LIST OF SCHEMES REVISION /ENHANCED DISTRICT COUNCIL BAHAWALNAGAR FOR THE YEAR 2017-18

Orignal Wrok Revised Wrok


Sr.No. Original Scheme Original Cost revised Scheme Revised Cost
Order No Order No
(i)    Const: of Metalled Road Basti Muhammad Pur (i)  Const: of Metalled Road Basti Muhammad
Sansaran U/C.21 23,28,29,30,33,34,35,36,37(ADP- 374 1175 Pur Sansaran U/C 23 ADP Phase -I (Revised
1 Phase-I Work No.2) Rs.95000000/- Rs.780000/-) Rs.1,02,80000/-
2/10/2017 29/6/2018

(i.)   Shamshad Bibi Lady Member Rs.500000/- (i)     Shamshad Bibi Lady Member Rs.500000/-
(ii.)   Nasreen Iqbal Lady Member Rs.500000/- (ii)     Nasreen Iqbal Lady Member Rs.500000/-
(iii.)  Rubina Kouser S/o Zulifqar Ali Rs.500000/- (iii)    Rubina Kouser S/o Zulifqar Ali Rs.500000/-
(iv.)  Yasmin Akhtar Lady Member. Rs.500000/- (iv)    Yasmin Akhtar Lady Member. Rs.600000/-
(v.)    Sughran Bibi S/o Bahdar Ali Shah. Rs.500000/- (v)     Sughran Bibi S/o Bahdar Ali Shah. Rs.500000/-
(vi.)  Rubina Bibi W/o Muhammad Iqbal. Rs.500000/- (vi)    Rubina Bibi W/o Muhammad Iqbal. Rs.500000/-
(vii.) Shahida Bibi. Rs.500000/- (vii)  Shahida Bibi. Rs.500000/-
(viii.) Nadia Jawad Wattoo . Rs.500000/- (viii) Nadia Jawad Wattoo. Rs.1000000/-
(ix.)  Akmal Rafiqa Lady Member. Rs.500000/- (ix)    Akmal Rafiqa Lady Member. Rs.500000/-
(x.)  Muhammad Ashfaq Hussain Former Member. 381 1167 (x)     Muhammad Ashfaq Hussain Former
2 Rs.500000/- Rs.500000/-
2/10/2017 25/6/2018 Member.
(xi.)  Humayyon Islam Former Member. Rs.500000/- (xi)    Humayyon Islam Former Member. Rs.500000/-
(xii.) Bilawal Hussain Bajwa Youth Member. Rs.500000/- (xii)  Bilawal Hussain Bajwa Youth Member. Rs.500000/-
(xiii.)  Najma W/o Sarfraz Minority Lady Member. (xiii) Najma W/o Sarfraz Minority Lady Member.
Rs.500000/- Rs.500000/-
(xiv.)  Shamoo Minority Member. Rs.500000/- (xiv) Shamoo Minority Member. Rs.500000/-
(xv.) Kalib Mashie Minority Member. Rs.500000/- (xv)  Kalib Mashie Minority Member. Rs.500000/-
(xvi.) Nadeem Mashie Minority Member. (xvi) Nadeem Mashie Minority Member.
(Work No.10)ADP-Phase-I Rs.500000/- Rs.500000/-
Rs.8000000/- Rs.8600000/-
(i)   Const: of,Drains,Nala Jat, Tuff, Culverts, water (i) Const: of soling, Drains, Nala Jat, Tuff,,
Supply Pipe line, Cattle Pond, Water Diggies, Culverts, water Pipe line, Cattle Pond, Water
Boundary, Janazgah, Musafar Khana Jat, Metalled Rs.1000000/- Diggies,Boundary,Janazg Musafar Khana Jat, Rs.2500000/-
Roads etc in Union Council No. 11. Metalled Roads etc in Union Council No. 11.

969 1162
3 a.        U/C No. 15. Rs.500000/- A U/C No. 15. Rs.2300000/-
26/4/2018 25/6/2018
b.        U/C No.13. Rs.500000/- B U/C No.13. Rs.1500000/-
c.        No.12. Rs.500000/- C U/CNo.12. Rs.1000000/-
26/4/2018 25/6/2018

(ii)   Const: of soling Mouza Dona Qatab Sarhu U/C (ii) Const: of soling Mouza Dona Qatab Sarhu
14 Hasil Sarhu. (Work No.1) Rs.500000/ U/C 14 Hasil Sarhu. Rs.700000/-
-Rs.3000000/- Rs.8000000/
(i)    Const:,Drains,Nala jat Pacca Khal, tuff (i)  Const:,Drains,Nala jat Pacca Khal, tuff
tile,culverts,water supply pipe line, water Diggi, tile,culverts,water supply pipe line, water Diggi,
boundary walls,musfar Khana Jat, metalled road in boundary walls,musfar Khana Jat, metalled road
973 1165 in
4 U/C No.58 . Rs.1000000/- U/C No.58 . Rs.1000000/-
26/4/2018 25/6/218
U/C No.65 . Rs.500000/- U/C No.65 . Rs.1000000/-
U/C No.67. Rs.1000000/- U/C No.67. Rs.1000000/-
ADP Phase-II Work No.5 Rs.2500000/- Rs.3000000/-
(i)   Const: of soling,Drains,Nala Jat, Tuff (i)   Const: of soling,Drains,Nala Jat, Tuff
Tiles,Sewerline,Culverts,water Supply Pipe line, Tiles,Sewerline,Culverts,water Supply Pipe line,
Cattle Pond, Water Diggies, Boundary Cattle Pond, Water Diggies, Boundary
Rs.1000000/- Rs.1000000/-,
Walls,Janazgah,Mussafar Khana Jat, Metalled Roads Walls,Janazgah,Mussafar Khana Jat, Metalled
etc in Union Council No. 10. Roads etc in Union Council No. 10.

(ii)  Const: of Soling Basti Punna to Maddrissa 1048 1173 (ii)  Const: of Soling Basti Punna to Maddrissa
5 26/04/2018 Rs.500000/- Rs.500000/-
Islamia 29/6/2018 Islamia
(iii)  Const: of Pulli Abadi Muhammad Yar Vazirka (iii) Const: of Pull Abadi Muhammad Yar Vazirka.
Rs.400000/- Rs.1100000/-
(iv) Const: of Soling Drains etc Basti Rohana. (iv)  Const: of Soling Drains etc Basti Rohana
(Work No.6) Rs.600000/- Rs.600000/-
Rs.2500000/- Rs.3200000/-
(i) Const: of soling,Drains,Nala Jat, Tuff Tiles, (i)  Const: of soling,Drains,Nala Jat, Tuff Tiles,
Sewerline,Culverts,water Supply Pipe line, Cattle Sewerline,Culverts,water Supply Pipe line, Cattle
Pond, Water Diggies, Boundary,Janazgah,Mussafar Pond, Water Diggies, Boundary
Khana Jat, Metalled Roads etc in Union Council Rs.1000000/- Walls,Janazgah,Mussafar Khana Jat, Metalled Rs.3500000/-
No.130. Roads etc in Union Council No.130 & U/C 131.
975 1180
6
26/4/2018 29/6/2018
(II) Const of Soling Drains Culverts Sewerage (II) Const of Soling Drains Culverts/Bridge
Rs.500000/- Rs.500000/-
Pipeline etc U/C 120. Sewerage Pipeline etc U/C 120.
(III) Const: of Park Chowk Chak No.234/9R. (III) Const: of Park Chowk Chak No.234/9R.
Rs.1000000/- Rs.1000000/-
(Work No.7) Rs.2500000/-
Rs.5000000/-
(i) Const: of soling,Drains,Nala Jat, Tuff, (i)  Const: of soling,Drains,Nala Jat, Tuff
Sewerline,Culverts,water Supply Pipe line, Tiles, Sewerline,Culverts,water Supply Pipe
Cattle Pond, Water Diggies, Boundary line, Cattle Pond, Water Diggies, Boundary
Walls,Janazgah,Mussafar Khana Jat, Metalled Walls,Janazgah,Mussafar Khana Jat,
Roads etc in Union Council No. Metalled Roads etc in Union Council No.
U/C No.6-

U/CNo.6. Rs.500000/- U/C 25 Rs.500000/- Rs.500000/-


977 1149
7 U/C 25 26/4/2018 Rs.500000/ 20/6/2018 Rs.2500000/
(ii  Const: of Soling Chak Mousamwala Rs. 500000/- (ii)  Const: of Soling Chak Mousamwala. Rs. 500000/-
(iii) Const/Repair of Metalled Road U/C Hassan (iii)  Const/Repair of Metalled Road U/C
Wala Basti Dewan Azmat Chishti Rs.700000/- Hassan Wala Basti Dewan Azmat Chishti Rs.700000/-
Rs.700000/-
(iv)  Const: of Soling Mouza Dongianwala U/C (iv)  Const: of Soling Mouza Dongianwala
Mat Wala. (Work No.9) Rs.500000/- U/C Mat Wala. Rs.1000000/-

Rs.2700000/- Rs.5200000/-
(i)  Const/Repair of Metalled Road Ali House (i)  Const/Repair of Metalled Road Ali House and
Khichiwala Rs.500000/- Chak No.235/9R to street Jam-e-Masjid Rs.1500000/-
(ii)                 Const: of Water Diggi & RCC Pipe (ii)  Const: of Water Diggi & RCC Pipe Chak
Chak No.191/7R (East). 979 Rs.600000/- 1181 No.191/7R (East). Rs.600000/-
8
26/4/2018 29/6/2018
(iii)  Construction of Water Diggi & RCC Pipe 12” Dia (iii) Construction of Water Diggi & RCC Pipe 12”
Chak No. 191/7R(East) Work No.11) Rs.1200000/- Dia Chak No. 191/7R(East Rs.1200000/-

Rs.2300000/- Rs.3300000/-
(i)                   Const: of Tuff Tile Street Noman (i)  Const of, Tuff tile street Noman Shahid / Chak
Shahid Khichiwala. Rs.500000/- No.235/9R in front of Jamia Masjid. Rs. 24,55,000/-
(ii)   Const: of Soling Street Ustad Bhola wala (ii) Const: of Soling Street Ustad Bhola wala
Khichiwala 982 Rs.1000000/- 1182 Khichiwala Rs.1000000/-
9
26/42018 29/6/2018
(iii)  Const: of Soling Chak 258/HLADP Phase-II (iii) Const: of Soling Chak 258/HL.ADP Phase-II
Rs.800000/- Rs.800000/-
Work No.14)
Rs.2300000/- Rs.4255000/-
(i)   Providing PVC Pipe U/C No.96 (i) Providing PVC Pipe & Culverts U/C No.96 &
Rs.500000/- U/C/ No.84 Rs.1730000/-
984 1183
10 (ii)   Const: of Water Diggi Chak No.126/6R . (ii) Cons: of Water Diggi/ RCC Pipe 15” Dia Chak
26/4/2018 Rs.1900000/- 29/6/218 Rs.2700000/-
(Work No.16) No.126/6R
Rs.2400000/- Rs.4430000/-
(i)   Const: of Bridge Canal 3/R Near Chak46/3R (i)  Const of Bridge Canal 3/R Near Chak46/3R
Rs.900000/- Rs.1200000/-
(ii)   Const :of Soling Chak No.63/4R Rs.450000/- (ii)  Const: of Soling Chak No.63/4R Rs.450000/-
(iii)   Const: of Soling Chak No.39/3R Rs.150000/- (iii)  Const: of Soling Chak No.39/3R Rs.150000/-
987 1163
11 (iv)   Const: of Soling Chak No.39/3R Rs.400000/- (iv)  Const: of Soling Chak No.39/3R Rs.400000/-
26/4/2018 25/6/2018
(v)   Const of Soling Chak No.44/3R Rs.300000/- (v)   Const of Soling Chak No.44/3R Rs.300000
(vi)  Const: of Soling Basti Fazal Lalika (Bhawan (vi)  Const: of Soling Basti Fazal (BhawanShah)
Shah) (Work No.19) Rs.650000/- Rs.800000/-
Rs.2850000/- Rs.3300000/-
(i)  Const/Repair of Metalled Road Lumbran wali (i)  Const/Repair of Metalled Roads /Culverts
Ghal Bhani Mehranwali. (Phase-1)(Work No.21) 989 Rs.3000000/- 1150 Lumbran wali Ghal Bhani Mehranwali. (Phase-1)
12 Rs.5242000/-
26/4/2018 20/6/2018

(i) Const: of Metalled Road Basti Musla U/C (i)  Const: of Metalled Road Basti Musla U/C
13 Kalyia Shah (Phase-1st).(Work No.22) 990264 Rs.2200000/- 1151206 Kalyia Shah (Phase-1st). Rs.5000000/-

(i)   Const: of Metalled Road Bara Qamer Din 991 1169 (i)  Const: of Metalled Road Bara Qamer Din
14 (Phase-I Work No. 23). Rs.2200000/- (Phase-I). Rs.3000000/-
26/4/2018 25/6/2018
(i)   Const of Metalled Road Tobba Qalandar Shah. (i)  Const/Repair of Metalled Road/Soling/Side
ADP Phase-II(Work No.29 997 1152 Soling Tobba Qalandar Shah .ADP Phase-II)
15 Rs.3000000/- Rs.9000000/-
26/4/2018 20/6/2018

(i)    Const. of Soling Drain, culverts, water supply (i) Const. of Soling Drain, culverts, water supply
pipeline Basti Tobba Allah Yar. Rs.1500000/- pipeline 3”, 4” dia Basti Tobba Allah Yar, Rs.3500000/-
999
16
(ii)   Const: of Soling Drain Khaim Garh (Work 26/04/2018 (ii)                 Const: of Soling in Khaim Garh.
No.31) Rs.1000000/- Rs.1000000/-

Rs.2500000/- Rs.4500000/-
(i)  Const: of Soling Basti Dr. Younas Rs.500000/- (i) Const: of Soling Basti Dr. Younas Rs.500000/-
(ii)  Const: of Soling Basti Borana Rs.400000/- (ii) Const: of Soling Basti Borana Rs.400000/-
1000 1177
17 (iii)  Const: of Soling Basti Faqiranwali. 26/4/2016 29/6/2018 (iii) Const: of Soling Basti Faqiranwali.
(Work No.32) Rs.2000000/- Rs.4100000/-
Rs.2900000/- Rs.5000000/-
(i)  Const: of Soling/Bridge Basti Brigadier Farooq (i)   Const: of Soling/Bridge Basti Brigadier
Sahib. Rs.1000000/- Farooq Sahib. Rs.1500000/-

1004 1153
18
26/4/2018 20/6/2018
(ii) Const/Repair of Metalled Road Chak No.125/6R (ii)   Const/Repair of Metalled Road Chak
Kamukan wali. 1004 Rs.1000000/- 1153 No.125/6R Kamukan wali. Rs.1000000/-
18
26/4/2018 20/6/2018
(iii)  Const/Repair of Metalled Road Head 7/R (Work (iii)  Const/Repair of Metalled Road Head 7/R.
No.36) Rs.1000000 Rs.1000000
Rs.3000000/- Rs.3500000/-
(i)   Const: of Soling Basti Chak 137/6R Rs.350000/- (i)   Const: of Soling Basti Chak 137/6R Rs.350000/-
(ii)   Const: of Soling Chak No.429/(Small) Rs.300000/- (ii)   Const: of Soling Chak No.429/(Small) Rs.300000/-
(iii)  Const: of Soling/ Drains, Boundary Wall Cattle (iii)   Const: of Soling/ Drains, Boundary Wall
Pond, Janazgah.(Izafi Basti Chak No.43/3R. Rs.700000/- Cattle Pond, Janazgah.(Izafi Basti Chak Rs.1650000/-
No.43/3R.
(iv) Const: of Soling Chak No.162/7R to School Rs.500000/- (iv)  Const: of Soling Chak No.162/7R to School. Rs.500000/-
1006 1154
19 (v)  Const: of Soling Chak 163/7R to School (v)   Const: of Soling Chak 163/7R to School.
26/4/2018 Rs.500000/- 20/6/2018 Rs.500000/-
(vi) Const: of Soling Drains/RCC Pipe Collecting Tank (vi)  Const: of Soling Drains/RCC Pipe Collecting
with Machinery etc. Chak No.62/4R Rs.300000/- Tank with Machinery etc. Chak No.62/4R Rs.300000/-
(Work No.38)
Rs.2650000/- Rs.3600000/-
(i)   Const: of Soling Chak No.197/HB Graveyard. (i) Const: of Soling Chak No.197/HB to end of
Rs.2000000/- Graveyard. Rs.3330000/-
1007 1137
20 (ii)   Const: of Bridge Saffon Etc Chak (ii) Const: of Bridge Saffon Etc Chak No.245/HL.
26/4/2018 Rs.850000/- 03/6/2018 Rs.850000/-
No.245/HL( Work No.39)
Rs.2850000/- Rs.4180000/-
(i)   Const of Soling Drain Pull Saim Nala Graveyard 1011 1174 (i)   Const of Soling Drain Pull Saim Nala
21 Hafiz Wala U/C Islampura. (Work No.43) Rs.2100000/- Graveyard Hafiz Wala U/C Islampura. Rs.5000000/-
26/4/2018 29/6/2018
(i)   Const: of Soling U/C Mussa Bhoota. Rs.800000/- (i)  Const: of Soling U/C Mussa Bhoota Rs.800000/-
(ii)  Cons: of Metalled Road Rojhan Wali More to (ii)  Cons: of Metalled Road Rojhan Wali More to
Basti Rojhanwali ADP(Phase –II ) Rs.1000000/- Basti Rojhanwali ADP(Phase-II) Rs.1500000/-

(iii)  Const of Soling Basti Riaz Baitu U/C Muhammad 1015 1164 (iii)  Const of Soling Basti Riaz Baitu U/C
22 Pur Rs.500000/- Muhammad Pur Rs.500000/-
26/4/2018 25/6/2018
(iv)   Const: of Soling /Drain Main Road Haroonabad (iv)  Const: of Soling /Drain Main Road
to Boys School Swaiwala. (Work No.46) Rs.500000 Haroonabad to Boys School Swaiwala. Rs.1000000

2800000/- Rs.3800000/-
(i)  Const: of Soling Chak No.319/HR via Basti (i)   Const: of Soling Chak No.319/HR via Basti
Baluchan to 319/HR (Alf) Rs.1500000/- Baluchan to 319/HR (Alf) Rs.1500000/-
(ii)  Const/Extension Water supply pipe line 319/HR (ii)  Const/Extension Water supply pipe line
to 319/HR(Alf) Rs.500000/- 319/HR to 319/HR(Alf) Rs.500000/-
1021 1185
23
(iii)  Const/Repair of Metalled Road Dahranwala 26/4/2018 29/6/2018 (iii)  Const/Repair of Metalled Road Dahranwala
Fortabbas Abbass Road to Chak No.175/7R (Work Rs.1000000/- Fortabbas Abbass Road to Chak No.175/7R & Rs.4400000/-
No.52) Chak 235/9R
Rs.3000000/- Rs.6400000/-
(i)  Const: of Soling Drain Basti Chawayka (i) Const: of Soling Drain Basti Chawayka
Rs.1000000/- Rs.2000000/-

(ii) Const: of Soling Basti Taj Jodhayka Rs.500000/- (ii) Const: of Soling Basti Taj Jodhayka Rs.500000/-
1029 1130
24 (iii)  Const: of Soling Lalika Road to Graveyard 26/4/2018 03/6/2018 (iii) Const: of Soling Lalika Road to Graveyard
Baba Said Rasul Shah. (Work No.60). Rs.1000000/- Baba Said Rasul Shah Rs.2500000/-

Rs.2500000/- Rs.5000000/-
(i)   Const: of Soling Basti Shera Baghar Rs.500000/- (i)  Const: of Soling Basti Shera Baghar Rs.1200000/-
(ii)  Const: of Soling Basti Bahma Hans Rs.600000/- (ii) Const: of Soling Basti Bahma Hans Rs.600000/-
(iii)  Const: of Soling Drain Father Pur Holaan Wali Rs.400000/- (iii) Const: of Soling Drain Fateh Pur Holaan Wali Rs.400000/-
(iv)  Providing of Manhole Cover/Water Supply Pipe (iv) Providing of Manhole Cover/Water Supply
1031 Rs.500000/- Rs.500000/-
25 line Chak Dinan Bashnoian. Pipe line Chak Dinan Bashnoian.
26/04/2018
(v)   Const; of Soling /drain from House Khuda (v) Const; of Soling /drain from House Khuda
Bakhsh(Late) to Masjid Sharif Basti Bhatta Mouza Rs.200000/- Bakhsh(Late) to Masjid Sharif Basti Bhatta Rs.500000/-
Rojhanwali .(Work No. 62) Mouza Rojhanwali to
Rs.2200000/- Rs.3200000/-
(i)  Const: of Cattle Pond Chak No.164/7R Rs.500000/- (i)  Const: of Cattle Pond Chak No.164/7R Rs.500000/-
(ii) Const: of Soling ,Boundary Wall, Cattle Pond (ii) Const: of Soling, Boundary Wall, Cattle Pond
Chak No.120/6R Rs.1120000/- Chak No.120/6R. Rs.1120000/-
(iii) Const: of Soling/Drains Ghalla Colony Khichiwala 1032 1186 (iii) Const: of Soling/Drains Ghalla Colony
26 Rs.500000/- Khichiwala & Chak No.238/9R,235/9R Rs.1580000/-
26/4/2018 29/6/2018
(iv) Providing& Fixing of Manhole covers Slabs etc (iv) Providing& Fixing of Manhole covers Slabs
Urban Union Council Faqirwali. (Work No.63) Rs.400000 etc Urban Union Council Faqirwali. Rs.400000/-
Rs.2520000/- Rs.4100000/-
(i)  Const: of soling,Drains,Nala Jat, Tuff Tiles, (i)  Const: of soling,Drains,Nala Jat, Tuff
Sewerline,Culverts,water Supply Pipe line, Cattle Tiles,Sewerline,Culverts,water Supply Pipe line,
Pond, Water Diggies, Boundary Rs.1000000/- Cattle Pond, Water Diggies, Boundary Rs.1000000/-
Walls,Janazgah,Mussafar Khana Jat, Metalled Roads Walls,Janazgah,Mussafar Khana Jat, Metalled
etc in Union U/C No.123. Roads etc in Union U/C No.123.
1035 1187
27
(ii) Const: of Soling Chak 239/9R to Basti Baba 26/4/2018 29/6/2018 (ii) Const: of Soling Chak 239/9R to Basti Baba
Rs.1200000/- Rs.3500000/-
Ahsan. Ahsan & Chak 235/9R.
(iii)  Const: of Shade Chak 235/9R. (Work No. 66) (iii) Const: of Shade Chak 235/9R.
Rs.500000/- Rs.500000/-

Rs.2700000/- Rs.5000000/-
(i)  .Const: of Boundary Wall ,Gate & Soling of (i) Const: of Boundary Wall ,Gate & Soling of
Graveyard.288/HR(Remaining Work) ADP Phase-II Graveyard.235/9R(Remaining Work) with
Rs.1000000/- protection wall & Grill on the Canal Road Chak Rs.1628000/-
No.235/9R (Izafi Basti) ADP Phase-II.
1046 1188
28 (ii)  P/L of PVC Pipe Water Supply Pipe line People (ii) Const: of soling Madina Colony Mosque
26/4/2018 Rs.300000/- 29/6/2018 Rs.800000/-
Colony Khichi wala. Street Khichi wala.
(iii)  Const : of soling Madina Colony Mosque street (iii) P/L PVC Pipe Water Supply People Colony
Khichi wala. (Work No.77) Rs.800000/- Khichi wala. Rs.300000/-
Rs.2100000/- Rs.2728000/-
(i)  Const: of soling,Drains,Nala Jat, Tuff, (i)   Const: of soling,Drains,Nala Jat, Tuff,
Sewerline,Culverts,water Supply Pipe line, Sewerline,Culverts,water Supply Pipe line,
Cattle Pond, Water Diggies, Cattle Pond, Water Diggies, Boundary
Boundary,Janazgah,Mussafar Khana Jat, Rs.1000000/- Walls,Janazgah,Mussafar Khana Jat, Rs.3000000/-
Metalled Roads etc in Union No. Metalled Roads etc in Union No.

1048
29 26/04/2018
U/C 79 Rs.1000000/- U/C 79 Rs.1000000/-
U/C No.75 Rs.500000/- U/C No.75. Rs.500000/-
(ii)  Const: of Soling Chak Mehatta Jhedu Road (ii)  Const: of Soling Chak Mehatta Jhedu
to Girls High School Mehatta Jhedu Rs.2500000/- Road to Girls High School Mehatta Jhedu Rs.4500000/-
(Work No.79)
(i) Const/Repair of Metalled Road Shadi Wala 1050 1189 (i)  Const/Repair of Metalled Road Shadi
30 Road. (Work No.81). Rs.2500000/- Wala Road. Rs.5000000/-
26/4/2018 29/6/2018
STATEMENT SHOWING QUANTITIES INFORMATION ORIGNAL/ REVISED SCHEMES
DISTRICT COUNCIL BAHAWALNAGAR FOR THE YEAR 2017-18
WORK NO
2

CONSTRUCTION OF SOLING /DRAIN ,NALA ,SERWER LINE


,CULVERTS,BRIDGES,DIGGI,RCC PIPE LINE,WATER SUPPLY PIPE LINE,
NAME OF SCHEME. CATTLE POND ,BOUNDRY WALL ,JANAZ GHAH MUSAFAR KHANA JAT
CONST.METALLED ROAD IN U/C NO 21,23,28,29,30,33,34,35,36,37,

WORK ORDER NO & DATE 374 , 2/10/2018 RS:9500000/-


ORIGNAL

WORK ORDER DATE 1175 , 29/6/2018 RS: 10280000/-


REVISED/ENHANCMENT

COMPLETION DATE ON GOING

ITEM ORIGNAL WORK REVISED WORK PAID


DESCRIPTION
NO QUANTITY RATE AMOUNT QUANTITY RATE AMOUNT QUANTITY RATE AMOUNT

PVC PIPE UC 21 BHAKAN


1 WALA (ORIGNAL RS: 1000000
& REVISED RS: 1000000)

1 EXCAVETION FOR PIPE LINE 39046 4271 166765.466 39046 4271 166765.466 37800 4271 161443.8
2 LAYING PVCPIPE LINE 5578 105.95 590989.1 5578 105.95 590989.1 6300 105.95 667485
3 SLUICE VALVE 6" 3 13109.15 39327.45 3 13109.15 39327.45 0 13109.15 0
4 SPIECIAL TEE BAND 1 63000 63000 1 63000 63000 1 62454 62454
5 BACK FILLING 31237 1420.3 44365.9111 31237 1420.3 44365.9111 30240 1420.3 42949.872
6 DRY BRICK SOLING 53.1 2889.05 1534.08555 53.1 2889.05 1534.08555 0 2889.05 0
7 MAKING CONNECTION 3 1620.95 4862.85 3 1620.95 4862.85 0 1620.95 0
8 P/F SIGN BORD 1 14800 14800 1 14800 14800 1 14800 14800
925644.86265 925644.86265 949132.672
Add 8% pst/Gp 74051.589012 D/D .10% pst/Gp 925.64486265 D/D .10% pst/Gp 949.132672
999696.451662 924719.21779 948183.539328
1000000 Add8% pst/Gp 73977.537423 Add8% pst/Gp 75854.6831462
998696.75521 1024038.22247
1000000

MATALLED ROADU/C NO 23
MUHAMMAD PUR
2 ((ORIGNAL RS: 1000000 &
REVISED RS:1780000)

1 DISMENTALING OF SOLING 2566.5 1516.9 38931.2385 2566.5 1516.9 38931.2385 2566.5 1516.9 38931.2385

2 Earth work 1/2 MILE 7656 7036 53867.616 13200 7036 92875.2 13200 7036 92875.2
SUB BASE COURSE BRICK
3 WORK 2565 5127 131507.55 2565 5127 131507.55 2565 5127 131507.55

4 SUB BASE COURSE OF STONE 1060 9403 99671.8 3685 9403 346500.55 3685 9403 346500.55

5 ROAD ENDING 1450 29.1 42195 2500 29.1 72750 2500 29.1 72750

6 BASE COURSE 2392.5 12757 305211.225 4125 12757 526226.25 4125 12757 526226.25

7 T S T COMPLETE 7250 3395.85 246199.125 12500 3395.85 424481.25 12500 3395.85 424481.25

8 Gi pipe sign board 1 14800 14800 1 14800 14800 1 14800 14800

932383.5545 1648072.0385 1648072.0385

Add 8% pst/Gp 74590.68436 D/D .10% pst/Gp 1648.0720385 D/D .10% pst/Gp 1648.0720385

1006974.23886 1646423.9665 1646423.96646

1000000 Add8% pst/Gp 131713.91732 Add8% pst/Gp 131713.917317

1778137.8838 1778137.88378

1780000 TOTAL= 1778137.88378


SOLING BASTI u/c 28
SANATEKA (ORIGNAL RS:
3 1000000 & REVISED RS:
1000000)

1 Earth work UP TO 100FT 33576 4765.25 159998.034 33576 4765.25 159998.034 41693 4765.25 198677.56825

2 DRY BRICK SOING 5565 13656.5 759984.225 5565 13656.5 759984.225 5211 13656.5 711640.215

3 Gi pipe sign board 1 14800 14800 1 14800 14800 1 14800 14800

934782.259 934782.259 925117.78325

Add 8% pst/Gp 74782.58072 D/D .10% pst/Gp 934.782259 D/D .10% pst/Gp 925.11778325

1009564.83972 933847.47674 924192.665467

1000000 Add8% pst/Gp 74707.798139 Add6% pst/Gp 55451.559928

1008555.2749 979644.225395

1000000

SOLING 29 MOMNABAD
4 (ORIGNAL RS: 1000000 &
REVISED RS: 1000000)

1 Earth work UP TO 101/2 MILE 33576 7554 253633.104 33576 7554 253633.104 29339 7554 221626.806
2 DRY BRICK SOING 5565 13656.5 759984.225 5565 13656.5 759984.225 5048.8 13656.5 689489.372
3 GI PIPE SIGN BOARD 1 14800 14800 1 14800 14800 1 14800 14800
1028417.329 1028417.329 925916.178
Add 8% pst/Gp 82273.38632 D/D .10% pst/Gp 1028.417329 D/D .10% pst/Gp 925.916178
1110690.71532 1027388.9117 924990.261822
1000000 Add8% pst/Gp 82191.112934 Add6% pst/Gp 55499.4157093
1109580.0246 980489.677531
1000000
SOLING 30 MARI MIAN SAHAB
BASTI KALANCHIAN (ORIGNAL
5 RS: 1000000 & REVISED RS:
1000000)
1 Earth work UP TO ONE MILE 32089.2 7554.3 242411.44356 32089.2 7554.3 242411.44356 31615 7554.3 238829.1945
2 DRY BRICK SOING 4967.8 13656.5 678427.607 4967.8 13656.5 678427.607 4943.04 13656.5 675046.2576
3 GI PIPE SIGN BOARD 1 14800 14800 1 14800 14800 1 14800 14800
935639.05056 935639.05056 928675.4521
Add 8% pst/Gp 74851.1240448 D/D .10% pst/Gp 935.63905056 D/D .10% pst/Gp 928.6754521
1010490.174605 934703.41151 927746.776648
1000001 Add8% pst/Gp 74776.272921 Add6% pst/Gp 55664.8065989
1009479.6844 983411.583247
1000001
SOLING 33 JHULAN ARIAN
6 (ORIGNAL RS: 1000000 &
REVISED RS: 1000000)
1 Earth work UP TO ONE MILE 27455.4 7554.3 207406.32822 29059 7554.3 219520.4037 29059 7554.3 219520.4037
3 DRY BRICK SOING 5197.5 13656.5 709796.5875 4867 13656.5 664661.855 4868 13656.5 664798.42

1 PACCA BRICK WORKS 1:5 F&P 163 16502 26898.26 163 16502 26898.26
4 GI PIPE SIGN BOARD 1 14800 14800 1 14800 14800 1 14800 14800
932002.91572 925880.5187 926017.0837
Add 8% pst/Gp 74560.2332576 D/D .10% pst/Gp 925.8805187 D/D .10% pst/Gp 926.0170837
1006563.148978 924954.63818 925091.066616
1000001 Add8% pst/Gp 73996.371055 Add6% pst/Gp 55505.463997
998951.00924 980596.530613
1000001
SOLING 37 ISLAM PURA
7 (ORIGNAL RS: 1000000 &
REVISED RS: 1000000)
1 Earth work UP TO ONE MILE 13781 7554.3 104105.8083 13781 7554.3 104105.8083 13780 7554.3 104098.254
2 DRY BRICK SOING 2524.32 13656.5 344733.7608 2524.32 13656.5 344733.7608 2518 13656.5 343870.67
3 GI PIPE SIGN BOARD 1 14800 14800 1 14800 14800 1 14800 14800
463639.5691 463639.5691 462768.924
Add 8% pst/Gp 37091.165528 D/D .10% pst/Gp 463.6395691 D/D .10% pst/Gp 462.768924
500730.734628 463175.92953 462306.155076
500000 Add8% pst/Gp 37054.074362 Add6% pst/Gp 27738.3693046
500230.00389 490044.524381
500000
SOLING 36 FATEH COT
8 (ORIGNAL RS: 1000000 &
REVISED RS: 1000000)
1 Earth work UP TO ONE MILE 32467 4765.25 154713.37175 32467 4765.25 154713.37175 33775 4765.25 160946.31875
2 DRY BRICK SOING 5381.25 13656.5 734890.40625 5381.25 13656.5 734890.40625 5125 13656.5 699895.625
3 PACC BRICK WORK 1;5 0 16501.5 0 0 16501.5 0 42.18 16501.5 6960.3327
4 FABRICATION OF MILD STEEL 128.57 11385.75 14638.658775 128.57 11385.75 14638.658775 76 11385.75 8653.17
5 RCC 1;2;4 42.24 342.9 14484.096 42.24 342.9 14484.096 25.6 342.9 8778.24
6 GI PIPE SIGN BOARD 1 14800 14800 1 14800 14800 1 14800 14800
933526.532775 933526.53278 900033.68645
Add 8% pst/Gp 74682.122622 D/D .10% pst/Gp 933.52653278 D/D .10% pst/Gp 900.03368645
1008208.655397 932593.00624 899133.652764
1000000 Add8% pst/Gp 74607.440499 Add6% pst/Gp 53948.0191658
1007200.4467 953081.671929
1000000

SOLING 34 TOBA QALANDAR


9 SHAH (ORIGNAL RS: 1000000
& REVISED RS: 1000000)

1 Earth work UP TO 100 FT 21411 4765 102023.415 21411 4765 102023.415 21411 4765 102023.415
2 Earth work UP TO ONE MILE 16374 7554 123689.196 16374 7554 123689.196 16374 7554 123689.196
3 DRY BRICK SOING 5028.94 13657 686802.3358 5028.94 13657 686802.3358 5021 13657 685717.97
4 GI PIPE SIGN BOARD 1 14800 14800 1 14800 14800 1 14800 14800
927314.9468 927314.9468 926230.581
Add 8% pst/Gp 74185.195744 D/D .10% pst/Gp 927.3149468 D/D .10% pst/Gp 926.230581
1001500.142544 926387.63185 925304.350419
1000000 Add8% pst/Gp 74111.010548 Add6% pst/Gp 55518.2610251
1000498.6424 980822.611444
1000000

PVC PIPE UC 35 MUHAMMAD


1 PUR (ORIGNAL RS: 1000000 &
REVISED RS: 1000000)

1 EXCAVETION FOR PIPE LINE 35980 5014 180403.72 35980 5014 180403.72 30960 5014 155233.44
2 LAYING PVCPIPE LINE 3"DIA 4360 105.95 461942 4360 105.95 461942 4360 105.95 461942
3 LAYING PVCPIPE LINE 4"DIA 780 158.95 123981 780 158.95 123981 780 158.95 123981
3 SLUICE VALVE 4" 1 7910.85 7910.85 1 7910.85 7910.85 2 7910.85 15821.7
4 SLUICE VALVE 3" 4 6722.6 26890.4 4 6722.6 26890.4 4 6722.6 26890.4
4 SPIECIAL TEE BAND 1 30000 30000 1 30000 30000 1 7885 7885
5 SLUICE VALVE CHAMBER 4 10000 40000 4 10000 40000 3 8337.6 25012.8
5 BACK FILLING 28784 1420.3 40881.9152 28784 1420.3 40881.9152 24768 1420.3 35177.9904
8 P/F SIGN BORD 1 14800 14800 1 14800 14800 1 14800 14800
926809.8852 926809.8852 866744.3304
Add 8% pst/Gp 74144.790816 D/D .10% pst/Gp 926.8098852 D/D .10% pst/Gp 866.7443304
1000954.676016 925883.07531 865877.58607
1000000 Add8% pst/Gp 74070.646025 Add6% pst/Gp 51952.6551642
999953.72134 917830.241234
1000000

COMPARATIVE STATEMENT REGARDING


CONSTRUCTION OF SOLING, DRAIN, SEWER LINE, SLUDGE CARRIER TUFF TILE, WATER DIGGI, BOUNDARY, WALL, CATTLE POND, JANAZ GAH, FOR LADY MEMBERS FORMER
MEMBERS YOUTH MEMBERS TECHNOCRATE MEMBERS, MINORITY MEMBERS DISTRICT COUNCIL BAHAWALNAGAR (ORIGIONAL COST Rs=8000000/ REVISED COST 8600000/)
Work 10
Orignal No & Date 381 , 02/10/2017
Revised No & Date 1167 , 29-06-2018
Date of Completion : On Going

Orignal Revised Paid


Sr. #
Description Quantity Rate Amount Quantity Rate Amount Quantity Rate Amount
Sub Work No. 10 (Const. of Cattle Pond 131/M)
1 Earth work excavation in
1284 5995.45 7698.1578 1284 5995.45 7698.1578 1284 5995 7697.58
foundation
2 Cement Concrete(1:6:12) 622 10373.45 64522 622 10373.45 64522 622 10373.45 64522.859
3 Providing, laying pacca brick
1867 17001.2 317412 1867 17001.2 317412 1867 17001.2 317412
work (1:4)
4 1/2" thick cement plaster
2548 1728.5 44042 2548 1728.5 44042 2548 1728.5 44042
(1:4)
5 Brick on edge flooring land
579 7250.7 41981 579 7250.7 41981 579 7250.7 41981
(1:6)
6 Earth work excavation in
250 5995.45 1499 250 5995.45 1499
foundation
7 Cement Concrete(1:6:12) 50 10373.45 5187 50 10373.45 5187
8 Providing, laying pacca brick
136 17001.2 23122 136 17001.2 23122
work (1:5)
9 1/2" thick cement plaster
120 1728.5 2074 120 1728.5 2074
(1:4)
10 Providing, laying pacca brick
65 18997.9 12349 65 18997.9 12349
work Arch
11 Earth work lead up to one
2765 6840.85 18915 2765 6840.85 18915
mile
12 Providing, laying dry brick
233 13656.45 31820 229 13656.5 31273
soling
570074.439
Sub Work No. 12 (Const. of Water Course M.Pur Sansaran
1 Earth work lead up to one
6975 6840.85 47714.92875 6975 6840.85 47715 6975 6840.85 47714.92875
mile
2 Cement Concrete(1:6:12) 715 10373.45 74170 1372 10373.45 142324 1324 10373.5 137345.14
3 Providing, laying pacca brick
work (1:4) 1532 17001.2 260458 2593 17001.2 440841 2674 454615.2968
17001.32
4 1/2" thick cement plaster
3542 1728.5 61223 6860 1728.5 118575 6369 110088.165
(1:4) 1728.5
5 Plain cement concrete
139 17001.2 30344 294 21830.35 64181.229 269 58723.8029
(1:2:4) 21830.41
Construction of Culvert (20,16)
feet1 Long
Earth Work Excavation in
450 2697.9525
foundation 5995.45
2 C.C 1;6:12 90 10373.45 9336.105
3 pacca brick work 1:4 276 17001 46922.76
4 Fabrication of mild steel 272 12315.95 33499.384
5 R.C.C 1:2:4 94 342.2 32166.8
6 Cement Plaster 1:4 216 1728.5 3733.56
936843.89495
Total
S/W Soling street Pavment 4000000 3761562
S/W Janazgah Basti Ragran 500000 472283
S/W Boundry wall Diggi 143/6R
500000
474196
S/W Sewar line Qader Pur 500000 473948
S/W Water Course Drain,
500000
Soling Mechlod Gung 470847
S/W Tuff Tile 185/7R 500000 472776
S/W Boundry wall 322 /HR 500000 472595
6598207
8105125.334

STATEMENT SHOWING QUANTITIES INFORMATION ORIGNAL/ REVISED SCHEMES


DISTRICT COUNCIL BAHAWALNAGAR FOR THE YEAR 2017-18

WORK NO
1

CONSTRUCTION OF SOLING ,DRAINS,NALA JAT, FUFF, SEWER LINE,


CULVERTS, WATER SUPPLY PIPE LINE, CATTLE POND, WATER DIGGIES,
NAME OF SCHEME. BOUNDARY WALLS, JANAZGAN, MUSAFAR KHANA JAT ,MATALLED ROAD
ETC, IN UNION COUNCIL .11.12.13.15, CONTSTRUCTION OF SOLING M
OUZA DONA QATAB SARHU U/C HASIL SARHU.

WORK ORDER NO & DATE 969 , 26/4/2018 RS:3000000/-


ORIGNAL
WORK ORDER DATE 1162 , 25/6/2018 RS: 8000000/-
REVISED/ENHANCMENT
COMPLETION DATE ON GOING

ITEM ORIGNAL WORK REVISED WORK PAID


DESCRIPTION
NO QUANTITY RATE AMOUNT QUANTITY RATE AMOUNT QUANTITY RATE AMOUNT
UC 11 MECHLOD GUNJ
(ORIGNAL RS:100000
&REVISED RS: 2500000)
1 Earth work UP TO 1 MILE 5080 7080.6 35969.448 40338 7080.6 285617.2428 40377 7080.6 285893.3862
2 DRY BRICK BLAST 25% SAND 1677.1 4120.3 69101.5513 3141.8 4120.3 129451.5854 3114 4120.3 128306.142
3 CONSTRUCTION OF KHAL 520 653.05 339586 520 653.05 339586 520 653.05 339586
4 CONSTRUCTION OF DRAIN 628 326.11 204797.08 628 326.11 204797.08
5 CONSTRUCTION OF SOLING 2999.3 13882.4 416374.8232 3001 13882.4 416610.824
6 UP LAVELING MAN HOLE 3 3500 10500 5 3500 17500 5 3500 17500
7 R C C PIPE 12 INC DIAMETRE 413.86 0 12 413.86 4966.32 12 413.86 4966.32
8 R C C PIPE 6 INC DIAMETRE 17 190.5 3238.5 0 190.5 0
9 FABRICATION OF MILD STEEL 1518 0 91 11385.8 10361.078 88 11385.8 10019.504
10 RCC WORK 1:2;4 40.21 342.8 13783.988 40 342.8 13712
11 TUFF TILE 60MM 4987.5 95.9 478301.25 9441 95.9 905391.9 9441 95.9 905391.9
933458.2493 2331068.5174 2326783.1562
Add 8% pst/Gp 74676.659944 D/D .65% pst/Gp 15151.945363 D/D .65% pst/Gp 15124.0905153
1008134.909244 2315916.572 2311659.06568
Add 8% pst/Gp 185273.32576 Add 6% pst/Gp 138699.543941
2501189.8978 A 2450358.60963
1000000 2500000

CONSTRUCTION SOLING UC
12 HASSAN WALA (ORIGNAL
RS:500000 & REVISED
RS:1000000)
1 EARTH FILLING UP TO I MILE 4700 7080.55 33278.585 15113 7080.55 107008.35215 15233.6 7080.55 107862.26648
2 DRY BRICKS SOLING 750 13882.35 104117.625 3612.31 13882.35 501473.51729 3612.2 13882.35 501458.2467
3 CONSTRUCTION OF DRAIN 600 326.11 195666 532 326.11 173490.52 532 326.11 173490.52
4 PACCA BRICKS WORK 105.46 16661.6 17571.32336 0 0
5 FABRICATION OF MILD STEEL 505.3 11051.85 55844.99805 0 0
6 CEMENT CONCERETE 1:2:4 165.07 349.2 57642.444 0 0
CONSTRUCTION OF RCC 151371.94 151371.94
7 CULVERT 2 75685.97 2 75685.97
464120.97541 933344.32944 934182.97318
Add 8% pst/Gp 37129.6780328 D/D .65% pst/Gp 6066.7381413 D/D .65% pst/Gp 6072.18932567
501250.6534428 927277.59129 928110.783854
Add 6% pst/Gp 55636.655478 Add 6% pst/Gp 55686.6470313
982914.24677 B 983797.430886
1000000

CONSTRUCTION SOLING UC
13 LALA AMIR SING (ORIGNAL
RS: 500000 & REVISED RS:
1500000)
1 EARTH FILLING 100 FT 25944 4045.75 104962.938 25943 4045.75 104958.89225 25943 4045.75 104958.89225
2 EARTH FILLING UP TO I MILE 0 22379 7080.55 158455.62845 22380 7080.55 158462.709
3 DRY BRICKS SOLING 2587 13882.35 359136.3945 6715.64 13882.35 932288.64954 6668 13882.35 925675.098
CONSTRUCTION OF DRAIN 515 326.11 167946.65 515 326.11 167946.65
RCC SEWER LINE 9 INC 16 352.2 5635.2 28 352.2 9861.6
FABRICATION OF MILD STEEL 145.4 11385.75 16554.8805 113 11385.75 12865.8975
CEMENT CONCERETE 1:2:4 47.5 342.8 16283 36 342.8 12340.8
464099.3325 1402122.9007 1392111.64675
Add 8% pst/Gp 37127.9466 D/D .65% pst/Gp 9113.7988548 D/D .65% pst/Gp 9048.72570388
501227.2791 1411236.6996 1401160.37245
Add 8% pst/Gp 112898.93597 Add 6% pst/Gp 84069.6223472
1524135.6356 C 1485229.9948
1500000

CONSTRUCTION SOLING UC
14 DONA QATAB SARO
(ORIGNAL RS: 500000 &
REVISED RS: 700000)
1 EARTH FILLING UP TO I MILE 12099 7080.6 85668.1794 16682 7080.55 118117.7351 16258 7080.55 115115.5819
2 DRY BRICKS SOLING 2744.13 13882.35 380949.731055 3872.58 13882.35 537605.10963 3874.4 13882.35 537857.7684
3 466617.910455 655722.84473 652973.3503
Add 8% pst/Gp 37329.4328364 D/D .65% pst/Gp 4262.1984907 D/D .65% pst/Gp 4244.32677695
503947.3432914 659985.04322 657217.677077
400000 Add 8% pst/Gp 52798.803458 Add 6% pst/Gp 39433.0606246
712783.84668 D 696650.737702
700000

CONSTRUCTION SOLING UC
15 MATT WALA (ORIGNAL RS:
500000 & REVISED RS:
2300000)
1 EARTH FILLING UP TO I MILE 22184 7080.6 157076.0304 83708 7080.6 592702.8648 83538 7080.6 591499.1628
2 DRY BRICKS SOLING 2212.5 13882.35 307146.99375 11177 13882.35 1551630.2595 11168.88 13882.35 1550503.01268
464223.02415 2144333.1243 2142002.17548
Add 8% pst/Gp 37137.841932 D/D .65% pst/Gp 13938.165308 D/D .65% pst/Gp 13923.0141406
501360.866082 2158271.2896 2155925.18962
400000 Add 8% pst/Gp 172661.70317 Add 6% pst/Gp 1854095.66307
2330932.9928 E 4010020.85269
2300000
TOTAL= A+B+C+D+E 9626057.62571
CONSTRUCTION OF SOLING DRAIN , NALA JAAT, TUFF TILE , SEWER LINE, CULVERTS, WATER SUPPLY PIPE LINE , CATTLE POND, WATER DIGGIS , BOUNDARY WALLS , JANAZ
GAH , MUSAFAR KHANA JAAT, MATALLED ROAD ETC IN UC 58,65,67 (ORIGIONAL COST Rs=2500000/ REVISED COST 3000000/)
Work 5
Orignal No & Date 973 , 26/04/2018
Revised No & Date 1165 , 25-06-2018
Date of Completion : On Going

ITEM ORIGNAL WORK REVISED WORK PAID


DESCRIPTION
NO QUANTITY RATE AMOUNT QUANTITY RATE AMOUNT QUANTITY RATE AMOUNT
arth filling in the street including its ramming, dressing lead upto
379301 miles.uc
cft 58 7080.55 %0cft Rs.268565/- 37930 cft 7080.55 %0cft 268565
Providing and laying dry
brick pavement/soling in 4688 cft 13882.35 p/%cft Rs.650735/- 4425 cft 13882.35p%cft 614294
streets or roads, etc.
Provision for
manufacturing and
1 no 25000 each Rs.25000/- NIL
installation of project
information board .
Construction of Pacca Sullag 488 rft 914.62 p/rft Rs.446333/-
Provision for project
1 no 25000 each Rs.25000/-
information board.
Earth filling in the street
including its ramming,
dressing lead upto 1 miles 32980 cft 7080.55 p%0cft Rs.233518/- 32733 cft 7080.55 p%0cft 231768
uc 67
Providing and laying dry
brick pavement/soling in 4931 cft 13882.35 p/%cft Rs.684573/- 4655 cft 13882.35 p%cft 646237
streets or roads, etc
Provision for manufacturing
and installation of project 1 no 25000 each Rs.25000/- NIL
information board .
Construction of Pacca
913 rft 914.62 p/rft Rs.835048/- 913 RFT 914.62 p/rft Rs.835048/-
Sullage Carrier 1.5 x 2 .
Construction of Culvrt . 1 no 81708 each Rs.81708/- 1 no 81708 each Rs.81708/-
Provision for manufacturing
and installation of project 1 no 25000 each Rs.25000/- NIL
information board .

STATEMENT SHOWING QUANTITIES INFORMATION ORIGNAL/ REVISED SCHEMES


DISTRICT COUNCIL BAHAWALNAGAR FOR THE YEAR 2017-18

WORK NO 6

CONSTRUCTION OF SOLING ,DRAINS,NALA JAT, FUFF, SEWER LINE,


CULVERTS, WATER SUPPLY PIPE LINE, CATTLE POND, WATER DIGGIES,
BOUNDARY WALLS, JANAZGAN, MUSAFAR KHANA JAT ,MATALLED ROAD
NAME OF SCHEME. ETC, IN UNION COUNCIL 10. CONSTRUCTION OF SOLING BASTI
PANNUAN TO MADRISSA ISLAMIA, CONSTRUCTION OF PULLI BASTI
MUHAMMAD YAR VAZIRKA, COSTRUCTION OF SOLING BASTI ROHANA.

WORK ORDER NO & DATE 974 , 24/4/2018 RS: 2500000/-


ORIGNAL
WORK ORDER DATE
REVISED/ENHANCMENT 1173 , 29/6/2018 RS: 3200000/-
COMPLETION DATE ON GOING

ORIGNAL WORK REVISED WORK PAID


ITEM DESCRIPTION
NO
QUANTITY RATE AMOUNT QUANTITY RATE AMOUNT QUANTITY RATE AMOUNT

UC 10 PEER GHAR CHISHTI


1 Earth work100 FT 19975 4045.75 80813.85625 19975 4045.75 80813.85625 16499 4045.75 66750.82925

Earth work UP TO 1 MILE 22898 7080.55 162130.4339 22898 7080.55 162130.4339 22189 7080.55 157110.32395

2 DRY BRICKS FOR SOLING 4680.26 13882.35 649730.07411 4680 13882.4 649696.32 4558 13882.4 632759.792

3 PACCA BRICKS WORK 21.75 16501.5 3589.07625 21.75 16501.5 3589.07625 16501.5 0
FABRICATION OF MILD STEEL
4 WORK 131.83 11636.5 15340.39795 131.83 11636.5 15340.39795 11636.5 0

5 R C C 1 : 2:4 43.065 342.8 14762.682 43.165 342.8 14796.962 342.8 0

926366.52046 926367.04635 856620.9452

Add 8% pst/Gp 74109.3216368 Add 8% pst/Gp 74109.363708 DD .625% LESS 5353.8809075

1000475.842097 1000476.4101 851267.064293

1000000 Add 8% Pst/Gp cont 1000000 Add 6% Pst/Gp cont 51076.0238576

CONSTRUCTION SOLING UC
BASTI ROHANA 902343.08815

EARTH FILLING UP TO I MILE 25728 7080.55 182168.3904 25728 7080.55 182168.3904 20335 7080.55 143982.98425
1

DRY BRICKS SOLING 2700 13882.35 374823.45 2700 13882.35 374823.45 3074 13882.35 426743.439
2

556991.8404 556991.8404 570726.42325


3

44559.347232 44559.347232
Add 8% pst/Gp Add 8% pst/Gp DD .625% LESS 3567.04014531

601551.187632 601551.18763
567159.383105

Add 6% Pst/Gp cont 34029.5629863

600000 600000 601188.946091


CONSTRUCTION SOLING BASTI
PUNNAN

EARTH FILLING UP TO I MILE 24440 7080.55 173048.642 24440 7080.55 173048.642 22120 7080.55 156621.766
1

DRY BRICKS SOLING 2100 13882.35 291529.35 2100 13882.35 291529.35 2044 13882.35 283755.234
2

464577.992 464577.992 440377


3

37166.23936 37166.23936
Add 8% pst/Gp Add 8% pst/Gp DD .625% LESS 2752.35625

501744.23136 501744.23136
437624.64375

500000 500000 Add 6% Pst/Gp cont 26257.478625

463882.122375

CONSTRUCTION SOLING PUL


WAZIRKA

EARTH FILLING UP TO I MILE 14861 7080.55 105224.05355 0


1

DRY BRICKS SOLING 1912.5 13882.35 265499.94375 0


2

370723.9973 0
3

29657.919784 DD 8% LESS 0
Add 8% pst/Gp

400381.917084 0

400000 500000

CONSTRUCTION PUL WAZIRKA

EXCAVATION OF BRIDGE 4774 6434.2 30716.8708 4774 6434.2 30716.8708


CEMENT CONCRETE 1;4:8 1063 12369.15 131484.0645 1063 12369.15 131484.0645
2990 17139.15 512460.585 2990 17139.15 512460.585
PACCA BRICKS WORK 1;4:F&P
FABRICATION OF MILD STEEL 2157 11051.85 238388.4045 2119 11051.85 234188.7015
R C C WORK SLAB 1:2:4 525 349.2 183330 525 349.2 183330
R C C WORK SLAB 1:2:4 91 254.05 23118.55 91 254.05 23118.55
WITHOUT SHUTTRING
P C C TOPING 1:2:4 10.5 21987.25 2308.66125 21987.25 0
1121807.1361 1115298.7718
1122000 DD .625% LESS 6970.61732375
1108328.15448
Add 6% Pst/Gp cont 66499.6892686
1174827.84374

QUANTITIES INFORMATION REGARDING REVISED SCHEMES DISTRICT COUNCIL BAHAWALNAGAR FOR THE YEAR 2017-18
WORK NO 7

Const: of soling,Drains,Nala Jat, Tuff Tiles, Sewerline, Culverts,water


Supply Pipe line, Cattle Pond, Water Diggies, Boundary
NAME OF SCHEME. Walls,Janazgah,Mussafar Khana Jat, Metalled Roads etc in Union Council
No.130 & U/C 131.

WORK ORDER DATE ORIGNAL 29/4/2018


WORK ORDER DATE 29/6/2018
REVISED/ENHANCMENT
COMPLETION DATE ON GOING

ORIGNAL WORK REVISED WORK PAID


ITEM NO DESCRIPTION
QUANTITY RATE AMOUNT QUANTITY RATE AMOUNT QUANTITY RATE AMOUNT

Construction of soling in uc 130,131


1 Earth work one mile 44035 7232.9 318501 40035 7232.9 318501 43436 7232.9 314168

2 Dry brick soling 3996 13882.35 55473 3996 13882.35 55473 3987 13882.35 553489

Construction of drain type 1 230 318.23 73193 230 318.23 73193

1 CC Brick Blast 1:6:12 86 10495.35 9026 86 10495.35 9026 86 10495.35 9026

2 Pacca Brick in foundation 1:5 86 16661.55 14324 86 16661.55 14324 86 16661.55 14324

3 pacca Brick on edge 1:5 345 7502.55 25884 345 7502.55 25884 345 7502.55 25884
Punjab Standard Drain 1
4 ( 1:6:12) 230 103.85 23885 230 103.85 23885 230 103.85 23885
Conststruction of culvert 50 47000 2350000

1 Excavation in foundation 8343 6434.2 53680 8343 6434.2 53680 8343 6434.2 53680

2 CC Brick Blast 1:6:12 3671 10495.35 385336 3671 10495.35 385336 2780 10495.35 291776

3 Pacca Brick in foundation 1:5 8784 16661.55 1463550 8784 16661.55 1463550 8653 16661.55 1441724

4 Brick work orch 1:3 1681 17855.55 300151 1681 17855.55 300151 1650 17855.55 294616

5 Cement plaster 1:4 10065 1798.1 180978 10065 1798.1 180978 7247 1798.1 130308

6 3152880
Add 6% 189172.8
3342052.8
S/W 2 Repair Bridge uc 120 500000 491307
S/W 3 Park chowk 234/9R 1000000 985057
4818416.8
REVISED STATEMENT FOR CONST: OF SOLING/DRAIN CUVERT RCC SLAB ,CATTLE PUND, WATER DIGGI , JANAZGAH, MUSAFAR KHANA, MATALLED ROAD , WATER SUPPLY PIPE,
SEWAR LINE, BOUNDARY WALL , KANAL BRIDGE BAHAWALNAGAR UC 25,6 ,15, CUSTRUCTION OF SOLING CHAT MOUSAM WALA , CONSTRUCTION /REPAIR OF MATTLED ROAD
UC HASSAN WALA BASTI DEWAN AZMAT CHISHTI, CONSTRUCTION OF SOLING MOUZA DOUNGIANWALA UC MUTT WALA (ORIGIONAL COST Rs=2700000/ REVISED COST 5200000/)
Work 9
Orignal No & Date 977 , 26/04/2018
Revised No & Date 1149 , 20-06-2018
Date of Completion : 15/08/2018

Estimate Soling/Bridge Estimate Soling/Bridge Paid


Sr. #
Description Quantity Rate Amount Quantity Rate Amount Quantity Rate Amount
Sub Work No. 5
UC 15 MUTT WALA
Earth work 1 mile 22184 7080.9 157082.6856 49749 7080.9 352267.6941 48207 7080.9 341348.9463
Dry Brick soling 2212.5 13882.35 307146.99375 4335 13882.35 601799.8725 4334 13882.35 601661.049
464229.67935 954067.5666 943009.9953
Add 8% pst/Gp 37138.374348 Add 6% pst/Gp 57244.054 Add 6% pst/Gp 56580.599718
501368.053698 1011311.621 999590.59502

Sub Work No. 2


UC 25 KABUTARI
Earth work excavation for 21450 4582 98283.9 103188 4582 472807.416 101737 4582 466158.934
trunch water supply
pvc pipe 3" 3300 106.2 350460 15875 106.2 1685925 15875 106.2 1685925
Earth work rehandling 17160 1523.2 26138.112 82550 1523.2 125740.16 81390 1523.2 123973.248
P/F pvc tee 3" 5 628.85 3144.25 5 628.85 3144.25
P/F pvc Bend 3" 5 225.25 1126.25 5 225.25 1126.25
P/F Plug 11 63.85 702.35 11 63.85 702.35
P/F Air valve 3 3368.55 10105.65 3 3368.55 10105.65
Sluice Valve 3" 1 6785.9 6785.9 1 6785.9 6785.9
Sluice Valve 4" 1 7979.7 7979.7 1 7979.7 7979.7
p/F G.I Flunch (10 No) 17.5 114.9 2010.75 17.5 114.9 2010.75
P/F Cost Iron special (10 50 111 5550 50 111 5550
No)
Sluice Valve chamber 1 18600 18600 1 18600 18600
Air Valve Chamber 3 6000 18000 3 6000 18000
474882.012 2358477.426 2350062.032
Add 6% pst/Gp 28492.92072 Add 6% pst/Gp 141508.6456 Add 6% pst/Gp 141003.72192
503374.93272 2499986.072 2491065.7539

Sub WorUC 6 500000 0 492616


Sub Wor
Chak musam wala 500000 0 493061
Sub Wor
Matt wala 700000 700000

G. TOTAL 2704742.98642 G. TOTAL G.Total 5176333.3489


D/D .19% pst/Gp 9835.033363
5166498.3156
COMPARATIVE STATEMENT REGARDING
CONSTRUCTION OF METALLED ROAD FROM ALI HOUSE KHICHI WALA AND STREET JAMIA MASJID CHAK NO. 235/9R, WATER DIGGI & RCC PIPE CHAK NO. 191/7R (EAST) AND RCC
PIPE 12" DIA CHAK NO. 191/7R TEHSIL FORT ABBAS DISTT. BAHAWALNAGAR
(ORIGIONAL COST Rs=2300000/ REVISED COST 3300000/)
Work 11
Orignal No & Date 979 , 26/04/2018
Revised No & Date 1181 , 29-06-2018
Date of Completion : On Going

Orignal Revised Paid


Sr. #
Description Quantity Rate Amount Quantity Rate Amount Quantity Rate Amount
Sub Work No. 2
1 Earth work excavation (95 to
4712 8384.4 39511 15213 8384.4 127548 14515 8384.4 121699.566
100%)
2 Earth work excavation (85%)
3190 7080.55 22566 18520 7080.55 131132 18517 7080.55 131110.54435
for berham
3 Providing, laying sub base
1450 10329.48 149777 4075 10329.48 420926 4075 10329.5 420927.125
course of crushed stone
4 Providing, laying road
580 29.75 17255 1630 29.75 48493 1630 29.75 48492.5
edging
6 Providing, laying base
957 13653.21 130661 2690 13653.21 367203 2689 13653.21 367134.8169
course of crushed stone
7 Providing, laying TST 3-coat
2900 3801.96 110257 8150 3801.96 309860 8150 3801.96 309859.74
TOTAL 470027 TOTAL 1405162 1399224.2923
add 6% 83953.457535
1483177.7498
Sub Work No. 1 600000 537973
Sub Work No. 3 W/D 1200000 1087140
G. total S.Work No. 1 to S.Work No. 3 1800000tal S.Work No. 1 to S.Work No. 3 0 3108290.7498
DD .18% 55949.233496
G.Total 3052341.5163

COMPERATIVE STATEMENT OF REVISED ESTIMATE FOR CONSTRUCTION OF :


TUFF TILE IN STREET NOMAN SHAHID KHICHIWALA/ CHOWK CHAK NO. 235/9R IN FRONT OF MASJID, CONSTRUCTION OF SOLING STREET USTAD BHOLY WALA KHICHI WALA , CONSTRUCT OF SOLING CHAT
258 /HL
Work 14
Orignal No & Date 982 , 26/04/2018 Amount : 2300000
Revised No & Date 1182 , 29-06-2018 Amount : 4255000
Date of Completion : On Going

Orignal Revised Paid


S.No. Description
Quantity Rate Amount Quantity Rate Amount Quantity Rate Amount
1 Dismantling of soling 920 1626.85 14967.02 920 1626.85 14967.02 920 1626.85 14967.02
2 Earth excavation 0 0 0 2483 4045.5 10044.9765 2483 4045.5 10044.9765
3 Earth filling upto 1 mile lead 6557 7232.9 47426.1253 35743 7232.9 258525.5447 35381 7232.9 255907.2349
4 Laying Brick ballast 1.5" to 2" 411 3670.9 15087.399 5951 3670.9 218455.259 5951 3670.9 218455.259
5 Laying Recoverd Brick ballast 920 4336.09 39892.028 920 4336.09 39892.028 920 4336.09 39892.028
6 P/L Tuff pavers 3550 95.9 340445 18324 95.9 1757271.6 18324 95.9 1757271.6
7 P/F Sign Board of steel. 1 14800 14800 1 14800 14800 1 14800 14800
2311338.1184
add 6% 138680.287104
Total 2450018.4055

S/W 2 Soling khichi wala 1000000 0 999205


S/W 3 Soling 258/ HR 800000 0 797786
4247009.4055
DD .18% 7644.61692991
G.Total 4239364.78857

COMPERATIVE STATEMENT OF REVISED ESTIMATE FOR :


II) P/L PVC PIPE 3" DIA UC 96 , RCC SLAB CULVERTS UC 84 , CONSTRUCTION OF WATER DIGGI /RCC PIPE 15" DIA CHAK NO 126 /6R
Work 16
Orignal No & Date 984 , 26/04/2018 Amount : 2400000
Revised No & Date 1183 , 29-06-2018 Amount : 4430000
Date of Completion : On Going

Orignal Revised Paid


S.No. Description
Quantity Rate Amount Quantity Rate Amount Quantity Rate Amount

II) PVC PIPE 3" dia UC 96 ,


RCC SLAB CULVERTS UC 84

1 Excavation in trenches upto 5' 19404 4582 88909 78320 4582 78352
2 P/L PVC Pipe 3"dia. 3234 106.2 343450 2850 102.2 302670
3 Back filling of trenchs 15523 1523.3 23648 13680 1420.3 19430
4 P/F Iron sign Board 1 15000 15000
excavation in open cutting in 5
5 0 1132 5995.45 6786.8494
to 10 ft depth
cement concrete Brick stone 18368
blast 149 12369.15
pacca brick work in ground
floor 339 17921.4 60689
Reinforced cement concrete in
roof slab 90 349.2 31344
Fabrication of mild steel 196 11636.5 22823
cement plaster 1:4 326 1798.1 5870
Rehandling of earth work 678 7693.05 5216
Dismatelling of road 306 1136 3476
excavation in open cutting in 5
to 10 ft depth 10880 5995.45 65233
cement concrete Brick stone
blast 106 12369.15 13150
pacca brick work in ground
floor 263 17921.4 47180
Reinforced cement concrete in
roof slab 71 349.2 24695
Fabrication of mild steel 120.19 11636.5 13985
cement plaster 1:4 364 1798 6550
Rehandling of earth work 10459 7693.05 80461
excavation in open cutting in 5
to 10 ft depth 1221 5995.45 7320
cement concrete Brick stone
blast 122 12369.15 15029
pacca brick work in ground
floor 302 17921.4 54092
Flat Brick flooring 1;6 270 5282.95 14277
Reinforced cement concrete in
roof slab 71 349.2 24695
Fabrication of mild steel 163.27 11636.5 18998
cement plaster 1:4 237 1798.1 4265
Rehandling of earth work 686 7693.05 5277
excavation in open cutting in 5
to 10 ft depth 1672 5995.45 10024
cement concrete Brick stone
blast 185 12369.15 22821
pacca brick work in ground
floor 409 17921.4 73334
Reinforced cement concrete in
roof slab 109 349.2 37993
Fabrication of mild steel 170.56 11636.5 19847
cement plaster 1:4 187 1798.1 3362
Rehandling of earth work 1218.25 7693.05 9372

Earth filling in the road and 5960 7080.45 360820


embankment Lead up to 1 Mile

excavation in open cutting in 5


to 10 ft depth 1221 5995.45 7322
cement concrete Brick stone
blast 122 12369.15 15029
pacca brick work in ground
floor 302 17921.4 54092
Flat Brick flooring 1;6 270 5282.95 14277
Reinforced cement concrete in
roof slab 71 349.2 24695
Fabrication of mild steel 146.3 11636.5 17024
cement plaster 1:4 237 1798.1 4261
Rehandling of earth work 686.25 7693.05 5279
COMPERATIVE STATEMENT OF REVISED ESTIMATE FOR CONSTRUCTION OF :
I) WATER DIGGIGI CHAK NO. 126/6R -
Work 16
Orignal No & Date 984 , 26/04/2018 Amount : 2400000
Revised No & Date 1183 , 29-06-2018 Amount : 4430000
Date of Completion : On Going

Orignal Revised Paid


S.No. Description
Quantity Rate Amount Quantity Rate Amount Quantity Rate Amount
1 Excavation of well in dry soil
0' - 5' depth 7955 4527.2 36015 7955 4527.2 36015 7955 4527.2 36013.876
5' - 10' depth 7955 4728.25 37615 7955 4728.25 37615 7955 4228.25 33635.72875
10' - 15' depth 7956 5319.15 42318 7956 5319.15 42318 7955 5319.15 42313.83825
15' - 20.75' depth 7955 6105.3 2539.08 7955 6105.3 48570 7955 6105.3 48567.6615
2 Cement conc. 1:6:12 956 10495..35 100336 956 10495..35 100336 956 10495.35 100335.546
3 Cement conc. 1:2:4 314 21987.25 69040 314 21987.25 69040 314 21987.25 69039.965
Pacca brick work other than
4 1656 19199.2 317939 1656 19199.2 317939 2858 19199.2 548713.136
building 1:4: upto 10' height.
Above 10' height. 1203 20939.6 251867 1203 20939.6 251867
5 P/F Angle iron 1.5x1.5x3/16" 18 251 4518 18 251 4518 18 251 4518
6 Flat brick flooring in 1:6 427 5282.95 22558 427 5282.95 22558 427 5282.95 22558.1965
7 Cement Plaster 1:4 2611 1798.1 46950 2611 1798.1 46930 2610 1798.1 46930.41
8 Const. of boundry wall 149 1527.13 227542 149 1527.13 227542 149 1527.13 227542.37
9 P/F Steel gate 3'x4' 16 717.4 11488 16 717.4 11478 2 6000 12000
10 P/L RCC Pipe 15" dia. 622 731.47 454974 1332 731.47 974318 500 500 250000
11 Manhole 4' dia 5' deep 3 38000 114000 7 38000 266000 0 0 0
12 RCC Pacca nacca 2 3500 7000 2 3500 7000 0 0 0
13 Earth filling upto 1 mile lead 0 0 0 4460 7080.55 31579 0 0 0
14 P/L Dry brick soling 0 0 0 375 13882.35 52059 0 0 0
1442168.728

Pvc Pipe 18 /1 R uc 96 500000 273007


Excavation 0 to 5 ft depth 19404 4582 88909 19404 4582 88909 12000 4582 45984
Pvc pipe 3" dia 3234 106.2 343451 3234 106.2 343451 2000 106.2 212400
Back filling 15523 1523.3 23646 15523 1523.3 23646 9600 1523.2 14623
p/f of iron sing boad 1 15000 15000 1 15000 15000 0 0 0
273007
COMPARATIVE STATEMENT REGARDING
CONST: OF BRIDGCE CANAL 3/R NEAR CHAK 46/3R, SOLING CHAK NO. 63/4R, 39/3R, 39/3R, 44/3R AND BASTI FAZAL LALEKA (BHAWAN SHAH) TEHSIL HAROON ABAD DISTT.
BAHAWALNAGAR (ORIGIONAL COST Rs=2850000/ REVISED COST 3300000)
Work 19
Orignal No & Date 987 , 26/04/2018
Revised No & Date 1163 , 25-06-2018
Date of Completion : 27-7-2018

Orignal Revised Paid


Sr. #
Description Quantity Rate Amount Quantity Rate Amount Quantity Rate Amount
Sub Work No. 1
1 Excavation in foundation 4032 6434.2 25943 4032 6434.2 25943 4032 6434.2 25942.6944
building bridges etc.
2 Cement concrete (1:4:8) 336 12369.15 41560 336 12369.15 41560 336 12369.15 41560
3 Pacca brick work (1:4) F&P 1678 17855.55 299527 1678 17734.85 299527 1678 17734.85 299527
4 RCC Slab (1:2:4) 426 349.2 148672 1266 349.2 442087 1266 349.2 442087
5 Fabrication of miled steel 2745 11636.5 335787 2583 11636.5 300570 2578 11636.5 299988.97
6 cement plaster (1:4) 558 1798.1 357 1798.1 6419 357 1798.1 6419
7 Earth work lead up to one 11083 7080.55 3345 7080.55 24194 3345 7080.55 24194
mile
8 Providing, laying dry brick 1073 13882.35 281 13882.35 39009 281 13882.35 39009
soling
1178727.6644
say 1177793
Sub Work No. 2 63/4R 450000 425839
Sub Work No. 3 39/3R soling 150000 141654
Sub Work No. 4 39/3R soling 400000 377742
Sub Work No. 5 34/3R soling 300000 284150
1229385
Sub Work No. 6
1 Earth work lead up to one 32469 7080.55 229898 42000 7080.55 270973 37464 7232.9 270973.3656
mile
2 Providing, laying dry brick 2730 13882.35 378988 3150 13882.35 437294 3150 13882.35 437294
soling
708267.3656
G.Total 3115445.3656
COMPARATIVE STATEMENT REGARDING
CONSTRUCTION OF METALLED ROAD, CULVERTS PHASE FIRST LUMBRAN WALI JHAAL TO BHENI MOHARAN TEHSIL MINCHIN ABAD DISTRICT BAHAWALNAGAR (ORIGIONAL
COST Rs=3000000/ REVISED COST 5242000/)
Work 21
Orignal No & Date 989 , 26/04/2018
Revised No & Date 1150 , 20-06-2018
Date of Completion : On Going

Orignal Revised Paid


Sr. #
Description Quantity Rate Amount Quantity Rate Amount Quantity Rate Amount
Sub Work No. 1
1 Earth work lead up to one
80661 8513.45 686707 125736 8513.45 1070446 125631
mile 8513.45 1069553.237
2 Providing, laying sub base
7500 10180.68 763551 12512 10180.68 1274112 12515
course of crushed stone 10180.68 1274112.102
3 Providing, laying road
30000 29.75 89250 5006 29.75 148929 5006
edging 29.75 148928.5
4 Providing, laying base
4950 13501.94 668346 8260 13501.94 1115260 8260
course of crushed stone 13501.94 1115260.244
5 Providing, laying TST 3-coat
15000 3792.66 568898 25030 3792.66 949303 25030
3792.68 949307.804
4557161.887
6 Construction of culverts 5 75000 375000
1 Earth work excavation in
1350
foundation 5419.05 7315.7175
2 C/C Brick Blast 1:510 140 11298.8 15818.32
3 Brick on Edge Flooring 340 7357.65 25016.01
4 Pacca Brick work 1:4 540 17555.8 94801.32
5 Fabrication of miled steel 850 11636.5 98910.25
RCC Slab 1:2:4 319 349.2 111394.8
Cement Plaster 1/2 Thick
120 1798.1
1:4 2157.72
355414.1375
G.Total 4912576.0245
add 6% 294754.56147
5207330.5859
DD.22% 11456.127289
G.Total 5195874.4586
COMPARATIVE STATEMENT REGARDING
CONSTRUCTION OF METALLED ROAD BASTI MUSLA U/C KALIYA SHAH TEHSIL & DISTRICT BAHAWALNAGAR
(ORIGIONAL COST Rs=2200000/ REVISED COST 5000000/)
Work 22
Orignal No & Date 990 , 26/04/2018
Revised No & Date 1151 , 20-06-2018
Date of Completion : On Going

Orignal Revised Paid


Sr. #
Description Quantity Rate Amount Quantity Rate Amount Quantity Rate Amount
Sub Work No. 1
1 Dismantling dry brick
1008 517.9 5222 1008 517.9 5222 1008 517.9 5220.432
masonary
2 Earth work lead up to one
38675 8513.45 329255 99852 8513.45 850085 99852 8513.45 850085.0094
mile
3 Providing, laying sub base
7577 10192.68 517448 12752 10192.68 1299770 12752 10192.68 1299770.5536
course of crushed stone
4 Brick Ballast 1-1/2" to 2"
1008 5224.02 52658 1008 5224.02 52658 1008 5224.02 52658.1216
gauge.
5 Providing, laying road
2434 29.75 72412 5504 29.75 163744 5504 29.75 163744
edging
6 Providing, laying base
4016 13514.14 542741 9081 13514.14 1227219 9081 13514.14 1227219.0534
course of crushed stone
7 Providing, laying TST 3-coat
12170 3793.41 461657 27520 3793.41 1043946 27520 3793.41 1043946.432
8 Const. of RCC Culverts 1 No. 14800 75000 1 No. 75000 75000 1 74272 74272
TOTAL 2056393 TOTAL 4717644 4716915.602
Add 6% 283014.93612
4999930.5381
DD..19% 9499.8680224
4990430.6701

STATEMENT SHOWING QUANTITIES INFORMATION ORIGNAL/ REVISED SCHEMES


DISTRICT COUNCIL BAHAWALNAGAR FOR THE YEAR 2017-18

WORK NO 23
NAME OF SCHEME. CONSTRUCTION OF MATALLED ROAD BARA QAMAR DIN

WORK ORDER NO & DATE 991 , 26/4/2018 RS: 2200000/-


ORIGNAL
WORK ORDER DATE
REVISED/ENHANCMENT 1169, 25/6/2018 RS: 3000000/-
COMPLETION DATE ON GOING

ORIGNAL WORK REVISED WORK PAID


ITEM DESCRIPTION
NO
ITEM DESCRIPTION
NO
QUANTITY RATE AMOUNT QUANTITY RATE AMOUNT QUANTITY RATE AMOUNT

SOLING BASTI DR YOUNIS

1 Earth work 1/2 MILE 73084 8241.2 602299.8608 103774 8241.2 855222.2888 103773 8241.2 855214.0476

2 SUB BASE COURSE 4636 10137.48 469973.5728 6425 10137.48 651333.09 6425 10137.48 651333.09

3 ROAD ENDING 1855 29.75 55186.25 2570 29.75 76457.5 2570 29.75 76457.5

4 BASE COURSE 3091 13458.02 415987.3982 4240 13458.02 570620.048 4221 13458.02 568063.0242

5 T S T COMPLETE 9312 3789.96 352921.0752 12850 3789.96 487009.86 12850 3789.96 487009.86

6 CONSTRUCTION OF RCC 1 140820 140820 1 140820 140820 1 140820 140820

7 2037188.157 2781462.7868 2778897.5218

9 Add 8% pst/Gp 162975.05256 DD .17% LESS 4728.4867376 DD .17% LESS 4724.12578706

2200163.20956 2776734.3001 2774173.39601

2200000 Add 8% Pst/Gp cont 222138.744 Add 6% Pst/Gp cont 221933.871681

2998873.0441 C 2996107.26769

TOTAL= 2996107.26769

COMPARATIVE STATEMENT REGARDING


REVISED DETAILED ESTIMATE FOR CONSTRUCTION/REPAIR OF METALLED ROAD & CONST. OF SOLING TOBA QALANDAR SHAH DISTRICT COUNCIL BAHAWALNAGAR
(ORIGIONAL COST Rs=3000000/ REVISED COST 9000000/)
Work 29
Orignal No & Date 997 , 26/04/2018
Revised No & Date 1152 , 20-06-2018
Date of Completion : 29/08/2018

Orignal Revised Revised


Sr. #
Description Quantity Rate Amount Quantity Rate Amount Quantity Rate Amount
Sub Work No. 1
1 Earth work lead up to one
41300 7690 317593 147587 7690 1134944 144046
mile 7690 1107713.74
2 Providing, laying road
2000 29.75 59500 6800 29.75 202300 6720
edging 29.75 199920
4 Providing, laying base
763 13431 102516 4295 13431 576817 4241.75
course of crushed stone 13431 569709.4425
5 Providing, laying TST 3-coat
54845 3788.3 2077696 127596 3788.3 4833708 128895
3788.3 4882929.285
6760272.4675
Add 17% 1149246.3195
Work Done Paid 7909518.787
Const. of Soling
1 Earth work lead up to one
40260 7080.55 285063 38395
mile 7080.55 271857.71725
2 Bed clearance earth work 2808 4613.7 12955 3037 4045.75 12286.94275
3 Providing, laying dry brick
6351 13882.35 744371 5350
soling 13882.35 742705.725
1026850.385
Add 6% 61611.0231
1088461.4081
Total 8997980.1951
DD. .25% 22494.950488
G.Total 8975485.2446

STATEMENT SHOWING QUANTITIES INFORMATION ORIGNAL/REVISED SCHEMES DISTRICT CONCIL BAHAWALNAGAR YAER 2017-18

WORK NO 31
CONST. OF SOLING, DRAIN, R.C.C. SLABS, BASTI KHEM GARH,CONSTRUCTION OF SOLING, WATER
SUPPLY PIPE LINE BASTI , MOUZA TOBA ALLAH YAR U.C. 38 MALIK PUR
NAME OF SCHEME

ORIGNAL WORK ORDER NO &


DATE 999 , 26/04/2018 Rs: 2500000/-
REVISED WORK ORDER NO &
DATE 1168, 25/06/2018 Rs; 4500000/-
COMLITION ON GOING

ITEM Orignal Estimate Revised Estimate Paid


DESCRIPTION
NO Quantity Rate Amount Quantity Rate Amount Quantity Rate Amount
SOLING, DRAIN, R.C.C. SLABS,
BASTI KHEM GARH

Earth filling 1 mile. 215638.15025 215638.15025


1 30455 7080.55 30455 7080.55 30431 7080.55 215468.21705
448174.9015 448174.9015
2 Providing and laying soling 3349 13382.35 3349 13382.35 3349 13382.35 448174.9015

3 Drain Type-Ist 585 328.32 192067.2 585 328.32 192067.2 274 328.32 89959.68

4 Reinforced cement concrete 86 349.2 30031.2 86 349.2 30031.2 35.75 349.2 12483.9
Fabrication of mild steel Grad 23761.4775 23761.4775
5 -40 215 11051.85 215 11051.85 92 11051.85 10167.702

SOLING, WATER SUPPLY PIPE


LINE BASTI , MOUZA TOBA
ALLAH YAR U.C. 38 MALIK PUR

Excavation of trenches for


1 water supply pipe 44100 4582 202066 49000 4582 224518 44100 4582 202066.2

2 P/L PVC pipe 3'' Dia 6300 106.2 669060 6300 106.2 669060 6300 106.2 669060

2 P/L PVC pipe 4'' Dia 0 159.25 0 700 159.25 111475 0 159.25 0

3 Pvc Tee 3 628.85 1886.55 3 628.85 1886.55 0 628.85 0

4 PVC Bend 4 225.25 901 4 225.25 901 0 225.25 0

5 Air valve 4 7628.55 30514.2 4 7628.55 30514.2 0 7628.55 0

6 Saluos Valve 1 6785.9 6785.9 3 6785.9 20357.7 0 6785.9 0

7 Back Filling 35280 1523.3 53742.024 39200 1523.3 59713.36 0 1523.3 0

8 Const. of Chambar 1 20303 20303 1 20303 20303 0 20303 0


Making connection for new
9 watersupply lines 1 1739 1739 1 1739 1739 0 1739 0
10 Earth filling 1/4 mile. 20511 6865.75 140823.39825 20511 6865.75 140823.39825 20438 6865.75 140322.1985
10 Earth filling 1mile. 0 7080.55 0 67193 7080.55 475763.39615 67148 7080.55 475444.7714

11 Providing and laying soling 1875 13382.35 250919.0625 10687 13382.35 1430171.7445 10687 13382.35 1430171.7445

STATEMENT SHOWING QUANTITIES INFORMATION ORIGNAL/ REVISED SCHEMES


DISTRICT COUNCIL BAHAWALNAGAR FOR THE YEAR 2017-18

WORK NO 32

CONSTRUCTION OF SOLING BASTI DR YOUNIS ,BASTI BORANA ,BASTI


NAME OF SCHEME. FAQEERAN WALA
WORK ORDER NO & DATE
ORIGNAL 1000 , 26/4/2018 RS: 2900000/-

WORK ORDER DATE 1177 , 29/6/2018 RS: 5000000/-


REVISED/ENHANCMENT
COMPLETION DATE ON GOING

ORIGNAL WORK REVISED WORK PAID


ITEM DESCRIPTION
NO
QUANTITY RATE AMOUNT QUANTITY RATE AMOUNT QUANTITY RATE AMOUNT

SOLING BASTI DR YOUNIS

1 Earth work 100 Ft 25869 4045.8 104660 25869 4045.8 104660 22682.8 4045.8 91770.07224

2 P/l Dry Brick soling 2587.5 13882.35 359205 2587.5 13882.35 359205 2322.5 13882.35 322417.57875

3 463865 463865 414187.65099

4 Add 8% pst/Gp 37109.2 D/d .65% T rate 3015.1225 D/d .65% T rate 2692.21973144

5 500974.2 466880.1225 411495.431259

6 Add 8% Pst/Gp cont 37350.4098 Add 6% Pst/Gp cont 24689.7258755

7 504230.5323 A 436185.157134

8 SOLING BASTI BORANA

Earth work 1 MILE LEAD 11074 7080.55 78410.0107 11074 7080.55 78410.0107 10993.5 7080.55 77840.026425

P/l Dry Brick soling 2103.75 13882.35 292049.938125 2103.75 13882.35 292049.93813 2087.24 13882.35 289757.96214

370459.948825 370459.94883 367597.988565

Add 8% pst/Gp 29636.795906 D/d .65% T rate 2407.9896674 D/d .65% T rate 2389.38692567

400096.744731 372867.93849 365208.601639

Add 8% Pst/Gp cont 29829.435079 Add 6% Pst/Gp cont 21912.5160984

402697.37357 B 387121.117738
BASTI FAQIRANAWALI
EARTH WORK100 FT 81216 4045.75 328579.632 182421 4045.75 738029.76075 182082 4045.75 736658.2515
EARTH WORK LEAD UPTO I
MILE 27495 7080.55 194679.72225 25916 7080.55 183499.5338 25865 7080.55 183138.42575

DRY BRICKS SOLING 9637.5 13882.35 1337911.48125 20762.7 13882.35 2882350.6835 20707.5 13882.35 2874687.62625

1861170.8355 3803879.978 3794484.3035

9 Add 8% pst/Gp 148893.66684 D/d .65% T rate 24725.219857 D/d .65% T rate 24664.1479728

2010064.50234 3779154.7581 3769820.15553

Add 8% Pst/Gp cont 302332.38065 Add 6% Pst/Gp cont 226189.209332

4081487.1388 C 3996009.36486

TOTAL= A+B+C 4819315.63973

REVISED STATEMENT FOR CONST: OF SOLING/BRIDGE BASTI BRIGADIER FAROOQ SAHIB, CONST/REPAIR OF METALLED ROAD CHAK NO.125/6R KAMUKAN WALI, CONST/REPAIR
OF METALLED ROAD HEAD 7/R TEHSIL HAROON ABAD DISTT. BAHAWALNAGAR (ORIGIONAL COST Rs=3000000/ REVISED COST 3500000/)
Work 36
Orignal No & Date 1004 , 26/04/2018
Revised No & Date 1153 , 20-06-2018
Date of Completion : 21/07/2018

Estimate Soling/Bridge Estimate Soling/Bridge Paid


Sr. #
Description Quantity Rate Amount Quantity Rate Amount Quantity Rate Amount
Sub Work No. 1
1 Excavation in foundation
1174 6434.2 7553 1174 6434.2 7553
building bridges etc. 1175 6434.2 7553
2 Cement concrete (1:4:8) 392 12369.15 48487 392 12369.15 48487 392 12369.15 48487
3 Pacca brick work (1:4) F&P
1434 17734.85 254317.749 1461 17734.85 259106
1461 17734.85 259106
4 RCC Slab (1:2:4) 546 349.2 190663.2 546 349.2 190663 546 349.2 190663
6 Fabrication of miled steel 1774 11636.5 206431.51 1774 11636.5 206432 1771 11636.5 206082
7 cement plaster (1:4) 558 1798.1 10033.398 720 1798.1 12946 720 1798.1 12946
8 Earth work lead up to one
11083 7080.55 78473.73565 37009 7080.55 262044
mile 37009 7080.55 262044
9 Providing, laying dry brick
1073 13882.35 148957.6155 3089 13882.35 428826
soling 3089 13882.35 428825
TOTAL 944914 TOTAL 1416057 1415706
Add 6% PST/GP 56694.84 Add 6% PST/GP 84963 Add 6% pst/Gp 84942.36
Total 1001608.84 1501020 1499999.96
SAY 1000000 1500000

Sub Work No. 2 1000000 Sub Work No. 2 1000000 1000000


Sub Work No. 3 1000000 Sub Work No. 3 1000000 1000000
G. TOTAL 3000000 G. TOTAL 3500000 3499999.96
D/D .22% pst/Gp 7700
3492299.96

COMPARATIVE STATEMENT REGARDING


CONST: OF SOLING CHAK NO. 137/6R, CONST. OF SOLING CHAK NO. 429/6R SMALL , CONST. OF SOLING , CATTLE POND , JANAZ GAH AZAFI BASTI CHAK NO. 43/3R, CONST. OF
SOLING 162/7R TO SCHOOL, CONST. OF SOLING 163/7R TO SCHOOL, RCC PIPE ETC. CHAK NO. 62/4R HAROON ABAD DISTT. BAHAWALNAGAR (ORIGIONAL COST Rs=2650000/
REVISED COST 3600000/)
Work 38
Orignal No & Date 1006 , 26/04/2018
Revised No & Date 1154 , 26-04-2018
Date of Completion : 03/08/2018

Orignal Revised Paid


Sr. #
Sr. #
Description Quantity Rate Amount Quantity Rate Amount Quantity Rate Amount
Sub Work No. 3
1 Earth work lead up to one
mile 12740 7232.9 92147 59124 7232.9 427638 60195 7232.9 435384.4155
2 Providing, laying dry brick
2438 13882.35 338452 6338 13882.35 879863 6325 13882.35 878058.6375
soling
3 Providing, laying brick tile 9"
4200 5905.85 248045 4200 5905.85 248045 4200 5905.85 248045.7
1561488.753
Sub Work No. 1 soling 137/6R 350000 329914
Sub Work No. 2 soling 429/6R 300000 283310
Sub Work No. 4 soling 162/7R 500000 472178
Sub Work No. 5 soling 163/7R 500000 472178
Sub Work No. 6 soling 62/4R 300000 283310
Total 1840890
G.Total 3402378.753

REVISED STATEMENT FOR : CONSTRUCTION OF CHAK NO. 197/HB TO END OF GRAVEYARD ,CONSTRUCTION OF BRIDGE SAFFON ETC CHAK NO.245/HL
Work 39
Orignal No & Date 1007 , 26/04/2018 Amount : 2850000
Revised No & Date 1137 , 03-06-2018 Amount : 4180000
Date of Completion : On Going

Orignal Revised Difference


S.No.
Description Quantity Rate Amount Quantity Rate Amount Quantity Rate Amount
1 Earth filling 1 mile lead 95155 7080.55 673749 174196 7080.55 1233403 163019 7080.55 1154264.18045
2 Dry brick soling 8288 13882.35 1150569 13209 13882.35 1833720 13930 13882.35 1933811.355
4 Construction of Arch culvert 1 47000 47000 1 47000 47000 1 46916 46916
3134991.53545
add 6 % 188099.492127
3323091.02758
Const. of Bridges Chak no.
245/HR 850000
834523
4157614.02758
dd .16 % 6652.18244412
G.Total 4150961.84513

STATEMENT SHOWING QUANTITIES INFORMATION ORIGNAL/ REVISED SCHEMES


DISTRICT COUNCIL BAHAWALNAGAR FOR THE YEAR 2017-18

WORK NO
43
CONSTRUCTION OF SOLING ,DRAINS , PULL SAIM NALA GRAVEYARD
NAME OF SCHEME. HAFIZWALA U/C ISLAMPURA,
WORK ORDER NO & DATE 1011 , 26/4/2018 RS:2100000/-
ORIGNAL
WORK ORDER DATE 1174 , 29/6/2018 RS:5000000/-
REVISED/ENHANCMENT

COMPLETION DATE 27/07/2018

ITEM ORIGNAL WORK REVISED WORK PAID


DESCRIPTION
NO QUANTITY RATE AMOUNT QUANTITY RATE AMOUNT QUANTITY RATE AMOUNT
CONSTRUCTION OF SOLING
DRAIN PULL HAFIZWALA

EXCAVATION OF BRIDGE 8941 6434.2 57528.1822 8940.8 6434.2 57526.89536 8981 6434.2 57785.5502
CEMENT CONCRETE 1;4:8 2000 12369.15 247383 1999.6 12369.15 247333.5234 2010 12369.15 248619.915
2968 17139.15 508689.972 2970.61 17139.15 509137.30382 2986 17139.15 511775.019
PACCA BRICKS WORK 1;4:F&P
FABRICATION OF MILD STEEL 2798 11385.75 318573.285 2658.62 11385.75 302703.82665 2640 11385.75 300583.8
R C C WORK SLAB 1:2:4 603 349.2 210567.6 602.5 349.2 210393 603 349.2 210567.6
R C C WORK SLAB 1:2:4 131 254.05 33280.55 93.75 254.05 23817.1875 93.75 254.05 23817.1875
WITHOUT SHUTTRING
EARTH WORK 1/2 MILE 39325 8241.2 324085.19 139711 8241.2 1151386.2932 139812 8241.2 1152218.6544
DRY BRICK SOLING 1947 13882.35 270289.3545 15346.33 13882.35 2130431.2428 15329.7 13882.35 2128122.60795
1970397.1337 4632729.2727 4633490.33405
Add 8% pst/Gp 157631.770696 DD .20% LESS 9265.4585454 DD .20% LESS 9266.9806681
2128028.904396 4623463.8141 4624223.35338
Add 8% pst/Gp 369877.10513 Add 6% Pst/Gp cont 277453.401203
4993340.9193 4901676.75458

STATEMENT SHOWING QUANTITIES INFORMATION ORIGNAL/ REVISED SCHEMES


DISTRICT COUNCIL BAHAWALNAGAR FOR THE YEAR 2017-18

WORK NO
46
CONSTRUCTION OF SOLING UC MUSSA BHOTA , CONSTRUCTION
MATALLED ROAD ROJHANWALI ROAD MORE TO BASTI ROJHANWALI,
NAME OF SCHEME. SOLING BASTI RIAZ BAITU UC MUHAMMAD PUR, SOLING DRAIN MAIN
ROAD HAROON ABAD TO BOYS SCHOOL SWAIWALA

WORK ORDER NO & DATE 1015 , 26/4/2018 RS:2800000/-


ORIGNAL

WORK ORDER DATE


1164 , 25/6/2018 RS: 3800000/-
REVISED/ENHANCMENT

COMPLETION DATE ON GOING

ITEM ORIGNAL WORK REVISED WORK PAID


DESCRIPTION
NO QUANTITY RATE AMOUNT QUANTITY RATE AMOUNT QUANTITY RATE AMOUNT
UC MUSSA BHOTA (ORIGNAL
RS: 800000 & REVISED RS:
800000)
1 Earth work 100 FT 39316 4045.75 159062.707 39316 4045.75 159062.707 39316 4045.75 159062.707
2 DRY BRICK SOING 3918.75 13882.35 544014.590625 3918.75 13882.35 544014.59063 3918.7 13882.35 544007.64945
3 ARCH CULVERTS 1 41207.4 41207.4 1 41207.4 41207.4 1 44548 44548
744284.697625 744284.69763 747618.35645
Add 8% pst/Gp 59542.77581 D/D .786% pst/Gp 5850.0777233 D/D .786% pst/Gp 5876.2802817
803827.473435 738434.6199 741742.076168
800000 Add8% pst/Gp 59074.769592 Add8% pst/Gp 59339.3660935
797509.38949 801081.442262
800000 800000
MATALLED ROAD
ROJHANWALI
1 DISMENTALING OF SOLING 1812.48 1516.9 27493.50912 2704.56 1516.9 41025.47064 2704 1516.9 41016.976

2 Earth work 1/2 MILE 19200 5350 102720 28650 5350 153277.5 28650 5350 153277.5
SUB BASE COURSE BRICK
3 WORK 1815 5224 94815.6 2700 5224 141048 2700 5224 141048
4 SUB BASE COURSE OF STONE 1385 10121 140175.85 2075 10121 210010.75 2075 10121 210010.75

5 ROAD ENDING 1280 29.75 38080 1910 29.75 56822.5 1910 29.75 56822.5

6 BASE COURSE 2112 13441 283873.92 3158.1 13441 424480.221 3158 13441 424466.78

7 T S T COMPLETE 6400 3788.9 242489.6 9570 3788.9 362597.73 9570 3788.9 362597.73

8 929648.47912 1389262.1716 1389240.236

9 Add 8% pst/Gp 74371.8783296 D/D .786% pst/Gp 10919.600669 Add 8% pst/Gp 111139.21888

1004020.35745 1378342.571 1500379.45488

1000000 Add8% pst/Gp 110267.40568 1000000

1488609.9766 C 2500379.45488

1500000 TOTAL= 2500379.45488

SOLING BASTI RIAZ BETU


(ORIGNAL RS: 500000 &
REVISED RS: 500000)

1 Earth work 100 FT 23336 4045.75 94411.622 23336 4045.75 94411.622 25506.9 4045.75 103194.540675

2 DRY BRICK SOING 2325 13882.35 322764.6375 2325 13882.35 322764.6375 2365.2 13882.35 328345.3422

3 RCC PIPE CULVERTS 2 23660 47320 2 23660 47320 2 17390 34780

464496.2595 464496.2595 466319.882875

Add 8% pst/Gp 37159.70076 D/D .786% pst/Gp 3650.9405997 D/D .786% pst/Gp 3665.2742794

501655.96026 460845.3189 462654.608596

500000 Add8% pst/Gp 36867.625512 Add8% pst/Gp 37012.3686876

497712.94441 499666.977283

500000
SOLING SAWAI WALA
(ORIGNAL RS: 500000 &
REVISED RS: 1000000)
1 Earth work UP TO I MILE 19623 7080.35 138937.70805 37835 7080.35 267885.04225 37366.5 7080.35 264567.898275
2 DRY BRICK SOING 2343.75 13882.35 325367.578125 4312.5 13882.35 598676.34375 4077.3 13882.35 566025.05655
3 FABRICATION OF MILD STEEL 0 83.81 11385.75 9542.397075 81.28 11385.75 9254.3376
RCC 1:2:4 464305.286175 36.96 342.8 12669.888 37.86 342.8 12978.408
RCC CULVERT 2 23660 47320 2 23660 47320
936093.67108 900145.700425
Add 8% pst/Gp 464305.286175 D/D .786% pst/Gp 7357.6962546 D/D .786% pst/Gp 7075.14520534
500000 928735.97482 893070.55522
Add8% pst/Gp 74298.877986 Add6% pst/Gp 53584.2333132
1003034.8528 946654.788533
1000000
REVISED STATEMENT FOR CONST & REPAIR OF MATALLED ROAD DAHRANWALA , FORTABAS ROAD CHAK 175/7R , 235/9R , WATER SPPLY PIPE 319/HR & SOLING 319/HR ALAF
(ORIGIONAL COST Rs=3000000/ REVISED COST 6400000/)
Work 52
Orignal No & Date 1021 , 26/04/2018
Revised No & Date 1185 , 29-06-2018
Date of Completion : ON GOING

Oringal Revised Paid


Sr. #
Description Quantity Rate Amount Quantity Rate Amount Quantity Rate Amount
Sub Work No. 3 (A)
Cons & Repair Road
Earth work 1 mile 9240 7232.79 66830.9796 9240 7232.79 66830.9796 9182 7232.79 66411.47778
P/L Road Edging 1680 29.75 49980 1680 29.75 49980 1680 29.75 49980
P/L Base Cource 3150 13653.21 430076.115 3150 13653.21 430076.115 3130 13653.21 427345.473
P/L TST 3-Cot 67 LBS 8400 3801.96 319364.64 8400 3801.96 319364.64 8400 3801.96 319364.64
863101.59078
Add 16% pst/Gp 138096.25452
1001197.8453
1000000
Sub Wor
New Matalled Road
Earth work 1 mile 0 42570 8384.4 356923.908 42519 8384.4 356496.3036
0 50126 7232.79 362550.8315 49855 7232.79 360590.74545
Earth filling for Baram (85%)
P/L Sub Base Cource 0 8850 10329.48 914158.98 8850 10329.48 914158.98
P/L Road Edging 0 3540 29.75 105315 3540 29.75 105315
P/L Base Cource 5841 13653.21 797483.9961 5841 13653.21 797483.9961
P/L TST 3-Cot 67 LBS 17700 3801.96 672946.92 17700 3801.96 672946.92
3206991.9452
Add 6% pst/Gp 192419.51671
3399411.4619
Total =A+B 4399411.4619
Sub Wor
Cons: of soling chak 319 1500000 0 1440731
Pvc Pipe chack 319 /hr 500000 0
Sub Wor 499221
Alaf
Total 6339363.4619
STATEMENT SHOWING QUANTITIES INFORMATION ORIGNAL/ REVISED SCHEMES
DISTRICT COUNCIL BAHAWALNAGAR FOR THE YEAR 2017-18

WORK NO
60
CONSTRUCTION OF SOLING BASTI CHAWAYKA, BASTI TAJ JODHAYKA,
NAME OF SCHEME. CONSTRUCTION OF SOLING LALIKA ROAD TO GRAVETARD BABA SAID
RASOOL SHAH.

WORK ORDER NO & DATE 1029 , 26/4/2018 RS:2500000/-


ORIGNAL

WORK ORDER DATE 1130 , 03/6/2018 RS: 5000000/-


REVISED/ENHANCMENT

COMPLETION DATE ON GOING

ITEM ORIGNAL WORK REVISED WORK PAID


DESCRIPTION
NO QUANTITY RATE AMOUNT QUANTITY RATE AMOUNT QUANTITY RATE AMOUNT
CHAWAYKA U/C 34 TOBA
QALANDAR SHAH(ORIGNAL
RS: 100000 & REVISED RS:
2000000)
1 Earth work UP TO 1 MILE 32460 7080.55 229834.653 64908 7080.55 459584.3394 66150.8 7080.55 468384.04694
2 DRY BRICK SOING 5021.25 13882.35 697067.499375 10020 13882.35 1391011.47 10020 13882.35 1391011.47
3 UP LAVELING MAN HOLE 0 3500 0 4 3500 14000 0 3500 0
926902.152375 1864595.8094 1859395.51694
Add 8% pst/Gp 74152.17219 D/D .65% pst/Gp 12119.872761 D/D .65% pst/Gp 12086.0708601
1001054.324565 1852475.9366 1847309.44608
1000000 Add8% pst/Gp 148198.07493 Add6% pst/Gp 110838.566765
2000674.0116 1958148.01284
2000000 A 2000000
CONSTRUCTION SOLING BASTI
TAJ JODHAYKA (ORIGNAL
RS:500000 & REVISED
RS:500000)
1 EARTH FILLING UP TO I MILE 2784.84 7080.55 19718.198862 2784.84 7080.55 19718.198862 2784.84 7080.55 19718.198862
2 DRY BRICKS SOLING 530.34 13882.35 73623.65499 530.34 13882.35 73623.65499 502.47 13882.35 69754.644045
3 FABRICATION OF MILD STEEL 186 11385.75 21177.495 186 11385.75 21177.495 119 11385.75 13549.0425
4 CEMENT CONCERETE 1:2:4 61.38 342.8 21041.064 61.38 342.8 21041.064 61.38 342.8 21041.064
5 CONSTRUCTION OF KHAL 339 962.41 326256.99 339 962.41 326256.99 339 962.41 326256.99
461817.402852 461817.40285 450319.939407
Add 8% pst/Gp 36945.39222816 Add 8% pst/Gp 36945.392228 D/D .65% pst/Gp 2927.07960615
498762.7950802 498762.79508 447392.859801
500000 500000 Add 6% pst/Gp 26843.5715881
B 474236.431389

CONSTRUCTION SOLING BABA


SAID RASOOL SHAH (ORIGNAL
RS :1000000 & REVISED
RS:2500000)
1 EARTH FILLING UP TO I MILE 28270 7080.6 200168.562 93545 7080.6 662354.727 93488 7080.55 661946.4584
2 DRY BRICKS SOLING 4818.75 13882.35 668955.740625 11690.8 13882.35 1622957.7738 11685.69 13882.35 1622248.38572
3 CONSTRUCTION OF DRAIN 1 63247 63247 1 48301 48301 1 48301 48301
932371.302625 2333613.5008 2332495.84412
Add 8% pst/Gp 74589.70421 D/D .17% pst/Gp 3967.1429514 D/D .65% pst/Gp 15161.2229867
1006961.006835 2329646.3578 2347657.0671
1000000 Add 8% pst/Gp 186371.70863 Add 6% pst/Gp 140859.424026
2516018.0665 C 2488516.49113
2500000
TOTAL =A+B+C 4962752.92252
STATEMENT SHOWING QUANTITIES INFORMATION ORIGNAL/REVISED SCHEMES DISTRICT CONCIL BAHAWALNAGAR YAER 2017-18
WORK NO 62

CONST, OF SOLING DRIEN BASTI SHARA BAGHAR (SHERA CHITRA) BASTI BAHMA HANS FATEH PUR
NAME OF SCHEME HOLAN WALI P/L WATER SUPPLY PIPE DEEN BASHNOIAN BHATA COLONY ROJHAN WALI

ORIGNAL WORK ORDER NO &


DATE 1031, 26/04/2018 Rs: 2200000/-

REVISED WORK ORDER NO & 1176, 29/06/2018 Rs; 3200000/-


DATE
COMLITION 0N GOING

ITEM Orignal Estimate Revised Estimate Paid


DESCRIPTION
NO
Quantity Rate Amount Quantity Rate Amount Quantity Rate Amount
SOLING BASTI SHARA
BAGHAR (SHERA CHITRA)

Earth filing in street lavling


1 dressing etc, 1 mile 18650 7080.55 132052.2575 45180 7080.55 319899.249 38361 7080.55 271616.97855

Providing laying dry brick on


edge soling / street pavement
i/c sand grouted complete in
2 all rspect 2400 13882.35 333176.4 5700 13882.35 791293.95 4641 13882.35 644279.8635
SOLING BHATA COLONY
ROJHAN WALI
Earth filing in street lavling
1 dressing etc, 1 mile 5475 7080.55 38766.01125 17043 7080.55 120673.81365 13197 7080.55 93442.01835
Providing laying dry brick on
edge soling / street pavement
i/c sand grouted complete in
2 all rspect 956 13882.35 132715.266 2355 13882.35 326929.3425 1885 13882.35 261682.2975
3 Pacca brick work in 1;5 93 16661.55 15495.2415 93 16661.55 15495.2415 93 16661.55 15495.2415
SOLING BASTI BAHMA HANS
Earth filing in street lavling
1 dressing etc, 100 feet 10834 4045.75 43831.6555 10834 4045.75 43831.6555 10834 4045.75 43831.6555
Earth filing in street lavling
1 dressing etc, 1 mile 11471 7080.55 81220.98905 11471 7080.55 81220.98905 11471 7080.55 81220.98905

Providing laying dry brick on


edge soling / street pavement
i/c sand grouted complete in
2 all rspect 3100 13882.35 430352.85 3101 13882.35 430491.6735 2978 13882.35 413416.383
SOLING FATEH PUR HOLAN
WALI
Earth filing in street lavling
1 dressing etc, 100 feet 7684 4045.75 31087.543 7684 4045.75 31087.543 7684 4045.75 31087.543
Earth filing in street lavling
1 dressing etc, 1 mile 7291 7080.55 51624.29005 7291 7080.55 51624.29005 4630 7080.55 32782.9465

Providing laying dry brick on


edge soling / street pavement
i/c sand grouted complete in
2 all rspect 2093 13882.35 290557.5855 2093 13882.35 290557.5855 1224 13882.35 169919.964
P/L WATER SUPPLY PIPE LINE
BASHNOIAN
Excavation of trenches for
1 water supply pipe 14000 4271 59794 15400 4271 65773.4 11200 4271 47835.2
2 P/L PVC pipe 4'' Dia 2000 158.95 317900 2200 158.95 349690 1600 158.95 254.32
3 Pvc Tee 0 0 0 3 1106 3318 0 1106 0
4 PVC Bend 0 0 0 3 385.05 1155.15 0 385.05 0
5 Air valve 0 0 0 2 7628.55 15257.1 0 7628.55 0
6 Saluos Valve 0 0 0 1 7979.7 7979.7 0 7979.7 0
7 Back Filling 11200 4271 47835.2 12320 1523 18763.36 8960 1523 13646.08
Making connection for new
8 watersupply lines 1 1620.95 1620.95 1 1739 1739 0 1739 0
COMPARATIVE STATEMENT REGARDING
CONST. OF CATTLE POND CHAK NO. 164/7R, CONST. OF SOLING, B/WALL CATTLE POND CHAK NO. 120/6R, CONST. OF SOLING/ DRAINS GHALLA COLONY KHICHIWALA, P/F
MANHOLE COVERS FAQIR WALI TEHSIL HAROON ABAD DISTT. BAHAWALNAGAR (ORIGIONAL COST Rs=2520000/ REVISED COST 4100000/)
Work 63
Orignal No & Date 1032 , 26/04/2018
Revised No & Date 1186 , 29-06-2018
Date of Completion : On Going

Orignal Revised Paid


Sr. #
Description Quantity Rate Amount Quantity Rate Amount Quantity Rate Amount
Sub Work No. 03
1 Earth filling lead up to one
24976 7232.9 180649 89114 7232.9 574522
mile 79432 7232.9 574523.7128
2 Providing, laying dry brick
2100 13882.35 291529 6775 13882.35 940529
soling 6769 13882.35 939696.2715
3 Pacca brick work (1:3) 2189 17855.55 390858 2189 17855.55 390857.9895
4 Earth work excavation 325 5995.49 1949 325 5995.5 1948.5375
5 Cement Concrete (1:4:8) 73 12160 8877 73 12160 8876.8
6 Pacca brick work (1:3) in
98 18215.35
F&P 17851 98 18215.35 17851.043
7 Pacca brick work on edge
195 7830.6
(1:3) 15270 195 7830.6 15269.67
8 Construction of Drain Type-
98.2
1st 130 12766 130 98.2 12766
1961790.0243
Sub Work No. 1 Cattle Pond 164/7R 500000 472965
Sub Work No. 2 Boundary wall , Cattle Pond 120/6R 1120000 1057337
Sub Work No. 4 Man hole Faqirwali 400000 377794
1908096
G.Total 3869886.0243

COMPARATIVE STATEMENT REGARDING


CONSTRUCTION OF SOLING DRAIN BOUNDARY WALL etc. U/C No. 123, CONST. OF SOLING CHAK NO. 239/9R TO BASTI BABA HUSSAIN WALI / CHAK NO. 235/9R CONST. OF SHED
CHAK NO. 235/9 R TEHSIL FORT ABBAS DISTT. BAHAWALNAGAR
(ORIGIONAL COST Rs=2700000/ REVISED COST 5000000/)
Work 66
Orignal No & Date 1037 , 26/04/2018
Revised No & Date 1187 , 29-06-2018
Date of Completion : ON GOING

Orignal Revised Revised


Sr. #
Description Quantity Rate Amount Quantity Rate Amount Quantity Rate Amount
Sub Work No. 3
1 Earth work excavation single
25554 4045.75 103385 25518
throrrow of kassi 4045.75 103239.4485
2 Earth work lead up to one
53224 7080.55 376855 53224 7080.55 376855 52905
mile 7080.55 374596.49775
3 Providing, laying dry brick
5273 13882.35 731947 20208 13882.35 2805398 20208
soling 13882.35 2805345.288
4 Providing, Fixing Sign Board
1 No. 14800 14800 1 No. 14800 14800 1
14800 14800
3297981.2343
add 6% 197878.87406
3495860.1083
Sub Work No. 1 UC 123 1000000 1000000
Sub Work No. 2 UC 131 500000 500000
Total 4995860.1083
DD. .16% 7993.3761733
G.Total 4987866.7321

COMPARATIVE STATEMENT REGARDING


CONSTRUCTION OF BOUNDARY WALL, GATE AND SOLING OF GRAVEYARD 235/9r , REMAINING WORK , PROTECTION WALL AND GRIL ON CANAL
ROAD CHAK NO 235/9R AZAFI BASTI FORTABAS, CONSTRUCTION OF MADINA COLONY MOSQE STREET KHICHI WALA, P/L PVC WATER SUPPLY
PEOPLE COLONY KHICHI WALA,
Work 77
Orignal No & Date 1046 , 26/04/2018 Amount : 2100000
Revised No & Date 1188 , 29-06-2018 Amount : 2728000
Date of Completion : On Going

(Based BI-ANNUAL 1ST-2018-DISTRICT BAHAWALNAGAR)


Orignal Revised Paid
Sr. #
Description Quantity Rate Amount Quantity Rate Amount Quantity Rate Amount
Sub Wor
Boundary Wall 340 1566.75 532695 340 1566.75 532695
1 Earth Work Excavation in
0 1376 6434.2 8853.4592
foundation
2 Cement concrete (1:4:8) 0 344 10495.35 36104.004
3 Pacca brick work (1:5) in
0 1117 16661.55 186109.5135
Foundation
4 DPC 1:2:4 0 385 4471.95 17217.0075
5 Pacca Brick Ground Floor
0 1114 18399 204964.86
1:4
6 cement plaster (1:4) 0 2040 1798.1 36681.24
7 cement Pointing (1:3) 0 1585 2143.35 33972.0975
8 Providing & Fixing iron Gate
240 777.49 186597.6 240 777.49 186597.6 150 777.49 116623.5
9 Excavation in foundation 180 6434.2 1158.156 2359 6434.2 15178.2778 1665 6434.2 10712.943
10 P/L C.C 1:6:12 36 10495.35 377.8326 451 10495.35 47334.0285 318 10495.35 33375.213
11 Pacca Brick in foundation
101 16661.55 16828.1655 1012 16661.55 168614.886 731 16661.55 121795.9305
1:5
12 DPC 1:2:4 311 4471.95 13907.7645 225 4471.95 10061.8875
13 Pacca Brick in ground Floor
268 18399 49309.32 194 18399 35694.06
1;4
14 Providing & Fixing iron Gril 415 621.4 257881 300 621.4 186420
15 pacca brick work (1:4) 101 18451.25 18635.7625 101 18451.25 18635.7625 50.36 18451.25 9292.0495
16 Fabrication of miled steel 131 11636.5 15243.815 131 11636.5 15243.815 65.37 11636.5 7606.78005
17 R.C.C 1:2:4 236 254.05 59955.8 237 254.05 60209.85 118 254.05 29977.9
18 cement plaster (1:4) 0 2412 1798.2 43372.584 1661 1798.2 29868.102
19 Earth filling up to 1 mile 6148 7080.55 43531.2214 6148 7080.55 43531.2214 0
20 Dry Brick Soling 629 13882.35 87319.9815 629 13882.35 87319.9815 0
1115330.5473
add 6 % 66919.832835
1182250.3801

Sub Work No. 2 Soling madina Colonty 800000 772080


Sub Work No. 3 Pvc Pipe khichi wala 300000
772080
G.Total 1954330.3801
REVISED ESTIMATE FOR THE CONSTRUCTION OF SOLING AND REHABILITATION OF RURAL WATER SUPPLY SCHEME CHAK 168/M UC 79 DISTRICT COUNCIL BAHAWALNAGAR
(ORIGIONAL COST Rs=2500000/ REVISED COST 4500000/)
Work 79
Orignal No & Date 1048 , 26/04/2018
Revised No & Date 1166 , 25-06-2018 Amount : 2728000
Date of Completion : On Going

Orignal Revised Paid


Sr. #
Description Quantity Rate Amount Quantity Rate Amount Quantity Rate Amount
Sub Wor
1 Excavation of trenches in all
kinds of soil, except cutting
rock, for watersupply
pipelines upto 5 ft. (1.5 m)
depth from ground level,
including trimming, dressing
sides, payable separately.
leveling the beds of trenches 23625 4582 108249.75
to correct grade and cutting
pits for joints, etc. complete
in all respects.uc 79
2 Providing, laying, cutting,
jointing, testing and
disinfecting P.V.C. pipe line
of B.S.S. with `B' Class
working pressure pipe, in
3350 Rft 106.2/Rft 355770
trenches, complete in all
respects:- made by Govt.
approved manufactuere

Providing, laying, cutting,


jointing, testing and
disinfecting P.V.C. pipe line
of B.S.S. with `B' Class
working pressure pipe, in
1900 Rft 159.25/Rft 302575
trenches, complete in all
respects:- made by Govt.
approved manufactuere

3 Provision specials for PVC


5/100 658345 32917
pipe line.
4 Providing and fixing sluice
valve of B.S.S. quality and
weight, Class `B', for cast
iron pipe line, and Asbestos 4 6785.9 27143.6
cement pipe line (including
cost of jointing material)

5 Construction of Sluice Valve


Chamber as per detail 4 18080 72320
attached
6 Back filling of trenches by
rehandling of earth work
lead upto single through of 18900 Cft 1523.3%0cft 28790
kassi.
7 P/F sign board at site as per
1No 14800each 14800
detail attached.
8 Boring for tubewell in all
types of soil except shingle
and rock,rom ground level to
100 ft: depth including 100 Rft 242.15 P/RFT 24215 90 RFT 242.15 P/RFT Rs21793/-
sinking and withdrawingof
casing pipe complete .

9 100 to 200 depth 20 RFT 377.25 P/RFT 7545 NIL


10 Furnishing samples of water
1 NO 170.70 EACH 171 1 NO 170.70 EACH 171
from bore hole
11 Electric Resistivity Survay &
1 PROBES 15000 EACH 15000 1 PROBES 15000 EACH 15000
report writing.
12 Direct rotary/ reverse rotary
drilling of bore of tube well in
all kinds of soil except
shingle and rock from 120 RFT 750.20 P/RFT 90024 90 RFT 750.20 P/RFT Rs.67518/-
ground level to 250 feet
below ground level.

13 Furnishing samples of water


1 SET 170.70 P/SET 171 1 SET 170.70 P/SET 171
from bore hole.
14 Providing and installing,
brass strainer in tubewell
bore hole including sockets,
special sockets, studs, etc 32 RFT 5225.40 P/RFT 167213 32 RFT 5225.40 P/RFT Rs.167213/-
complete:- 12" i/d, ¼"
(300 mm i/d 6 mm) thick

15 Providing and installing M.S


blind pipe socket/ welded
joint M.S reducer (where
necessary in tube well bore
hole I/c jointing welding with 96 RFT 2302.75 P/RFT 221064 96 RFT 2302.75 P/RFT Rs.221064/-
strainer etc: complete 12"
I/dia 5.5mm thick.

16 Shrouding with graded pea


graver 3/8" to 1/8" around 337.92 CFT 95.40 P/CFT 32238 253 CFT 95.40 P/CFT Rs.24136/-
the tube well in bore hole.
17 Development & testing of
tube well with contractor on
pumping machinery upto 24
hours or till water is sand 24 HOURS 1184.15 P/HOUR 28420 24 HOURS 1184.15 P/HOUR 28420
free and the discharge is
uniform.Upto 1.5 Cusec
discharge

18 Providing, Fixing in position


suspension clamp for 12"
dia pipe including cost of
plain cement concrete 1:2:4 1 NO 10000 P/EACH 10000 1 NO 10000 P/EACH 10000
ratio block foundation. (N. S)

19 Providding and fixing 3/8"


Thick M.S well cap on tube
well for 12" dia pipe with 1 NO 1200 P/EACH 1200 1 NO 1200 P/EACH 1200
lock and locking
arrangement. (N. S)
20 Testing of strata and water
samples from PHED
Laboratory complete will all 1 NO 800 P/EACH 800 1 NO 800 P/EACH 800
charges. (N. S)
21 Excavation in foundation for
building, bridges & other
structures, including
dagbelling, dressing, refilling
around structures with
excavated earth, watering 667.125 CFT 6434.20 P%CFT 4292 667.125 CFT 6434.20 P%CFT 4292
and ramming lead upto one
chain 100 ft. and lift upto 5
ft, in ordinary soil.

22 Cement concrete brick or


stone ballast 1.5" to 2"
gauge in foundation and 321.82 CFT 10846.35 P%CFT 34906 321.82 CFT 10846.35 P%CFT 34906
plinth ratio 1:6:12
23 Pacca brick work in cement
sand mortar foundation and
plinth 1:6 ratio. 873 CFT 16810.15 P/%CFT 146753 793.31 CFT 16810.15 P/%CFT Rs.34906/-

24 Providing and laying damp


proof course of cement
concrete 1:2:4 (using 118.125 SFT 5691.80 P/%SFT 6723 118.125 SFT 5691.80 P/%SFT 6723
cement, sand and shingle),
including bitumen coating:
25 Providing and laying vertical
damp proof course with
cement sand plaster and
bitumen coating:-1/2" Thick
1:3
48 SFT 3117.25 P%SFT 1496 48 SFT 3117.25 P%SFT 1496
(a) with one coat of bitumen
and one coat of polythene
sheet 500 gauge:

26 Pacca brick work in (1:5)


cement sand mortar in 695.5 CFT 18461.40 P/%CFT 128405 695.5 CFT 18461.40 P/%CFT 128405/-
ground floor.
27 Filling, watering and
ramming earth under floors
with surpulas earth from 371.637 CFT 3083 P%0CFT 1146 371.637 CFT 3083 P%0CFT 1146
foundation etc:
28 Supplying and filling sand
under floor or plugging in 67.57 CFT 1933.90 P/CFT 1307 67.57 CFT 1933.90 P/CFT 1307
well.
29 Cement plaster 1:4 upto 20
ft, height. 648 SFT 1837.50 P/SFT 11907 648 SFT 1837.50 P/SFT 11907
(b) 1/2" thick.
30 Providing and laying P.C.C.
(1:2:4) in bed and topping
complete with finishing etc; 351 SFT 6578.15 P/SFT 23089 351 SFT 6578.15 P/SFT 23089
3" Thick & divided in pannal
31 Providing and laying
reinforced cement concrete
(including presstressed
concrete), using course
sand and screened graded
and washed aggregate in
required shape and design
including forms, moulds,
shuttering, lifting,
compacting, curing,
rendering and firn(a) (i) 93.09 CFT 358.70 P/CFT 33392 93.09 CFT 358.70 P/CFT 33392
reinforced cement concrete
in roof slab, beams,
columns, lintels, girders and
other structural members
laid in position, or
prestressed members cast
in situ, complete in all
respect.

32 Febrication of mild steel


reinforcement for cement
concrete, including cutting,
bending, laying, in position,
making joints and fastening,
including cost of binding wire
and labour charges for 285.11 KG 6272.35 P%KG 17883 285.11 KG 6272.35 P%KG 17883
binding of steel
reinforcement (also includes
removal of rust of bar.

33 Making and fixing steel


grated door with 1/16" thick
(1.5mm) sheeting, including
angle iron frame 2"x2"x3/8"
(50x50x10 mm) and ¾" (20
28 SFT 1005.50 P/SFT 28154 28 SFT 1005.50 P/SFT 28154
mm) square bars 4" (100
mm) centre to centre, with
locking arrangement.
34 Providing and fixing steel
windows with openable
glazed panels, using beam
section for frame
1½"x1"x5/8"x1/8"
(40x25x16x3 mm),
Z-section for leaves
¾"x1"x¾"x1/8" (20x25x20x3
mm), T-section sashes
1"x1"x1/8" (25x25x3 mm),
glass panes, wooden screed
for glazing embedded over a
thin layer of putty duly 32 SFT 435.95 P/SFT 13950 32 SFT 435.95 P/SFT 13950
screwed with leaves, brass
fittings, holdfast, duly
painted, complete in all
respects, including all cost of
material and labour, etc. as
per approved design and as
directed by the Engineer-in-
charge:-

35 Cement pointing 1:2 strick


joint on walls upto 20 Ft,
height, i/c cost of red oxide 709.50 SFT 2290.10 P%SFT 16248 709.50 SFT 2290.10 P%SFT 16248
pigment.
36 Single layer of tiles 9" x 4-
1/2" x 1-1/2" laid over 4"
earth and 1" Mud plaster
without bhossa grouted with
cement sand 1:3 on top of
144 SFT 6487.55 P%CFT 9342 144 SFT 6487.55 P%CFT 9342
RCC roof slab providing with
34 Lb. bitumen coating sand
blinded.

37 White wash three coats on


new surface wall and ceiling. 720 SFT 278.90 P%CFT 2008 720 SFT 278.90 P%CFT 2008
38 Preparing surface and
painting of doors and
windows any type (including 120 SFT 1156 P%CFT 1388 120 SFT 1156 P%CFT 1388
edges):- three coats.

39 Khassi parnalas in cement


sand mortar 1: 2 outside
12" width finished smoth 14 RFT 101 P%CFT 1414 14 RFT 101 P%CFT 1414
with a floating coat of neat
cement.
40 Bottom Khurras of brick
masonry in cement sand
mortar 1:6, 4ft x 2ft x 4-1/2 1 NO 846.30 P%CFT 846 1 NO 846.30 P%CFT 846
inch over 3 inch cement
concrete 1:4:8
41 Khurras on roof 2ft x 2ft x
1 NO 498.90 P%CFT 499 1 NO 498.90 P%CFT 499
6inch.
42 Fabrication of heavy steel
work, with angle, tees, flat
iron
round iron and sheet iron for
making trusses, girders,
tanks, etc., including cutting,
drilling, revitting, handling, 85 KG 14258.35 P%KG 12155 85 KG 14258.35 P%KG 12155
assembling and fixing, but
excluding erection in
position.

43 S/E of ceilling Fan Sweepest


1 NO 3500 EACH 3500 1 NO 3500 EACH 3500
Quality
44 Providing, fixing in position
and testing vertical turbine
pumping unit capable to give
a discharge of 0.25 cusec of
clear water against a total
head of 210 feet with 60 feet
column pipe with assembly
directly coupled with Vertical 1 SET 700000 P/SET 700000 1 SET 700000 P/SET Rs.700000/-
turbine 3-phase electric
motor 15 BHP 380/440 Volts
(SIEMENS) with following
Accessories complete in all
respect.

45 Supplying of chain Pully


block 5 ton capacity having
5 meter long chain complete 1 SET 15000 P/SET 15000 1 SET 15000 P/SET 15000
in all respects.
46 Provisioin for Over Head
2 SPAN 25000 P/SPAN 50000 NIL
Electric Transmission Line.
47 Provision for Shifting of 25
KVA Transformer with sub 1 NO 70000 EACH 70000 NIL
station & energy meter.
48 Excavation of trenches for
water supply pipe line in all
kinds of soil except cutting
rock upto 5 Ft. depth from
ground level including
trimming dressing the sides
leveling the bed of trenches 26640 CFT 4582 P%0CFT 122064 900 CFT 4582 P%0CFT Rs.4124/-
to correct grade and cutting
pits for joint etc, complete in
all respect.
49 Providing, laying, cutting,
jointing, testing and
disinfecting PVC Pipe of
BSS with Class working 2400 RFT 165.40 P/RFT 396960 200 RFT 165.40 P/RFT Rs.33080/-
pressure in trenches,
complete in all respects.4
inch

50 Providing, laying, cutting,


jointing, testing and
disinfecting PVC Pipe of
BSS with Class working 2040 RFT 110.90 P/RFT 226236 NIL
pressure in trenches,
complete in all respects.3
inch

51 Providing and fixing cast iron


special of B.S.S. Class `B'
(such as bend, tee cross
collar, reducer, tail piece
flanged spigot, cap, flanged
socket, taper, angle branch
plug etc.) for cast iron pipe
line , complete:- a) C.I.S.S. 1 NO 14046 P/NO 14046 NIL
Specials, with spigot. And
socket joint:- i) 3" to 6" (75 to
150 mm) i/d (Detail
Attached)

52 Providing and fixing C.I.


sluice valves of BSS Quality
and weight class B. (i/c cost 1 NO 7979.70 EACH 7980 NIL
of Jointing material) 4 inch

53 Providing and fixing C.I.


sluice valves of BSS Quality
and weight class B. (i/c cost 1 NO 6785.90 EACH 6786 NIL
of Jointing material) 3 inch

54 Providing and fixing air valve


1 NO 7628.55 EACH 7629 NIL
2-1/2" dia (Double).
55 Providing and fixing Non
return valve BSS Quality
and weight . (i/c cost of 1 NO 6998.40 EACH 6998 NIL
Jointing material)
56 Construction of masonry
Sluice valve/ Air valve
chambers 3.00 Ft. x 3.00 Ft. 1 NO 16770 EACH 16770 NIL
x 4.50" (as per detail
attached)
57 Back filling of trenches by
rehandling of earth work
lead upto a single throw of
kassi phorah or shovel
including mining moising 21312 CFT 1523.30 P%0CFT 32465 720 CFT 1523.30 P%0CFT Rs1097/-
arht to optimum content in
layers complete. Quantity
80% of item No. 1

58 Providing and fixing M.S


Signe Board 4'x 6' i/c fixing 1 NO 31815 EACH 31815 NIL
charges.
59 Providing and fixing C.I
Specials of BSS B-Class
such as tees, bends, 61.67 KGS 108.10 P/KG 6667 NIL
reducer, tailpieces of BBS
Class B for PVC Pipe.
60 Providing and fixing C.I
flanges on pipe i/c Turing
threading facing, and fitting 36.68 KGS 114.90 P/KG 4215 NIL
etc: complete in all respect.

61 Providing and installing


P.V.C. tees, of B.S.S.
i) Class `B' working 3 NO 628.85 EACH 1887 NIL
pressure:-
62 Providing and fixing PVC
taper core of BBS Class B 2 NO 141.25 EACH 283 NIL
working pressure.3"dia
63 Providing and fixing PVC 166.05 EACH
taper core of BBS Class B 6 NO Rs.996/- NIL
working pressure.4"dia
1 Earth filling in the street
including its ramming,
dressing lead upto 1 39434 Cft 7080.55%0Cft 279214 37857 Cft 7080.55%0Cft Rs.268046/-
miles.uc 75
2 Providing and laying dry
brick pavement/soling in
streets or roads, etc. sand
grounted, laid in proper
camber, including
4688 Cft 13882.35%Cft 650735 4248 Cft 13882.35%Cft Rs.589722/-
preparation, watering,
compaction of bed to proper
camber, and sand cushion.

3 Provision for manufacturing


and installation of project
information board at site as 1 No 14800 Each 14800 NIL
per detail attached.
1 Earth filling in the street
including its ramming,
dressing lead upto 1 19402 Cft 7080.55%0Cft 137373 18928 Cft 7080.55%0Cft Rs.134023/-
miles.Mehatta jhedu
2 Providing and laying dry
brick pavement/soling in
streets or roads, etc. sand
grounted, laid in proper
camber, including
2306 Cft 13882.35 %Cft 320162 2124 Cft 13882.35 Rs.294861/-
preparation, watering,
compaction of bed to proper
camber, and sand cushion

3 Provision for manufacturing


and installation of project
information board at site as 1 No 14800 Each 14800 NIL
per detail attached.
work no 81 repair of metal
road shadi wala
1 Earthowrk in ordinary soil for
embankments including
ploughing and mixing with
blade grade , or disc harrow
or other suitable equipment,
and compaction by
mechanical means at 38880 cft 8513.45 p%0cft 331003
optimum moisture content
and dressing to designed
section, complete in all
where necessary respects:-

2 Providing and laying road


edging of 3" (75 mm) wide
and 9" (225 mm) deep brick 2000 rft 29.75 p/rft 59500
on end, complete in all
respects.
3 Providing, laying base
course of crushed stone
Aggregate of approved
quality, grade and screening
i/c placing, mixing,
spreading, and compaction
Of base course material to
required depth, camber and 6235 cft 13408.91 p%cft 836093
Grade to achieve 100%
maximum modified AASHO
dry Density including
carriage of all material to site
of work.
4 Providing,Double surface
treatment to roads including
supply Bitumen and
bajri/crushed stone
aggregate of approved
Quality including cleaning of
road surface, heating and
Spraying bitumen, spreading
bajri and rolling with road
Roaller ( including its 25920 sft 1827.00 p%sft 473558
operation cost of fuel and
hire charges Etc) complete
including carriage of all
material to site of Work.
Three coats using 3.5 Cft
Bajri and 32 lbs bitumen Per
% Sft.

Providing, surface treatment


to roads including supply
Bitumen and bajri/crushed
stone aggregate of
approved Quality including
cleaning of road surface,
heating and Spraying
bitumen, spreading bajri and
rolling with road Roaller
( including its operation cost 12000 sft 3786.94 p%sft 454432
of fuel and hire charges Etc)
complete including carriage
of all material to site of
Work. Three coats using 7.5
Cft Bajri and 67 lbs bitumen
Per % Sft.
Earthowrk in ordinary soil for
embankments including
ploughing and mixing with
blade grade , or disc harrow
or other suitable equipment,
and compaction by
mechanical means at 129456 cft 8513.45 p%0cft 1102117 129456 cft 8513.45 p%0cft RS.1102117/-
optimum moisture content
and dressing to designed
section, complete in all
where necessary respects:-

Providing and laying road


edging of 3" (75 mm) wide
and 9" (225 mm) deep brick 3000 rft 29.75 p/rft 89250 3000 rft 29.75 p/rft RS.89250/-
on end, complete in all
respects.
Providing, laying base
course of crushed stone
Aggregate of approved
quality, grade and screening
i/c placing, mixing,
spreading, and compaction
Of base course material to
required depth, camber and 8003 cft 13408.91 p%cft 1073048 8002 cft 13408.9 p%cft RS.1073048/-
Grade to achieve 100%
maximum modified AASHO
dry Density including
carriage of all material to site
of work.
Providing,Double surface
treatment to roads including
supply Bitumen and
bajri/crushed stone
aggregate of approved
Quality including cleaning of
road surface, heating and
Spraying bitumen, spreading
bajri and rolling with road
Roaller ( including its 86304 sft 1827 p%sft 1576774 86304 sft 1827 p%sft 1576774
operation cost of fuel and
hire charges Etc) complete
including carriage of all
material to site of Work.
Three coats using 3.5 Cft
Bajri and 32 lbs bitumen Per
% Sft.

Providing, surface treatment


to roads including supply
Bitumen and bajri/crushed
stone aggregate of
approved Quality including
cleaning of road surface,
heating and Spraying
bitumen, spreading bajri and
rolling with road Roaller
( including its operation cost 12000 sft 3786.94 p%sft 454432 12000 sft 3786.94p%sft RS.4544342/-
of fuel and hire charges Etc)
complete including carriage
of all material to site of
Work. Three coats using 7.5
Cft Bajri and 67 lbs bitumen
Per % Sft.

Provision for manufacturing


and installation of project
information board at site as 1 no 14800 Each 14800 NIL
per detail
REVISED ESTIMATE FOR REPAIR OF MATALLED ROAD SHADI WALA (ORIGIONAL COST Rs=2500000/ REVISED COST 5000000/)
Work 81
Orignal No & Date 1050 , 26/04/2018
Revised No & Date 1189 , 29-06-2018
Date of Completion : On Going

Orignal Revised Paid


Sr. #
Description Quantity Rate Amount Quantity Rate Amount Quantity Rate Amount
1 Earthowrk in ordinary soil
for embankments
including ploughing and
mixing with blade grade ,
or disc harrow or other
suitable equipment, and
compaction by
mechanical means at 38880 cft 8513.45 p%0cft Rs.331003/-
optimum moisture content
and dressing to designed
section, complete in all
where necessary
respects:-

2 Providing and laying road


edging of 3" (75 mm) wide
and 9" (225 mm) deep
brick on end, complete in 2000 rft 29.75 p/rft Rs.59500/-
all respects.
3 Providing, laying base
course of crushed stone
Aggregate of approved
quality, grade and
screening i/c placing,
mixing, spreading, and
compaction Of base
course material to
required depth, camber
and Grade to achieve 6235 cft 13408.91 p%cft Rs.836093/-
100% maximum modified
AASHO dry Density
including carriage of all
material to site of work.
4 Providing,Double surface
treatment to roads
including supply Bitumen
and bajri/crushed stone
aggregate of approved
Quality including cleaning
of road surface, heating
and Spraying bitumen,
spreading bajri and rolling
with road Roaller
( including its operation
cost of fuel and hire
charges Etc) complete 25920 sft 1827.00 p%sft Rs.473558/-
including carriage of all
material to site of Work.
Three coats using 3.5 Cft
Bajri and 32 lbs bitumen
Per % Sft.
Providing, surface
treatment to roads
including supply Bitumen
and bajri/crushed stone
aggregate of approved
Quality including cleaning
of road surface, heating
and Spraying bitumen,
spreading bajri and rolling
with road Roaller
( including its operation
cost of fuel and hire
charges Etc) complete 12000 sft 3786.94 p%sft Rs.454432/-
including carriage of all
material to site of Work.
Three coats using 7.5 Cft
Bajri and 67 lbs bitumen
Per % Sft.

Earthowrk in ordinary soil


for embankments
including ploughing and
mixing with blade grade ,
or disc harrow or other
suitable equipment, and
compaction by
mechanical means at 129456 cft 8513.45 p%0cft Rs.1102117/- 129456 cft 8513.45 p%0cft RS.1102117/-
optimum moisture content
and dressing to designed
section, complete in all
where necessary
respects:-
Providing and laying road
edging of 3" (75 mm) wide
and 9" (225 mm) deep
brick on end, complete in 3000 rft 29.75 p/rft Rs.89250/- 3000 rft 29.75 p/rft RS.89250/-
all respects.

Providing, laying base


course of crushed stone
Aggregate of approved
quality, grade and
screening i/c placing,
mixing, spreading, and
compaction Of base
course material to
required depth, camber
and Grade to achieve 8003 cft 13408.91 p%cft Rs.1073048/- 8002 cft 13408.9 p%cft RS.1073048/-
100% maximum modified
AASHO dry Density
including carriage of all
material to site of work.
Providing,Double surface
treatment to roads
including supply Bitumen
and bajri/crushed stone
aggregate of approved
Quality including cleaning
of road surface, heating
and Spraying bitumen,
spreading bajri and rolling
with road Roaller
( including its operation
cost of fuel and hire
charges Etc) complete 86304 sft 1827 p%sft Rs.1576774/- 86304 sft 1827 p%sft 1576774
including carriage of all
material to site of Work.
Three coats using 3.5 Cft
Bajri and 32 lbs bitumen
Per % Sft.
Providing, surface
treatment to roads
including supply Bitumen
and bajri/crushed stone
aggregate of approved
Quality including cleaning
of road surface, heating
and Spraying bitumen,
spreading bajri and rolling
with road Roaller
( including its operation
cost of fuel and hire
charges Etc) complete 12000 sft 3786.94 p%sft Rs.454432/- 12000 sft 3786.94p%sft RS.4544342/-
including carriage of all
material to site of Work.
Three coats using 7.5 Cft
Bajri and 67 lbs bitumen
Per % Sft.

Provision for
manufacturing and
installation of project 1 no 14800 Each Rs.14800/- NIL
information board at site
as per detail

Sub Engineer District Engineer (I&S)


District Council Bahawalnagar District Council Bahawalnagar
RS.1102117/-
RS.1073048/-
RS.4544342/-