Sunteți pe pagina 1din 5

1989

Measurements with respect to the electromagnetic compatibilt y (EMC) of


telecontrol systems in substations of medium-voltage distribution networks
W. Hei6, F. Hirsch,

EAM-Kassel, FGH Mannheim


Federal Republic of Germany

Summary allows the compact installation of the sub-


stations in one part of the building.
In the construction of substations electro- Due to the earthed enclosure, telecon-
magnetic compatibility becomes more and trol systems can be installed directly next
more important due to the fact that modern to the substation.
microelectronic components are installed This development is mainly based on econo-
in the close surroundings of power enginee- mic considerations and leads to a higher
ring systems. Microelectronic elements in sensibility of the electronic elements and
MV-substations are increasingly placed in circuits against external and internal
the close proximity of the components to be interferring signals.
measured or controlled. Owing to the ear-
thed enclosure of substations, telecontrol In order to make proper use of the advanta-
systems are installed directly next to the ges of microelectronic elements in substa-
functional unit. tions, the electromagnetic compatibility
Sources of interference, especially swit- of these elements must be considered and
ching operations of the circuit breakers guaranteed when installed in the close sur-
and disconnectors in the primary circuit, roundings of substations. Basic data was
affect the process environment. The sources obtained from measurements made in two 24-
of interference - above all transient ma- kV substations. The transient magnetic field
gnetic fields - endanger modern electronic strengths in the room were measured (by
elements via the coupling devices. means of aerial frames) as well as the con-
Secondary cables, current transformers ducted transient interference voltage oc-
and couplings in the fuctional units re- curring in current transformers during nor-
present characteristic coupling devices. mal switching operations.
Measurements of 24-kV substations were made
in order to determine transient magnetic One gas-insulated and one conventional
field strengths in the room. The following MV-substation with a nominal voltage of s4 KV
report presents the first results and com- are taken into consideration. The MV-sub-
pares the behaviour of conventional and gas- stations are uniformly equipped with va-
insulated substations in relation to tran- cuum circuit breakers.
sient interferences.
2. Interference Sources
1. Introduction
Microelectronics in substations, especially High-frequency electromagnetic transient
in telecontrol and protection systems leads reactions can result from the operation of
to new developments, i.e. concerning measu- capacitances; these capacitances under- -
ring, control and regulating of the com- ground cable sections, unloaded busbar sec-
ponents. Considering the technological deve- tions or cylindrical parts of the enclosure
lopment of the microelectronic elements, a of gas-insulated substations (GIS) - are
change can be observed to lower signal am- energized and de-energized by means of
plitudes, higher integration and increa- circuit breakers or disconnectors. When
sing signal speed. Microelectronic ele- making capacitances, the first spark-over
ments are increasingly arranged in the occurs when the switch contacts have rea-
close proximity of the substation"s compo- dhed a specific distance. In this process,
nents relative to power engineering. the voltage across the contacts in SF6 or
vacuum interruptors changes abruptly in just
A further development can be seen in elec- a few nanoseconds. Restrikes can occur when
trical power engineering in the decentrali- capacitive circuits are de-energized. In-
zation of "intelligence"; in the future, side the substation, transient waves spread
a sensor with microelectronic elements and out as a result of the change in volta-
a device carrying out the local evaluation ge, demonstrating a complex voltage shape
(in order to reduce the data) will be in- along the substation-s components due to re-
stalled near the components to be measured flection and refraction effects. In
or controlled, e.g. a HV-switching device. gas-insulated metal-enclosed substations the
General aspects related to environmental transient waves leave the enclosure through
control and to rationalization, additional- the connectors to overhead lines and cables
ly result in an increase of SF6 gas-insula- as well as through discontinuous points in
. - -. . .- - -= ---A..-+-.--
according to the laws of waves. Interferen- 1
ces are furthermore decoupled via current
transformers, sensors and driving shafts of
the switching devices.
In conventional non-gas-insulated substa-
tions, transient waves travelling along
the open busbars cause direct radiation of
transient electromagnetic fields into the
room. Additionally, conducted transient
interference voltage occurs mainly in the
current transformer circuits, as is the case lb
in G I s .

The interferences to be expected during ope-


ration and caused by switching opera-
tions, possess high-energy spectral parts
ranging at above several MHz. For these
wavelengths, integrated circuits and elec-
tronic components are considered to be elec-
trically short, so that interference ra-
diation is not coupled directly into the
components but rather into the conductors
of printed circuit boards and into the cable I,
system. I 1 I

3 . Layout of the substations investigated

In the framework of the electromagnetic


influence to be described and the measure-
ments made, this section shall treat the
construction and layout of the 24-kV substa-
tions investigated.

Measurements were made considering a sin-


gle-pole metal-enclosed gas-insulated sub-
station and a conventional substation with
Figure 1: Layout of conventional substation
combined air and solid insulation. a) Sectional view 1. vacuum circuit breaker
2. current tranef ormer 3. voltage transf ormer
Conventional Substation Panel width 800 mm b) Single line diagram

Figure la shows the structure of a functio-


20 - L1 L2 L3

nal unit. All components of the substation


conducting high voltage, are furnished with
air and solid insulation: the vacuum circuit
breaker is mounted on a withrawable part and
performs disconnecting functions by means of
the disconnecting contacts. The functional
units have no metal enclosure. Inductive cur-
rent and voltage transformers are installed
directly in the unit. The sealing ends of
the connected cables are installed in the
cellar. Single busbar sections are coupled
with insulated busbars (cf.Fiaure lb).
The single line diagram of the investiga-
ted double busbar substation is shown in 24 kV
Figure lb. When measurements were made, all
circuit breakers were closed and connected
to underground cable lines, up to several
kilometers in length. For these experiments,
the circuit breakers in units 5,11 and 25
were activated.

Gas-insulated substations
Figure 2: Layout of gas-insulated substation
Figure 2a shows the structure of a functio- a) Sectional view 1. voltage transformer
nal unit of the substation: there is one 2. three-position disconnector 3. vacuum cir-
three-position disconnector provided for each cuit breaker 4. toroidal transformer Panel
width 600 m m b) single line diagram
unit - for the function "disconnect" and
117
“earthing - ready“ and one vacuum circuit
breaker. The connection to earth of an - Large frame, 6 0 cm diameter, up to 30 MHz
cable unit is put into effect by a three- - Small aerial, 15 cm diameter, > 100 MHz
position disconnector and a vacuum circuit
breaker. The enclosure of the substation is A digital oscilloscope with a scanning
made up of aluminum alloy: SF6 is used as frequency of 100 MHz was used to record the
insulating gas. The current is measured by time characteristics. Uncomplicated treat-
means of toroidal transformers encompassing ment - integration and / or frequency ana-
each switch cover. lysis - was guaranteed by this method of di-
Figure 2b shows the single line diagram of rect digitalization. Together with the
the investigated substation. The two busbar small aerial it became possible to present
sections are connected by a synthetic cable processes accurately up into the 30 MHz area;
5 m in length. Switching operations were accuracy was still sufficient to allow an
carried out by the circuit breaker in unit estimation up to approx. 50 MHz.
J02. All the remaining units were connec-
ted to the underground cables. During the In order to show even more rapid processes,
switching operation of the three-position an oscilloscope with scanner digitalization
disconnector in the coupler panel JOla, the was installed as a support.
circuit breaker of the coupler unit (JO1) was The applicability of this principle, howe-
open. ver, proved to be only limited since supe-
rimposed radiation of curve shapes lying
The transient interference voltage of the next to each other was so strong that the
24-kV current transformers was - in both scanner was no longer able to distinguish
substations - measured at the secondary the different parts of the curve. Voltage
terminals under the condition of normally shapes obtained in this way can give an im-
loaded windings in the control cubicle, pression of the frequencies to be expected,
which was installed in a separate relay room the voltage itself however, cannot be eva-
next to the substation room. luated.

4. Principles and equipment used for measu- 5. Survey of the experiments made and of the
rement numerical evaluation

The investigation of the interference Conventional substation


field aimed at the determination of the time
characteristic of the magnetic induction E , 1. Field measurement with the 30-MHz frame
which also determines the interference vol- in front of functional unit 5 (Figure 1):
tage in the conductors via its time deriva- Energizing an underground cable line ap-
tive. prox. 1000 m in length with an open end.
The aerial was positioned in the middle of
Measurements were made of voltage U< (in the control aisle in front of the functional
V) which is produced by the induction B at unit, aligned horizontally approx. 1 m
the ends of a conductor loop. In order to above the ground.
obtain the magnetic field fraction only, the
aerials used for measurement were 2.1 Field measurement with a 30-MHz frame
electrically screened. in front of functional unit 11 (Figure 1):
Energizing an underground cable line ap-
The physical relations: prox. 3300 m in length with an open end.
The aerial was positioned in front of func-
- measured voltage I ‘
dt
1 tional unit 11, aligned horizontally, as
described in 1.
Limit frequency of the oscilloscope: 20 MHz
- magnetic flux 4= B e F (F is the 2.2 Field measurements with the small ae-
rial under the same conditions as experiment
area of the aerial) L.I.

from 3 . Field measurements with the small aerial


at the location of experiment 2.1, limit fre-
quency of the oscilloscope: 50 MHz.
the induction B producing the voltage U; Inserting the switch truck into functio-
is calculated nal unit 11 with open switch. The open
t circuit breaker was inserted into the con-
tacts of the busbar, which was energized.
(3)
G
4 . Field measurements with the small aerial
at the location of experiments 2.1; (limit
Two circular aerial frames were used; frequency of the oscilloscope: 50 MHz)
their maximum operating frequency had been and measurements at the secondary terminals
determined previously. of the matching current transformer in

118
t-

t :: la
B(PT)..

'i--
B ~ T )

t(us)-10
t
B (UT)

$7t (JlS)-+10

119
operating condition. The voltage appearing at the secondary
Energizing of the bus coupling (unit 25). windings of current transformers ranges
During these experiments, a busbar approx at approx. 100 V in both types of substa-
18 m in length was energized. tions (cf. Table 1). These values however,
largely depend on the local conditions rela-
Gas-insulated substation ted to the geometrical distance to the acti-
ve parts of the substation, the installa-
1. Field measurements with the small ae- tion of secondary circuits as well as on the
rial, aligned vertically, in front of type of transformer used.
functional unit 502, center point approx. 80 The absolute values of the magnetic induc-
cm above the ground, distance to the next tion in the area of the normally accessible
enclosure approx. 50 cm (Figure 2). Measure- operating aisle ranges at approx. 3 0 p T in
ments at the secondary terminals of the cur- both types of substations. In contrast to
rent transformer in operating condition Ener- this, essential differences could be obser-
gizing of an underground cable line ap- ved in the maximum change of the field
prox. 800 m in length with an open end.Limit strength in relation to time. The voltage Ui
frequency of the oscilloscope: 50 MHz induced by the magnetic field in the conduc-
2. Field measurements with the small aerial tor loop is however, determined by dB /at.
as described in experiment 1 in front of Considering the fact that the values are
the functional unit JOla (Figure 2) (circuit nearly 10 times the interference voltage to
breaker in the coupler open). be expected in secondary installations of
Inserting and opening the earthing discon- gas-insulated substations, the difficulties
nector JOla (Figure 2a). In these experiments arising when putting into operation this
the short line between the two busbar sec- type of substation become quite obvious.
tions was energized.
Experiments B,,, Characteristic
frequencies
1
): I V / d (pTI (UHz)
The results obtained from the experi-
ments concerning conventional and gas- I. c a b l e line - 10 17 0.04 : 0.33
1000 m
insulated substations are shown in Table 1.
2. c a b l e line
The values (dB/dt),, and B mO,x 3300 m
a ) 30-MHz frames - 5 46 0.012: 0.08; 0.5
were calculated from -

11 1
b ) small aerial 4 36 0.012; 0.08; 0.5
the measured values with the aid of 3. S w i t c h truck - 13 0.07 40; 1 0 0 $1)
equation(2) and (3). 4. switch bus
coup11ng
a) f i e l d
6 . Comparison of the two types of substations measurement - 2: 1;41 2.5; 25: 40
b ) at t r a n s -
former 120 4; 17: 25; 50

One of the targets of the experiments car-

1; I “1
1. c a b l e line
ried out, was to compare conventional sub- 800 m
a) f x e l d
stations with gas-insulated substations. b ) at trans-
measurement :11 0.2; 2.4; 25: 60
In addition to Table 1, Figures 3 - 5 farmer 0.2: 2.2; 4.5; 22

show examples of the recorded voltages I I I I 50

and the calculated inductions .


In the course of the - chronologically -
first experiments related to substations, the ( 1 ) Frequency evaluation from incomplete scanner oscillograms

characteristic frequencies of up to approx. -T Numerical evaluation of t h e experiments

500 KHz can be explained by the propagation


time of the current ripple inside the con- 7. Concluding remarks
nected cable lines. A frequency of the same
order of magnitude also appears in relation The present results allow a first impres-
to measurements executed in a gas-insulated sion of the interferences to be expected
substation when a cable line is energized. due to transient magnetic fields.

When energizing a longer busbar section in MV-substations definitely have a higher sha-
the conventional substation (experiment K4a), re of high-energy frequency, owing to
the voltage at the aerial includes fre- their substantially smaller size as compared
quencies ranging from 2 MHz to approx. 40 to HV-substations: nevertheless, it can
MHz. Similar frequencies can be observed also be observed - although to a lesser
when evaluating all switching operations in degree - in conventionally built substa-
the gas-insulated substation: in both ca- tions. Since the prevention of interference
ses, transient waves within the respective fields would not be reasonable technically
substation or busbar are probably responsi- and economically, special attention must be
ble for this phenomenon. Still higher fre- paid to the immunity to interference of se-
quencies, exceeding 100 MHz, must be expec- condary equipment and its cable connec-
tions, which are increasingly installed
ted from the oscillograms (unfortunately in-
in the close proximity of the interference
complete) when inserting extremely short
sources.
busbar sections. This applies to both types
of substations.
120

S-ar putea să vă placă și