CFB BOILER DESIGN AND OPERATION MANUAL

SECTION 3 - DESIGN AND OPERATION MANUAL


AMENDMENT RECORD SHEET
(PART 1, SECTION 3)

AMENDMENT RECORD
SHEET
The following Instruction Manual Amendment Record Sheet contains
a complete listing of those items that have been added to, or have
replaced information in this manual. Upon initial issue of this manual,
this list may contain items which were not included because they
were not available at the time of delivery. However, their delivery is
anticipated and appropriate locations have been provided for them in
the manual as indicated in the index. When they are shipped, the
shipment date will be added to the amendment record sheet, and a
new sheet accompany the delivery.

Whenever additional or revised information is added to the manual, a


new record sheet will be issued. As shown, the sheet will list each
item sequentially, indicate its location by Volume, Tab and Section
number, as applicable, and give a brief description of the information
and any special instructions required, such as the removal or
repositioning of existing information.

When a new amendment sheet is issued, the old sheet must be


removed and destroyed and the new amendment sheet inserted
in its place.

1-3-1
CFB BOILER DESIGN AND OPERATION MANUAL

Design and Operation Instruction Manual Amendment Record Sheet

Item Part Sect. Tab Description Date

1 2 3 Revise combustion temperature range. 2015/08/31

2 2 4 Revise combustion temperature range. 2015/08/31

3 2 6 Revise combustion temperature range. 2015/08/31

Add Particle Size Distribution (PSD) test periods of


4 2 7 3 2016/03/07
raw material and bottom ash.

Add Particle Size Distribution (PSD) test periods of


5 2 8 6 2016/03/07
raw material and bottom ash.

10

11

12

13

14

15

1-3-2