Para: Laura Cabrera – Gerente de operaciones

CC: Andrew Tong

CC: David Burga

De: Jorge Castillón – Superintendente de Mina

Asunto: Trabajos realizados en el presente mes

Fecha: 01 de Noviembre del 2014

Por medio del presente, pongo en conocimiento los diversos trabajos realizados durante el presente mes:

OPERACIÓN MINA:

a.- Cuadro de Avances Laboreo Minero:

MES : OCTUBRE AÑO: 2014

AVANCE EN
METRO MT/FASE
TIPO DE TRABAJO NIVEL VETA LABOR SECCION ANCHO VETA CAJA LINEAL OPERATIVA
EXPLORACION 3230 ESPERANZA Cx. 3584 NE 2.40 x 2.40 2.40 MT. 19.20
19.20
DESARROLLO 3230 ESPERANZA GL.6530 NW 1.80 x 2.10 0.20 MT. 25.13
DESARROLLO 3230 ESPERANZA GL. 6530 SE 1.80 x 2.10 0.20 MT. 41.90
DESARROLLO 3260 ESPERANZA GL.2530 SE 1.80 x 2.10 0.10 MT. 9.70

76.73
PREPARACION 3230 ESPERANZA CH. 544-3 1.20 x2.40 1.20 MT. 7.50
PREPARACION 3230 ESPERANZA CH. 796-2 NW 1.20 x 2.40 1.20 MT. 4.40
PREPARACION 3230 ESPERANZA SN. 5443 SE 0.80 x1.80 0.20 MT. 22.05
PREPARACION 3230 ESPERANZA SN. 5443 NW 0.80 x1.80 0.20 MT. 13.30
PREPARACION 3230 ESPERANZA SN. 796-2 SE 0.80 x 1.80 0.10 MT. 8.00
55.25
b.- Cuadro de Producción Labores de Avance y Recuperación:

REPORTE MINERAL TRANSPORTADO

DESTINO: PLANTA MOLLEHUACA MES: OCTUBRE

SULFUROS

TOTAL
FECHA 09/10/2014 22/10/2014 27/10/2014 28/10/2014 (TC)
PLACA VEHICULO V5T-751 V5T-751 V5T-751 V5T-751
NUMERO LOTE E-0003 E-0004 E-0006 E-0007
HUMEDAD 2% 2% 2% 2%
PESO BRUTO 32.62 43.97
PESO TARA 15.22 15.27
PESO NETO 17.4 28.7 26.14 26.5 98.74
PESO SECO 17.052 28.126 25.617 25.97 96.77
LEY CABEZA (gr/tc)
LEY CABEZA (gr/tc) 12.478 6.200 3.000 1.5

OXIDOS

TOTAL
FECHA 24/10/2014 (TC)
TIPO MINERAL OXIDOS
PLACA VEHICULO
NUMERO LOTE E-0005
HUMEDAD 2%
PESO BRUTO
PESO TARA
PESO NETO 25.41 25.41
PESO SECO 24.90 24.90
LEY CABEZA (gr/tc) pendiente
c.- Consumos realizados durante el mes:
REPORTE DIARO DE STOCK EXPLOSIVOS
OCTUBRE 2014

EXPLOSIVOS ACCESORIOS
FECHA ANFO DINAMITA 65DINAMITA 45 CORDON CARMEX 2.1 CARMEX 2.7 MECHA RÁP
U.M KG UN UN Mt UN UN Mt.
01/10/2014 2,311.0 9,416.0 3,242.0 1,152.0 5,877.0 6,992.0 4,252.0
02/10/2014 2,275.0 9,374.0 3,202.0 1,134.0 5,825.0 6,992.0 4,240.0
03/10/2014 2,149.0 9,227.0 3,062.0 1,071.0 5,643.0 6,992.0 4,198.0
04/10/2014 2,095.0 8,953.0 2,942.0 1,026.0 5,554.0 6,942.0 4,160.0
05/10/2014 1,997.0 8,712.0 2,752.0 962.0 5,398.0 6,917.0 4,106.0
06/10/2014 1,997.0 8,712.0 2,752.0 962.0 5,398.0 6,917.0 4,106.0
07/10/2014 1,997.0 8,712.0 2,752.0 962.0 5,398.0 6,917.0 4,106.0
08/10/2014 1,997.0 8,712.0 2,752.0 962.0 5,398.0 6,917.0 4,106.0
09/10/2014 1,997.0 8,712.0 2,752.0 962.0 5,398.0 6,917.0 4,106.0
10/10/2014 1,967.0 8,612.0 2,502.0 920.0 5,368.0 6,877.0 4,076.0
11/10/2014 1,887.0 8,472.0 2,322.0 872.0 5,248.0 6,857.0 4,031.0
12/10/2014 1,887.0 8,472.0 2,322.0 872.0 5,248.0 6,857.0 4,031.0
13/10/2014 1,869.0 8,393.0 2,292.0 872.0 5,222.0 6,857.0 4,031.0
14/10/2014 1,779.0 8,245.0 2,096.0 825.5 5,068.0 6,857.0 3,986.0
15/10/2014 1,671.0 8,146.0 1,928.0 777.5 4,954.0 6,857.0 3,944.0
16/10/2014 1,671.0 8,146.0 1,928.0 777.5 4,954.0 6,857.0 3,944.0
17/10/2014 1,671.0 8,078.0 1,765.0 777.5 4,947.0 6,857.0 3,921.0
18/10/2014 1,671.0 7,863.0 1,729.0 744.5 4,921.0 6,782.0 3,886.0
19/10/2014 1,623.0 7,704.0 1,661.0 709.5 4,885.0 6,689.0 3,866.0
20/10/2014 1,567.0 7,636.0 1,628.0 685.5 4,859.0 6,647.0 3,849.0
21/10/2014 1,559.0 7,636.0 1,618.0 685.5 4,859.0 6,637.0 3,848.0
22/10/2014 1,533.0 7,589.0 1,592.0 666.5 4,833.0 6,618.0 3,836.0
23/10/2014 1,481.0 7,355.0 1,528.0 638.5 4,753.0 6,570.0 3,805.0
24/10/2014 1,458.0 7,263.0 1,528.0 624.5 4,713.0 6,558.0 3,796.0
25/10/2014 1,408.0 7,139.0 1,480.0 596.5 4,645.0 6,534.0 3,779.0
26/10/2014 1,364.0 6,980.0 1,462.0 561.5 4,550.0 6,510.0 3,758.0
27/10/2014 1,286.0 6,792.0 1,360.0 516.5 4,434.0 6,498.0 3,730.0
28/10/2014 1,194.0 6,573.0 1,360.0 516.5 4,353.0 6,410.0 3,680.0
29/10/2014 1,081.0 6,349.0 1,360.0 516.5 4,247.0 6,344.0 3,632.0
30/10/2014 1,019.0 6,176.0 1,360.0 516.5 4,166.0 6,309.0 3,608.0
31/10/2014 1,004.0 6,153.0 1,348.0 506.5 4,148.0 6,309.0 3,603.0
Geología:

Control de Calidad.-
Se continuó con los avances programados del mes de Octubre a la par con la recuperación de mineral;
pallaqueando, cerniendo y tamizandoo. En las siguientes labores:
 Galería 6530 S.E Nivel 3230
 Galería 6530 NW Nivel 3230
 Sub nivel 5443 S.E Nivel 3230
 Sub Nivel 796-2 Nivel 3230
 Tajo 796-2 Nivel 3230
 Chimenea 594-1 Nivel 3230
Se contorneo la veta de las mismas labores para su respectivo proceso de disparo.
En canchas de mineral se acumulo cargas luego de su respectivo muestreo para la ubicación acorde a sus
leyes.
Adjunto en el cuadro de Excel las muestras enviadas y pagos de ella misma del mes de Octubre.
REPORTE DE ENVIO DE MUESTRAS DEL MES DE OCTUBRE DEL
2014

ENSAYO TOTAL ENSAYO TOTAL


FECHA CODIGO
POR Au PAGAR (Au) POR Ag PAGAR (Ag)
Rs 00195 S/. 30.00
Rs 00196 S/. 30.00 S/. 30.00
Rs 00197 S/. 30.00
Rs 00198 S/. 30.00 S/. 30.00

03/10/2014
Rs 00199 S/. 30.00 S/. 30.00
Rs 00200 S/. 30.00
Rs 00201 S/. 30.00 S/. 30.00
S/. 420.00 S/. 180.00
Rs 00202 S/. 30.00
Rs 00203 S/. 30.00 S/. 30.00
Rs 00204 S/. 30.00 S/. 30.00
Rs 00205 S/. 30.00
Rs 00206 S/. 30.00
Rs 00207 S/. 30.00
Rs 00208 S/. 30.00 TOTAL PAGADO S/ . 600
Rs 00209 S/. 30.00
Rs 00210 S/. 30.00
Rs 00211 S/. 30.00
06/10/2014

Rs 00212 S/. 30.00


Rs 00213 S/. 30.00
Rs 00214 S/. 30.00
S/. 360.00
Rs 00215 S/. 30.00
Rs 00216 S/. 30.00
Rs 00217 S/. 30.00
Rs 00218 S/. 30.00
Rs 00219 S/. 30.00
Rs 00220 S/. 30.00 TOTAL PAGADO S/ . 360
Rs 00221 S/. 30.00
16/10/2014 10/10/2014 09/10/2014

Rs 00222 S/. 30.00


Rs 00223 S/. 30.00
Rs 00224 S/. 30.00 S/. 210.00
Rs 00225 S/. 30.00
Rs 00226 S/. 30.00
Rs 00227 S/. 30.00 TOTAL PAGADO S/ . 210
Rs 00228 S/. 30.00
Rs 00229 S/. 30.00
Rs 00230 S/. 30.00
Rs 00231 S/. 30.00
S/. 150.00
Rs 00232 S/. 30.00

TOTAL PAGADO S/. 150


Rs 00233 S/. 30.00
Rs 00234 S/. 30.00
Rs 00235 S/. 30.00
Rs 00236 S/. 30.00 S/. 210.00
Rs 00237 S/. 30.00
Rs 00238 S/. 30.00
Rs 00239 S/. 30.00 TOTAL PAGADO S/ . 210
Rs 00240 S/. 30.00
Rs 00241 S/. 30.00
Rs 00242 S/. 30.00
Rs 00243 S/. 30.00 S/. 30.00
Rs 00244 S/. 30.00
Rs 00245 S/. 30.00
18/10/2014

Rs 00246 S/. 30.00


Rs 00247 S/. 30.00
Rs 00248 S/. 30.00 S/. 510.00 S/. 30.00
Rs 00249 S/. 30.00
Rs 00250 S/. 30.00
Rs 00251 S/. 30.00
Rs 00252 S/. 30.00
Rs 00253 S/. 30.00
Rs 00254 S/. 30.00
Rs 00255 S/. 30.00
Rs 00256 S/. 30.00 TOTAL PAGADO S/ . 540
Rs 00257 S/. 30.00
Rs 00258 S/. 30.00 S/. 30.00
Rs 00259 S/. 30.00
Rs 00260 S/. 30.00
Rs 00261 S/. 30.00
Rs 00262 S/. 30.00
21/10/2014

Rs 00263 S/. 30.00


Rs 00264 S/. 30.00
Rs 00265 S/. 30.00 S/. 510.00 S/. 30.00
Rs 00266 S/. 30.00
Rs 00267 S/. 30.00
Rs 00268 S/. 30.00
Rs 00269 S/. 30.00
Rs 00270 S/. 30.00
Rs 00271 S/. 30.00
Rs 00272 S/. 30.00
Rs 00273 S/. 30.00 TOTAL PAGADO S/ . 540
Rs 00274 S/. 30.00
Rs 00275 S/. 30.00 S/. 30.00
Rs 00276 S/. 30.00
Rs 00277 S/. 30.00
23/10/2014

Rs 00278 S/. 30.00 S/. 30.00


Rs 00279 S/. 30.00
Rs 00280 S/. 30.00 S/. 30.00
S/. 420.00 S/. 90.00
Rs 00281 S/. 30.00
Rs 00282 S/. 30.00
Rs 00283 S/. 30.00
Rs 00284 S/. 30.00
Rs 00285 S/. 30.00
Rs 00286 S/. 30.00
Rs 00287 S/. 30.00 TOTAL PAGADO S/ . 510
Rs 00288 S/. 30.00 S/. 30.00
31/10/2014 30/10/2014 27/10/2014 24/10/2014

Rs 00289 S/. 30.00


Rs 00290 S/. 30.00
Rs 00291 S/. 30.00 S/. 120.00 S/. 30.00

TOTAL PAGADO S/ . 150


Rs 00292 S/. 30.00
Rs 00293 S/. 30.00
Rs 00294 S/. 30.00
Rs 00295 S/. 30.00
S/. 240.00 S/. 30.00
Rs 00296 S/. 30.00 S/. 30.00
Rs 00297 S/. 30.00
Rs 00298 S/. 30.00
Rs 00299 S/. 30.00 TOTAL PAGADO S/ . 270
Rs 300 S/. 30.00
Rs 301 S/. 30.00
Rs 302 S/. 30.00
Rs 303 S/. 30.00 S/. 30.00
S/. 180.00 S/. 30.00
Rs 304 S/. 30.00
Rs 305 S/. 30.00

TOTAL PAGADO S/ . 210


Rs 00306 S/. 30.00
Rs 00307 S/. 30.00
Rs 00308 S/. 30.00
Rs 00309 S/. 30.00
Rs 00310 S/. 30.00
S/. 300.00
Rs 00311 S/. 30.00
Rs 00312 S/. 30.00
Rs 00313 S/. 30.00
Rs 00314 S/. 30.00
Rs 00315 S/. 30.00 TOTAL PAGADO S/ . 300

T OT AL PAGADO DEL M ES S/. 4050


Topografía.-
Durante el periodo de octubre 2014, se han levantado y avanzado como se especifica en el cuadro a ver en
la siguiente página. En estos primeros días de noviembre se están avanzando en la Gl. 6530 SE 9.50 mt., en
la Gl. 6530 NW. 14 mt. . Los trabajos en los subniveles y chimeneas se van a realizar en los próximos días
por el tema de tajeo e inestable el terreno. A continuación detallo el plano de avance.
AVANCE EN UBICACIÓN,DESCRIPCION EN METRO DESCRIPCION EN METROS
VEL VETA LABOR SECCION ANCHO VETA CAJA METRO LINEAL LINEAL CUBICOS UNID. M3 DENSIDAD TN3 2.65 MATERIAL PISO OBSERVACIONES
ESPERANZA GL.6530 NW 1.80 x 2.10 0.20 MT. 25.131 MT. Del pto. R - 7.05 + 18.081 MT. Tope 0.20x25.131x2.1= 10.555 MT3 10.555 27.971 MINERAL 0
ESPERANZA GL.6530 NW 1.80 x 2.10 1.60 MT. 25.131 MT. Del pto. R - 7.05 + 18.081 MT. Tope 1.60x25.131x2.1= 84.440MT3 84.44 223.766 DESMONTE 0
ESPERANZA CM. 2530 2.40 x 2.40 2.40 MT. 19.20 MT. Desde Fl.Cm. + 19.20 MT. Tope 2.40x19.20x2.40= 110.592 MT3 110.592 293.069 DESMONTE 0
ESPERANZA GL. 6530 SE 1.80 x 2.10 0.20 MT. 41.90 MT. Del pto. N1 - 3.49 + 38.41 MT. Tope 0.20x41.90x2.10= 17.598 MT3 17.598 46.635 MINERAL 0
ESPERANZA GL. 6530 SE 1.80 x 2.10 1.60 MT. 41.90 MT. Del pto. N1 - 3.49 + 38.41 MT. Tope 1.60x41.90x2.10= 140.784 MT3 140.784 373.078 DESMONTE 0
ESPERANZA GL.2530 SE 1.80 x 2.10 0.10 MT. 9.70 MT. Del pto. D4 - 3.60 + 6.10 MT. Tope 0.10x9.70x2.10= 2.037MT3 2.037 5.398 MINERAL 0
ESPERANZA GL.2530 SE 1.80 x 2.10 1.70 MT. 9.70 MT. Del pto. D4 - 3.60 + 6.10 MT. Tope 1.70x9.70x2.10= 34.629MT3 34.629 91.767 DESMONTE 0
ESPERANZA CH. 796-2 NW 2.40 x 2.40 2.40 MT. 3.20 MT. F/GL.6530 NW. + 3.20 MT. Inicio CH. 2.40x2.40x3.20= 18.43 MT3 18.43 48.845 DESMONTE DESQUINCHE
ESPERANZA CH. 5443 SE 1.20 x2.40 1.20 MT. 7.50 MT. F/Techo Gal. + 7.50 MT. Al Techo SN. 1.20x2.40x7.50= 21.600 MT3 21.6 57.24 DESMONTE 0 AVANCE
ESPERANZA SN. 5443 SE 0.80 x1.80 0.20 MT. 22.050 MT. F/CH + 22.050 MT. Tope 0.20x22.050x1.80= 7.938MT3 7.938 21.036 MINERAL 0
ESPERANZA SN. 5443 SE 0.80 x1.80 0.60 MT. 22.050 MT. F/CH + 22.050 MT. Tope 0.60x22.050x1.80= 23.814MT3 23.814 63.107 DESMONTE 0
ESPERANZA SN. 5443 NW 0.80 x1.80 0.20 MT. 13.30 MT. F/CH + 13.30 MT. Tope 0.20x13.30x1.80= 4.788MT3 4.788 12.688 MINERAL
ESPERANZA SN. 5443 NW 0.80 x1.80 F/CH + 13.30 MT. Tope 0.60x22.050x1.80= 14.364MT3 14.364 38.065 DESMONTE
ESPERANZA CH. 796-2 NW 1.20 x 2.40 1.20 MT. 4.40 MT. F/Techo Gal. + 4.40 MT. Al Techo SN. 1.20x2.40x4.40= 12.672 MT3 12.672 33.581 DESMONTE 0 AVANCE
ESPERANZA SN. 796-2 SE 0.80 x 1.80 0.10 MT. 8.00MT. F/CH + 6.70 Tope 0.10x6.70x1.80= 1.206 MT3 1.206 3.196 MINERAL 0
ESPERANZA SN. 796-2 SE 0.80 x 1.80 0.70 MT. 8.00MT. F/CH + 6.70 Tope 0.70x6.70x1.80= 8.442 MT3 8.442 22.371 DESMONTE 0
ESPERANZA TJ. 796-2 SE 0.80 x 2.00 0.20 MT. 9.10 MT. Techo/SN + 2.68 MT. 0.20x9.10x2.68=6.240 MT3 4.878 12.926 MINERAL
ESPERANZA TJ. 796-2 SE 0.80 x 2.00 0.60 MT. 9.10 MT. Techo/SN + 2.68 MT. 0.60x9.10x2.68= 14.633MT3 14.633 38.777 DESMONTE
CÁMARA
GL.6530
NW
GL.6530 SE

CH.796-2

SN.5443 NW SN.5443 SE

CX.3584

BOCA MINA

CANCHA
Administración:

PERSONAL ELADIUM S.A.C


OCTUBRE 2014
N° NOMBRES Y APELLIDOS CARGO
ADMINISTRACION GENERAL
1 CASTILLON SANABRIA, JORGE SUPERINTENDENTE DE MINA
2 MAMANI MATOS, RAPHAEL DAVID ING. GEOLOGO
3 LOZANO, MÁXIMO ING.MINAS
4 MARQUEZ CORTEZ, ALEJANDRO ISMAEL ADMINISTRADOR DE MINA
5 VASQUEZ RAMIREZ, JUAN ANTONIO ADMINISTRADOR
6 BRAVO RAEZ, ISMAEL EUSEBIO ADMINISTRADOR
GEOLOGÍA - INGENIERÍA
7 HUERTO HUANUCO, CESAR TOPOGRAFO
8 BALDEON TRUJILLO, ORESTES MIGUEL MUESTRERO
9 ALCALDE ANDIA, KALLET EDINSSON MUESTRERO
PERSONAL DE CAMPO
10 GALARRETA COLLANTES, EDWARD ELVIS AYUDANTE
11 LUQUE APAZA, JUAN GALINDO AYUDANTE
12 SANCHEZ VELASQUEZ, TEOFILO AYUDANTE
13 QUISPE PARIONA, SAUL MAESTRO PERFORISTA
14 GRANADOS PALOMINO, ISAIAS AYUDANTE PERFORISTA
SEGURIDAD PATRIMONIAL
15 ESPETIA HUAMANGA, PERCY PREVENCIONISTA
16 LORENZO GALLEGOS, NESTOR PREVENCIONISTA
17 SOTO MAMANI, JIMMY RONALD PREVENCIONISTA

SERVICIOS DE ALIMENTACIÓN MINA


OCTUBRE 2014
EMPRESA: CORPSAN
SEPTIEMBRE OCTUBRE VARIAC IÓN %

ELADIUM S/. 4,329.00 S/. 5,023.00 16%


VIGILANCIA Y PREVENCIONISTAS S/. 1,996.00 S/. 2,907.00 46%
TRANSPORTE CAMIONETA - CAMION S/. 609.00 S/. 878.00 44%
JB MINING SAC S/. 668.00 S/. 705.00 6%
VISITAS S/. 642.00 S/. 258.00 -60%
OTROS S/. 690.00 S/. 2,697.00 291%
TOTAL S/. S/. 8,934.00 S/. 12,468.00 40%
TOTAL US$ 3,765.04 5,254.37 40%
SERVICIOS DE TRANSPORTE MINA
OCTUBRE 2014
SEPTIEMBRE OCTUBRE VARIAC IÓN %

MULTISERVICIOS RODRIGO Y PIERO HERMANOS $ 1,100.00 $ 1,100.00 0%


SANYG $ 630.00 $ 2,100.00 233%
$ 1,730.00 $ 3,200.00 85%

Conclusiones:
- Se tuvo muchas restricciones respecto a explosivos por lo que la capacidad de avance se redujo al
50%. Se remontó el déficit de avances en lo que queda del mes llegando a cumplir 60 % del
programa mensual de avances.
- La apertura de la veta Vanessa en el nivel 3230, nos dará la posibilidad de explorar una nueva
estructura y acumular mineral del laboreo que se ejecute con la cuadrilla especial Mina.
- Se está programando para el mes de Octubre mayor metraje para cubrir el déficit de los meses
anteriores y se pueda tener tajeo de explotación preparados para el mes de Noviembre.
- Se está replanteando todo lo referido al plan de minado. Esto se relaciona con la capacidad de
planta para poder recuperar los minerales de sulfuro que tenemos en mina.

Atte.

Ing. Jorge Castillón Sanabria


Superintendente de Mina
Cia. Minera Eladium Sac.