System 2d 2d 02-Dec-2018 07:00*
03-Dec-2018 17:00
A14- GTP Receiver 13d 20-Nov-2018 15:00 20-Nov-2018 15:00
13d 08-Nov-2018 07:00
MC-GTPR-920 Nitrogen System 2d 2d 08-Nov-2018 07:00*
09-Nov-2018 17:00
MC-GTPR-950 Instrument System 1d 1d 20-Nov-2018 07:00*
20-Nov-2018 15:00
PRECOMMISIONNING 12d 12d 21-Nov-2018 15:00
03-Dec-2018 13:00 03-Dec-2018 13:00
A6 - LVS6 3d 3d 28-Nov-2018 15:00
01-Dec-2018 13:00 01-Dec-2018 13:00
PRECOM-LVS6-16 Instrument System 2d 2d 28-Nov-2018 15:00
30-Nov-2018 15:00
PRECOM-LVS6-26 Precomm'g completion - A6 (LVS6) 1d 1d 30-Nov-2018 15:00
01-Dec-2018 13:00
A0 -CPF 1d 1d 02-Dec-2018 15:00
03-Dec-2018 13:00 03-Dec-2018 13:00
PRECOM-CPF-16 Instrument System 1d 1d 02-Dec-2018 15:00
03-Dec-2018 13:00
PRECOM-CPF-255 Precomm'g completion - A0 (CPF) 0d 0d 03-Dec-2018 13:00
A14 -GTP R 10d 10d 21-Nov-2018 15:00
01-Dec-2018 15:00 01-Dec-2018 15:00
PRECOM-GTP-33 Instrument System 10d 10d 21-Nov-2018 15:00
01-Dec-2018 15:00
PRECOM-GTP-26 Precomm'g completion - A14 (GTP R) 0d 0d 01-Dec-2018 15:00
COMMISSIONNING, START UP & OPERATIONS READINESS 309d 306d 04-Nov-2018 14:00
10-Sep-2019
A 08:00 10-Sep-2019 08:00
24" PIPELINE (without HC) 265d 262d 04-Nov-2018 14:00
27-Jul-2019
A 17:00 27-Jul-2019 17:00
GTP CB 0d 0d 08-Nov-2018 07:00 08-Nov-2018 07:00
08-Nov-2018 07:00
A66220 RFSU Certificates GTP CB 0d 0d 08-Nov-2018 07:00
GTP PG Rec 0d 0d 08-Nov-2018 07:00 08-Nov-2018 07:00
08-Nov-2018 07:00
A66230 RFSU Certificates GTP PG Rec 0d 0d 08-Nov-2018 07:00
LVS12 0d 0d 08-Nov-2018 07:00 08-Nov-2018 07:00
08-Nov-2018 07:00
A66250 RFSU Certificates LVS12 0d 0d 08-Nov-2018 07:00
LVS11 0d 0d 08-Nov-2018 07:00 08-Nov-2018 07:00
08-Nov-2018 07:00
A67160 RFSU Certificates LVS11 0d 0d 08-Nov-2018 07:00
LVS10 0d 0d 08-Nov-2018 07:00 08-Nov-2018 07:00
08-Nov-2018 07:00
A67300 RFSU Certificates LVS10 0d 0d 08-Nov-2018 07:00
LVS09 0d 0d 08-Nov-2018 11:00 08-Nov-2018 11:00
08-Nov-2018 11:00
A67440 RFSU Certificates LVS09 0d 0d 08-Nov-2018 11:00
LVS08 15d 12d 05-Nov-2018 13:00
17-Nov-2018
A 13:00 17-Nov-2018 13:00
A67550 Telecom Equipment Power up 2d 0d 05-Nov-2018 13:00
08-Nov-2018
A 07:00
A67560 RTU commissioning 1d 1d 08-Nov-2018 15:00
09-Nov-2018 13:00
A67570 E&I commissioning 3d 3d 09-Nov-2018 13:00*
11-Nov-2018 17:00
A67580 RFSU Certificates LVS08 0d 0d 17-Nov-2018 13:00

Doc Number : NAWPPL-BIMS-NPPL-000-PL-SCH-00005 Date Revision Checked Approved


Actual Work Critical Remaining Work summary
Remaining Work Milestone Page 3 of 11
NAWARA PIPELINE PROJECT NAWARA PIPELINE PROJECT  
L3 schedule 07/11/2018
Activity ID Activity Name Original Remaining Start Finish Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019
Duration Duration Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
Telecom and Security Comm 4d 1d 05-Nov-2018 13:00
08-Nov-2018
A 08-Nov-2018 15:00
15:00
Telecom syst 2d 0d 05-Nov-2018 13:00
08-Nov-2018
A 08-Nov-2018 07:00
07:00
A67590 SDH 2d 0d 05-Nov-2018 13:00
08-Nov-2018
A 07:00
A67600 LAN/WAN 2d 0d 05-Nov-2018 13:00
08-Nov-2018
A 07:00
A67610 SOEM/NMS 2d 0d 05-Nov-2018 13:00
08-Nov-2018
A 07:00
A67620 IPBX 2d 0d 05-Nov-2018 13:00
08-Nov-2018
A 07:00
A67630 TAS 2d 0d 05-Nov-2018 13:00
08-Nov-2018
A 07:00
Security System 4d 1d 05-Nov-2018 13:00
08-Nov-2018
A 08-Nov-2018 15:00
15:00
A67640 ACS 2d 0d 05-Nov-2018 13:00
08-Nov-2018
A 07:00
A67650 IDS / CCTV Integration 1d 1d 08-Nov-2018 07:00
08-Nov-2018 15:00
LVS07 17d 21-Nov-2018 13:00 21-Nov-2018 13:00
17d 08-Nov-2018 07:00
A67680 Distribution board 1d 1d 08-Nov-2018 07:00
08-Nov-2018 15:00
A67690 Telecom Equipment Power up 2d 2d 08-Nov-2018 15:00*
10-Nov-2018 11:00
A67700 RTU commissioning 1d 1d 12-Nov-2018 15:00
13-Nov-2018 13:00
A67710 E&I commissioning 3d 3d 13-Nov-2018 13:00*
15-Nov-2018 17:00
A67720 RFSU Certificates LVS07 0d 0d 21-Nov-2018 13:00
Telecom and Security Comm 4d 11-Nov-2018 17:0011-Nov-2018 17:00
4d 08-Nov-2018 15:00
Telecom syst 2d 10-Nov-2018 11:0010-Nov-2018 11:00
2d 08-Nov-2018 15:00
A67730 SDH 2d 2d 08-Nov-2018 15:00
10-Nov-2018 11:00
A67740 LAN/WAN 2d 2d 08-Nov-2018 15:00
10-Nov-2018 11:00
A67750 SOEM/NMS 2d 2d 08-Nov-2018 15:00
10-Nov-2018 11:00
A67760 IPBX 2d 2d 08-Nov-2018 15:00
10-Nov-2018 11:00
A67770 TAS 2d 2d 08-Nov-2018 15:00
10-Nov-2018 11:00
Security System 4d 11-Nov-2018 17:0011-Nov-2018 17:00
4d 08-Nov-2018 15:00
A67780 ACS 2d 2d 08-Nov-2018 15:00
10-Nov-2018 11:00
A67790 IDS / CCTV Integration 2d 2d 10-Nov-2018 11:00
11-Nov-2018 17:00
LVS06 20d 20d 11-Nov-2018 09:00
27-Nov-2018 09:00 27-Nov-2018 09:00
A67820 Distribution board 1d 1d 11-Nov-2018 09:00
11-Nov-2018 17:00
A67830 Telecom Equipment Power up 2d 2d 12-Nov-2018 07:00*
13-Nov-2018 13:00
A67840 RTU commissioning 2d 2d 16-Nov-2018 07:00
17-Nov-2018 13:00
A67850 E&I commissioning 5d 5d 17-Nov-2018 13:00*
21-Nov-2018 13:00
A67860 RFSU Certificates LVS06 0d 0d 27-Nov-2018 09:00
Telecom commissioning 4d 15-Nov-2018 09:00 15-Nov-2018 09:00
4d 12-Nov-2018 07:00
Telecom syst 2d 13-Nov-2018 13:0013-Nov-2018 13:00
2d 12-Nov-2018 07:00
A67870 SDH 2d 2d 12-Nov-2018 07:00
13-Nov-2018 13:00
A67880 LAN/WAN 2d 2d 12-Nov-2018 07:00
13-Nov-2018 13:00
A67890 SOEM/NMS 2d 2d 12-Nov-2018 07:00
13-Nov-2018 13:00
A67900 IPBX 2d 2d 12-Nov-2018 07:00
13-Nov-2018 13:00
A67910 TAS 2d 2d 12-Nov-2018 07:00
13-Nov-2018 13:00
Security System 4d 15-Nov-2018 09:00 15-Nov-2018 09:00
4d 12-Nov-2018 07:00
A67920 ACS 2d 2d 12-Nov-2018 07:00
13-Nov-2018 13:00
A67930 IDS / CCTV Integration 2d 2d 13-Nov-2018 13:00
15-Nov-2018 09:00
LVS05 21d 21d 14-Nov-2018 11:00
01-Dec-2018 09:00 01-Dec-2018 09:00
A67960 Distribution board 1d 1d 14-Nov-2018 11:00
15-Nov-2018 09:00
A67970 Telecom Equipment Power up 2d 2d 15-Nov-2018 09:00*
16-Nov-2018 15:00
A67980 RTU commissioning 1d 1d 22-Nov-2018 11:00
23-Nov-2018 09:00
A67990 E&I commissioning 3d 3d 23-Nov-2018 09:00*
25-Nov-2018 13:00
A68000 RFSU Certificates LVS05 0d 0d 01-Dec-2018 09:00
Telecom commissioning 3d 17-Nov-2018 13:00 17-Nov-2018 13:00
3d 15-Nov-2018 09:00

Doc Number : NAWPPL-BIMS-NPPL-000-PL-SCH-00005 Date Revision Checked Approved


Actual Work Critical Remaining Work summary
Remaining Work Milestone Page 4 of 11
NAWARA PIPELINE PROJECT NAWARA PIPELINE PROJECT  
L3 schedule 07/11/2018
Activity ID Activity Name Original Remaining Start Finish Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019
Duration Duration Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
Telecom syst 2d 16-Nov-2018 15:00 16-Nov-2018 15:00
2d 15-Nov-2018 09:00
A68010 SDH 2d 2d 15-Nov-2018 09:00
16-Nov-2018 15:00
A68020 LAN/WAN 2d 2d 15-Nov-2018 09:00
16-Nov-2018 15:00
A68030 SOEM/NMS 2d 2d 15-Nov-2018 09:00
16-Nov-2018 15:00
A68040 IPBX 2d 2d 15-Nov-2018 09:00
16-Nov-2018 15:00
A68050 TAS 2d 2d 15-Nov-2018 09:00
16-Nov-2018 15:00
Security System 3d 17-Nov-2018 13:00 17-Nov-2018 13:00
3d 15-Nov-2018 09:00
A68060 ACS 2d 2d 15-Nov-2018 09:00
16-Nov-2018 15:00
A68070 IDS / CCTV Integration 1d 1d 16-Nov-2018 15:00
17-Nov-2018 13:00
LVS04 23d 23d 16-Nov-2018 15:00
05-Dec-2018 09:00 05-Dec-2018 09:00
A68100 Distribution board 1d 1d 16-Nov-2018 15:00
17-Nov-2018 13:00
A68110 Telecom Equipment Power up 2d 2d 17-Nov-2018 13:00*
19-Nov-2018 09:00
A68120 RTU commissioning 1d 1d 25-Nov-2018 13:00
26-Nov-2018 11:00
A68130 E&I commissioning 4d 4d 26-Nov-2018 11:00*
29-Nov-2018 13:00
A68140 RFSU Certificates LVS04 0d 0d 05-Dec-2018 09:00
Telecom commissioning 4d 20-Nov-2018 15:00 20-Nov-2018 15:00
4d 17-Nov-2018 13:00
Telecom syst 2d 19-Nov-2018 09:00 19-Nov-2018 09:00
2d 17-Nov-2018 13:00
A68150 SDH 2d 2d 17-Nov-2018 13:00
19-Nov-2018 09:00
A68160 LAN/WAN 2d 2d 17-Nov-2018 13:00
19-Nov-2018 09:00
A68170 SOEM/NMS 2d 2d 17-Nov-2018 13:00
19-Nov-2018 09:00
A68180 IPBX 2d 2d 17-Nov-2018 13:00
19-Nov-2018 09:00
A68190 TAS 2d 2d 17-Nov-2018 13:00
19-Nov-2018 09:00
Security System 4d 20-Nov-2018 15:00 20-Nov-2018 15:00
4d 17-Nov-2018 13:00
A68200 ACS 2d 2d 17-Nov-2018 13:00
19-Nov-2018 09:00
A68210 IDS / CCTV Integration 2d 2d 19-Nov-2018 09:00
20-Nov-2018 15:00
LVS03 43d 39d 04-Nov-2018 14:00
09-Dec-2018
A 09:00 09-Dec-2018 09:00
A68230 50% Charge State 4d 0d 04-Nov-2018 14:00
08-Nov-2018
A 07:00
A68240 Distribution board 1d 1d 20-Nov-2018 07:00
20-Nov-2018 15:00
A68250 Telecom Equipment Power up 2d 2d 20-Nov-2018 15:00*
22-Nov-2018 11:00
A68260 RTU commissioning 1d 1d 29-Nov-2018 13:00
30-Nov-2018 11:00
A68270 E&I commissioning 4d 4d 30-Nov-2018 11:00*
03-Dec-2018 13:00
A68280 RFSU Certificates LVS03 0d 0d 09-Dec-2018 09:00
Telecom commissioning 3d 3d 20-Nov-2018 15:00
23-Nov-2018 09:00 23-Nov-2018 09:00
Telecom syst 2d 2d 20-Nov-2018 15:00
22-Nov-2018 11:00 22-Nov-2018 11:00
A68290 SDH 2d 2d 20-Nov-2018 15:00
22-Nov-2018 11:00
A68300 LAN/WAN 2d 2d 20-Nov-2018 15:00
22-Nov-2018 11:00
A68310 SOEM/NMS 2d 2d 20-Nov-2018 15:00
22-Nov-2018 11:00
A68320 IPBX 2d 2d 20-Nov-2018 15:00
22-Nov-2018 11:00
A68330 TAS 2d 2d 20-Nov-2018 15:00
22-Nov-2018 11:00
Security System 3d 3d 20-Nov-2018 15:00
23-Nov-2018 09:00 23-Nov-2018 09:00
A68340 ACS 2d 2d 20-Nov-2018 15:00
22-Nov-2018 11:00
A68350 IDS / CCTV Integration 1d 1d 22-Nov-2018 11:00
23-Nov-2018 09:00
LVS02 46d 44d 06-Nov-2018 15:00
13-Dec-2018
A 09:00 13-Dec-2018 09:00
A68370 50% Charge State 4d 0d 06-Nov-2018 15:00
08-Nov-2018
A 07:00
A68380 Distribution board 1d 1d 23-Nov-2018 09:00
23-Nov-2018 17:00
A68390 Telecom Equipment Power up 2d 2d 24-Nov-2018 07:00*
25-Nov-2018 13:00
A68400 RTU commissioning 1d 1d 03-Dec-2018 13:00
04-Dec-2018 11:00
A68410 E&I commissioning 4d 4d 04-Dec-2018 11:00*
07-Dec-2018 13:00
A68420 RFSU Certificates LVS02 0d 0d 13-Dec-2018 09:00

Doc Number : NAWPPL-BIMS-NPPL-000-PL-SCH-00005 Date Revision Checked Approved


Actual Work Critical Remaining Work summary
Remaining Work Milestone Page 5 of 11
NAWARA PIPELINE PROJECT NAWARA PIPELINE PROJECT  
L3 schedule 07/11/2018
Activity ID Activity Name Original Remaining Start Finish Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019
Duration Duration Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
Telecom commissioning 3d 3d 24-Nov-2018 07:00
26-Nov-2018 11:00 26-Nov-2018 11:00
Telecom syst 2d 2d 24-Nov-2018 07:00
25-Nov-2018 13:00 25-Nov-2018 13:00
A68430 SDH 2d 2d 24-Nov-2018 07:00
25-Nov-2018 13:00
A68440 LAN/WAN 2d 2d 24-Nov-2018 07:00
25-Nov-2018 13:00
A68450 SOEM/NMS 2d 2d 24-Nov-2018 07:00
25-Nov-2018 13:00
A68460 IPBX 2d 2d 24-Nov-2018 07:00
25-Nov-2018 13:00
A68470 TAS 2d 2d 24-Nov-2018 07:00
25-Nov-2018 13:00
Security System 3d 3d 24-Nov-2018 07:00
26-Nov-2018 11:00 26-Nov-2018 11:00
A68480 ACS 2d 2d 24-Nov-2018 07:00
25-Nov-2018 13:00
A68490 IDS / CCTV Integration 1d 1d 25-Nov-2018 13:00*
26-Nov-2018 11:00
LVS01 91d 91d 06-Nov-2018 07:00
06-Feb-2019
A 17:00 06-Feb-2019 17:00
A68510 50% Charge State 4d 4d 06-Nov-2018 07:00
11-Nov-2018
A 09:00
A68520 Distribution board 1d 1d 26-Nov-2018 11:00*
27-Nov-2018 09:00
A68530 Telecom Equipment Power up 2d 2d 27-Nov-2018 09:00*
28-Nov-2018 15:00
A68540 RTU commissioning 1d 1d 07-Dec-2018 13:00
08-Dec-2018 11:00
A68550 E&I commissioning 4d 4d 08-Dec-2018 11:00*
11-Dec-2018 13:00
A68560 RFSU Certificates LVS01 Before Modification 0d 0d 17-Dec-2018 09:00
A68740 RFSU Certificates LVS01 Affter Modificatio 52d 52d 17-Dec-2018 09:00*
06-Feb-2019 17:00
Telecom commissioning 3d 3d 27-Nov-2018 09:00
29-Nov-2018 13:00 29-Nov-2018 13:00
Telecom syst 2d 2d 27-Nov-2018 09:00
28-Nov-2018 15:00 28-Nov-2018 15:00
A68570 SDH 2d 2d 27-Nov-2018 09:00
28-Nov-2018 15:00
A68580 LAN/WAN 2d 2d 27-Nov-2018 09:00
28-Nov-2018 15:00
A68590 SOEM/NMS 2d 2d 27-Nov-2018 09:00
28-Nov-2018 15:00
A68600 IPBX 2d 2d 27-Nov-2018 09:00
28-Nov-2018 15:00
A68610 TAS 2d 2d 27-Nov-2018 09:00
28-Nov-2018 15:00
Security System 3d 3d 27-Nov-2018 09:00
29-Nov-2018 13:00 29-Nov-2018 13:00
A68620 ACS 2d 2d 27-Nov-2018 09:00
28-Nov-2018 15:00
A68630 IDS / CCTV Integration 1d 1d 28-Nov-2018 15:00
29-Nov-2018 13:00
CPF PGL 10d 10d 20-Jul-2019 07:00
27-Jul-2019 17:00 27-Jul-2019 17:00
A65820 Power up 3d 3d 20-Jul-2019 07:00
22-Jul-2019 11:00
A65910 RTU commissioning 1d 1d 24-Jul-2019 15:00
25-Jul-2019 13:00
A65900 E&I commissioning 3d 3d 25-Jul-2019 13:00
27-Jul-2019 17:00
A66390 RFSU Certificates CPF PGL 0d 0d 27-Jul-2019 17:00
Telecom commissioning 3d 3d 22-Jul-2019 11:00
24-Jul-2019 15:00 24-Jul-2019 15:00
Telecom syst 1d 1d 22-Jul-2019 11:00
23-Jul-2019 09:00 23-Jul-2019 09:00
A65830 SDH 1d 1d 22-Jul-2019 11:00
23-Jul-2019 09:00
A65840 LAN/WAN 1d 1d 22-Jul-2019 11:00
23-Jul-2019 09:00
A65850 SOEM/NMS 1d 1d 22-Jul-2019 11:00
23-Jul-2019 09:00
A65860 IPBX 1d 1d 22-Jul-2019 11:00
23-Jul-2019 09:00
A65870 TAS 1d 1d 22-Jul-2019 11:00
23-Jul-2019 09:00
Security System 3d 3d 22-Jul-2019 11:00
24-Jul-2019 15:00 24-Jul-2019 15:00
A65890 ACS 1d 1d 22-Jul-2019 11:00
23-Jul-2019 09:00
A65880 IDS / CCTV Integration 2d 2d 23-Jul-2019 09:00
24-Jul-2019 15:00
24" PIPELINE (with HC) 193d 193d 28-Feb-2019 15:00
10-Sep-2019 08:00 10-Sep-2019 08:00
A66210 Gas in from LVS 2 1d 1d 28-Feb-2019 15:00
01-Mar-2019 13:00
A17330 Perform for 24" Pipeline with HC for Adam 14d 14d 01-Mar-2019 13:00
15-Mar-2019 13:00
A68840 Perform for Exportline with GTP Gas 0d 0d 30-Mar-2019 07:00 30-Mar-2019 07:00
A68820 Perform for 24" Pipeline with HC for CPF Gas 20d 20d 21-Aug-2019 08:00
10-Sep-2019 08:00
CP Commissioning 10d 17-Nov-2018 17:00 17-Nov-2018 17:00
10d 08-Nov-2018 07:00

Doc Number : NAWPPL-BIMS-NPPL-000-PL-SCH-00005 Date Revision Checked Approved


Actual Work Critical Remaining Work summary
Remaining Work Milestone Page 6 of 11
NAWARA PIPELINE PROJECT NAWARA PIPELINE PROJECT  
L3 schedule 07/11/2018
Activity ID Activity Name Original Remaining Start Finish Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019
Duration Duration Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
N.1.1.CM.PL.70 Energization of LVS - TR Test 10d 10d 08-Nov-2018 07:00*
17-Nov-2018 17:00
N.1.1.CM.PL.80 Ground_bed Test 10d 10d 08-Nov-2018 07:00*
17-Nov-2018 17:00
N.1.1.CM.PL.90 Commissioning Test Line 10d 10d 08-Nov-2018 07:00*
17-Nov-2018 17:00
DEMOBILIZATION 0d 0d 27-Jul-2019 17:00
27-Jul-2019 17:00 27-Jul-2019 17:00
N.1.1.C.TF.CC.DM.10 Demobilization 0d 0d 27-Jul-2019 17:00
SP2 650d 262d 18-Aug-2014 08:00
27-Jul-2019
A 17:00 27-Jul-2019 17:00
PROJECT MANAGEMENT 650d 262d 18-Aug-2014 08:00
27-Jul-2019
A 17:00 27-Jul-2019 17:00
N.1.2.PM.MM.10 Project management 650d 262d 18-Aug-2014 08:00
27-Jul-2019
A 17:00
10 KM X 6" CONDENSATE PIPELINE 1807d 274d 18-Aug-2014 08:00
09-Aug-2019
A 08:00 09-Aug-2019 08:00

SP1 424d 274d 14-May-2018 00:00


09-Aug-2019
A 08:00 09-Aug-2019 08:00
HOME OFFICE 37d 37d 08-Nov-2018 07:00
14-Dec-2018 17:00 14-Dec-2018 17:00
DETAILED ENGINEERING 37d 37d 08-Nov-2018 07:00
14-Dec-2018 17:00 14-Dec-2018 17:00
AS BUILT 37d 37d 08-Nov-2018 07:00
14-Dec-2018 17:00 14-Dec-2018 17:00
N.2.1.H.E.PL.31 As Built submission 37d 37d 08-Nov-2018 07:00
14-Dec-2018 17:00
CONSTRUCTION 404d 254d 14-May-2018 00:00
19-Jul-2019
A 17:00 19-Jul-2019 17:00
CONSTRUCTION (Without Temporary Facilities) 404d 254d 14-May-2018 00:00
19-Jul-2019
A 17:00 19-Jul-2019 17:00
LAUNCHING FACILITIES 6" @ NAWARA CPF 404d 254d 14-May-2018 00:00
19-Jul-2019
A 17:00 19-Jul-2019 17:00
SUB-CLASS 404d 254d 14-May-2018 00:00
19-Jul-2019
A 17:00 19-Jul-2019 17:00
DIVISION 404d 254d 14-May-2018 00:00
19-Jul-2019
A 17:00 19-Jul-2019 17:00
SUB-DIVISION 404d 254d 14-May-2018 00:00
19-Jul-2019
A 17:00 19-Jul-2019 17:00
CIVIL 1d 1d 01-Sep-2018 07:00
08-Nov-2018
A 08-Nov-2018 15:00
15:00
A68730 Punch List Clerance 1d 1d 01-Sep-2018 07:00
08-Nov-2018
A 15:00
MECHANICAL 1d 1d 01-Sep-2018 18:00
08-Nov-2018
A 08-Nov-2018 15:00
15:00
A68750 Punch List Clerance 1d 1d 01-Sep-2018 18:00
08-Nov-2018
A 15:00
ELECTRICAL & INSTRUMENTATION 131d 1d 14-May-2018 00:00
08-Nov-2018
A 08-Nov-2018 15:00
15:00
N.2.1.C.LF.EI.15 Instruments & Electrical connection 8d 0d 14-May-2018 00:00
08-Nov-2018
A 07:00
A68760 Punch List Clerance 1d 1d 01-Sep-2018 18:00
08-Nov-2018
A 15:00
TELECOMMUNICATION 273d 254d 01-Sep-2018 18:00
19-Jul-2019
A 17:00 19-Jul-2019 17:00
A68770 Punch List Clerance 1d 1d 01-Sep-2018 18:00
08-Nov-2018
A 15:00
N.2.1.C.LF.TL.10 Telecommunication & Security System Installation Works "including CB activities by others" 80d 80d 01-May-2019 07:00
19-Jul-2019 17:00
RECEIVING FACILITIES 6" @ TRAPSA 1d 1d 01-Sep-2018 18:00
08-Nov-2018
A 08-Nov-2018 15:00
15:00
SUB-CLASS 1d 1d 01-Sep-2018 18:00
08-Nov-2018
A 08-Nov-2018 15:00
15:00
DIVISION 1d 1d 01-Sep-2018 18:00
08-Nov-2018
A 08-Nov-2018 15:00
15:00
SUB-DIVISION 1d 1d 01-Sep-2018 18:00
08-Nov-2018
A 08-Nov-2018 15:00
15:00
CIVIL 1d 1d 01-Sep-2018 18:00
08-Nov-2018
A 08-Nov-2018 15:00
15:00
A68780 Punch List Clerance 1d 1d 01-Sep-2018 18:00
08-Nov-2018
A 15:00
MECHANICAL 1d 1d 01-Sep-2018 18:00
08-Nov-2018
A 08-Nov-2018 15:00
15:00
A68790 Punch List Clerance 1d 1d 01-Sep-2018 18:00
08-Nov-2018
A 15:00
ELECTRICAL & INSTRUMENTATION 1d 1d 01-Sep-2018 18:00
08-Nov-2018
A 08-Nov-2018 15:00
15:00
A68800 Punch List Clerance 1d 1d 01-Sep-2018 18:00
08-Nov-2018
A 15:00
TELECOMMUNICATION 1d 1d 01-Sep-2018 18:00
08-Nov-2018
A 08-Nov-2018 15:00
15:00
A68810 Punch List Clerance 1d 1d 01-Sep-2018 18:00
08-Nov-2018
A 15:00
Mechanical Completion 30d 30d 08-Nov-2018 07:00
07-Dec-2018 17:00 07-Dec-2018 17:00
A0- CPF 28d 28d 08-Nov-2018 07:00
05-Dec-2018 17:00 05-Dec-2018 17:00
MC-CPF-530 Instrument System 0d 0d 08-Nov-2018 07:00
MC-CPF-560 Valve Actuator System/SDV 0d 0d 08-Nov-2018 07:00
MC-CPF-500 Nitrogen System 2d 2d 04-Dec-2018 07:00*
05-Dec-2018 17:00
A13- TRAPSA 2d 2d 06-Dec-2018 07:00
07-Dec-2018 17:00 07-Dec-2018 17:00
MC-TRAPSA-710 Nitrogen System 2d 2d 06-Dec-2018 07:00*
07-Dec-2018 17:00

Doc Number : NAWPPL-BIMS-NPPL-000-PL-SCH-00005 Date Revision Checked Approved


Actual Work Critical Remaining Work summary
Remaining Work Milestone Page 7 of 11
NAWARA PIPELINE PROJECT NAWARA PIPELINE PROJECT  
L3 schedule 07/11/2018
Activity ID Activity Name Original Remaining Start Finish Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019
Duration Duration Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
PRECOMMISIONNING 1d 1d 08-Nov-2018 07:00 08-Nov-2018 17:00
08-Nov-2018 17:00
A0 -CPF 1d 1d 08-Nov-2018 07:00 08-Nov-2018 17:00
08-Nov-2018 17:00
PRECOM-CPF-35 Valve Actuator System/SDV * 1d 1d 08-Nov-2018 07:00
08-Nov-2018 17:00
PRECOM-CPF-42 Precomm'g completion - A0 (CPF) 0d 0d 08-Nov-2018 17:00
PRECOM-CPF-32 Instrument System 0d 0d 08-Nov-2018 17:00
COMMISSIONNING, START UP & OPERATIONS READINESS 274d 274d 08-Nov-2018 07:00
09-Aug-2019 08:00 09-Aug-2019 08:00
PIPELINE 6" (CONDENSATE) (without HC) 266d 266d 08-Nov-2018 07:00
31-Jul-2019 17:00 31-Jul-2019 17:00
TRAPSA 266d 266d 08-Nov-2018 07:00
31-Jul-2019 17:00 31-Jul-2019 17:00
A68680 Full Discharge State 5d 5d 08-Nov-2018 07:00*
11-Nov-2018 17:00
A68690 50% Charge State 4d 4d 11-Nov-2018 09:00
14-Nov-2018 11:00
A68700 Distribution board 5d 5d 25-Jan-2019 11:00
29-Jan-2019 11:00
A65950 Telecom Equipment Power up 2d 2d 29-Jan-2019 11:00
31-Jan-2019 11:00
A66040 RTU commissioning 1d 1d 02-Feb-2019 11:00
03-Feb-2019 11:00
A66030 E&I commissioning 4d 4d 28-Jul-2019 07:00
31-Jul-2019 17:00
A66400 RFSU Certificates TRAPSA 0d 0d 31-Jul-2019 17:00
Telecom commissioning 2d 2d 31-Jan-2019 11:00
02-Feb-2019 11:00 02-Feb-2019 11:00
Telecom syst 1d 1d 31-Jan-2019 11:00
01-Feb-2019 11:00 01-Feb-2019 11:00
A65960 SDH 1d 1d 31-Jan-2019 11:00
01-Feb-2019 11:00
A65970 LAN/WAN 1d 1d 31-Jan-2019 11:00
01-Feb-2019 11:00
A65980 SOEM/NMS 1d 1d 31-Jan-2019 11:00
01-Feb-2019 11:00
A65990 IPBX 1d 1d 31-Jan-2019 11:00
01-Feb-2019 11:00
A66000 TAS 1d 1d 31-Jan-2019 11:00
01-Feb-2019 11:00
Security System 2d 2d 31-Jan-2019 11:00
02-Feb-2019 11:00 02-Feb-2019 11:00
A66020 ACS 1d 1d 31-Jan-2019 11:00
01-Feb-2019 11:00
A66010 IDS / CCTV Integration 1d 1d 01-Feb-2019 11:00
02-Feb-2019 11:00
PIPELINE 6" (CONDENSATE) (with HC) 8d 8d 01-Aug-2019 08:00
09-Aug-2019 08:00 09-Aug-2019 08:00
A17340 Commissioning Condensate 6" with HC 8d 8d 01-Aug-2019 08:00
09-Aug-2019 08:00
DEMOBILIZATION 0d 0d 08-Nov-2018 07:00 08-Nov-2018 07:00
08-Nov-2018 07:00
N.2.1.C.TF.CP.DM.10 Demobilization 0d 0d 08-Nov-2018 07:00
SP2 953d 0d 18-Aug-2014 08:00
08-Nov-2018
A 08-Nov-2018 07:00
07:00
PROJECT MANAGEMENT 953d 0d 18-Aug-2014 08:00
08-Nov-2018
A 08-Nov-2018 07:00
07:00
N.2.2.PM.MM.10 Project management 825d 0d 18-Aug-2014 08:00
08-Nov-2018
A 07:00
FREE ISSUE FINAL PRODUCT LINE 1668d 136d 18-Aug-2014 08:00
23-Mar-2019
A 13:00 23-Mar-2019 13:00

SP1 362d 136d 01-Aug-2018 07:00


23-Mar-2019
A 13:00 23-Mar-2019 13:00
HOME OFFICE 7d 14-Nov-2018 17:00 14-Nov-2018 17:00
7d 08-Nov-2018 07:00
DETAILED ENGINEERING 7d 14-Nov-2018 17:00 14-Nov-2018 17:00
7d 08-Nov-2018 07:00
AS BUILT 7d 14-Nov-2018 17:00 14-Nov-2018 17:00
7d 08-Nov-2018 07:00
N.3.1.H.E.PL.31 As Built submission 7d 7d 08-Nov-2018 07:00
14-Nov-2018 17:00
CONSTRUCTION 251d 30d 01-Aug-2018 07:00
07-Dec-2018
A 17:00 07-Dec-2018 17:00
CONSTRUCTION (Without Temporary Facilities) 251d 30d 01-Aug-2018 07:00
07-Dec-2018
A 17:00 07-Dec-2018 17:00
PIPELINE 10d 3d 18-Oct-2018 07:00
10-Nov-2018
A 17:0010-Nov-2018 17:00
SPREAD 10d 3d 18-Oct-2018 07:00
10-Nov-2018
A 17:0010-Nov-2018 17:00
PROPANE EXPORT PIPELINE 6" 10d 3d 18-Oct-2018 07:00
10-Nov-2018
A 17:0010-Nov-2018 17:00
PROPANE PIPELINE 10d 3d 18-Oct-2018 07:00
10-Nov-2018
A 17:0010-Nov-2018 17:00
PIPELINE WORKS (Propane) 10d 3d 18-Oct-2018 07:00
10-Nov-2018
A 17:0010-Nov-2018 17:00
N.3.1.C.PE.PP.PL.60 Marker Post 10d 3d 18-Oct-2018 07:00
10-Nov-2018
A 17:00
BUTANE EXPORT PIPELINE 4" 10d 3d 18-Oct-2018 07:00
10-Nov-2018
A 17:0010-Nov-2018 17:00
BUTANE PIPELINE 10d 3d 18-Oct-2018 07:00
10-Nov-2018
A 17:0010-Nov-2018 17:00
PIPELINE WORKS (Butane) 10d 3d 18-Oct-2018 07:00
10-Nov-2018
A 17:0010-Nov-2018 17:00

Doc Number : NAWPPL-BIMS-NPPL-000-PL-SCH-00005 Date Revision Checked Approved


Actual Work Critical Remaining Work summary
Remaining Work Milestone Page 8 of 11
NAWARA PIPELINE PROJECT NAWARA PIPELINE PROJECT  
L3 schedule 07/11/2018
Activity ID Activity Name Original Remaining Start Finish Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019
Duration Duration Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
N.3.1.C.BE.BP.PL.60 Marker Post 10d 3d 18-Oct-2018 07:00
10-Nov-2018
A 17:00
BUTANE RECEIVING FACILITIES @ SNDP 237d 30d 01-Aug-2018 07:00
07-Dec-2018
A 17:00 07-Dec-2018 17:00
SUB-CLASS 237d 30d 01-Aug-2018 07:00
07-Dec-2018
A 17:00 07-Dec-2018 17:00
DIVISION 237d 30d 01-Aug-2018 07:00
07-Dec-2018
A 17:00 07-Dec-2018 17:00
SUB-DIVISION 237d 30d 01-Aug-2018 07:00
07-Dec-2018
A 17:00 07-Dec-2018 17:00
CIVIL 237d 11d 01-Aug-2018 07:00
18-Nov-2018
A 17:00 18-Nov-2018 17:00
N.3.1.C.BE.RF.CV.27 Punch List Clearance 30d 0d 01-Aug-2018 07:00
08-Nov-2018
A 07:00
N.3.1.C.BE.RF.CV.10 Asphalt Road 16d 8d 31-Oct-2018 07:00
15-Nov-2018
A 17:00
N.3.1.C.BE.RF.CV.15 Reinstatement 3d 3d 16-Nov-2018 07:00
18-Nov-2018 17:00
MECHANICAL 30d 0d 01-Aug-2018 18:00
08-Nov-2018
A 08-Nov-2018 07:00
07:00
N.3.1.C.BE.RF.MC.13 Punch List Clearance 30d 0d 01-Aug-2018 18:00
08-Nov-2018
A 07:00
ELECTRICAL & INSTRUMENTATION 30d 30d 01-Aug-2018 07:00
07-Dec-2018
A 17:00 07-Dec-2018 17:00
N.3.1.C.BE.RF.EI.21 Punch List Clearance 30d 30d 01-Aug-2018 07:00
07-Dec-2018
A 17:00
TELECOMMUNICATION 30d 0d 01-Aug-2018 07:00
08-Nov-2018
A 08-Nov-2018 07:00
07:00
N.3.1.C.BE.RF.TL.11 Punch List Clearance 30d 0d 01-Aug-2018 07:00
08-Nov-2018
A 07:00
PROPANE RECEIVING FACILITIES @ SNDP 62d 30d 01-Aug-2018 07:00
07-Dec-2018
A 17:00 07-Dec-2018 17:00
SUB-CLASS 62d 30d 01-Aug-2018 07:00
07-Dec-2018
A 17:00 07-Dec-2018 17:00
DIVISION 62d 30d 01-Aug-2018 07:00
07-Dec-2018
A 17:00 07-Dec-2018 17:00
SUB-DIVISION 62d 30d 01-Aug-2018 07:00
07-Dec-2018
A 17:00 07-Dec-2018 17:00
CIVIL 62d 30d 01-Aug-2018 07:00
07-Dec-2018
A 17:00 07-Dec-2018 17:00
A66540 Punch List Clearance 30d 30d 01-Aug-2018 07:00
07-Dec-2018
A 17:00
A13560 Asphalt Road 16d 8d 31-Oct-2018 07:00
15-Nov-2018
A 17:00
A13570 Reinstatement 3d 3d 16-Nov-2018 07:00
18-Nov-2018 17:00
MECHANICAL 30d 0d 01-Aug-2018 07:00
08-Nov-2018
A 08-Nov-2018 07:00
07:00
A66550 Punch List Clearance 30d 0d 01-Aug-2018 07:00
08-Nov-2018
A 07:00
ELECTRICAL & INSTRUMENTATION 30d 30d 01-Aug-2018 07:00
07-Dec-2018
A 17:00 07-Dec-2018 17:00
A66560 Punch List Clearance 30d 30d 01-Aug-2018 07:00
07-Dec-2018
A 17:00
TELECOMMUNICATION 30d 0d 01-Aug-2018 07:00
08-Nov-2018
A 08-Nov-2018 07:00
07:00
A66570 Punch List Clearance 30d 0d 01-Aug-2018 07:00
08-Nov-2018
A 07:00
BUTANE LAUNCHING FACILITIES @ GTP 69d 30d 01-Aug-2018 07:00
07-Dec-2018
A 17:00 07-Dec-2018 17:00
SUB-DIVISION- 69d 30d 01-Aug-2018 07:00
07-Dec-2018
A 17:00 07-Dec-2018 17:00
CIVIL 69d 30d 01-Aug-2018 07:00
07-Dec-2018
A 17:00 07-Dec-2018 17:00
A66580 Punch List Clearance 30d 30d 01-Aug-2018 07:00
07-Dec-2018
A 17:00
A11900 Asphalt Road 20d 5d 27-Oct-2018 07:00
15-Nov-2018
A 17:00
A11910 Reinstatement 10d 10d 16-Nov-2018 07:00
25-Nov-2018 17:00
MECHANICAL 30d 30d 01-Aug-2018 07:00
07-Dec-2018
A 17:00 07-Dec-2018 17:00
A66590 Punch List Clearance 30d 30d 01-Aug-2018 07:00
07-Dec-2018
A 17:00
ELECTRICAL & INSTRUMENTION 30d 30d 01-Aug-2018 07:00
07-Dec-2018
A 17:00 07-Dec-2018 17:00
A66600 Punch List Clearance 30d 30d 01-Aug-2018 07:00
07-Dec-2018
A 17:00
TELECOMMUNICATIONS 30d 30d 01-Aug-2018 07:00
07-Dec-2018
A 17:00 07-Dec-2018 17:00
A66610 Punch List Clearance 30d 30d 01-Aug-2018 07:00
07-Dec-2018
A 17:00
PROPANE LAUNCHING FACILITIES @ GTP 69d 30d 01-Aug-2018 07:00
07-Dec-2018
A 17:00 07-Dec-2018 17:00
SUB-DIVISION- 69d 30d 01-Aug-2018 07:00
07-Dec-2018
A 17:00 07-Dec-2018 17:00
CIVIL 69d 30d 01-Aug-2018 07:00
07-Dec-2018
A 17:00 07-Dec-2018 17:00
A66620 Punch List Clearance 30d 30d 01-Aug-2018 07:00
07-Dec-2018
A 17:00
A12120 Asphalt Road 20d 5d 27-Oct-2018 07:00
15-Nov-2018
A 17:00
A12130 Reinstatement 10d 10d 16-Nov-2018 07:00
25-Nov-2018 17:00
MECHANICAL 30d 30d 01-Aug-2018 07:00
07-Dec-2018
A 17:00 07-Dec-2018 17:00
A66630 Punch List Clearance 30d 30d 01-Aug-2018 07:00
07-Dec-2018
A 17:00

Doc Number : NAWPPL-BIMS-NPPL-000-PL-SCH-00005 Date Revision Checked Approved


Actual Work Critical Remaining Work summary
Remaining Work Milestone Page 9 of 11
NAWARA PIPELINE PROJECT NAWARA PIPELINE PROJECT  
L3 schedule 07/11/2018
Activity ID Activity Name Original Remaining Start Finish Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019
Duration Duration Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
ELECTRICAL & INSTRUMENTION 30d 30d 01-Aug-2018 07:00
07-Dec-2018
A 17:00 07-Dec-2018 17:00
A66640 Punch List Clearance 30d 30d 01-Aug-2018 07:00
07-Dec-2018
A 17:00
TELECOMMUNICATIONS 30d 30d 01-Aug-2018 07:00
07-Dec-2018
A 17:00 07-Dec-2018 17:00
A66650 Punch List Clearance 30d 30d 01-Aug-2018 07:00
07-Dec-2018
A 17:00
SALES GAS LAUNCHING FACILITIES @ GTP 69d 30d 01-Aug-2018 07:00
07-Dec-2018
A 17:00 07-Dec-2018 17:00
SUB-DIVISION- 69d 30d 01-Aug-2018 07:00
07-Dec-2018
A 17:00 07-Dec-2018 17:00
CIVIL 69d 30d 01-Aug-2018 07:00
07-Dec-2018
A 17:00 07-Dec-2018 17:00
A66660 Punch List Clearance 30d 30d 01-Aug-2018 07:00
07-Dec-2018
A 17:00
A12330 Asphalt Road 20d 5d 27-Oct-2018 07:00
15-Nov-2018
A 17:00
A12340 Reinstatement 10d 10d 16-Nov-2018 07:00
25-Nov-2018 17:00
MECHANICAL 30d 30d 01-Aug-2018 07:00
07-Dec-2018
A 17:00 07-Dec-2018 17:00
A66670 Punch List Clearance 30d 30d 01-Aug-2018 07:00
07-Dec-2018
A 17:00
ELECTRICAL & INSTRUMENTION 30d 30d 01-Aug-2018 07:00
07-Dec-2018
A 17:00 07-Dec-2018 17:00
A66680 Punch List Clearance 30d 30d 01-Aug-2018 07:00
07-Dec-2018
A 17:00
TELECOMMUNICATIONS 30d 30d 01-Aug-2018 07:00
07-Dec-2018
A 17:00 07-Dec-2018 17:00
A66690 Punch List Clearance 30d 30d 01-Aug-2018 07:00
07-Dec-2018
A 17:00
SALES GAS RECEIVING FACILITIES @ STEG 59d 30d 01-Aug-2018 07:00
07-Dec-2018
A 17:00 07-Dec-2018 17:00
SUB-CLASS 59d 30d 01-Aug-2018 07:00
07-Dec-2018
A 17:00 07-Dec-2018 17:00
DIVISION 59d 30d 01-Aug-2018 07:00
07-Dec-2018
A 17:00 07-Dec-2018 17:00
SUB-DIVISION 59d 30d 01-Aug-2018 07:00
07-Dec-2018
A 17:00 07-Dec-2018 17:00
CIVIL 59d 30d 01-Aug-2018 07:00
07-Dec-2018
A 17:00 07-Dec-2018 17:00
A66700 Punch List Clearance 30d 30d 01-Aug-2018 07:00
07-Dec-2018
A 17:00
N.3.1.C.SG.RF.CV.15 Asphalt Road 25d 8d 22-Oct-2018 07:00
15-Nov-2018
A 17:00
N.3.1.C.SG.RF.CV.20 Reinstatement 6d 6d 10-Nov-2018 07:00
15-Nov-2018 17:00
MECHANICAL 30d 30d 01-Aug-2018 07:00
07-Dec-2018
A 17:00 07-Dec-2018 17:00
A66710 Punch List Clearance 30d 30d 01-Aug-2018 07:00
07-Dec-2018
A 17:00
ELECTRICAL & INSTRUMENTATION 30d 30d 01-Aug-2018 07:00
07-Dec-2018
A 17:00 07-Dec-2018 17:00
A66720 Punch List Clearance 30d 30d 01-Aug-2018 07:00
07-Dec-2018
A 17:00
TELECOMMUNICATION 30d 0d 01-Aug-2018 07:00
08-Nov-2018
A 08-Nov-2018 07:00
07:00
A66730 Punch List Clearance 30d 0d 01-Aug-2018 07:00
08-Nov-2018
A 07:00
Mechanical Completion 8d 15-Nov-2018 17:00 15-Nov-2018 17:00
8d 08-Nov-2018 07:00
A14- GTP L 4d 11-Nov-2018 17:0011-Nov-2018 17:00
4d 08-Nov-2018 07:00
MC-GTP-1160 Instrument System 0d 0d 08-Nov-2018 07:00
MC-GTP-1130 Nitrogen System 2d 2d 10-Nov-2018 07:00*
11-Nov-2018 17:00
A15- SNDP 2d 13-Nov-2018 17:0013-Nov-2018 17:00
2d 12-Nov-2018 07:00
MC-SNDP-1550 Nitrogen System 2d 2d 12-Nov-2018 07:00*
13-Nov-2018 17:00
A16- STEG 2d 15-Nov-2018 17:00 15-Nov-2018 17:00
2d 14-Nov-2018 07:00
MC-STEG-1340 Nitrogen System 2d 2d 14-Nov-2018 07:00*
15-Nov-2018 17:00
PRECOMMISIONNING 24d 24d 08-Nov-2018 17:00
03-Dec-2018 08:00 03-Dec-2018 08:00
A14 GTP L 24d 24d 08-Nov-2018 17:00
03-Dec-2018 08:00 03-Dec-2018 08:00
PRECOM-GTP-16 Instrument System 0d 0d 08-Nov-2018 17:00
PRECOM-GTP-111 Precomm'g completion - A14 (GTP) 0d 0d 03-Dec-2018 08:00
COMMISSIONNING, START UP & OPERATIONS READINESS 136d 136d 08-Nov-2018 07:00
23-Mar-2019 13:00 23-Mar-2019 13:00
FREE ISSUE FINAL PRODUCT LINE (without HC) 36d 36d 26-Nov-2018 08:00
31-Dec-2018 15:00 31-Dec-2018 15:00
GTP PG Launch 29d 29d 03-Dec-2018 08:00
31-Dec-2018 15:00 31-Dec-2018 15:00
A68670 Power up Telecom 2d 2d 03-Dec-2018 08:00*
05-Dec-2018 08:00
A63990 SCADA/RTU 1d 1d 19-Dec-2018 15:00
20-Dec-2018 15:00
A64000 E&I commissioning 4d 4d 20-Dec-2018 15:00*
24-Dec-2018 15:00
A66240 RFSU Certificates GTP PG Launch 0d 0d 31-Dec-2018 15:00

Doc Number : NAWPPL-BIMS-NPPL-000-PL-SCH-00005 Date Revision Checked Approved


Actual Work Critical Remaining Work summary
Remaining Work Milestone Page 10 of 11
NAWARA PIPELINE PROJECT NAWARA PIPELINE PROJECT  
L3 schedule 07/11/2018
Activity ID Activity Name Original Remaining Start Finish Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019
Duration Duration Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
Telecom syst 1d 1d 05-Dec-2018 08:00
06-Dec-2018 08:00 06-Dec-2018 08:00
A63920 SDH 1d 1d 05-Dec-2018 08:00*
06-Dec-2018 08:00
A63930 LAN/WAN 1d 1d 05-Dec-2018 08:00
05-Dec-2018 16:00
A63940 SOEM/NMS 1d 1d 05-Dec-2018 08:00
05-Dec-2018 16:00
A63950 IPBX 1d 1d 05-Dec-2018 08:00
05-Dec-2018 16:00
A63960 TAS 1d 1d 05-Dec-2018 08:00
05-Dec-2018 16:00
Security System 2d 2d 05-Dec-2018 08:00
06-Dec-2018 16:00 06-Dec-2018 16:00
A63980 ACS 1d 1d 05-Dec-2018 08:00
05-Dec-2018 16:00
A63970 IDS / CCTV Integration 1d 1d 05-Dec-2018 16:00
06-Dec-2018 16:00
STEG + BBG 27d 27d 29-Nov-2018 14:00
26-Dec-2018 15:00 26-Dec-2018 15:00
A68710 Distribution board 1d 1d 29-Nov-2018 14:00*
30-Nov-2018 12:00
A65580 Telecom Power up 1d 1d 30-Nov-2018 12:00*
01-Dec-2018 12:00
A65670 RTU commissioning 1d 1d 15-Dec-2018 15:00
16-Dec-2018 15:00
A65660 E&I commissioning 3d 3d 16-Dec-2018 15:00
19-Dec-2018 15:00
A66370 RFSU Certificates STEG + BBG 0d 0d 26-Dec-2018 15:00
Telecom commissioning 2d 2d 01-Dec-2018 12:00
03-Dec-2018 10:00 03-Dec-2018 10:00
Telecom syst 1d 1d 01-Dec-2018 12:00
02-Dec-2018 10:00 02-Dec-2018 10:00
A65590 SDH 1d 1d 01-Dec-2018 12:00
02-Dec-2018 10:00
A65600 LAN/WAN 1d 1d 01-Dec-2018 12:00
02-Dec-2018 10:00
A65610 SOEM/NMS 1d 1d 01-Dec-2018 12:00
02-Dec-2018 10:00
A65620 IPBX 1d 1d 01-Dec-2018 12:00
02-Dec-2018 10:00
A65630 TAS 1d 1d 01-Dec-2018 12:00
02-Dec-2018 10:00
Security System 2d 2d 01-Dec-2018 12:00
03-Dec-2018 10:00 03-Dec-2018 10:00
A65650 ACS 1d 1d 01-Dec-2018 12:00
02-Dec-2018 10:00
A65640 IDS / CCTV Integration 1d 1d 02-Dec-2018 10:00
03-Dec-2018 10:00
SNDP 27d 27d 26-Nov-2018 08:00
22-Dec-2018 15:00 22-Dec-2018 15:00
A68720 Distribution board 1d 1d 26-Nov-2018 08:00*
26-Nov-2018 16:00
A65700 Telcom Power up 2d 2d 26-Nov-2018 16:00
28-Nov-2018 16:00
A65790 RTU commissioning 1d 1d 11-Dec-2018 13:00
12-Dec-2018 13:00
A65780 E&I commissioning 3d 3d 12-Dec-2018 13:00
15-Dec-2018 15:00
A66380 RFSU Certificates SNDP 0d 0d 22-Dec-2018 15:00
Telecom commissioning 2d 2d 28-Nov-2018 16:00
30-Nov-2018 14:00 30-Nov-2018 14:00
Telecom syst 1d 1d 28-Nov-2018 16:00
29-Nov-2018 14:00 29-Nov-2018 14:00
A65710 SDH 1d 1d 28-Nov-2018 16:00
29-Nov-2018 14:00
A65720 LAN/WAN 1d 1d 28-Nov-2018 16:00
29-Nov-2018 14:00
A65730 SOEM/NMS 1d 1d 28-Nov-2018 16:00
29-Nov-2018 14:00
A65740 IPBX 1d 1d 28-Nov-2018 16:00
29-Nov-2018 14:00
A65750 TAS 1d 1d 28-Nov-2018 16:00
29-Nov-2018 14:00
Security System 2d 2d 28-Nov-2018 16:00
30-Nov-2018 14:00 30-Nov-2018 14:00
A65770 ACS 1d 1d 28-Nov-2018 16:00
29-Nov-2018 14:00
A65760 IDS / CCTV Integration 1d 1d 29-Nov-2018 14:00
30-Nov-2018 14:00
FREE ISSUE FINAL PRODUCT LINE (with HC) 8d 8d 15-Mar-2019 13:00
23-Mar-2019 13:00 23-Mar-2019 13:00
A17350 Commissioning Free Issue Final Product Line with HC 8d 8d 15-Mar-2019 13:00
23-Mar-2019 13:00
DEMOBILIZATION 0d 0d 08-Nov-2018 07:00 08-Nov-2018 07:00
08-Nov-2018 07:00
N.3.1.C.TF.CP.DM.10 Demobilization 0d 0d 08-Nov-2018 07:00
SP2 792d 0d 18-Aug-2014 08:00
08-Nov-2018
A 08-Nov-2018 07:00
07:00
PROJECT MANAGEMENT 792d 0d 18-Aug-2014 08:00
08-Nov-2018
A 08-Nov-2018 07:00
07:00
N.3.2.PM.MM.10 Project management 684d 0d 18-Aug-2014 08:00
08-Nov-2018
A 07:00

Doc Number : NAWPPL-BIMS-NPPL-000-PL-SCH-00005 Date Revision Checked Approved


Actual Work Critical Remaining Work summary
Remaining Work Milestone Page 11 of 11