NO ISSUES STEPS TAKEN TO RESOLVE

1. Construction Period Delayed The intended construction period originally is that the mosque
must finish in 2 years’ time. Then the construction period had
to be extended to 5 years. This delay happen according to the
government instruction and the government is the client in this
project. This delayed happen due to the budget for the
construction must be plan carefully so that the construction can
be proceed during a period when the country economic is
balance .

2. The design of this mosque initially had To ensure the client satisfaction and value for money the
problem and can cause many problems in problematic design where being redesign.
the future. The engineers responsible had to reevaluate the design so
that in the future the mosque can stay durable in a very
long time.

3. Major defect of the mosque during and after


the completion of the project

i)Beam and Column To solve this presence of moisture in beam and column
It is noticeable that the column and the the contractor remove or control the source of the
beam in the mosque had moisture problems moisture , remove excessive internal moisture sources in
at the basement of the mosque. This can be the basement ,use dehumidification, and use a membrane
seen in figure 1 and figure 2 or coating on the inside (Safrinaz, Safwan and Hui,
2014).
ii) Pool The floor tiles at the pool is the being hacked off as soon
Mr Mohd Rafi bin Khalid an Assistant as the project had been handover toward the client and
Manager at Ahmad Zaki Resources state when doing the tiling work the client had to make sure
that the ceramic tiles at the pool collapse that the collapsing of the tiles dint happen anymore, so
and maybe this is because in a wet condition before making the pool being filled with water the client
the connection between the tiles and its make sure that the connection of tiles is strong and free
floor become weaker. from any presence of water that may affect the tiles
durability.
.

iii) External area for praying area The tiles at this area had to be hacked off too, to make
The tile for this area exploded due to the sure all the bad tiles are being removed and then new
incorrect installation method and they are tiles are being brought out and more mortar is placed
not using enough mortar to join the tiles between the tiles in order to strengthen the combination
with the floor together of the tiles. Also this this time they make sure that they
install the tiles properly.

iii) Rain water is stagnant on the floor at the To solve this problem the parties involve must done a fast
basement of the mosque. The whole stretch maintenance since it is on the floor. They had to touched up
of the floor from the front to the rear of the the floor and make sure that the floor is flat and straight so
mosque is choked and molds are spotted. that it would not become like a mud road. Since people are
using the mosque they had done their job quickly.
Figure 1(Safrinaz, Safwan and Hui, 2014)

THE PRESENCE OF
MOISTURE

Figure 2(Safrinaz, Safwan and Hui, 2014)


CRACK IN RETAINING WALL

Figure 3(Safrinaz, Safwan and Hui, 2014)

Example of exploding tiles

Figure 4 (Beaumont-tiles.com.au, 2014)


Reference

Beaumont-tiles.com.au, (2014). My Floor Tiles Have Popped Up or They Are Buckling. [online] Available
at: http://www.beaumont-tiles.com.au/TileDIYInfo/TheTileDoctor/BucklingFloorTiles.aspx [Accessed 9
Nov. 2014].

Safrinaz, N., Safwan, A. and Hui, L. (2014). dSTRUCTURE IIBDC202MASJID BESI,PUTRAJAYA.PN MAZLINA.
[online] prezi.com. Available at: https://prezi.com/xprgcmvhi7ot/dstructure-ii-bdc202-masjid-
besiputrajaya-pn-mazlina/ [Accessed 9 Nov. 2014].