Sunteți pe pagina 1din 64

 

 
Mezzanine Floor, Tirumailai Railway Station, Mylapore, Chennai – 600 004 
Telefax : 044 ‐ 24618460  
 
 
 

 
Volume II – Price Proposal 
 

” Proposed new BG line between Obluvaripalle and Venkatachalam – Execution of 
earthwork in formation, bridges, road under bridges, station buildings, staff quarters, 
general electrical works including power line crossings from Km. 00 to Km. 17 between 
Obulavaripalle to Nethavaripalle in South Central Railway” 

 
FEBRUARY 2010 
  

 
Corporate Office: 
 

RAIL VIKAS NIGAM LIMITED 
First floor, August Kranti Bhavan,  
Bhikaji Cama Place, New Delhi – 110 066  

Tele : + 91‐11‐26738195 , Fax : + 91‐11‐26182957, web : www.rvnl.org 
 
 

   

1 Volume II – Bill of Quantities


Bill of Quantities 
PREAMBLE 
 
1. The Bill of Quantities shall be read in conjunction with the Instructions to Bidders, General 
Conditions, Particular Conditions of Contract, Works Requirement (Technical Specifications, 
and Drawings). 

2. The quantities given in the Bill of Quantities are estimated and provisional, and are given to 
provide  a  common  basis  for  bidding.  The  basis  of  payment  will  be  the  actual  quantities  of 
work ordered and carried out, as measured by the Contractor and verified by the Engineer 
and valued at the rates and prices tendered in the priced Bill of Quantities, where applicable, 
and  otherwise  at  such  rates  and  prices  as  the  Engineer  may  fix  within  the  terms  of  the 
Contract. 
 
3. In the Bill of Quantities, quantity and unit rates and thereby the amount against each item 
have  been  indicated.  From  this,  the  estimated  price  of  each  bill  has  been  worked  out  and 
indicated  in  the  summary  sheet  in  BOQ.  The  Bidder  shall  quote  rates  as  percentage 
above/below/at  par  for  each  schedule  in  the  summary  sheet.  If  no  percentage  as  above, 
below or par is indicated for any particular bill, the same will be considered as percentage at 
par.   
4. The rates for each bill shall be written in indelible ink or type written in the summary sheet 
against each bill in words and figures as percentage above /below/at par with RVNL’s cost.  
Thereby, quoted price for each bill shall be calculated and written against each bill.  The total 
price, as sum of quoted price for all the bills shall be shown at the bottom of the summary 
sheet.  The total price shall also be written in words and figures. 
 
5. General  directions  and  descriptions  of  work  and  materials  are  not  necessarily  repeated  or 
detailed  in  the  Bill  of  Quantities.  References  to  the  relevant  specifications  and  sections  of 
the contract documentation should be made before quoting rates in the Bill of Quantities. 
 
6. The rates and prices Bid in the priced  Bill of Quantities shall, except as otherwise provided 
under the Contract, include all construction equipment, plant, labour, supervision, materials, 
erection, maintenance, insurance, profit, royalty, octroi, taxes and duties, together with all 
general risks, liabilities and obligations set out or implied in the Contract.  
 
7. The rates are deemed to be inclusive of all lead (except as otherwise specifically provided in 
the description of the particular item), lifts, ascend, descend, handling, rehandling crossing 
of nallah/streams/tracks any other obstructions. 
8. All  enabling  works  for  executing  the  work  e.g.  approach  road  to  site,  launching 
arrangements,  procuring  right  of  way,  arrangement  of  water  and  electricity  etc  is  to  be 
arranged by the contractor at his own cost and deemed to be included in the quoted rates. 
 
9. Storage of Material: All the material at site will have to be properly stacked & stored so as to 
facilitate inspection. The material should be properly protected from the detrimental effects 
of nature and fire, theft etc. The contractor shall be responsible for watch & ward and any 
loss or deterioration on account of above shall lead to rejection of material and contractor 
has to replace the same at his own cost. 
 

2 Volume II – Bill of Quantities


10. The  method  of  measurement  of  completed  work  for  payment  shall  be  in  accordance  with 
provisions in Works Requirements (Specifications) except as otherwise specifically provided 
in  the  description  of  item  or  particular  bill  of  quantities  or  explanatory  notes  to  the 
particular bill of quantities.  
 
11. (a) In items of Bill No. 6: (Building and related items) and Bill No.9: (Site facilities), the rates 
are inclusive of cost of all materials including cement, steel, etc. required to deliver the final 
product. 
 
  (b)  In  items  of  bill  No.2:  (Bridges),  Bill  No.5:  (track  linking),  and  Bill  No.7:  (Platforms, 
passenger amenities and Misc works) where ever cement, reinforcement steel and HTS wire 
(strands)are  required  to  be  consumed  in  the  item,  the  rates  are  exclusive  of  cost  of  these 
materials  and  the  same  shall  be  paid  separately  under  relevant    items  for  supply  of  these 
materials.   
 
(c) In items of Bill No.4: (P. Way supply) the rates are inclusive of all materials including cement, steel 
and  HTS  wire  (strands).    Rails  required  for  manufacture  of  item  under  Bill  No.4  shall  be 
issued free of cost by RVNL. 
 
12. NOTES SPECIFIC TO EACH BILL OF QUANTITIES. 
 
12.1. BILL NO.1 FOR EARTH WORK IN FORMATION 
   
12.1.1 The earth work in formation and blanketing has to be executed as per latest RDSO guidelines 
for  earthwork  in  railway  projects  with  up  to  date  correction  slips.  If  naturally  available 
material in the project area is not suitable for using as blanketing material directly then the 
blanketing  material  conforming  to  RDSO  specification  has  to  be  produced  by  blending 
various naturally available materials in required proportion in a pug mill. 
 
12.1.2 Obtaining  prior  permission  for  felling  of  trees  including  payment  of  royalty  and  taxes  etc 
shall be contractor’s responsibility and deemed to be included in the rates. 
 
12.1.3 Joining of new formation with existing embankment has to be done with benching of 30 cm 
(V),  60  cm  (H)  in  the  existing  bank  slope.  The  rate  of  earthwork  includes  the  cost  of 
benching. 
 
12.1.4 Locations where blasting is warranted, prior permission of the employer must be obtained 
to  ascertain  whether  blasting  is  permitted  or  prohibited.  Rate  of  rock  cutting  includes  the 
cost of all precautionary measures necessary for safety during blasting of rock. 
 
12.2 BILL  NO.2:  BRIDGES  AND  BILL  NO.7:  PLATFORM,  PASSENGER  AMENITIES  AND 
MISCELLANEOUS WORK FOR CC, RCC AND PSC ITEMS. 
 
12.2.1 All material, equipment, labour, casting beds, stress frames, from work staging, scaffolding, 
etc is to be arranged by the contractor within the quoted rates. 
 
12.2.2 1:4:8,  1:3:6  and  1:2:4  indicates  concrete  prepared  using  volumetric  mix  in  proportion  of 
cement: coarse sand: stone aggregate of specified size, respectively. 
 

3 Volume II – Bill of Quantities


12.2.3 All  design  mix  concrete  shall  be  machine  batched  with  automatic  weigh  batcher,  machine 
mixed and machine vibrated or Ready Mix Concrete prepared in depot and transported by 
transit mixer to the site of work.  
 
12.2.4 Prior  to  demolishing  of  any  structure  measurements  have  to  be  taken,  scheme  of 
dismantling has to be got approved from the Engineer. 
 

12.2.5  The  following  items  of  work  are  to  be  done  as  pre‐cast  in  addition  to  PSC  girder  for 
major/minor bridge:  
 
(a) CC blocks for pitching on quadrants of the bridges –2785 cum (approx.). 
(b) CC slabs for providing on slopes of bank – 4230 cum (approx.). 
(c) CC slabs for inspection steps – 50 cum (approx.).  
(d) CC slabs for Key men’s inspection path – 55 cum (approx.) 
(e) CC coping slabs for bridges – 38 cum (approx.) 

12.2.6 The  Contractor  has  to  cast  CC  slabs/blocks  at  suitable  location  where  sufficient  space  for 
casting  with  adequate  availability  of  water  &  materials.    Thereafter,  these  have  to  be 
transported to the required location and to be laid.  Payment for these items will be made 
under items No. 2005 of Bill No. 2.  Transportation cost is included in the cost of the items 
and no separate payment shall be made for any transportation.  The Contractor is advised to 
cater for this cost while bidding for the work. 
 
12.3 BILL NO.4: (PERMANENT WAY SUPPLY) 
 
12.3.1 All  P.  Way  materials  shall  be  procured  only  from  suppliers  included  in  part  I  list  of 
RDSO approved suppliers for the particular item. Where, such a list is not maintained 
by RDSO, prior approval of source of supply shall be obtained from the employer. 
 
12.3.2 All P. Way materials shall be inspected by the inspecting authority as prevalent over 
zonal  railway  for  the  particular  material.  However,  employer  reserves  the  right  to 
nominate any authority or its own representative to inspect the material. 
 
12.3.3 Payment of inspection charges shall be borne by the employer. 
 
12.3.4 If the rails required for manufacture of the finished material are to be issued free of 
cost  by  the  Employer,  as    specified  in  the  description  of  item,  the  employer  shall 
issue such rails either in project area or from Bhilai. The quoted rates include cost of 
handling  and  transportation  of  rails  to  the  manufacturers  workshop  and  finished 
materials from the manufacturers workshop to the site of work. 

 
12.3.5 All  P.  Way  material  shall  be  neatly  stacked  and  stored  in  the  project  area  and 
protected against loss/ deterioration by proper watch and ward staff, insurance, etc, 
the cost of which is deemed to be included in the rates. 

4 Volume II – Bill of Quantities


12.4 BILL NO.5: (PERMANENT WAY LINKING) 
 
12.4.1 Painting  of  rails  for  loops  &  platform  lines  shall  be  done  before  fixing  in  position  and 
touching to be done after laying in position. 
 
12.4.2 Rates include day as well as night working and lighting arrangement as per requirement and 
to the satisfaction of the engineer. 
 
12.4.3 The welds found defective in USFD, shall have to be replaced by the contractor at his own 
cost. 
 
12.4.4 For  Mechanized  laying  of  track  only  service  rails  will  be  made  available  by  RVNL.  All  other 
materials  such  as  wooden  blocks,  fish  plates,  rail  screw  etc  will  have  to  be  arranged  by 
contractor. The rails will be provided at convenient location within the project jurisdiction. 
All leads, lifts & transportation etc shall have to be done by contractor including depositing 
back after completion of works at his own cost. 
 
12.4.5 During the maintenance of track after commissioning, all arrangement for transportation of 
labour, T&P etc will have to be done by contractor at his own cost. Necessary T&P for track 
maintenance will be procured by the contractor including consumables. The rate includes all 
such requirements. 
 
12.4.6 The payment of rail cuts and drilling holes will be done as per final layout of mainline/loop 
line/sidings and turnouts etc. Rail cuts/hole drilling required for temporary working will not 
be paid. 
 
12.5 Bill No.8: (Supply of Cement): Payment for supply shall only be made after the quantity is 
consumed  in  the  related  item  of  work.  The  consumption  of  cement  shall  be  worked  out 
based  on  cement  consumption  coefficients  as  given  below  or  the  actual  consumption 
whichever is less. 
 
COEFFICIENTS FOR CEMENT CONSUMPTION 
 
Sl.  Item  Unit  Cement  consumption 
No.  coefficients  per  unit  in  Kg. 
(Maximum) 
Cement Concrete     
1.  1:3:6 (1 Cement 3 coarse sand, 6 graded stone  Cum  220 
  aggregate) 
2.  1:2:4 (1 cement, 2 coarse sand, 4 graded  Cum  320 
stone aggregate) 
3.  M20  Cum  400 
4.  M25  Cum  410 
5.  M30  Cum  420 
6.  M35  Cum  428 
7.  M40  Cum  435 
8.  M45  Cum  480 

5 Volume II – Bill of Quantities


9.  M50  Cum  500 
Cement Mortar 
5.  Cement  Mortar 1:2 (1 Cement: 2 Sand)  Cum  680 
6.  Cement  Mortar 1:3 (1 Cement: 3 Sand)  Cum  510 
7.  Cement  Mortar 1:4 (1 Cement: 4 Sand)  Cum  380 
8.  Cement  Mortar 1:5 (1 Cement: 5 Sand)  Cum  310 
9.  Cement  Mortar 1:6 (1 Cement: 6 Sand)  Cum  250 
Brick Work 
11.  Cement Mortar 1:4 (1 cement: 4 coarse sand)  Cum  95 
12.  Cement Mortar 1:6 (1 cement: 6 coarse sand)  Cum  62.5 
13.  Cement Mortar 1:3 (1 cement: 3 coarse sand)  Sqm  14.28 
half brick 
14.  Cement Mortar 1:4 (1 cement: 4 coarse sand)  Sqm  10.64 
half brick 
 
Note:    Cement consumption for any item if not mentioned above is to be worked out as per CPWD DSR 2007.
   
TECHNICAL SPECIFICATION FOR CONSTRUCTION OF  SERVICE & RESIDENTIAL 
BUILDINGS 
 
1. These specifications shall be applicable to service & residential buildings of various 
types to be constructed along the project length with reference to Bill No.6 of BOQ. 
 
2. Technical Specifications common to all type of buildings : 
 
2.1. Technical specifications for various activities involved in the work shall generally be 
in  accordance  with  RVNL  Standard  Specifications  for  materials  &  works  (Section‐
2100)  as  amended  up  to  date.  In  case  specification  for  any  activity  necessary  for 
completion of building is not available in RVNL Standard Specifications for materials 
&  works,  relevant  BIS  codes  of  practices  shall  be  applicable.  In  case  of  any 
contradicting  instructions  in  the  specifications,  Engineer’s decision  will  be  final  and 
binding. 
 
2.2. General  Arrangement  Drawings  (GAD)  provided  in  the  bidding  documents  are 
sample drawings for the guidance of bidders and are indicative of type of buildings 
to be constructed. However, particular GAD to be adopted at particular locations of 
the  project  shall  be  made  available  to  the  contractor  during  the  currency  of  the 
contract. The buildings may also be required to be constructed in continuation of the 
existing  building,  in  such  a  case  the  new  structure  is  to  be  constructed  by  proper 
joints  and  connections,  the  design  and  detailed  drawings  shall  have  to  be  made 
accordingly and ,cost of which is deemed to be included in plinth area rates. 
 
2.3. Suitable  economical  structural  and  architectural  design  for  foundation  and  super 
structure consisting of masonry walls, reinforced columns/beams/slabs shall be done 

6 Volume II – Bill of Quantities


by the Contractor as per site conditions for the service building and others structures 
including  all  detailed  designs  of  RCC  works  i.e.  columns,  beams stair case, balcony, 
slabs  etc.  keeping  in  view  the  relevant  seismic  zone  &  making  the  building 
earthquake  resistant  Working  drawings  will  have  to  be  prepared  by  the  contractor 
for  each  activity  of  work,  giving  details  of  reinforcement,  water  arrangements, 
drainage, sewerage, floorings, fittings etc. and got approved from the Engineer. The 
construction will be done with approved drawings.  
 

2.4. The  plinth  area  rates  for  construction  of  buildings  includes  cost  of  all  design, 
drawings, materials, labour, tools & plants, equipments, taxes, ascent, descent, lead 
and  lift,  cement  and  steel  etc.  Nothing  will  be  paid  extra  and  buildings  have  to  be 
handed  over  complete  in  all  respect  to  house  the  Signaling/Electrical/Operating 
equipments  and  machines  including  provision  of  ducts,  trenches,  ramps  etc. 
complete in all respect required to make it functional. This also includes cost of all 
architectural  features  and  preparation  of  detailed  drawings  and  designs  thereof. 
RVNL  reserves  the  right  to  ask  the  contractor  to  adopt  available  drawings  of 
RVNL/Railways, without making any deductions or extra payments on this account. 
 
2.5. If  any  activity  of  the  work  is  essential  for  completion  of  the  building  but  is  not 
mentioned  specifically  in  these  specifications  or  elsewhere  in  the  bidding 
documents,  the  same  shall  be  deemed  to  be  included  in  the  rates  and  shall  be 
executed  by  the  Contractor  as  per  specifications  decided  by  the  Engineer  and  the 
building shall be handed over in functional manner, complete in all respects. 
 

2.6. Water & electricity shall be arranged by the Contractor at his own cost for execution 
of works. 
 

2.7. Contractor has to make arrangements for approach to site, stacking of materials and 
all temporary works necessary for the execution of work at his own cost. 
 
2.8. Contractor  will  have  to  make  arrangements  for  required  tests  (as  directed  by  the 
Engineer)  for  testing  the  soundness  of  the  work  or  any  of  the  materials  at 
Contractor’s own cost. 
 
2.9. Sampling  and  testing  of  work/material  at  site/laboratory  shall  be  as  per  the  RVNL 
Standard  Specification  for  materials  and  works  and  relevant  Indian  Standard 
Specifications, with up to date corrections. 
 
2.10. If  any  work is  found  unsatisfactory or  under  specification  the  same  will  have  to  be 
redone by the Contractor at Contractor’s own cost. In case, the Contractor fails to do 
so, the same will be got done by Engineer at the Contractor’s cost. 
 
2.11. The Engineer will be at liberty to get any work or material dismantled/removed by 
any  other  means  at  Contractor’s  cost  if  it  is  found  unsatisfactory  or  under 
specification, and the contractor fails to rectify the same within specified time. 

7 Volume II – Bill of Quantities


 
2.12. The site shall be cleared of all debris etc. before commissioning of work. 
 
2.13. The  contractor  shall  take  all  necessary  safety  precautions  during  fabrication, 
launching,  of  members,  casting  of  RCC  slabs  etc.  He  shall  also  ensure  safety  of 
railway  track  if  the  work  is  required  to  be  done  near  the  track  or  above  railway 
tracks. 
 
2.14. In case there is any damage to road, drain or other structure during construction of 
the work by the contractor, the damages will have to be rectified by the contractor 
at his own cost. 
 
2.15. Earth work:  Earthwork in filling in plinth and floors including for plinth protection, if 
required shall be done by contractor with Contractor’s own earth of good quality. No 
earth is to be taken from the Railway premises except surplus earth from excavation 
for the building. The cost of such earthwork is included in plinth area rates 
 
2.16. Concrete  work:    All  plain  and  reinforced  concrete  work  to  be  done  as  per  IS:  456 
Code  of  Practice.  Design  mix  concrete  as  approved  by  Engineer  shall only  be  used. 
Nominal  mix  can  be  permitted  by  the  Engineer  only  in  exceptional  circumstances. 
The  cement  concrete  flooring,  roof  and  other  RCC/Concrete  structures  are  to  be 
levelled and compacted with vibrator of suitable size and specification.  
 

2.17. Anti‐termite treatment: Anti‐termite treatment shall be provided as per para 2901 of 
RVNL Standard Specifications for materials & works, cost of which is deemed to be 
included  in  plinth  area  rates.  The  chemical  shall  be  approved  by  the  Engineer  and 
used as per the manufacturer’s instructions/ specifications. 
 
2.18. Plinth  protection  –  If  not  mentioned  otherwise  in  the  detailed  drawings,  plinth 
protection of one meter width all around the building shall be provided as per para  
2902 of RVNL Standard Specifications for materials & works  
 

2.19. Damp  Proof  Course  (DPC)  –  Unless  otherwise  mentioned  in  the  drawings,  DPC  will 
consist of 40mm thick 1:2:4 PCC with two coats of bitumen over it. 
 
2.20. Masonry work – Masonry work has to be in well burnt clay bricks of class designation 
75,  as  approved  by  the  Engineer.  All  outer  and  load  bearing  walls  shall  be  of 
minimum  230  mm  thickness  or  more  as  per  design,  in  cement  mortar  1:6,  all 
partition walls shall be 115 mm thick in cement mortar 1:4. Fly ash bricks or cement 
concrete blocks (hollow/ solid) confirming to the BIS or stone masonry can be used  
as per local availability in lieu of clay bricks, but nothing shall be paid extra on this 
account. 
 

8 Volume II – Bill of Quantities


2.21. Plaster: 15‐19 mm thick in cement mortar 1:4 on all outer and inner walls except in 
ceiling. Inner walls shall be finally finished with POP. Underside of the slabs shall be 
rendered smooth wherever required and finished with POP. 
 
2.22. Painting – Two coats of  synthetic enamel paint  of 1st quality over a priming coat of  
Asian, Berger, Nerolac or equivalent brand and shade as approved by the Engineer, 
on all exposed steel and wooden surfaces. 
 

2.23. Sanitary fittings/sewerage system: 
 

2.23.1. Manholes and junction chambers to be constructed by Contractor as per the design 
by the Contractor & approved by the Engineer and to be connected with RCC pipes 
of  150/200  mm  dia.  with  each  other  and  to  septic  tank  or  to  existing  sewerage 
arrangement  (up  to  15m  from  extreme  outer  wall  of  building  in  the  direction  of 
source  to  be  connected,  including  obtaining  necessary  clearance  from  concerned 
authorities required for the same. In case sewerage system is not to be connected to 
trunk sewer as stipulated, contractor will furnish appropriate design of septic tank to 
be approved by Engineer and will construct the septic tank accordingly.  
 
2.23.2. Rain water pipes: Adequate number of rain water pipes of min 100 mm dia, PVC of 
approved quality and make as approved by the Engineer to be provided. Inlet of the 
rain water pipe to be provided with shoe and CI gratings and at the outlets necessary 
protection to be done to prevent erosion of soil.  
 
2.23.3. Soil and vent pipes: PVC pipes of min 100 mm dia to be provided for soil and vent 
pipes including all branches of required degree, access door and other accessories as 
necessary  for  laying  the  pipes  of  approved  quality  and  make  as  approved  by  the 
Engineer to be provided. Before embedding the pipes under the floor the same will 
have to be tested against any leakage. Necessary floor traps, gully traps as essential 
will be provided. Storm water drain of suitable size to be provided as approved by 
the Engineer. 
 
2.23.4. Wash Basins and Sink: Wash basins (Ceramic) of approved size, colour and make to 
be  provided  in  ladies  and  gents  toilet  with  shelf,  looking  glass  and  towel  rails  (CP 
Brass). Urinals/Squatting pans (ceramic) of approved size and make to be provided 
with  ceramic  flushing  systems  as  per  requirement.  Stainless  steel/Ceramic  sinks  of 
approved size and makes to be provided in battery rooms, Kitchen of Rest room. All 
water services and sinks will be connected through bottle traps to concealed outlet 
pipe. 
 
2.24. Water supply: Necessary layout for water supply distribution in the Kitchen, toilets & 
baths to be designed by the Contractor and submitted for approval of Engineer and 
to be connected with GI pipe of designed dia to the existing main water line (up to 
15m from extreme outer wall of building in the direction of source to be connected, 
including obtaining necessary clearance from concerned authorities required for the 
same.  All  internal  pipes  will  be  laid  concealed  in  walls  and  tested  for  leakages  for 

9 Volume II – Bill of Quantities


minimum 12m head of water. All necessary taps, stop valve etc. of approved size and 
make  to  be  provided  by  Contractor  to  make  the  toilets  and  kitchens  functional 
including  provision  of  water  tank  of  designed  capacity  Moulded  Polyethylene 
overhead tank Sintax make or equivalent in accordance with IS 127012 – 1996. This 
will  include  provision  of  float  valve,  copper/  brass  rod  and  plastic  ball  with  inlet, 
outlet,  overflow,  washout  connections  etc.  for  the  overhead  tank  complete  in  all 
respect. Taps in platform toilets will be self‐closing type.  
 
2.25. Water proofing and heat insulation of roofs: Roof shall be painted with two coats of 
bitumen as per para 2405 of RVNL Standard Specifications for materials and works 
followed  by  mud  phuska  terracing  with  tile  brick  paving  as  per  para  2406  of  RVNL 
standard specification for material and works.  
 
2.26. Drip  courses‐  Drip  course  of  approved  design  has  to  be  provided  all  around  the 
building, chajjas etc. 
 
3. Technical Specifications Specific to S&T/Electrical and office buildings: 
 
3.1. Interior finish – Two coats of 1st quality oil bound distemper of approved shade over 
POP  coating  to  make  the  surface  smooth.    3rd  coat  may  be  done  before  handing 
over of assets. 
3.2. Exterior finish – Two coats of 1st quality cement paint of approved shade over POP 
coating to make the surface smooth. 3rd coat shall be done before handing over of 
assets. 
 

3.3. Flooring: 
 

3.3.1. Cable entry and Exchange Room , Equipment Room and Electrical panel room, IPS, 
Data logger room, traffic store and other store rooms: 40 mm thick, cement concrete 
flooring  1:2:4    (1  cement,  2  coarse  sand  and  4  stone  aggregate  20  mm  and  down 
size)  laid  in  one  layer  finished  with  cement  slurry  to  a  true  smooth  surface  with 
proper  joints  duly  provided  with  glass  strips  of  4mm  thick  to  form  panels  not 
exceeding 1200x1200mm , laid over 100 mm thick CC 1:4:8 over 100 mm thick sand 
filling over well rammed and consolidated earth filling.  
 
3.3.2. Battery  Room:  Acid  proof  tiles  conforming  to  IS  4457‐1967  as  approved  by  the 
Engineer over 20m thick cement sand mortar 1:4, over 100 mm thick CC 1:4:8 over 
100  mm  thick  sand  filling  over  well  rammed  consolidated  earth  filling.  Acid  proof 
tiles also to be provided in dado as per requirement up to 1M height.  
 

3.3.3. Stair Case: Chequerred terrazzo tile 22 mm thick with graded marble chips size up to 
6 mm to be provided in risers, treads and landings of steps laid on with neat cement 
slurry  mixed  with  pigment  to  match  the  shade  of  tile  including  rubbing  polishing 
complete on 20mm thick cement and sand mortar 1:3. 
 

10 Volume II – Bill of Quantities


3.3.4. Verandah Flooring & Ground Floor Passage: 1st quality Vitrified tiles(600 x 600 mm) 
flooring over average 20 mm thick base of cement and sand mortar 1:4 and jointed 
with  grey  cement  slurry  mixed  with  pigment  to  match  the  shade  of  stone  slab, 
including rubbing and polishing complete over 100 mm thick CC 1:4:8 over 100 mm 
thick sand filling on well rammed and consolidated earth filling. 
 
3.3.5. Toilets ‐ Finished floor to be kept 25 mm below the normal floor of the building. 300 
x 300 mm ceramic antiskid floor tiles confirming to IS 13630‐1993 of Kajaria, Nitco or 
similar  make  and  shade  and  approved  by  Engineer  laid  over  20  mm  thick  bed  of 
cement and sand mortar 1:4 with neat cement slurry mixed with pigment to match 
the shade of tiles between joints and over the base in floors laid over 100 mm thick 
CC  1:4:8  over  100  mm  thick  sand  filling  on  well  rammed  and  consolidated  earth 
filling on ground floor. On subsequent floors the tiles will be laid directory on mortar 
bed. 5 mm thick of suitable size glazed tiles confirming to IS 13630‐1993 of Kajaria 
,Nitco or similar make, quality and shade as approved by the Engineer to be provided 
on  walls  for  full  height  up  to  ceilings  over  13  mm  thick  cement  mortar  1:2.  All  the 
tiles to be laid with zero gaps between them. 
 

3.3.6. Relay  Rooms,  Axle  counter  room  ,booking  ,  Panel  Room  and  other  S&T  structures 
etc.  1st  quality  600  x  600  mm  vitrified  floor  tiles  conforming  to  IS  13630‐1993  of 
Kajaria, Nitco or similar make and shade as approved by Engineer laid over 20 mm 
thick  bed  of  cement  and  sand  mortar  1:4  with  neat  cement  slurry  mixed  with 
pigment to match the shades of tiles between joints and over the base in floors over 
100  mm  thick  CC  1:4:8  over  100  mm  thick  sand  filling  on  well  rammed  and 
consolidated  earth  filling  for  ground  floor.  On  subsequent  floors    tiles  shall  be  laid 
directly  on  mortar  bed  .5  mm  thick  glazed  tiles  of  suitable  size    confirming  to  IS 
13630‐1993 of Kajaria, Nitco or similar make, quality and shade as approved by the 
Engineer to be provided on walls in dado up to 90 cm height from floor level or up to 
the window sill. All the tiles to be laid with zero gap between them. 
 

3.4. Door Frames: The door frame shall be of MS Tee 40mmx40mmx6mm.  
 

3.4.1. Door  Shutters:  35  mm  thick  flush  door  shutter,  commercial  type  thermosetting, 
synthetic  resin  bound  core  of  block  board  construction  with  lipping  of  1st  class 
commercial  quality  timber,  such  as  elm  or  its  equivalent,  battens  on  all  edges  and 
well  matched  commercial  ply  veneering  with  vertical  grains  on  both  faces  of 
shutters.  Veneer  and  board  shall  be  as  per  BIS  specifications  with  brass  fittings  of 
approved size and make as per requirement. 
 
3.4.2. Windows/Ventilators:  Steel  windows  of  standard  rolled  steel  sections  as  approved 
by  the  Engineer.  Glass  panes  4  mm  thick  with  glazing  clips  and  special  metal  sash 
putty,  of  approved  make  with  brass  fittings  of  approved  size  and  make  as  per 
requirement. 
 

11 Volume II – Bill of Quantities


3.4.3. Windows  in  Relay  Room  shall  be  mix  of  double  shutters/Fixed  Panes  to  provide 
insulation for effective air conditioning. 
 

3.4.4. MS grill of approved design shall be provided in the windows and ventilators. 
 
3.5. Necessary exhaust fan opening to be provided as required. 
 
3.6. Railings in balcony – RCC Design to be submitted for approval and to be constructed 
as per approved design. Railing in staircase – Suitable design to be prepared by the 
Contractor  and  submitted  for  the  approval  of  Engineer  and  railing  to  be  provided 
with PVC covering as per approved design. 
 

4. Technical specifications  specific to Station Buildings: 
 
4.1. Exterior Doors:  
 
4.1.1. Main  entrance  from  circulating  area  to  the  station  building  shall  be  provided  with 
fully glazed Aluminium Door.  Remaining portion of entrance shall be provided with 
fixed glazing with aluminium frames as per approved drawing.  The frames shall be 
manufactured from extruded aluminium alloy sections of standard sizes and designs 
as  per  IS  1948  and  IS  1949  or  as  manufactured  by  Indian  Aluminium  Co.  Ltd  or 
approved  equivalent.    The  alloy  used  shall  conform  to  IS  designation  HE9‐WP  of 
IS:733.  Para  2310  of  RVNL  Standard  Specification  for  material  and  works  shall  be 
followed for execution. 
 
4.1.2. Door  frames  of  office  of  Station  Master/SS/Dy.SS/Waiting  Rooms/Booking  Office 
shall be of well seasoned steam beech/ 2nd class of teak wood of minimum section of 
65mm x 100mm  
 

4.1.3. Door  Shutters:    The  door  shutters  shall  be  of  35mm  thick  flush  door  shutter, 
commercial  type  thermosetting,  synthetic  resin  bound  core  of  block  board 
construction  with  lipping  of  1st  class  commercial  quality  timber,  such  as  elm  or  its 
equivalent,  battens  on  all  edges  and  well  matched  commercial  ply  veneering  with 
vertical  grains  on  both  faces  of  shutters.    Veneer  and  board  shall  be  of  BIS 
specifications.    These  door  shutters  may  be  partially  glazed  as  per  requirement,  as 
per  drawing  approved  by  the  Engineer.    Glazing  shall  be  of  glass  pane  of  6mm 
thickness.   Doors shall be finished with duco painted of desired shade and colour or 
melamine polished complete with all fittings including door closures. 
 

4.1.4. Windows/Ventilators Shutters: The frames of windows and ventilators in the station 
building  shall  be  same  as  mentioned  in  item  4.1.2  above  with  fully  glazed  shutters 
made of teak 2nd class of 30mm thickness and 4mm thick glass panes.  The design of 
the ventilators may be top or central hung as decided by the Engineer and suitably 
designed. 

12 Volume II – Bill of Quantities


 

4.1.5. Door/Window fittings:  These shall be chromium plated brass, of size and make as 
approved by the Engineer. 
 

4.2. Interior finish: Two coats of 1st quality oil bound distemper of approved shade over 
POP  coating  to  make  the  surface  smooth.    3rd  coat  may  be  done  before  handing 
over of assets 
 

4.3. Exterior finish – Two coats of 1st quality cement paint of approved shade over POP 
coating to make the surface smooth. 3rd coat shall be done before handing over of 
assets. 
 

4.4. Flooring and Dado: 
 

4.4.1. 1st quality 600 x 600 mm vitrified floor tiles conforming to IS 13630‐1993 of Kajaria, 
Nitco or similar make and shade as approved by Engineer laid over 20 mm thick bed 
of  cement  and  sand  mortar  1:4  with  neat  cement  slurry  mixed  with  pigment  to 
match the shades of tiles between joints and  over the base in floors  over 100 mm 
thick CC 1:4:8 over 100 mm thick sand filling on well rammed and consolidated earth 
filling.  On  subsequent  floors    tiles  shall  be  laid  directly  on  mortar  bed  .5  mm  thick 
glazed tiles of suitable size  confirming to IS 13630‐1993 of Kajaria ,Nitco or similar 
make,  quality  and  shade  as  approved  by  the  Engineer  to  be  provided  on  walls  in 
dado up to 90 cm height from floor level or up to the window sill. All the tiles to be 
laid with zero gap between them. 
 
4.4.2. Chequered terrazzo tile 22 mm thick with graded marble chips size up to 6 mm to be 
provided in risers, treads and landings of steps laid on with neat cement slurry mixed 
with  pigment  to  match  the  shade  of  tile  including  rubbing  polishing  complete  on 
20mm thick cement and sand mortar 1:3. 
 

4.4.3. Toilets: Finished floor to be kept 25 mm below the normal floor of the building. 300 
x300 mm ceramic floor tiles conforming to IS 13630‐1993 of Kajaria or similar make 
and shade as approved by Engineer laid over 20 mm thick bed of cement and sand 
mortar 1:4 with neat cement slurry mixed with pigment to match the shade of tiles 
between joints and over the base in floors laid over 100 mm thick CC 1:4:8 over 100 
mm thick sand filling on well rammed and consolidated earth filling. 5 mm thick 200 
x 200 mm glazed tiles conforming to IS 13630‐1993 of Kajaria or similar make, quality 
and shade as approved by the Engineer to be provided on walls for full height up to 
ceilings  over  13  mm  thick  cement  mortar  1:2.  Tiles  shall  be  laid  with  zero  gaps 
between them. 
 
4.5. Booking Counter: 
 

13 Volume II – Bill of Quantities


4.5.1. Counters to be made with laminated block board in attractive form as per approved 
design. 
 
4.5.2. Booking  window  shall  be  of  toughened  sheet  glass  10  mm  thick  with  a  hole  for  4 
intercommunication  at  suitable  height  above  the  counter  top  and  a  suitable  gap 
between  the  partition  and  counter  for  collection  of  fare  and  issue  of  tickets,  the 
partition  being  protected  on  the  passenger  side  by  a  aluminium  grill  of  approved 
design. 
 
4.5.3. Facilities  for  physically  handicapped  Ramps  of  desired  width  with  a  slope  of  1:12 
shall  be  provided  as  per  the  provisions  of  “The  persons  with  disabilities  (Equal 
opportunities protection of rights and full participation): Act 1995. 
 
 
5. Technical specifications  specific to Residential  Buildings: 
 
5.1 The building will be constructed as per zonal Railways standard plans duly approved 
for adoption by RVNL for the specific project.  

5.2 Interior  finish  –  In  type‐I,  type‐II  and  type‐III  quarters,  two  coats  of  white  wash  of 
over priming coat. 3rd  coat may be done before handing over of assets. In type‐IV 
and type‐V quarters Two coats of 1st quality oil bound distemper of approved shade 
over POP coating to make the surface smooth. 

5.3 Exterior finish –In type I, Type II and type III quarters Two coats of colour wash over 
a priming coat and in type‐IV and type‐V, 1st quality cement paint of approved shade 
over POP coating to make the surface smooth. 3rd coat shall be done before handing 
over of assets. 

5.4 Flooring: 

5.4.1 40 mm thick, cement concrete flooring 1:2:4 (1 cement, 2 coarse sand and 4 stone 
aggregate 20 mm and down size) laid in one layer finished with cement slurry to a 
true smooth surface with proper joints duly provided with glass strips of 4mm thick 
to form panels not exceeding 1200x1200mm, laid over 100 mm thick CC 1:4:8 over 
100 mm thick sand filling over well rammed and consolidated earth filling, in Type‐I, 
II &  III. In Type IV & V  flooring to  be done with 1st quality Vitrified tiles (600 x 600 
mm) laid over average 20 mm thick base of cement and sand mortar 1:4 and jointed 
with  grey  cement  slurry  mixed  with  pigment  to  match  the  shade  of  stone  slab, 
including rubbing and polishing complete over 100 mm thick CC 1:4:8 over 100 mm 
thick  sand  filling  on  well  rammed  and  consolidated  earth  filling.  On  subsequent 
floors, flooring shall be done without under layer of CC 148. 
 
5.4.2 Toilets and Bathrooms ‐ Finished floor to be kept 25 mm below the normal floor of 
the building. 300 x 300 mm ceramic antiskid floor tiles confirming to IS 13630‐1993 
of Kajaria, Nitco or similar make and shade and approved by Engineer laid over 20 
mm  thick  bed  of  cement  and  sand  mortar  1:4  with  neat  cement  slurry  mixed  with 

14 Volume II – Bill of Quantities


pigment to match the shade of tiles between joints and over the base in floors laid 
over  100  mm  thick  CC  1:4:8  over  100  mm  thick  sand  filling  on  well  rammed  and 
consolidated earth filling on ground floor. On subsequent floors the tiles will be laid 
directory  on  mortar  bed.  5  mm  thick  of  suitable  size  glazed  tiles  confirming  to  IS 
13630‐1993 of Kajaria, Nitco or similar make, quality and shade as approved by the 
Engineer to be provided on walls in Dado up to lintel level in Bathroom/Toilet and up 
to 90 cms height in WC, over 13 mm thick cement mortar 1:2. All the tiles to be laid 
with zero gaps between them. 
 

5.4.3 Door and Window Frames: The door frame shall be of MS Tee 40mmx40mmx6mm in 
type  I,  II  &  III  quarters.    In  type  IV  &  V  frames  shall  be  of  well  seasoned  steam 
beech/2nd class teak of minimum section of 65mm x 100mm with single rebate and 
of section 65mmx125mm with double rebate (For fixing double shutters).  
 

5.4.4 Door Shutters: Flush Door 30mm thick, if the width of the shutter is less than 750mm 
and  of  35mm  thick,  if  the  width  of  the  shutter  is  equal  to  or  more  than  750  mm, 
commercial  type  thermosetting,  synthetic  resin  bound  core  of  block  board 
construction  with  tipping  of  1st  class  commercial  quality  timber,  such  as  elm  or  its 
equivalent,  battens  on  all  edges  and  well  matched  commercial  ply  veneering  with 
vertical grains on both faces of shutters.  Kitchen and main entrance door also to be 
provided with double shutters, one flush door and another with mosquito proof GI 
wire netting. 
 

5.4.5 Window/Ventilator  Shutters:  For  type  I,  II  &  III  shall  be  of  standard  rolled  steel 
sections (as approved by Engineer), window shutters shall be glazed with glass panes 
4 mm thick.  These glazed shutters shall be fixed with projected hinges suitable for 
180 degree rotation.  These shutters have to open towards inside.  Mosquito proof 
GI wire netting to be provided on the outer side of window openings which is to be 
fixed with suitable MS flat and screws.   
 

For type IV & V shutters shall be of 30mm thick of 2nd class teak wood/steam beech.  
Double shutters to be provided in the windows.  Inside shutters shall be fixed with GI 
wire netting and outside shutters to be fully glazed with glazing of 4mm thick glass.   
 

5.4.6 Windows and ventilators to be provided with MS Grill of approved design.  
 
5.4.7 Doors, Windows/Ventilator fittings:  Oxidized MS fittings of approved size and make 
as per requirement in type I, II & III.  In type IV & V chromium plated brass fittings of 
approved size and make shall be provided. 
 

5.5 Railings  in  balcony:  Design  of  suitable  M.S.  railing  to  be  got  approved  from  the 
Engineer and work to be done accordingly 

15 Volume II – Bill of Quantities


6 Water Supply and Sewerage System:   
 
6.1  Zonal Railway plan duly approved by RVNL shall be followed for all water supply and 
sewerage  system.    However  contractor  will  submit  layout  plan  of  sewerage  and 
water supply system using medium quality of GI pipes, making provision for scale of 
amenities  as  indicated  in  annexure  and  the  work  to  be  executed  after  approval  of 
the  engineer.    Where  pipe  water  supply  is  not  available  one  hand  pump  at 
nominated  place  shall  be  provided  common  for  two  units.    Water  supply  and 
sewerage  system  shall  be  connected  to  the  external  system/source  up  to  15m 
beyond  the  outermost  wall  in  the  direction  of  the  source.    Necessary  manholes, 
traps within 15m of the outer wall of the building and septic tank will be constructed 
by  the  contractor.    The  discharge  from  kitchen  and  bath  room  shall  be  separately 
taken  to  outer  drains.    Storm  water  drains  within  15m  of  the  outer  wall  of  the 
building and will be suitably designed and approved by the engineer and constructed 
accordingly. 
 
7 Payment  Conditions  common  to  all  buildings:    Payment  shall  be  made  on  plinth 
area  basis  as  per  actual  measurements.  The  plinth  area  rates  include  all  works 
specified  in  the  foregoing  paras  but  not  limited  to  the  same  required  to  make  the 
building functional.  External water supply, sanitary (excluding septic tank), drainage 
works required beyond 15m of the outer wall of the building are not included in the 
rates and shall be paid separately under bill No.7.  Payment shall be made in stages 
depending upon the progress as below:‐  
 
 
7.1 Ground Floor: 
 
7.1.1 Completion of ground floor up to plinth        : 10% 
7.1.2 After casting of ground floor roof slab and provision of walls  : 30% 
7.1.3 After completion in all respects          : 50% 
7.1.4 After commissioning              : 10% 
 
7.2 First and Subsequent Floor: 
 
7.2.1 After casting of roof slab and construction of the masonry walls  : 30% 
7.2.2 After completion in all respects          : 60% 
7.2.3 After commissioning              : 10% 
 
Note:        a)              For  the  purpose  of  measurement  shall  be  calculated  on  the  following 
principles:  
i) The  plinth  area  shall  be  measured  separately  for  every  floor  and  the 
basement if, any.   
ii) Internal sanitary shafts shall not be included in the plinth area. 
iii) The  area  of  the  stair  case  and  lift  shall  be  included  but  area  of  the 
mumty at the terrace level shall not be included in the plinth area.  If a 

16 Volume II – Bill of Quantities


barsati is provided jointly with mumty then area of the barsati excluding 
mumti at the terrace level shall be included in the plinth area. 
b) Plinth  area  of  ground  floor:  The  plinth  area  of  the  ground  floor  shall  be 
calculated  at  the  plinth  level  excluding  the  plinth  off‐sets.    In  case  where  the 
building  consists  of  columns  projecting  beyond  cladding,  the  plinth  area  shall 
be taken to the external face of the cladding and the projection of the columns 
shall not be included.  In case of  open verandah with parapets are protected at 
the ground floor projecting out of the building, the full area shall be taken up to 
the  outer  line  of  the  external  verandah  lintel  and  in  case  of  un  protected 
verandah and porches , only 50% of the area shall be taken into consideration.  
Open  platform  without  parapets  and  terraces  at  ground  floor,  shall  not  be 
included in the plinth area. 
c) Plinth area at first and subsequent floor: The plinth area shall be calculated at 
the relevant floor level.  Architectural bonds, cornice etc shall not be included 
in  the  plinth  area  even  though  they  may  occur  at  the  floor  level,  vertical  sun 
breakers or box louvers projecting out also shall not be included in the plinth 
area 
In  case  of  projecting  balconies  protected  to  their  full  width  and  length  by 
sunshade or upper balcony roof full area shall be taken into consideration.  In 
case of unprotected balconies equivalent area to the extent of 50% of the area 
of the balcony shall be considered in the plinth area. 

17 Volume II – Bill of Quantities


SCALE OF AMENITIES FOR RESIDENTIAL BUILDING 
 
Item  Item  Type I  Type II Type III Type IV Type V
No. 
1  Kitchen     Covered   
(i)  Shelves  in  tiers  Yes  Yes  Yes  cupboards  Same as Type IV 
  not  more  than        above 
  400  mm  wide        lintel  level 
  along  one  wall     over 
  1” thick    cooking 
      platform, 
  with  pre‐
laminated 
decorative 
board.  

(ii)  Kitchen sink  Stainless  Same  as  Same  as  Stainless  Stainless  steel  sink  of 
    steel  sink  Type‐I  Type‐I  steel  sink  size  510x1040  mm  with 
without      with  drain  bowl  depth  of  250  mm 
drain  board  board  size  with  draining  board/ 
size  510x1040  vitreous  china  sink  with 
610x510  mm  with  draining  board  of  size 
mm  with  bowl depth  600x450x250 mm 
bowl  depth  200 mm   
200 mm   
 
(iii)  Dado  Yes  Yes Yes Yes Ceramic  glazed  tiles  up 
  Ceramic  glazed          to  60  cm  above  cooking 
tiles  for  60  cm  platform all around 
above  work  top   
and  around 
sunken floor 
 
(iv)  Built in cupboard  Yes  Yes Yes Built  in  Built  in  cupboard  below 
  with  open        cupboard  cooking  platform  with 
shelves  below  below  shutters  of  pre‐
cooking platform  cooking  laminated particle board 
  platform  18 mm thick with fittings 
with   
shutters  of 
pre‐
laminated 
particle 
board  18 
mm  thick 
with 
fittings 
 
(v)  Cooking Platform  Yes  Yes Yes Yes Yes 
Standing  with 
granite top 
2   Wardrobes  Built  in  Built  in  Built  in  Built  in  Built  in  cupboard  with 
(i)    cupboard  cupboard  cupboard  cupboard  pre‐laminated  particle 
with  with  with  particle  with  pre‐ board/shelves  and 
particle  particle  board/shelv laminated  shutters  up  to  ceiling 

18 Volume II – Bill of Quantities


Item  Item  Type I  Type II Type III Type IV Type V
No. 
board/shelv board/shelv es  and  particle  height 
es  and  es  and  shutters.  board/shel (One in each Bedroom)  
shutters.  shutters.  (One in each  ves  and 
(One  in  (One  in  Bedroom)   shutters up 
each  each  7’‐00”  to  ceiling 
Bedroom)   Bedroom)   height  height 
7’‐00”  7’‐00”  (One  in 
height  height  each 
Bedroom)  
 
(ii)  Magic  eye  in  One  One One  One One 
front door   
(iii)  Curtain rods with  All rooms  All rooms All rooms Drapery  Drapery rods 
brackets  rods 
(iv)  Set of Pegs  In  bath  and  In  bath and  In  bath,  bed  In  bath,  In  bath,  bed  and 
bed rooms  bed rooms  and  bed  and  wardrobes 
wardrobes   wardrobes 
 
SCALE OF  SANITARY FITTINGS FOR RESIDENTIAL BUILDING 
 
Item  Item  Type I  Type II Type III Type IV  Type V
No. 
1.   Indian  W.C.  Pan  One  W.C.  Pan  One  Same  One  Same  as  One W.C. Pan  One W.C. Pan 
  with  flushing  Orissa  pattern  as Type‐I  Type‐I  Orissa pattern  Orissa pattern 
cistern  with  low  level      with low level  with low level 
PVC  Flushing      PVC Flushing  PVC Flushing 
Cistern        Cistern  Cistern 
   
 
2.   European  type  ‐  ‐ ‐ One  with  low  Two  (symphonic 
W.C.  with  high  level PVC flushing  type)  with 
level flushing  cistern  matching  low 
level cistern  
2(a)  Water  Jet  with  ‐  ‐ ‐ One One 
low  level 
European 
W.C/Hand 
shower. 
3.   Wash  basin  with  One  One One Two  mixer  type  Three mixer type 
one tap each  for  hot  &  cold  for  hot  &  cold 
water  water 
4.   Tap  (Kitchen,  Brass  Brass   Brass Chromium Plated  Chromium 
bath  &  W.C.)  C.P.  Brass  Plated Brass 
Brass/PTMT  bib 
cock 
5.   Shower  C.P.  One PTMT  One PTMT One PTMT Two C.P. Brass  Three C.P. Brass
Brass/PTMT   
6.   Towel  rail  C.P.  One PTMT  One PTMT One PTMT Two C.P. Brass  Three C.P. Brass
Brass/ PTMT   
7.   Mirror/Beveled  One  One One Two Three
edge/  PVC  frame 
with  PTMT  glass 
shelf  

19 Volume II – Bill of Quantities


Item  Item  Type I  Type II Type III Type IV  Type V
No. 
8.   Soap  rack  (Nitch  One  One One Two Three
in W.C./Bath) 
9.   Liquid  soap  ‐  ‐ ‐ Two Three
container   
10.   Storage tank  500 ltr.  500 ltr. 500 ltr. 1000 ltr.  1000  ltr.  +  500 
ltr.  
 
Note:  Waste  coupling  in  wash  basins  and  grating  over  the  floor  trap  shall  be  only  of 
PTMT. 
 
   

20 Volume II – Bill of Quantities


OBULAVARIPALLI‐NETHVARIPALLI IN OBVP & VKT SECTION  
 
Explanatory Notes to RVNL STANDARD BOQ NO. 22 – General Services Electrical Works  
 
These  Explanatory  Notes  are  for  guidance  only.  Each  work  has  its  own 
particular  requirements  and  must  be  carried  out  in  accordance  with  the  best 
code of practices. 
1. GENERAL 
     
i  (a)  The Contractor shall have a valid Electrical Contractor’s License, issued by any 
State Government, for carrying out electrical installation works. All works shall 
be  executed  by  the  Contractor  under  the  direct  supervision  of  his  Engineer 
holding valid certificate of competency issued by any State Government 
 
  (b)  The  Contractor  shall  furnish  the  names  and  particulars  of  the  certificate  of 
competency  of  Supervisors  and  workmen  to  be  engaged  for  carrying  out  this 
work. 
 
  (c)  All  electrical  works  should  comply  with  Indian  Electricity  Act  2003  and  Rules 
framed there under. 
 
ii    All electrical installations shall conform to the relevant Indian Standard and shall 
be  carried  out  as  per  the  relevant  safety  Code  of  Practices.  Guide  for  Safety 
Procedures in Electrical Works as per I.S:5216/Pt I & II/1982 shall be observed. 
 
iii    Notwithstanding  the  ratings  specified  in  the  BOQ,  all components  proposed  to 
be used in the installations, shall be of appropriate rating of voltage, current and 
frequency. Discrepancies, if any, in this regard, shall be brought to the notice of 
the Engineer by the Contractor. 
 
iv    All  minor  items  viz.  hardware  items,  foundation  bolts,  termination  lugs  for 
electrical connections etc. as required and necessary for proper working of the 
equipment  shall  be  deemed  to  have  been  included  in  the  Bill  of  Quantities, 
whether such items are specifically mentioned or not. 
 
v  (a)  The basic quantities of  components & materials required to make up  a unit of 
work  for  selected  items  are  approximate.  The  Contractor  shall  plan  the  work, 
estimate  the  actual  quantities  required  and  get  the  same  approved  by  the 
Engineer before placing orders.  
 
  (b)  In estimating the prices for various items of work, provision for loss or wastage 
in transit and erection including freight, handling, taxes and duties, insurance if 
any etc. should be taken into account and firm unit price offered for a complete 
unit of work to be done by the contractor. 
 
vi    The various items to be supplied/provided/erected should be as per the list of 
approved suppliers included in RVNL’s Technical Specifications. 

21 Volume II – Bill of Quantities


 
Items  not  appearing  in  the  approved  list  shall  be  procured  from  good  quality 
sources  in  line  with  best  industries  practices  and  shall  be  either  ISI  marked  or 
conforming  to  latest  IS  (if  any).  Before  procurement,  vendor  approval  shall  be 
obtained from the Employer. 
 
vii    Good workmanship and total compliance with safety and other statutory rules 
and regulations, shall invariably be observed by the Contractor.  
 
viii    All  approvals  from  the  relevant  and  appropriate  government  &  statutory 
authorities  shall  be  the  total  responsibility  of  the  Contractor  unless  specified 
otherwise. 
 
ix    All  quoted  rates  shall  cover  supply  of  materials,  handling  of  materials,  labour 
    required,  civil  works,  taxes  and  duties,  fabrication,  installation,  testing  and 
    commissioning,  training  and  free  maintenance  till  handling  over  to  the 
    Employer’s representative. 
x    If any activity of work is essential for the satisfactory completion of the work but 
is not mentioned specifically in the Bill of Quantities or elsewhere in the bidding 
documents, the same shall be deemed to be included In the scope of work and 
shall be executed by the contractor within the accepted cost. The work shall be 
handed over in a functional manner complete in all respects. The inspection will 
be  done  at  the  manufacture’s  work  and  the  inspection  fees  chargeable  by 
RITES/INSPECTING AGENCY will be borne by the contractor. 
 
2.    DRAWINGS:   
 
1  The  contractor  shall  prepare  drawings  in  Auto  Cad  for  all  LT/HT  installations, 
indicating proposed works and prior to taking up the work and obtain approval of 
Engineer. Such drawings shall be prepared in coordination with all other agencies 
executing works at the same site.  
 
2.2  After  commissioning,  these  drawings  shall  be  duly  updated  and  submitted  in 
quadruplicate, as Completion Drawings, along with a soft copy 
 
2.3  Where  the  contractor  proposes  to  use  an  item  of  equipment,  other  than  that 
specified  or  detailed  on  the  drawings,  which  requires  any  re‐design  of  the 
structure,  partitions,  foundation,  piping,  wiring  or  any  other  part  of  the 
mechanical, electrical or architectural layouts, he shall inform the Engineer well in 
advance and obtain his approval. Delays resulting from such re‐design shall be ON 
Contractor’s  account.  He  shall  also  submit  all  related  information  as  may  be 
required for approval such redesign, to the Engineer. 
 
2.4  Where the work of the Contractor has to be executed in close proximity to or will 
  interfere  with  work  of  other  agencies,  the  Contractor  shall  work  out  space 
  adjustments  in  coordination  with  other  agencies.  If  the  contractor  installs  his 
  work  before  coordinating  with  other  agencies,  so  as  to  cause  any  interference 

22 Volume II – Bill of Quantities


with  their  work,  he  shall  make  the  necessary  changes  without  extra  cost  to  the 
owners of the installation. 
 

3.0  Scope of Work : 
 
  1. Supply  and  erection  of  D.P.  structure  with  M.S.  Channel  Cross  arms 
complete. 
2. Supply, laying, testing and commissioning of HTUG/ LTUG cables including 
termination. 
3. Cutting and removal of existing OH spans with terminal structures. 
4. Supply and fixing of PVC / GI /CI/ RCC pipes 
5. Supply and fixing of LA/Insulator/Danger Board/Anti‐climbing device 
6. Supply and provision of LT/ HT earthing arrangements. 
7. Provision of Mass concrete. 
8. Supply and fixing Cable route indicator 
9. Supply and provision of electrical installation including wiring 
10. Supply  and  provision  of  light  fittings  of  sorts  &  fans/switches  /Danger 
boards. 
11. Supply and fixing of MCB/MCCB/RCCB /FSU/COS / Contactors/Timers. 
12. Supply and fixing of M.T. Panel, MCB type TPN/SPN DB complete with all 
accessories. 
13. Testing  and  commissioning  of  the  entire  electrical  installations,  duly 
keeping  close  liaison  with  State  Electricity  Board  &  concerned    Railway 
authorities. 
 
 
4.0  TECHNICAL AND PARTICULAR SPECIFICATIONS FOR VARIOUS WORKS IN TENDER 
SCHEDULE:  POWER LINE CROSSING 
 
NOTE:          The  particulars  and  specifications  are  in  respect  of  different  items 
indicated in the various items of works as applicable, with reference to context 
of the work.  
 
4.1  ERECTION OF DP STRUCTURE: Erection of MS Beam pole shall be as per IS:5613 
Pt.1/sec. 1&2 (Latest       Version). The portion of pole to be planted in ground, 
shall be as per IS  2713/part 1 to 3/1980 (Latest    Version). Size of base plate shall 
not be less than 300x300x10 mm A suitable pad of cement, stone or steel shall be 
provided at the bottom of the pit before pole is erected. After erection, pole shall 
be treated with two coats of anti‐corrosion red oxide primer and thereafter final 
two coats of superior quality Aluminium  Paint (ISI marked). Black paint shall be 
applied  up  to  1.5  m.  above  muffing  and  remaining  portion  shall  be  made  with 
mixture of cement, sand & concrete ballast in ratio 1:3:6 and shall not less than 
200 mm from edge of pole. Muffing shall be plastered  and finished. 
 
4.2  ERECTION OF STRUT:   The strut post which is made of MS Beam shall be erected 
in  a  pit  of      1.2  M  long  X  0.6  M  with  and  1.5  M  depth  with  base  plate  of 

23 Volume II – Bill of Quantities


320x320x10mm size in a mass concrete of 1:3:6 mix with coping of 0.3 x 0.3 x 0.3 
M smoothly finished.  The strut clamp shall be made out of MS flats of not less 
than  50x10  mm  size.    The  strut  pole  and  clamps  should  be  painted  with  a  base 
coat of Red oxide and finished with two coats of aluminium paints.  One coat of 
enamelled Black paint shall be applied up to 0.6 M height from the ground level 
on the strut post including coping as per the Drg. No. CEE/CN/MS/23‐2004. 
 
4.3  ERECTION OF STAY SET: The stay shall be erected in a pit of 1.2 M long x 0.6 M 
width and 1.5 M depth with a MS beam type with a base plate of 320 x 320 x 10 
mm thick.  The pit shall be filled with concrete of 1:3:6 mix and coping of 0.3 x 0.3 
x0.3 M Smoothly finished. The stay set shall comprise of stay wire, stay insulator 
and stay clamp with adjuster tightener of 50 x 10 mm size.  One no ‘B’ Class G.I 
pipe of 40 mm dia. 2M long shall be used to cover the bottom of stay wire.  The 
stay wire shall be of 45 T quality 7/11 SWG size steel galvanized, sty tightener as 
per the Drg. No. CEE/CN/MS/24‐2004. 
 
4.4  FOUNDATION:  Cement  to  be  used  for  all  works  shall  be  of  OPC  43  grade  and 
conforming to IS:8112, unless stated   otherwise in the specification and supplied 
in the HDPE bag conforming to IS No.11652 and concrete should  be with 20 mm 
size metal specified mix given in the schedule.  All metal part should be applied 
with two coats of primer zinc chromate paint and finished with aluminium paints 
unless otherwise specified 
 
 
4.5  CROSS ARMS: Galvanized mild steel angle (cross arm) and holding GI clamp shall 
conform  to  IS  808/1989  (Latest  Version).    GI  washers  shall  conform  to  IS 
2016/1967 (Latest Version). GI Nut & Bolt shall conform to IS 6639/1972 (Latest 
Version)  with  mechanical  properties  conforming  to  IS  1367/Pt.  3/1991  (Latest 
Version). Hot dipped galvanizing of bolts, nuts and washers etc. shall conform to 
IS 1367/Pt. XIII/1983 (Latest Version). 
 
4.6  ERECTION  OF  STAY  SETS:  Galvanized  stay  set  shall  conform  to  IS;10019/1981 
(Latest  Version).  Porcelain  guy  strain  insulator  shall  conform  to  IS  5360/1969 
(Latest Version) and installation shall be in conformity with IS 5613/Pt. 1 Sec 1 & 
2/1985  (Latest  Version).    Foundation  around  the  stay  rod  shall  be  made  with 
mixture of cement, sand & concrete ballast in ratio 1:2:3 & shall not be less than 
200  mm  from  edge  of  stay.  Stay  wire  shall  conform  to  IS  214/2000(Latest 
Version). 
 
4.7  LT  INSULATOR:  Supply  and  erection  of  LT  porcelain  Pin/shackle  insulator  1100V 
grade  shall  be  in  conformity  to  IS  5613/Pt.  I  sec.  1  &  2/1985  (Latest  Version) 
Porcelain  insulator  shall  conform  to  IS  1445/1977  (Latest  Version),  Hexagonal 
bolts shall conform to IS 66389/1972 (Latest Version), Hot dip galvanized coating 
on fastener shall conform to IS 1367 (Part XIII)/1983. Insulator fitting for overhead 
power lines shall conform to IS 7935/1975 (Latest Version). 
 
4.8  HT  INSULATORS:  Supply  and  erection  of  HT  33kV/11kV(120  KN)  porcelain  Pin/ 

24 Volume II – Bill of Quantities


Disc Type insulators complete with galvanized iron hardware etc shall confirming 
to relevant IS Specification. 
 
4.9  SPECIFICATION FOR HTUG CABLES 11/ 33kV RATINGS:  11/33 kV HTUG (E) cable 
of  size  indicated  in  the  schedule,  stranded  compact  aluminium  conductor  with 
extruded  semi  conducting  XLPE  compound  screening,  XLPE  insulated  screened 
with semi conducting XLPE compound and copper tape laid – up with PVC fillers, 
wrapped inner sheath of PVC tape, Galvanized steel strips armoured and overall 
PVC  sheathed  cable  conforming  to  IS:  7098  (pt.  II)/785  or  latest,  with  latest 
amendments. 
 
4.10  SPECIFICATION FOR  EXCAVATION OF CABLE TRENCH AND METHOD OF LAYING 
OF UG CABLES: The  earth for cable trench shall be excavated in all kinds of soil 
and obstructions in the way of cable trench shall also be removed.  The cable shall 
be  laid  at  site  generally  following  the  cable  lay  out  plans.    The  route  will  be 
marked by the Railway representative.  The cable trench should of 1.0  M depth 
and  0.40  m  width  or  as  required  at  site.    A  bed  of  sand  cushion  for  height  of 
150mm shall be provided below and above the cable wherever necessary. (Where 
the RCC/CI pipes not used for protection)  work shall be done as per the Drawing 
CEE/CN/MS/10‐2004  and  cable  laying  shall  be  done  as  per  the  directions  of  the 
Engineer at site. 
 
4.11  HT/LT UG CABLE TERMINATION: Supply, termination, testing and commissioning 
of  33kV/11kV  outdoor  type  heat  shrinkable  end  termination  kit,  making 
termination and connecting to the overhead lines work of installation shall be in 
conformity with IS 5613/1985.  
 
4.12  LIGHTENING  ARRESTOR:  Single  pole  Station  class  Non‐linear  resistance  type 
lightning  arrestor,  suitable  for  out  –  door  vertical  pole  mounting  provided  with 
effectively earthed neutral terminal. This shall be supplied complete with all the 
standard  accessories  and  conforming  to  relevant  IS  Specification  and  rating  of  9 
KV  –  10  KA  for  11  KV  grounded  neutral  system.  The  earthing  conductor  of 
Lightning Arrestor shall be grounded directly by using the porcelain insulators on 
the structure. 
 
4.13  EARTHING: HT /LT Earthing with CI 100mm dia. LA Class / 50 mm ‘ B’ Class  pipe 3 
meter  long  shall  be  in  conformity  to  IS  3043/1987  (Latest  Version).  Excavation 
shall be done complying with Code of Safety as per IS 3764/1992(Latest Version). 
 
5.0  LAYOUT OF WIRING: 
 
5.1  Power  circuits  if  any  shall  be  kept  separate  and  distinct  from  the  light  and  fan 
circuits.  The wiring shall be done in such a way to facilitate easy inspection.  The 
wiring  shall  be  carried  out  in  an  approved  manner  satisfying  the  relevant  IS  
Specification, code of practice available and additional specifications applicable if 
any for concealed conduit wiring system. 
 

25 Volume II – Bill of Quantities


5.2  No joints shall be permitted in the wiring. If any jointing of cables is found to have 
been carried out in the PVC pipe wiring, subsequently a penalty of Rs. 500/‐ per 
joint will be levied and deducted.  In addition to, the contractor has to redo the 
portion of the wiring found to have been carried out with jointing at his own cost 
to an acceptable standard. 
 
5.3  Necessary  earth  continuity  connection  shall  be  provided  keeping  in  mind  the 
maintenance requirements, safety etc., in addition to the above earth connection 
the  contractor  is  required  to  make  separate  earth  pit  and  earth  connections  as 
detailed in the schedule of work. 
 
5.4  The  route  of  the  wiring  is  to  be  decided  in  consultation  with  the  authorized 
representative  of  Engineer‐in‐charge.    The  wiring  work  shall  be  supervised  by 
contractors  representative  who  possess  a  competency  certificate  by  Electricity 
Board/Electrical Inspector. 
 
5.5  Before commissioning the installations the following tests shall be conducted and 
the results shall conform the values specified and shall be certified by the person 
whose competency certificate has been attached. 
(i) Insulation resistance test.       
(ii) Testing of polarity of non‐linked SP switches. 
(iii) Earth continuity path (Bell Tester) 
(iv) Earth resistance Value. 
(v) Any other test as desired by Engineer‐in‐charge on safety point of view. 
 
5.6  The  wiring  point  shall  be  catered  2  Nos.  PVC  Multi  Strand  flexible  copper  cable 
including supply fixing of flush type switch, ceiling rose, pendent cord from ceiling 
to light/fan including earth continuity as specified in BOQ. 
 
5.7  The work shall be executed strictly as per approved samples. 
 
5.8  Separate neutral for each wiring is to be run and neutral should be looped only in 
the control box and not in the ceiling rose or elsewhere. 
 
5.9  As long as possible, conduits are to be laid only in the ceiling and not along the 
wall in the rooms.  The contractor has to furnish a conduit layout drawing in the 
ceiling in advance and get it approved before casting of roof slab. 
 
  NOTE: 
(i)              The  leads  of  phases,  neutral  and  earth  of  different  circuits  should  be  
collectively  taken,  bunched  and  routed  as  below  inside  the  control 
boards. All phase leads to be taken on the left hand side of the board. All 
neutral leads to be taken in the centre of the board and all earth leads to 
be taken on the right hand side of the control board.  
(ii)       All looping of phase and neutral leads inside control board should be done 
only using Bakelite strip connections of sufficient rating. 
(iii)     Earth lead shall be terminated on a bolt/stud/connector fixed on the board 

26 Volume II – Bill of Quantities


and all earth tapping should be done only from this earth bolt/stud. 
(iv)        Separate colour code scheme has to be adopted for live, return and earth 
leads. 
 
5.10  WIRING SPECIFICATION: 
 
  MS/PVC  conduit  shall  be  in  conformity  with  IS  732/1989  (Latest      Version),  IS  4648/1968 
(Latest Version).  
 
Fittings for rigid conduit for electrical wiring shall conform to IS 2667/1988 (Latest Version) 
and accessories shall conform to IS:383/1976 (Latest Version.  
 
Fittings  for  rigid  non‐metallic  conduit  shall  conform  to  IS  :  3419/1989  (Latest  Version  and 
accessories  shall  conform  to  relevant  IS.PVC  insulated  multi‐stranded  copper  conductors  to 
various sizes shall be conforming to IS 694. Accessories shall be provided in conformity with 
IS 732/1989 (Latest Version). 
 
Wiring of installation shall be in conformity with IS 732/1989 (Latest Version), IS 4648/1968) 
(Latest Version). Provision of switch boxes in conformity with IS 732/1989 (Latest Version). IS 
4648/1968 (Latest Version). Phenolic laminated sheet cover shall conform to relevant IS. 
 
Lamp Holder shall conform to IS 1258/1987 (Latest Version) & ceiling rose shall conform to IS 
371/1979 (Latest Version). Lamp Holder and ceiling rose shall be provided in conformity with 
IS 732/1989 (Latest Version). IS 4648/1968 (Latest Version).  
 
Drawing  of  GI  wire  in  laid  pipe  shall  be  in  conformity  with  IS  732/1989  (Latest  Version).  IS 
4648/1968 (Latest Version).  
 
5.10  LAMP STANDARD POSTS: Erection of Tubular pole shall be as per IS : 5613 Pt.1/ 
Sec. 1&2 (Latest Version).  The portion of pole to be planted in ground, shall be as 
per IS 2713/part 1 to 3/1980 (Latest Version). Size of base plate shall not be less 
than  300x300x10  mm.  After  erection,  pole  shall  be  treated  with  two  coats  of 
anticorrosion red oxide primer and thereafter final two coats of superior quality 
green/black paint (ISI marked) shall be applied  up to 1.5 M. above muffing and 
remaining portion shall be painted with aluminium paint (ISI marked). Foundation 
around the pole shall be made with mixture of cement, sand & concrete ballast in 
ration 1:3:6 and shall not be less than 200 mm from edge of pole. Muffing shall be 
plastered and finished. Bracket diameter shall be matching with inlet hole of the 
Street light luminaries. 
 
5.11  LUMINARIES:  Street  Light  Luminaries  HPSV/Metal  Hallade  fillings  shall  be  Single 
piece  die  cast  aluminium  (LM6)  housing.  Control  gear  compartment  shall  be 
complete  with  energy  efficient  copper  ballast,  electronic  ignitor,  Power  Factor 
improvement  capacitor  etc.,  and  shall  be  pre‐wired  up  to  terminal  block. 
Reflector  shall  be  of  high  purity  aluminium,  electrochemically  brightened  and 
anodized.  Luminaries  shall  have  high  transparency  clear  acrylic  cover  with 
Stainless Steel toggles for fixing acrylic cove. Luminaries shall conform to IS 10322 
(Pt.  1&2)  /  1982  and  Pt.5  Sec.  1/1985  &  Pt.5  Sec.31987  (Latest  Versions)  with 
Degree of protection not be less than IP 54. 
 

27 Volume II – Bill of Quantities


NOTE:        Southern  Railway  Drawings,  CEE/CN/MS  (Series)  for  various  General 
services, electrical works mentioned in the schedules are available in the office of 
RVNL/Chennai for reference for the bidders.  
 
   
 
   

28 Volume II – Bill of Quantities


Price Proposal Submission sheet 
 
  Date:  .......................................................  
  Invitation for Bid No.:  ................................................  
 
 
To: ......................................................................................................................................................................  
 
We, the undersigned, declare that:  
 
(a) We have examined and have no reservations to the Bidding Documents, including Addenda issued in 
accordance with Instructions to Bidders (ITB) 8; 
 
(b) We offer to execute the Work in conformity with the Bidding Documents;    
 
(c) The  total  price  of  our  Bid,  excluding  any  discounts  offered  in  item  (d)  below  is…………… 
…………………………………………………………………………………………………………… 
 
(d) The  discounts  offered  and  the  methodology  for  their  application  are  ………………………... 
……………………………………………………………………………………………….………….. 
 
(e) We  understand  that  this  bid,  together  with  your  written  acceptance  thereof  included  in  your 
notification  of  award,  shall  constitute  a  binding  contract  between  us,  until  a  formal  contract  is 
prepared and executed; and 
 
(f) We  have  not  made  any  tampering    or  changes  in  the    bidding  documents  on  which  the  bid  is 
being  submitted  and if any tampering or  changes are detected at any stage, we understand the 
bid will invite summery rejection and forfeiture of bid security/the contract  will  be liable  to be 
terminated along with forfeiture  of performance security, even if LOA  has been issued. 
 
(g) We understand that you are not bound to accept the lowest evaluated bid or any other bid that you 
may receive. 
 
Name  ................................................................................................................................................................  
In the capacity of  ..............................................................................................................................................  
Signed  ............................................................................................................................................................... 
 ...........................................................................................................................................................................  
Duly authorized to sign the Bid for and on behalf of  .......................................................................................  
Date  ..................................................................................................................................................................    
 
   

29 Volume II – Bill of Quantities


Summary Sheet of  Bill  of  quantities  

RVNL  Contractors % above/at par/below to 
Description of  Estimated cost  Total cost in Rs. 
Bill  be quoted in figures and words. 
Schedule  in Rs. 
No.  In Figures   In Words  In Figures  In Words 
1  2  3  4  5  6  7 
____________  ____________      
%age  %age 
Earthwork in      
1  Above/Below/at  Above/Below/at 
Formation  266,771,800.00  
par over  par over estimated 
estimated Rates  Rates 
  ____________  ____________       
2A  Bridge work  %age  %age 
    
(Other than  Above/Below/at  Above/Below/at 
209,041,163.00  
Steel works)  par over  par over estimated 
estimated Rates  Rates 
2B  Bridge work  ____________  ____________       
(Steel items  %age  %age 
      
Involving  Above/Below/at  Above/Below/at 
12,835,000.00  
Fabrication and  par over  par over estimated 
Erection)  estimated Rates  Rates 
____________  ____________       
Bridge work  %age  %age 
    
2C  (Supply of Steel  Above/Below/at  Above/Below/at 
156,775,800.00  
items )  par over  par over estimated 
estimated Rates  Rates 
____________  ____________       
%age  %age 
        
6  Buildings  Above/Below/at  Above/Below/at 
9,468,613.47  
par over  par over estimated 
estimated Rates  Rates 
  Platform,       
7A  Passenger  ____________  ____________ 
Amenities and  %age  %age 
      
Miscellaneous  Above/Below/at  Above/Below/at 
10,340,200.00  
Works : Other  par over  par over estimated 
than Steel  estimated Rates  Rates 
items 
____________  ____________       
%age  %age 
Supply of        
8  Above/Below/at  Above/Below/at 
Cement  85,250,000.00  
par over  par over estimated 
estimated Rates  Rates 

30 Volume II – Bill of Quantities


____________  ____________       
%age  %age 
        
9  Site Facility  Above/Below/at  Above/Below/at 
7,087,200.00  
par over  par over estimated 
estimated Rates  Rates 
Electrical     
General Service 
works 
____________  ____________ 
Conversion of 
%age  %age 
Power line 
22  26669892  Above/Below/at  Above/Below/at 
crossings (HT 33 
par over  par over estimated 
kV‐7 nos.  11 
estimated Rates  Rates 
kV‐25 Nos. & LT 
400 V‐8 Nos.)  
into UG Cable  
____________  ____________     
Electrical  %age  %age 
22  General Service  36,44,659  Above/Below/at  Above/Below/at 
Works  par over  par over estimated 
estimated Rates  Rates 
        
Total Amount   78,78,84,327.47   Total Quoted price    = 

 
   

31 Volume II – Bill of Quantities


 

BILL No.1 OF STANDARD BOQ OF RVNL 

 
RVNL 
S.  Rate in 
BOQ  Description of Item  Qty  Unit  Amount in Rs. 
No.   Rs. 
No. 
Earthwork  in  filling  in 
formation  including  trolley 
refuges,  etc  using 
contractor's  earth  of 
approved  quality  procured 
from  outside  railway  land 
including  site  clearances, 
setting  out  and 
demarcation,  benching, 
initial  compaction  of  subsoil 
after  levelling  the  surface 
after  site  clearance, 
spreading  loose  earth  in  30 
CM layers using grader up to 
extra width of 0.5 M beyond 
designed  profile, 
compaction  using  vibratory 
compactors so as to achieve 
           
1  1001  minimum  in  situ  dry  density  1649400  Cum  120 
197,928,000.00 
of 98% of MDD, top and side 
dressing  and  removal  of 
extra  earth  from  sides  to 
provide  final  formation  as  
per  designed  profile.  The 
rate  shall  include  cutting  of 
trees with girth up to 60 CM, 
making  good  the  pockets 
and  depressions  left  in  soil 
during  clearing  and 
uprooting  of  jungle/trees  at 
site and one round of heavy 
rolling of sub‐soil thereafter.  
The  rate  shall  not  include 
cutting  of  trees  of  girth 
beyond  60  CM  and 
compaction  which  shall  be 
paid separately. 

32 Volume II – Bill of Quantities


RVNL 
S.  Rate in 
BOQ  Description of Item  Qty  Unit  Amount in Rs. 
No.   Rs. 
No. 
Earthwork  in  cutting  in 
formation,  trolley  refuges, 
side  drains,  yard  drains, 
catch  water  drains,  etc. 
including  leading  usable  cut 
spoils  up  to  200  M  and 
making  formation  in  filling 
using  the  cut  spoils,  site 
clearances,  setting  out  and 
demarcation,  disposing  off 
2  1002             
surplus  unusable  cut  spoils 
as  per  directions  of  the 
engineer,  and  top  and  side 
dressing  to  provide  final 
formation  as  per  designed 
profile.  The  rate  shall  not 
include cutting of trees with 
girth  above  60  CM  and 
compaction,  which  shall  be 
paid separately. 
               
2a  1002 a  Soil excluding rock.  63000   Cum   65 
4,095,000.00  
               
2b  1002 b  Rock not requiring blasting.   12600   Cum   130 
1,638,000.00  
Rock  requiring  blasting,  but 
blasting  not  permitted                 
2c  1002 d  8400  Cum  354 
hence  to  be  excavated  by  2,973,600.00  
chiselling. 
Incremental  rate  for  every 
Km  or  part  thereof  over 
Cum                    
3  1003  item  1002  for  leading  cut  75600  3 
Km   226,800.00  
spoils  beyond  200  M  for 
making formation in filing. 
Providing  and  laying 
blanketing  materials  of 
grading  as  per  latest 
guidelines  of  RDSO  in  layers 
of 30 CM in loose state using 
             
4  1004  graders  and  compaction  124500   Cum   264 
32,868,000.00  
using  vibratory  compactors 
so as to achieve minimum in 
situ  dry  density  of  98%  of 
MDD,  top  and  side  dressing 
to provide final formation as 

33 Volume II – Bill of Quantities


RVNL 
S.  Rate in 
BOQ  Description of Item  Qty  Unit  Amount in Rs. 
No.   Rs. 
No. 
per  designed  profile.    The 
rate  shall  not  include 
compaction,  which  shall  be 
paid separately. 

Mechanical  compaction  of 


earth and blanket materials 
in  layers  of  30  CM  in  loose 
state  using  vibratory               
5  1005  1800000   Cum   12 
compactors so as to achieve  21,600,000.00  
minimum  in  situ  dry  density 
of  98%  of  maximum  dry 
density.   
Turfing  with  sods,  10CM 
thick  and  20CM  square 
closely  laid,  including 
dressing,  repair  to  rain  cuts 
and  watering  as  required 
until  turfing  is  properly                 
6  1006  330000  Sqm  13 
rooted.  Payment  to  be  4,290,000.00  
released  in  two  stages:  (i) 
50%  on  completion  of 
turfing; and (ii) balance 50% 
after  proper  rooting  of  the 
turf. 
Providing  and  erecting 
safety  fencing  by  fixing 
minimum 75 MM dia 2.10 M 
long  wooden  bally  posts  at 
3.0  M  interval  embedded  in 
M10  cement  concrete  block 
of  45  CM  x  45  CM  x  60  CM 
(with  Contractor's  cement) 
and interconnected with five                      
7  1007  500  Meter  97 
rows  of  12  MM  dia  nylon  48,500.00  
rope of approved colour and 
quality  and  maintenance  in 
proper  position  throughout 
the period of requirement. 2 
bands  (red  and  white)  300 
MM long shall be painted on 
the  ballies  from  top  and  2 
bands  (100  MM  apart)  of 

34 Volume II – Bill of Quantities


RVNL 
S.  Rate in 
BOQ  Description of Item  Qty  Unit  Amount in Rs. 
No.   Rs. 
No. 
yellow  luminous  tape  of 
width  50  MM  shall  be 
pasted  on  top  white  band. 
After  execution  of  all  works 
requiring  safety  fencing  in 
particular  stretch,  the 
fencing  shall  be  removed 
with  the  approval  of  the 
Engineer and formation shall 
be repaired to its profile and 
released  materials  will  be 
contractor’s property.  
Cutting  down  trees  and 
uprooting  of  roots  including 
transporting  the  wood  to 
nearby  railway  store  or 
forest  godown  as  per 
direction  of  the  Engineer‐in‐
charge.                                  
8  1008          
Note:  Clearance  of  trees  ‐    
with  girth  less  than  60  CM 
and  their  clearance  is 
covered  under  item  No. 
1001  &  1002.  Girth  will  be 
measured at a height of 1 M 
above ground level. 
Girth above 60 CM and up to                      
8a  1008 a  100  Each  258 
90 CM  25,800.00  
Girth above 90 CM and up to                      
8b  1008 b  25  Each  644 
180 CM  16,100.00  
Supplying  and  filling  in 
water  logging    lake  areas  
with  locally  available  sand  
under formations   including 
watering,    consolidating  and                 
9  NS‐1  2000  Cu.M  531 
dressing  complete  with  all  1,062,000.00  
contractor's  men,  materials, 
lead,  lift  transportation  etc., 
and  as  directed  by  the 
Engineer‐in‐charge. 
Total for Bill No.1 (Carried forward to                   
  
Summary)  266,771,800.00 
 

35 Volume II – Bill of Quantities


BILL NO.1. NOTE SPECIFIC FOR EARTH WORK IN FORMATION 

1   The earth work in formation and blanketing has to be executed as per latest RDSO guidelines 
for earthwork in railway projects with up to date correction slips. If naturally available material 
in the project area is not suitable for using as blanketing material directly then the blanketing 
material  conforming  to  RDSO  specification  has  to  be  produced  by  blending  various  naturally 
available materials in required proportion in a pug mill. 
2   Obtaining prior permission for felling of trees including payment of royalty and taxes etc shall 
be contractor’s responsibility and deemed to be included in the rates. 
3   Joining of new formation with existing embankment has to be done with benching of 30 cm 
(V), 60 cm (H) in the existing bank slope. The rate of earthwork includes the cost of benching. 
4   Locations where blasting is warranted, prior permission of the employer must be obtained to 
ascertain whether blasting is permitted or prohibited. Rate of rock cutting includes the cost of 
all precautionary measures necessary for safety during blasting of rock. 
   

36 Volume II – Bill of Quantities


 
BILL No.2  OF  STANDARD BOQ OF RVNL 
 
RVNL 
S.  Rate in  Amount in  
BOQ  Description of Item  Qty  Unit 
No.   Rs  Rs 
No. 
Earth  work  in  excavation  in          
foundation  of  bridges  to 
desired  profile  including 
1  2001  backfilling,  compaction  of  back    
fill,  and  disposal  of  surplus 
earth  as  per  directions  of  the 
Engineer. 
      
1a  2001 a  Soil excluding rock.   22800  Cum   104 
2,371,200.00  
      
1b  2001 b  Rock not requiring blasting.   7000  Cum   184 
1,288,000.00  
      
1c  2001 c  Rock requiring blasting   5000  Cum   297 
1,485,000.00  
Rock  requiring  blasting,  but 
      
1d  2001 d  blasting  not  permitted,  hence  3200  Cum  361 
1,155,200.00  
to be excavated by chiselling. 
Extra  over  item  2001(a)  for 
quantities of works, executed in 
or  under  water  and/or  liquid 
mud/under  foul  position 
including pumping out water as 
required. 
 
Note: The extra percentage rate 
is  applicable  limited  to 
quantities  of  work  executed  in  Cum 
these  difficult  conditions.    The  Per             
2  2002  1000  22 
unit, namely metre depth, to be  Metre  22,000.00  
considered  for  payment,  shall  Depth 
be  the  depth  measured  from 
the  sub  soil  water  level  up  to 
the  centre  of  gravity  of  the 
quantity  executed  in  difficult 
conditions.    The  depth  shall  be 
reckoned  correct  to  0.1  metre, 
0.05  metre  or  more  shall  be 
taken  as  0.1  metre  and  less 
than 0.05 metre ignored. 

37 Volume II – Bill of Quantities


RVNL 
S.  Rate in  Amount in  
BOQ  Description of Item  Qty  Unit 
No.   Rs  Rs 
No. 
Providing  and  laying  cement 
concrete  1:3:6  in  foundation 
    
3  2003  and  floor  using  well  graded  5800  Cum  1880 
10,904,000.00  
stone  aggregate  of  40  MM 
nominal size. 
Providing and laying design mix 
control  concrete  M20/M25  in 
piers,  retaining  walls,  wing 
walls, return walls, bottom/top      
4  2004  7400  Cum  2845 
plug  of  wells  and  protection  21,053,000.00  
work  etc.  using  well  graded 
stone  aggregate  of  40  MM 
nominal size. 
Providing  and  laying  Design 
mix  control  concrete 
M25/M30/M35/M40/M45  in 
RCC  works  of  raft,  pile  cap,  
pier,  abutment,  well  stening, 
RCC  well  kerb,  well  cap,  pier 
cap, Jacketing,  dirt wall, return 
wall,  wing  wall,  fly  wing  wall,      
5  2005  21900  Cum  3748 
retaining  wall,  approach  slab,  82,081,200.00  
foot path slab,  wearing course, 
ballast  retainers,  RCC  railing, 
inspection  platform,  pedestal, 
boxes  and  other  miscellaneous 
works  using  well  graded  stone 
aggregate  of  20  MM  nominal 
size. 
Providing  Cast‐in‐situ  post 
tensioned  PSC  slabs  as  per 
approved  drawing    with  design 
mix  control  concrete 
M45/M50/M55  including 
sheathing,  anchorages,  bearing 
plates,  permanent  wedges, 
    
6  2006  positioning  of  strands  in  1100  Cum  10700 
11,770,000.00  
sheathing  as  per  profile, 
stressing  and  detressing, 
grouting,    launching  precast 
girders  in  position  by 
slewing/lowering, etc. 
Note: 
1.    Rate  excludes  cost  of  HTS 

38 Volume II – Bill of Quantities


RVNL 
S.  Rate in  Amount in  
BOQ  Description of Item  Qty  Unit 
No.   Rs  Rs 
No. 
strands  (their  placement  in 
sheathing,  stressing  and 
grouting),  sheathing, 
anchorages,  TMT  bars  and 
cement,  admixture  which  shall 
be  paid  separately  under 
relevant  items. 
2.    Payment  for  precast  girders 
shall  be  released  in  three 
stages:  (i)  75%  on  casting  and 
stressing of girders; and (ii) 20% 
after  lowering  girders  in 
position and (iii) balance 5% on 
completion in all respects. 
Providing    of  PSC 
Superstructure  (Box  Girder) 
with  design  mix    controlled 
concrete  M45/M50/M55  to 
suite  clear  span  of  18.3  m. 
(Overall  width  of  deck  slab  is 
5.80  m.)  including  casting  of 
Post  Tensioned,  pre‐stressed 
concrete  box  girder  (with  key 
man  path  of  1.00  m.  on  one 
side)  with  stressing  and 
grouting,  including  provision  of 
elastomeric bearing, RCC ballast 
retainer,  rain  water  outlet      
   2006a  1245  Cum  10700 
arrangements,  MS  Inspection  13,321,500.00 
ladder  to  the  required  slope  to 
be  provided  on  both  side  to 
inspect  top  of  the  abutment 
and  pier,  expansion  joints,  CC 
wearing  coat,  RCC  railing 
arrangements on key man path 
including launching of girders in 
position,  etc.  complete 
conforming  to  the  details  as 
shown in approved drawing and 
subject  to  technical 
specification,  as  directed  by 
Engineer‐in‐charge.    

39 Volume II – Bill of Quantities


RVNL 
S.  Rate in  Amount in  
BOQ  Description of Item  Qty  Unit 
No.   Rs  Rs 
No. 
NOTE:‐                                                
i)  The  above  rate  excludes  the 
cost  of  HTS  strands,  sheathing, 
anchorage,  elastomeric 
bearings,  RCC  ballast  retainer, 
inspection  ladder,  expansion 
joints,  CC  wearing  coat,  RCC 
hand  rail  arrangements, 
admixture,  reinforcement  steel 
and cement, which shall be paid 
separately  under  relevant 
items.  ii)  Casting  of  PSC  girder 
shall be done at one pour.           
Extra  for  laying  concrete  in  or 
under  water  and/or  liquid 
mud/under  foul  position 
including  cost  of  pumping  or 
bailing out water and removing 
slush  etc  complete.
Note:  The  quantity  will  be 
calculated  by  multiplying  the 
Cum 
depth  measured  from  the  sub‐
Per               
7  2007  soil  water  level  up  to  centre  of  50  197 
Metre  9,850.00  
gravity  of  concrete  under  sub‐
Depth 
soil water level with quantity of 
concrete  in  cum  executed 
under  sub‐soil  water.    The 
depth  of  centre  of  gravity  shall 
be  reckoned  correct  to  0.1m, 
0.05m or more shall be taken as 
0.1m  and  less  than  0.05m 
ignored. 
Providing  and  fixing 
elastomeric  bearings  as  per      
8  2008  27894000 Cu.CM  0.7 
specifications  provided  as  per  19,525,800.00  
drawing. 
Providing  and  laying  40  MM 
      
9  2009  expansion  joint  as  per  RDSO  250  M  11800 
2,950,000.00  
drawing No. B‐1757R. 
Conducting  deflection  test  of 
prestressed concrete deck with 
10  2010  uniformly distributed static load  0                               ‐    
as per clause 10.5 of IRS bridge 
code.   

40 Volume II – Bill of Quantities


RVNL 
S.  Rate in  Amount in  
BOQ  Description of Item  Qty  Unit 
No.   Rs  Rs 
No. 
           
10a  2010a   9.14 M PSC slab  1  Each  41900 
41,900.00  
           
10b  2010b  12.20 M PSC Slab  1  Each  55900 
55,900.00  
           
10c  2010c  18.3 M PSC "BOX" Girder   1  Each  71600 
71,600.00  
Providing  and  laying  dry  stone 
backing  behind  abutments, 
wing  walls,  return  walls,  RCC 
boxes with stones not less than        
11  2012  3500  Cum  748 
15 CM in any direction and not  2,618,000.00  
less than 15 KG (except smaller 
boulders  required  for  filling 
voids) in weight.  
Providing  and  laying  backfill 
material  behind  boulder  filling 
of  abutments,  wing  walls, 
    
12  2013  return  walls  consisting  of  40000  Cum  277 
11,080,000.00  
granular  materials  of  GW,  GP, 
SW  groups  as  per  IS  1498‐1970 
in required profile .  
Providing  and  fixing  bridge 
plaque (750 MM base, 720 MM 
height  triangular  section  with 
400  MM  thickness)  on  both 
sides  of  parapet  using  cement 
concrete  of  specified  mix 
including  engraving  bridge             
13  2017  78  Each  211 
number,  direction  of  flow  and  16,458.00  
other  details  including  painting 
the letters with enamel paint of 
black colour of approved quality 
with  white  back  ground  as  per 
standards of railway as directed 
by the engineer.  

41 Volume II – Bill of Quantities


RVNL 
S.  Rate in  Amount in  
BOQ  Description of Item  Qty  Unit 
No.   Rs  Rs 
No. 
Providing and fixing river name 
boards  of  size  2.10  M  x  1.0  M 
made  of  MS  sheet  6  MM  thick 
and  ISA  50  x  50  x  5  MM  frame 
all  around,  fixed  on  rail  posts 
erected with railway's rails fixed 
in cement concrete base of size 
60  CM  x  60  CM  x  75  CM  of  CC               
14  2018  2  Each  4115 
1:2:4  including  painting  with  8,230.00  
two  coats  of  paint  of  approved 
quality  and  colour  over  one 
coat  of  primer,  writing  the 
name  of  the  river  in  vernacular 
and English in black colour with 
yellow  back  ground  as  directed 
by the engineer. 
Providing and fixing of 100 MM 
dia PVC pipe for weep holes in 
abutments,  wing  walls,  return           
15  2025  1680  Meter  199 
walls,  face  wall,  etc  at  suitable  334,320.00  
intervals  as  directed  by  the 
engineer. 
Supplying  and  filling  in 
foundations  with  locally 
available  sand          including 
watering,  ramming, 
consolidating  and  dressing        
16  NS‐1  5500  Cu.M  531 
complete  with  all  contractor's  2,920,500.00  
men,  materials,  lead,  lift 
transportation  etc.,  and  as 
directed  by  the  Engineer‐in‐
charge at site. 
Supplying,  and  laying  of  heavy 
duty RCC hume pipe NP‐4 class 
1.8M  dia  as  per  RDSO  drawing 
joining with cement mortar 1 : 2 
mix    with  all  contractor's  men,        
17  NS‐2  378  M  11760 
materials,  lead,  lift,  4,445,280.00  
transportation,  loading, 
unloading etc., including testing 
and  as  directed  by  the 
Engineer‐in‐charge at site.             

42 Volume II – Bill of Quantities


RVNL 
S.  Rate in  Amount in  
BOQ  Description of Item  Qty  Unit 
No.   Rs  Rs 
No. 
 Note:‐  1.  70%  payment  will  be 
released  after  casting  of  at  site 
           
and  balance  payment  will  be 
made after erection.  
Providing  water  proofing 
course  including  supply  and 
laying  polymeric  hyper 
multiplas  mat  4mm  thick  with 
additional  core  of  puncher 
resistance  polyester  (in  seven 
layers  of  integrated  water 
proofing limited or similar) over 
         
18  NS‐3  bituminous primer over finished  900  Sq.M  650 
585,000.00  
back  side  and  side  walls  of 
subway  and  wherever  required 
with  all  contractor's  men, 
materials,  lead,  lift, 
transportation,  loading, 
unloading  etc.,  and  as  directed 
by  the  Engineer‐in‐charge  at 
site.  
Providing  and  laying    of  brick 
wall  11CM  thick  with  CM  1:5 
mix  for  protection  of  polymer 
sheet  provided  in  the  sub  way 
with  all  contractor's  men, 
         
19  NS‐4  materials,  lead,  lift,  160  Cu.M  3000 
480,000.00  
transportation,  loading, 
unloading  etc.,  and  as  directed 
by  the  Engineer‐in‐charge  at 
site  including  the  cost  of 
cement. 
Providing  protective  layer  to 
water  proof  membrane  in  the 
form  of  cement  screened  and 
chicken  mess  with  contractor 
supply  of  25SWG  GI  chicken 
mess  placed  over  the  water           
20  NS‐5  900  Sq.M  232 
proof  membrane  with  10CM  208,800.00  
over  lap  at    joints  and  pressing 
the  mesh  gently  to  keep  in 
position  fixed  to  the  chicken 
mesh  to  membrane  by  using 
buttons  made  of  multiplas  and 

43 Volume II – Bill of Quantities


RVNL 
S.  Rate in  Amount in  
BOQ  Description of Item  Qty  Unit 
No.   Rs  Rs 
No. 
plastering  over  the  chicken 
mesh to a thickness of 20mm in 
CM  1  :  5  mix  to  the  required 
gradient neatly finishing the top 
and  curing  the  plastered  work 
for a period of 7days. The work 
to be carried out as directed by 
the  Engineer‐in‐charge  with 
contractor's  labour,  materials 
except  cement  which  will  be 
paid separately. 
Making  island  for  bridge 
foundations  in  Pier  & 
Abutments  in  running  or 
standing  water/diversion  up  to 
a  average  water  depth  of  3.5M  
for  the  completion  of  the  work  
including  cost  of  making 
platform    sheet  piling,           
21  NS‐6  6  Each  132100 
earth/sand  filling,  gunny  bags,  792,600.00  
bamboos,  split  bamboo  mats, 
etc.  and  maintaining  the  same 
in  good  shape  till  successful 
completion up to bed level and 
clearing  water  way  up  to  the 
bed  level  after  completion  of 
work. 
Supplying,  laying  of  300mm 
thick  with  well  graded  gravel 
for  road,  levelling,  watering, 
ramming,  compacting  with    10 
Ton  capacity    roller    with  all 
contractor's  men,  materials,        
22  NS‐7  5775  Cu.M  323 
tools,  plants,  lead,  lift,  1,865,325.00  
transportation  of  materials  to 
site  of  work  etc.,  as  per  the 
technical  specification  and  as 
directed  by  the  Engineer‐in‐
charge at site. 

44 Volume II – Bill of Quantities


RVNL 
S.  Rate in  Amount in  
BOQ  Description of Item  Qty  Unit 
No.   Rs  Rs 
No. 
Casting, supplying and installing 
of  precast  cement 
slabs/pitching blocks/inspection 
steps/bridge  coping  slabs  of 
sizes 
45x45x7.5CM/25x25x20cm/ 
37.5x22.5x15  cm/60x60x15  cm 
or  required  sizes  for  protective 
works  at  bridge  /  banks  using 
Cement  concrete  mix  1  :  2  :4  
    
with  20mm  metal  including  3000  Cu.M  4670 
14,010,000.00  
contractor's  shuttering,  leading 
to  bridge  site  from  casting 
depot,  including  earth  work, 
gravel  backing  laying  with 
23  NS‐8 
contractor's  labour  including 
pointing  with  CM  1 :  2 mix  and 
as  directed  by  the  Engineer‐in‐
charge.  (All  labour  and 
materials  excluding  cement  by 
contractor) 
NOTE:                                                 
i)  Payment  for  gravel  backing 
will be paid under relevant item 
of  this  schedule.      (ii)  60% 
payment  shall  be  made  after             
casting of precast concrete slab. 
The  balance  40%  will  be  made 
on  completion  of  laying  & 
finishing.) 
Supply  and  laying  of  150mm 
thick  well  graded  stone 
aggregate/gravel as above layer 
over the slopes of embankment 
with  manual  dressing  with 
water compaction including the        
24  NS‐9  4500   CUM  349 
cost  of  supply  of  materials,  1,570,500.00  
labour,  lead,  lift,  tools,  plants, 
etc.,  complete  as  per  the 
drawing  and  technical 
specifications  and  as  directed 
by the Engineer‐in‐charge. 

45 Volume II – Bill of Quantities


RVNL 
S.  Rate in  Amount in  
BOQ  Description of Item  Qty  Unit 
No.   Rs  Rs 
No. 
   Total For Bill No 2A (carried             
  
Forward)  209,041,163.00 
 

NOTE SPECIFIC FOR BILL NO.2:  BRIDGES WORK FOR CC, RCC AND PSC ITEMS. 

1   All material, equipment, labour, casting beds, stress frames, from work staging, scaffolding, etc 
is to be arranged by the contractor within the quoted rates. 
2   1:4:8, 1:3:6 and 1:2:4 indicates concrete prepared using volumetric mix in proportion of cement: 
coarse sand: stone aggregate of specified size, respectively. 
3   All design mix concrete shall be machine batched with automatic weigh batcher, machine mixed 
and machine vibrated or Ready Mix Concrete prepared in depot and transported by transit mixer 
to the site of work.  
4   Prior to demolishing of any structure measurements have to be taken, scheme of dismantling 
has to be got approved from the Engineer. 
   

46 Volume II – Bill of Quantities


Bill No. 2B OF STANDARD BOQ OF RVNL 
 
RVNL 
Rates in   Amount in  
S. No.   BOQ  Description of Item  Quantity Unit 
Rs.  Rs 
No. 
Providing  trolley/men  refuges,  
inspection ladder, hand railing, 
other  miscellaneous 
components    made  of  GI 
pipe/structural  steel 
conforming  to  IS:  226  
bolted/welded  construction 
            
1  2042  including  fixing  on  bridges  as  15  MT  85000 
1,275,000.00  
per  drawing  and  painting  with 
one  primer  coat  of  red  lead 
paint  conforming  to  IS:  102  or 
zinc chromate paint conforming 
to IS:104 (with total DFT of 160 
microns).  Work  shall  be  carried 
out as per I.S. 800. 
Supply  of  Pre‐stressing  cables 
of  required  size  and 
configuration  of  low  relaxation 
high  tensile  steel  strands  (class 
II)  confirming  to  IS:  14268.  The 
rate  includes  cost  of  sheathing, 
anchorages,  placing  of  strands 
placing  of  the  strands  in  HDPE 
sheething of required diameters 
and  of  ID  specification  as  per 
IRS,  as  per  profile,  stressing  &            
2  2051  85  MT  136000 
destressing  and  grouting  11,560,000.00 
complete  as  directed  by 
Engineer. 
Note:  The  quantity  of 
prestressing  cables  provided  in 
permanent  work  excluding 
wastages  shall  only  be 
measured  for  payment  and 
payment  shall  be  made  after 
the quantity is consumed in the 
relevant item.  
Total for Bill No. 2 B (Carried                     
     
forward)  12,835,000.00 
   

47 Volume II – Bill of Quantities


Bill No. 2C OF STANDARD BOQ OF RVNL  
RVNL 
Rates in   Amount in  
BOQ  Description of Item  Quantity  Unit 
Rs   Rs 
No. 
Supplying  TMT  Fe‐500 
reinforcement  steel  conforming  to 
IS:  1786‐1985  including  decoiling, 
straightening,  cutting,  bending, 
placing  in  position,  binding  with 
1MM dia GI binding wire. 
  
Note:  Reinforcement,  shall  be 
2061  measured  in  length  for  different  2800  MT  56000  156,800,000.00 
diameters  used  in  the  works  and 
then paid as per standard weights as 
per  IS  1732.  Wastages,  overlaps, 
coupling,  welded  joints,  space  bars, 
chairs  and  binding  wire  shall  not  be 
measured  and  cost  of  these  items 
shall be deemed to be included in the 
rates. 
Reduction over item No: 2061 above 
for  supply  of  TMT  Fe‐415 
NS‐1  20  MT  ‐1210  ‐24,200.00 
reinforcement  steel  in  place  of  Fe‐
500. 

Total for Bill No. 2C (Carried forward)           156,775,800.00 

 
 
   

48 Volume II – Bill of Quantities


BILL No.6  OF STANDARD BOQ OF RVNL 
Rates in   Amount in 
S. No.   Description of Item  Quantity  Unit 
Rs  Rs 
6001  Construction of service buildings  at 
stations, in yards and in mid section 
as  per  layout  drawing  provided  by 
the  employer  and  detailed 
specifications  provided  in  para  4.2 
of section 5: works requirements of       
the  bidding  documents  including 
preparation  of  architectural  plan 
and structural design and drawings. 
Rate  includes  cost  of  cement  steel 
and all other materials and labour.       
6001 a  Service  building  of  single  storey 
(foundation  to  be  designed  to  take 
load  of  double  storey)  with  open 
     
foundation up to 1.2 m depth from  364.47  Sqm   9561 
3,484,697.67 
ground level and plinth height up to 
0.6m  from  ground  level  with  floor 
height up to 3.35m. 
Extra  payment  for  provision  of 
        
6001 e  internal  sanitary  and  water  supply  364.47  Sqm   363 
132,302.61  
installations 
6001 f  Extra  for  every  0  .3  m  or  part 
thereof  higher  plinth  over  normal          
1093.41  Sqm   165 
plinth  height  of  0.6m(on  ground  180,412.65  
floor area only)   
6001g  Extra  for  every  0.3m  part  thereof 
deeper  foundations  over  normal       
10934.1  Sqm.  165 
depth  of  1.2m  (on  ground  floor  1,804,126.50 
area only) 
6002  Construction  of  residential 
buildings  for  staff  accommodation  
near  railway  stations,  level 
crossings  or  any  other  nominated 
location as per layout drawings and 
standard  railway  plans  for  each 
type of staff quarters,   provided by 
           
the  employer  and  detailed 
specifications  provided  in  para  4.3 
of section 5: works requirements of 
the  bidding  documents  including  
structural  design  and  preparation 
of  detailed  structural  drawings. 
Rate  includes  cost  of  cement  steel, 

49 Volume II – Bill of Quantities


internal  water  supply  and  sanitary 
installations and all other materials 
and labour. 

Type  I,II,III  Double  storeyed    floor       


6002 b  431.16  Sqm   7649 
height up to 2.9 m  3,297,942.84 
Extra  for  every  0.3m  additional 
        
6002 i  height above normal height  of 2.90  1724.64  Sqm   165 
284,565.60  

6002 l  Extra  for  every  0  .3  m  or  part 
thereof  higher  plinth  over  normal          
862.32  Sqm   165 
plinth  height  of  0.6m  (on  ground  142,282.80  
floor area only)  
6002 m  Extra for every 0.3m or part thereof 
deeper  foundations  over  normal          
862.32  Sqm   165 
depth  of  1.2m  (on  ground  floor  142,282.80  
area only)  
                 
     
TOTAL VALUE FOR BILL No.6          
9,468,613.47 
 
   

50 Volume II – Bill of Quantities


Bill No. 7A OF STANDARD BOQ OF RVNL 

RVNL 
Rates in  Amount in  
S. No.   BOQ  Description of Item  Quantity  Unit 
Rs  Rs 
No.  
Providing  seal  coat  of 
premixed  fine  aggregate 
(passing  2.36  MM  and 
retained  on  180  micron 
sieve)  with  bitumen  using 
128  KG  of  bitumen  of 
          
1  7011  grade 8500 per Cum of fine  5250  Sqm  40 
210,000.00  
aggregate and 0.60 Cum of 
fine  aggregate  per  100 
Sqm  of  road  surface 
including  rolling  and 
finishing  with  road  roller 
complete.  
For  50  MM  compacted 
thickness  using  coarse 
aggregate  of  size  40‐20         
2  7012a  5250  Sqm  240 
MM  graded  and  key  1,260,000.00  
aggregate of size 12.5 MM 
graded. 
For  75  MM  compacted 
thickness  in  two  layers 
using  stone  aggregate  of         
3  7012b  5250  Sqm  340 
size 63‐41 MM graded and  1,785,000.00  
key  aggregate  of  size  20 
MM graded. 
Transplantation  of  trees 
by  pruning,  trenching  or 
preparation  of  the  root 
ball, digging,  preparing the 
tree  pit,  planting  and 
guying the trees,   watering 
the  trees  twice  or  thrice 
depending  upon  climate 
4  NS‐1             
condition,  without 
damaging  the  tree  roots 
and  maintaining  the  trees 
for  ninety  days  after 
replantation  with  all 
contractor's    labour, 
materials,  tools,  plants, 
manures  of natural,  as per 

51 Volume II – Bill of Quantities


specifications  of  
transplantation  of  trees  of 
Horticulture 

a)  Trees  of  average  sizes  ‐ 


       
      20  to  40  cm  girth  75  Each  17825 
1,336,875.00  
irrespective of height 
b)  Trees  of  average  sizes  ‐ 
       
      40  to  70  cm  girth  50  Each  20125 
1,006,250.00  
irrespective of height 
a)  Trees  of  average  sizes  ‐ 
70  to  100  cm  girth  and         
      50  Each  22425 
above  irrespective  of  1,121,250.00  
height 
Providing  Wet  Mix 
Macadam  road  300mm 
thick  over  existing  bed 
with  25mm  to  50mm  size 
graded  stone  aggregate 
and quarry dust as per the 
mix  proportion  mentioned 
in  the  specification 
including  compaction  in 
       
5  NS‐1  uniform  thickness,  rolling  1575  Cu.M  1823 
2,871,225.00  
with  3  wheeled 
steel/vibrator roller 8 to 10 
Ton  capacity  in  stages  to 
proper  grade  and  camper, 
watering  and  compacting 
to  the  required  thickness. 
(Payment  will  be  made 
base on the thickness after 
the consolidation) 
Casting,  supplying  and 
installing  of  pre  cast    RCC 
boundary  pillars    of  size 
0.25  x  0.15    x  2.33  M  at 
nominated  locations  using 
M.30  mix    with  20mm 
metal  including            
6  NS‐2  400  Each  1874 
contractor's  labour,  749,600.00  
materials,  tools,  plants, 
shuttering,    leading  to  site 
from  casting  depot, 
including excavation of pit, 
fixing    the  pillar  in  the  pit 
with    CC  1:3:6  mix  with 

52 Volume II – Bill of Quantities


40mm metal, engraving of 
letters  and  painting  with 
synthetic  enamel  paint  in 
two coats over primer coat  
including  writing  of  letters 
as  per  the  drawing  and  as 
directed  Engineer‐in‐
charge  including  the  cost 
of cement and steel.        
   TOTAL VALUE FOR BILL No.7 A (Carried forward to summary) 
10,340,200.00 
 
   

53 Volume II – Bill of Quantities


BILL No:8 OF STANDARD BOQ OF RVNL 
RVNL 
Rates in  Amount in  
S. No.   BOQ   ITEM OF WORK    Quantity   UNIT   
Rs   Rs 
No. 
Supply of    43/53 grade cement 
OPC    conforming  to  relevant  IS 
specifications  and  using  the 
same in the work as per RVNL's 
approved  mix  design  as  per 
RVNL's  prescribed  rates  of           
1  8001a  310000  Bag  275 
consumption  including  all  lead  85,250,000.00 
lift,  labour,  loading  unloading, 
ascent,  descent,  crossing  of 
Railway  lines(s),  royalty,  taxes, 
transport  (contractor's  own), 
tools and plant complete. 
         
   Total for Bill No. 8 :‐  (Carried forward to Summary)       
85,250,000.00 
Note  :  OPC    cement  has  to  be  supplied  as  per  requirement  of  the  work  in  terms  of  RVNL 
   standard  specifications  for  material  and  works.  Payment  against  supply  will  be  made  only 
after consumption of cement  in the relevant items of work. 
 
12.2       Bill No.8: (Supply of Cement): Payment for supply shall only be made after the quantity is 
consumed  in  the  related  item  of  work.  The  consumption  of  cement  shall  be  worked  out  based  on 
cement consumption coefficients as given below or the actual consumption whichever is less. 
COEFFICIENTS FOR CEMENT CONSUMPTION 
  Cement 
consumption 
S. No.  Item  Unit  coefficients per 
unit in Kg. 
(Maximum) 
Cement Concrete 
  1  1:3:6  (1  Cement  3  coarse  sand,  6  graded  stone  Cum  220 
aggregate) 
  2  1:2:4 (1 cement, 2 coarse sand, 4 graded stone  Cum  320 
aggregate) 
  3  M20  Cum  400 
  4  M25  Cum  410 
  5  M30  Cum  420 
  6  M35  Cum  428 
  7  M40  Cum  435 
  8  M45  Cum  480 
  9  M50  Cum  500 

54 Volume II – Bill of Quantities


Cement Mortar 
  5  Cement  Mortar 1:2 (1 Cement: 2 Sand)  Cum  680 
  6  Cement  Mortar 1:3 (1 Cement: 3 Sand)  Cum  510 
  7  Cement  Mortar 1:4 (1 Cement: 4 Sand)  Cum  380 
  8  Cement  Mortar 1:5 (1 Cement: 5 Sand)  Cum  310 
  9  Cement  Mortar 1:6 (1 Cement: 6 Sand)  Cum  250 
Brick Work 
  11  Cement Mortar 1:4 (1 cement: 4 coarse sand)  Cum  95 
  12  Cement Mortar 1:6 (1 cement: 6 coarse sand)  Cum  62.5 
  13  Cement Mortar 1:3 (1 cement: 3 coarse sand) half  Sqm  14.28 
brick 
  14  Cement Mortar 1:4 (1 cement: 4 coarse sand) half  Sqm  10.64 
brick 
Cement consumption for any item if not mentioned above is to be worked out as per CPWD 
Note:    DSR 2007. 
 
   

55 Volume II – Bill of Quantities


 
Bill No.9 OF STANDARD BOQ OF RVNL. 
RVNL 
Rates in  Amount in 
S. No.  BOQ   ITEM OF WORK    Quantity   UNIT   
Rs   Rs 
No: 
Providing  site  office  for 
Employer/Engineer  with 
contractor's  hired 
accommodation  at  site  or  at 
suitable  place  including 
provision  of  water  supply, 
drainage  arrangements,  power 
supply,  office  maintenance  etc., 
as  per  Clause  3.2  and  3.3  of 
Section 5 – Volume I.                       
Note:‐                                                  
(a)  10%  payment  shall be  made 
Sqm/             
1  NS‐1  on  completion  of  one  month  3600  427 
Month  1,537,200.00 
from  the  date  of  making 
available  the  office  fit  or 
functioning. 
(b)  Remaining  90%  payment 
shall  be  made  in  equal  monthly 
instalments  i.e.  (0.0  x  Quoted 
rate)/(stipulated  completion 
period  in  months  +  defect 
liability    period  in  months) 
completion  of  one  month  from 
the date of making available the 
office fit for functioning. 
Providing road vehicle of model 
"Tata  Sumo,  Bolero  of  similar 
for  the  use  of 
Engineer/Employer  as  per  the 
conditions  mentioned  in 
Vehicle             
2  9003b  clause3.4.3  i.e.  3.4.3.1  to  150  37000 
month  5,550,000.00 
3.4.3.3.  of  chapter  3  (site 
facilities  for  the  employer  and 
the  Engineer)  of  section  
requirements  of  tender 
documents. 
           
   Total for Bill No. 9 :‐  (Carried forward to Summary)       
7,087,200.00 
 
   

56 Volume II – Bill of Quantities


   
Bill No. 22  OF STANDARD BOQ OF RVNL (Electrical General Service works) 
Conversion of  Power line crossings ( HT 33 kV‐7 nos.  11 kV‐25 Nos. & LT 400 V‐8 Nos.)  in 
to UG Cable between Obulavaripalle & Nethavaripalli section.  
 
Rate/  Total          
Sl.  Description  Qty  Unit   Unit  Cost 
(Amount in Rs.) 
1  Supply of 11 m /9m long MS Beam of size 150 mm x 75 mm x  42 MT 48351  2030742
5 mm duly painted with two coats of primer Zinc Chromate 
&  Aluminium  paints  for  Double/Singe  pole  structure 
confirming to IS:2062‐99. Make: SAIL/Jindal 
2  Erection  of  D.P  Structure  with  cement  concrete  (1:3:6  mix)  64 set 15740  1007360
complete with all accessories as per specification in Drg. no. 
CEE/CN/MS/26‐2004.  The accessories include supply, fixing 
and  painting  of  of  2  Nos.  of  Cross  bracing  angles  of  size 
50x50x6mm  each  4.2  mtr.  Length  and  horizontal  MS 
Channels‐2  Nos.  of  size  100x50x6.4mm  (Flange  thickness‐
6.4mm  &  web  thickness  4.0mm)  each  3.3  mtr.    long  along  
with  suitable MS Clamps, GI Bolts, Nuts,  Washers etc.  
3  Supply  and  fixing  of  additional  3.3  Mtr.  Long  M.S.  channel  64 Nos 2880  184320
cross arm of size 100 x 50 (Flange thickness ‐ 6.4 mm & web 
thickness  ‐  4.0  mm)  on  the  D.P.  Structure  wherever 
necessary 
4  Erection of strut post with accessories as per specification in  128 Each 3380  432640
Drg. No. CEE/CN/MS/23‐2004 including painting  
5  Supply  and  erection  of  stay  set  as  per  specification  in  Drg.  144 Each 3690  531360
No. CEE/CN/MS/24‐2004 with Guy rod & Insulator. 
6  Supply of 33 KV ‐ HTUG XLPE insulated PVC sheathed 3 core  1000 m 3781  3781000
X  240  sq.mm  Alu.    Cable  as  per  IS  7098/Pt.  II/85.    (A  spare 
cable with end termination is required at each crossing) (65 
m. each approx) 
7  Supply of 11kV ‐ HTUG XLPE insulated PVC sheathed 3 core X  3250 m 2990  9717500
240  sq.mm  Alu.  Cable  as  per  specifications.    (A  spare  cable 
with end termination at each crossing) (65 m. each approx) 
8  Supply of 1100V ‐ LTUG XLPE insulated PVC sheathed 4 core  500 m 827  413500
X  95  sq.mm  Alu.  Cable  as  per  IS  7098/Pt.  II/85.    (A  spare 
cable with end termination is required at each crossing) (65 
m. each approx) 
9  Supply of 1100V ‐ LTUG XLPE insulated PVC sheathed 4 core  500 m 504  252000
X  50  sq.mm  Alu.  Cable  as  per  IS  7098/Pt.  II/85.    (A  Spare 
cable with end termination is required at each crossing) (65 
m. each approx) 
10  Excavation of cable trench (1.0 m depth) and back filling as  2000 m 130  260000
per specification in all kinds of soil without sand as per Drg. 
No. CEE/CN/MS/10‐2004 (for each crossing) 
11  Excavation of cable trench 1.2 m below the track and   back  240 m 195  46800
filling  without  sand  as  per  specification  in  all  kinds  of  soil. 
Ref. Drg. No. CEE/CN/MS/10‐2004 
12  Laying/drawing/fixing  of  all  types  of  HTUG/LTUG  XLPE  (E)  5250 m 52  273000
cable in excavated cable trench/RCC, GI, CI pipe/structure as 
per specifications. 
13  Excavation of cable loose coil pit of depth 1.5. M and 4.0 M.  64 Each 7800  499200
dia. for 11kV & 33 kV HTUG Cable including supply and laying 

57 Volume II – Bill of Quantities


Rate/  Total          
Sl.  Description  Qty  Unit   Unit  Cost 
(Amount in Rs.) 
of  RCC  plate  cover  as  per  specification  in  Drg.  No. 
CEE/CN/MS/31‐2004 
14  Supply and filling of river sand  in the excavated cable loose  50 Cu.m 2600  130000
coil pit as per specification in  Drg. No.CEE/CN/MS/31 
15  Supply  and  laying  of  150  mm  dia.  (cast  iron)  CI  pipe  of  LA  480 m 1919  921120
class in the excavated trench (under the track 
16  Supply and fixing of 150 mm dia. 'B' Class GI Pipe 5.8 M long  160 Nos 8190  1310400
cable  leading  pipe  along  with  supply  and  fixing  of  suitable 
MS  clamps  using  Flat  of  size  40X6mm,  bolts,  nuts  and  GI 
washers on the D.P. structures 
17  Supply and laying of RCC pipe 150 mm internal dia. And 25  1900 m 234  444600
mm thick with suitable collar confirming to NP2 class as per 
IS  No.  458  including  jointing  using  gunny  bag  and  cement 
grouting in the already excavated trench/road area 
18  Supply,  fixing,  testing  and  commissioning    of    'Push  On'  28 Nos 23400  655200
outdoor  type    termination  kit  for  33  KV  ,  XLPE  HTUG  cable   
(3C  X  240  sq.mm)  similar  to  Denson/  Mahindra/Raychem 
make. 
19  Supply,  fixing,  testing  and  commissioning    of    'Push  On'  100 Nos 11700  1170000
outdoor  type    termination  kit  for  11  KV  ,  XLPE  HTUG  cable   
(3C  X  240  sq.mm)  similar  to  Denson/  Mahindra/Raychem 
make. 
20  Supply,  fixing,  testing  and  commissioning  of  33  KV  Non‐ 14 set 12285  171990
linear  Station  class  type  Lightening  Arrestor  30  kV/10  kA 
rating  and  all  accessories  (1  set  means  3  Nos.)  on  the  D.P. 
Structure  with  supporting  base  clamps  complete  as  per 
specification. 
21  Supply, fixing, testing and commissioning of 11 kV Non‐linear  50 set 5265  263250
Station class type Lightening Arrestor 9 kV/5 kA rating and all 
accessories (1 set means 3 Nos.) on the D.P. Structure with 
supporting base clamps complete as per specification. 
22  Supply and fixing of 33 KV Disc. Insulator with all accessories  50 No 1872  93600
as per IS No. 731. 
23  Supply and fixing of 11 KV Disc. Insulator with all accessories  160 No 819  131040
as per IS No. 731. 
24  Supply  and  erection  of  33  KV  Pin  Type  Insulator with  all  50 No 1170  58500
accessories as per IS No. 731 Specification 
25  Supply  and  erection  of  11  KV  Pin  Type  Insulator  with  all  160 No 176  28160
accessories as per IS No. 731 Specification 
26  Supply and erection of 4 way LT Cross arm with 4 Nos. of LT  16 set 1820  29120
pin/shackle  insulator,  MS  clamps  and  other  accessories  as 
per  Drg.  No.29‐2009.  Insulator  should  conform  IS  731 
wherever necessary or as directed by engineer in charge.  
27  Supply  and  fixing  of  'Danger  board’  for  440V/11kV/  160 No 325  52000
22kV/33kV  with  all  accessories  as  directed  by  engineer  in 
charge. 
28  Supply  and  erection  of  "Anti‐climbing  devices"  as  per  the  160 No 211  33760
sample  approved  on  terminal  structures  with  suitable 
clamps using MS flats of size 40 x 4 mm including painting. 
29  Supply and erection of RCC Slab type cable route indicator ‐ 192 Nos 650  124800
as per CEE/CN/MS/Drg. No. 11‐2004. 

58 Volume II – Bill of Quantities


Rate/  Total          
Sl.  Description  Qty  Unit   Unit  Cost 
(Amount in Rs.) 
30  Supply,  erection,  testing  and  commissioning  of  HT  Earthing  192 Nos 7020  1347840
arrangements with LA Class CI Pipe of 100 mm dia. 4 SWG GI 
wire  duly  inter  connected  with  posts  &  earth  electrode.  
Earth Value to be stencilled with date on the brick masonry   
as per Drg. No.CEE/CN/MS/37‐2009. 
31  Supply,  erection,  testing  and  commissioning  of  LT  Earthing  16 Nos 2145  34320
arrangements with 'B' Class GI Pipe of 50 mm dia. 4 SWG GI 
wire  duly  inter  connected  with  posts  &  earth  electrode.  
Earth Value to be stencilled with date on the brick masonry 
as per Drg. No. CEE/CN/MS/16‐2009. 
32  Supply and laying of 4 SWG GI wire for earth continuity duly  480 m 12  5760 
inter  connecting  the  earth  sockets  with  posts/electrical 
installations. 
33  Erection  of  Additional  MS  Post  wherever  necessary  as  per  15 Nos 2340  35100
specification in Drg. No.CEE/CN/MS/22‐2004.  
34  Supply and fixing of PG clamp aluminium & Bronze alloy for  80 Nos 70  5600 
terminations of cables on the post/stanchion/structure. (one 
termination  is  for  all  the  3    phases  for  HT  &  3  phase  with 
neutral for LT) 
35  Supply and fixing of Jumper arrangements in DP structure for  50 m 59  2950 
interconnecting  the  HT  equipments  by  Suitable    Aluminium 
bare ACSR Conductor  with proper termination and clamping 
arrangements etc. wherever necessary 
36  Cutting and removal of existing O.H .Crossing span (3 Lines ‐ 40 span 1040  41600
above  railway  track)  with/without  guarding  but  with 
terminal structure and guarding structure and allied items if 
any and handing over it to APSPDCL Stores. 
37  Removal and re‐stringing of adjacent span of exg. O.H. Lines  64 Span 1560  99840
on  either  side  of  crossing  span  terminated  to  the  newly 
erected terminal DP structure 
38  Transportation of released materials to the concerned TNEB  32 Each 1300  41600
official / stores 
39  Preparation  and  submission  of  CAD  completion  Deg.  after  32 Each 260  8320 
completion of work 
TOTAL 26669892
(Rupees Two crores sixty six lakhs sixty nine thousand eight hundred and ninety two  only) 
  PAYMENT CONDITION:     
1. For supplied items 80% payment will be made on receipt, acceptance and accountals of the materials.
2.  Invoices  shall  be  accompanied  with  Manufacturer  &  suppliers  Challan,  Inspection  certificate  by  the 
nominated Inspecting agency. 
3. The work shall be executed strictly as per the approved make, sample and  drawing.
4. 10% payment shall be made after installation, erection/laying etc. of the     particular item.  
5. The remaining 10% shall be paid after commissioning/completion of the relevant portion of the work. 
 
   

59 Volume II – Bill of Quantities


 
Bill No. 22  OF STANDARD BOQ FOR ELECTRICAL GENERAL SERVICE WORKS 
Electrification of Station Buildings, PF lighting, Circulation Area lighting and Staff Quarters in 
OBVT ‐ VKT Section. 
 
S.  Rate  Total          
Description of  work  Unit  Qty 
No  Rs.    Rs.   
1  Supply and fixing in concealed manner by 1 No of PVC pipe  m 4500 36  162000
heavy  25mm  dia/2.0mm  wall  thickness  with  accessories, 
Deep  Junction  box  etc.  Make:  Avon 
Plast/Aeroplast/Godavari 
2  Supply & wiring to light/ fan points in concealed manner by  point 250 359  89750
drawing  2  runs  of  1.5  Sq.mm  (30/0.25)  multi  strand  PVC 
FRLS insulated copper cables of 1100 V grade confirming to 
IS: 694 latest, 1 No of 1.0 Sq.mm single strand copper wire 
for  earth  in  the  existing  PVC  Pipe  including  Flush  Type 
Switch,  3  plate  ceiling  rose  and  other  accessories.  Make: 
Havells/finolex/Orbit 
3  Supply  and  wiring  in  concealed  manner  including  m 800 42  33600
termination  for  raising  mains  by  2  Nos.  of  2.5  Sq.mm 
(36/0.3mm)  PVC  multi  strand  flexible  copper  cable  with  1 
no of 14 SWG tinned copper wire in the exg. PVC pipe. (2 
Nos. of 2.5 sq.mm copper cable and 1 no of 14 SWG Tinned 
copper  1  mtr.  each  shall  be  taken  as  1  Mtr.  for 
Measurement purpose.) Make: Havells/Finolex/Orbit 
4  Supply  and  wiring  in  concealed  manner  including  m 1450 54  78300
termination  for  raising  mains  by  2  Nos  of  4.0  Sq.mm 
(56/0.3mm)  PVC  multi  strand  flexible  copper  cable  with  1 
no of 14 SWG tinned copper wire in the exg. PVC pipe. (2 
Nos. of 4 sq.mm copper cable and 1 no of 14 SWG Tinned 
copper  1  mtr  each  shall  be  taken  as  1  Mtr  for 
Measurement purpose.)  
5  Supply  and  wiring  in  concealed  manner  including  m 500 66  33000
termination  for  raising  mains  by  2  Nos  of  6.0  Sq.mm 
(84/0.3mm)  PVC  multi  strand  flexible  copper  cable  with  1 
no of 14 SWG tinned copper wire in the exg. PVC pipe. (2 
Nos. of 6 sq.mm copper cable and 1 no of 14 SWG Tinned 
copper  1  mtr  each  shall  be  taken  as  1  Mtr  for 
Measurement purpose.) Make: Finolex/Havells/Orbit 
6  Supply  and  wiring  in  concealed  manner  including  m 100 153  15300
termination  for  raising  mains  by  2  Nos  of  10.0  Sq.mm 
(140/0.3mm) PVC multi strand flexible copper cable with 1 
no of 14 SWG tinned copper wire in the exg. PVC pipe. (2 
Nos. of 10 sq.mm copper cable and 1 no of 14 SWG Tinned 
copper  1  mtr  each  shall  be  taken  as  1  Mtr  for 
Measurement purpose.) Make: Finolex/Havells/Orbit 
7  Supply  of  1  X  4  feet  28  W  T‐5  Box  Type  fluorescent  light  No 90 930  83700
fitting  conforming  to  IS:10322  part  5  Sec.2/82  with  lamp 
etc.  (similar  to  Havells  Extruded  al.  batten  popular)   
Make: Phillips/Crompton/Havells 
8  Fixing, Testing and commissioning of  1 X 4 feet 28 W T‐5  No 90 215  19350
Box  Type  fluorescent  light  fitting    shall  be  fixed  with  ball 
and socket, TW round block and 2 nos. of MS conduit pipes 
19mm  dia.  on  ceiling  or  with  MS  angular  clamps  on  side 
walls  Including  wiring  by  3CX1.0  Sq.mm  PVC  insulated 

60 Volume II – Bill of Quantities


S.  Rate  Total          
Description of  work  Unit  Qty 
No  Rs.    Rs.   
copper cable. Make: Havells/Finolex/Orbit

9  Supply  of  AC  Ceiling  fan  1200  mm  sweep  (conforming  to  No 45 1221  54945
IS:374/79)  complete  with  double  ball  bearing.   
Make: Usha/Khaitan/Crompton/polar.   
10  Fixing,  Testing  and  commissioning  of  AC  Ceiling  Fan   No 45 110  4950
complete including wiring by 3CX1.0 Sq.mm PVC insulated 
copper cable as per IS Specification. 
11  Supply, fixing, testing and commissioning of Electronic Fan  No 45 195  8775
Regulator  400  W  (flush  switch  type)  complete  in  the  exg. 
Board. (Make : Oswal/Rider/Anchor) 
12  Supply  of  300  mm/1400  rpm  Heavy  duty  Exhaust  Fan  ‐ No 6 2505  15030
capacitor  start  and  run  type  motor,  continuously  rated, 
totally  enclosed  and  ruggedly  built  complete  as  per  IS 
2312/67.   Make: Almonard/Polar/Havells 
13  Fixing, Testing and commissioning of Exhaust Fan complete  No 6 165  990
including wall opening with plastering for housing Exhaust 
Fan and  wiring with  3CX1.0 Sq.mm PVC insulated copper 
cable as per IS Specification.   
14  Supply  of  Outdoor  type  corrosion  proof  fluorescent  light  No 55 1200  66000
fitting (poly carbonate for wet location) 1X36W with Lamp 
confirming to IS: 10322 part 5 sec.2/82. (similar to Havells ‐ 
Magnum 1 type)  make: Havells, Crompton, Bajaj 
15  Fixing, Testing and commissioning of Outdoor FL WT fitting  No 20 110  2200
with angular pipe bracket as desired by Engineer‐in‐charge. 
16  Supply, fixing Testing and commissioning of 450 mm (18")  No 4 5585  22340
Heavy Duty Wall mounting Air Circulators fan complete as 
per  IS‐2312/67, Make: Almonard/ Polar/Khaitan/Havells 
17  Supply, fixing, Testing & commissioning of CFL 11W fittings  No 20 388  7760
complete with Lamp. 
18  Supply, fixing, testing and commissioning of 5A Switch & 5  No 60 77  4620
pin  Socket  including  internal  wiring  in  the  exg.  Control 
Board as desired by Engineer‐in‐charge. 
19  Supply,  fixing,  testing  and  commissioning  of  Switch  &  No 15 123  1845
Socket 15 A – 5 pin with indicator including internal wiring 
in the exg. Control Board 
20  Supply,  fixing,  testing  and  commissioning  of  6‐32A  Single  No 20 120  2400
Pole  Mini  MCB  complete  in  the  exg.  Control  Board  as 
desired by Engineer‐in‐charge.    Make: Havells/Standard 
21  Supply and concealing of 16 SWG MS switch box of size 300  No 25 332  8300
x 200 x 100 mm conforming to IS : 5133 (Part – I) – 1969 
(latest)  with  3mm  decolum  laminated  Hylum  sheet  & 
suitable strip connector complete with painting 
22  Supply  and    concealing  of  16  SWG  MS  switch  box  of  size  No 25 215  5375
200 x 100 x 60 mm conforming to IS : 5133 (Part – I) – 1969 
(latest)  with  3mm  decolum  laminated  Hylum  sheet  & 
suitable strip connector complete with painting. 
23  Supply  and    concealing  of  16  SWG  MS  switch  box  of  size   No 25 108  2700
150 x 100 x 60 mm conforming to IS : 5133 (Part – I) – 1969 
(latest)  with  3mm  decolum  laminated  Hylum  sheet  & 
suitable strip connector complete with painting. 
24  Supply,  fixing,  testing  and  commissioning  of  20  A  Metal  No 10 660  6600
plug  &  Socket  (2  pole  and  Earth)  in  a  concealed  manner 

61 Volume II – Bill of Quantities


S.  Rate  Total          
Description of  work  Unit  Qty 
No  Rs.    Rs.   
with 20 A DP MCB.  Make : Standard/Havells/MDS

25  Supply,  erection,  testing  and  commissioning  of  Sheet  Iron  No 5 39600  198000
Kiosk – of size 1200 x750x450 mm  on masonry plinth with 
one  4  pole  100  A  MCCB  for    incoming,  6  nos.  of  100A  
porcelain  Fuse  unit,    Neutral/earth  link  fitted  with  Hylum 
sheet  and  space  for  provision  of  KWHr  Meter  and  other 
accessories complete   to avail 3 ph. Power Supply. 
26  Masonry  Plinth  (Mass  concrete  1:3:6  with  20  mm  metal)  Cum 10 4160  41600
foundation  for  erection  of  SI  kiosk/water  cooler  etc 
wherever required as directed by engineer in charge. 
27  Supply,  Erection,  Testing  and  commissioning  of  wall/Floor  set 2 50963  101926
Mounting Medium Tension MCCB Distribution  Board  2X6 
Way  with  cable  two  cable  alley  one  on  LHS  and  RHS  with 
One  incomer  100 A/25kA MCCB and  outgoing  MCCBs – 
4P/63A/25kA  ‐  02  Nos.,    single  pole  10‐32A‐    12  nos.  
Including  internal  wiring  with  Digital  volt  meter    0‐500V,   
Digital Ammeter  0‐300A  Energy Meter, 3 phase indication, 
Selector switches  duly with powder coated paint (Siemens 
gray) as per specifications Make : Standard/Havells & MDS) 
28  Laying, Drawing, Fixing, Testing & commissioning  of LTUG  m 2700 9  24300
Cable of various sizes in the excavated cable trench/inside 
the  RCC  Pipe/cable  duct/fixing  the  cable  on  the  roof 
tress/side  stanchion  with  suitable  clamps  and  termination 
the  cable  ends  to  the  switch/aerial  mains  with  suitable 
aluminium  socket/proper  binding  methods  as  desired  by 
Engineer‐in‐charge. 
29  Excavation of Cable trench and refilling as per specification  Cum 950 88  83600
In  all  kinds  of  soils/Concrete  surfaces/Black  topped  roads 
or elsewhere (0.45 M width and 1.0 M depth) 
30  Supply  &  commissioning  of  following  LTUG  Cable  of  XLPE  * *  * 
Insulated  PVC  sheathed  (Heavy  Duty)  Armoured  Electric 
Cable  with  Aluminium  Conductor  for  working  Voltage 
1100V confirming to IS:7098 (Part I).   
a)     3.5 Core 70 Sq.mm  m 1000 533  533000
b)     3.5 Core 25 Sq.mm  m 800 262  209600
c)     4.0 Core 16 Sq.mm  m 1500 213  319500
31  Supply  &  fixing  of  suitable  Alu.  end  Termination  socket  No 230 117  26910
with cable Gland for   XLPE LTUG cable for  item 31 above 
32  Supply  and  fixing  of  GI  wire  of  6  SWG to  run  along  with  m 3000 6  18000
LTUG cable for earth inter connections etc., 
33  Provision  of  Masonry  Inspection  pit  of    0.9    x  0.9  x  0.6  M  No 14 2925  40950
depth (Inner dimension)  for laying of cable with brick wall 
of 0.2 M thick on all the four sides with plastering and RCC 
Slab top cover of 2“ with 10mm MS rod – 5 nos. each laid 
crisscross and tied at joints.   
34  Supply  and  placing  of  L.T  cable  route  indicator  Cast  Iron  No 80 154  12320
plate type as per specification/drg. 
35  Supply  and  laying  of  RCC  Pipe  150mm  internal  diameter  m 2150 184  395600
and  25  mm  thick  with  suitable  collar  confirming  to  NP2 
class  as  per  IS  Nol.458  including  jointing  using  gunny  bag 
and  cement  grouting  in  the  already  excavated 
trench/under track 

62 Volume II – Bill of Quantities


S.  Rate  Total          
Description of  work  Unit  Qty 
No  Rs.    Rs.   
36  Supply, fixing of 50 mm dia. 'B' Class GI Pipe with suitable  m 90 355  31950
clamp  where  ever  necessary  as  desired  by  Engineer  ‐in  ‐
charge.  
37  Supply, erection, testing and commissioning of LT Earthing  No 16 1688  27008
arrangements  using  9’‐0”  long  “heavy”  classified 
Galvanized  pipe  of  50  mm  dia.  shaped  to  form  earth 
electrode,  duly  by  excavation/auguring  of  earth  pit  in  all 
kinds  of  soil/concrete  surface  or  elsewhere,.  Construction 
of  masonry  earth  pit  enclosure,  provision  of  cover  etc.  as 
per  specification/Drg.  and  complete  including 
supply/leading/laying/burring  and  concealing  of  4  SWG  GI 
wire  form  earth  electrode  to  proposed  MDB/SDB  or 
elsewhere  and  in  manner  as  directed  by  Engineer‐in‐
charge.   
38  Supply  Fixing  testing  &  commissioning  of  On  Load  phase  set 2 15400  30800
Changing  Rotary switch (Phase Selector Switch) 100A  with 
Incoming  &  Outgoing  Indicator  (R,Y,B  &  G)    enclosed  in  a 
powder coated  Sheet Steel enclosure with TPN MCCB 63A‐
1  no.  complete                      (for  Signal  Loads)    as  desired  by 
Engineer‐in‐charge. 
39  Supply  &  Fixing  of  SMC  Junction  Boxes  No 10 1254  12540
(indoor/Outdoor/recess in wall/surface) of size 430 X 265 X 
170 mm with hinged door with accessories complete with 
knockout  for  wire/Cable  entry,  earthing  bolt,  mounting 
hardware etc  for cable loop in out wherever necessary as 
directed by engineer‐in‐charge.  
40  Supply  of  Lamp  Standard  Tubular  Post125  mm  dia.  with  Set 56 8665  485240
single/double arm Bracket/Pipe bracket 200mm long made 
out of ‘C’ class M S heavy pipe suitable for providing FL/W 
T  Street  Light  fitting  complete  with  Base  Plate,  Earthing 
Bolt, etc. conforming to IS : 2713 part I to III 1980 (latest) 
Post to be fabricated and painted as per specification. 
(Drg.CEE.CN/MS/07/2004) 
41  Supply    of  Lamp  Standard  tubular    post  made  out  of  “C”  set 4 8190  32760
Class  heavy  MS  pipe  125  mm  dia.  Suitable  for  providing  ‘ 
Name  Board  ‘  light  fitting  FL/WT  fittings  1  no  along  with  
accessories  like  GI  pipe  bracket,  base  plate,  Earthing  bolt, 
etc. conforming to IS : 2713 part I to III 1980 (latest)  Post 
to  be  fabricated  and  painted  as  per  specification  (Drg. 
CEE/CN Drg.CEE.CN/MS/08/2004) 
42  Erection  and  fixing  of  Lamp  Standard  Post/Name  Board  No 60 1235  74100
Post with suitable foundation including coping and muffing 
as per technical specification/Drg. 
43  Supply, fixing, testing and commissioning of Angular Batten  No 30 145  4350
Holder with 11W CFL for staff Quarters 
44  Supply,  fixing  and  testing  of    Call  Bell/Buzzer  to  work  on  No 10 150  1500
DC/AC 230V for staff Qrs. 
45  Supply  and  fixing  of  TW  switch  board  with  3mm  Hylum  No 50 190  9500
sheet  of size 200X100 mm  (25 mm thick) in a concealed 
manner with Strip connector etc. 
46  Supply  and  fixing  of  TW  switch  board  with  3mm  Hylum  No 30 175  5250
sheet  of size 150 X 100 mm (25 mm thick) in a concealed 
manner with Strip connector etc. 

63 Volume II – Bill of Quantities


S.  Rate  Total          
Description of  work  Unit  Qty 
No  Rs.    Rs.   
47  Supply  and  fixing  of  TW  switch  board  with  3mm  Hylum  No 30 100  3000
sheet  of size 100 X 100 mm (25 mm thick) in a concealed 
manner with Strip connector etc. 
48  Supply,  Fixing,  Testing  and  commissioning  of  4  Quadrant  set 2 9848  19696
Double  door  Horizontal  type  2+4  way  MCB  Distribution 
Board in concealed manner with 3 ph Indicator, 12 nos. of 
6‐20 A MCB, one RCCB  4 pole 40 A/30 mA and neutral & 
earth  link  bars  etc  similar  to  Havells  cat. 
DHDSSNVDRZO4040 
49  Supply,  Fixing,  Testing  and  commissioning  of  SP  &  N  set 6 7250  43500
prewired    2+8  way  MCB  Distribution  Board  in  concealed 
manner  with  power  Indicator,  7  nos.  of  6‐20  A  MCB,  one 
RCCB    4  pole  40  A/30  mA    similar  to  Havells  cat.  Make 
Havells/Anchor 
50  Supply,  Fixing,  Testing  and  commissioning  of  SP  &  N  set 2 6858  13716
prewired    2+6  way  MCB  Distribution  Board  in  concealed 
manner  with  power  Indicator,  5  nos.  of  6‐20  A  MCB,  one 
RCCB    4  pole  40  A/30  mA    similar  to  Havells  cat.  Make 
Havells/Anchor 
51  Supply,  fixing,  testing  and  commissioning  of  Sintex  meter  set 7 2273  15911
box with 20 ‐ 40A Single phase KWHr Meter   
52  Supply,  fixing,  testing  and  commissioning  of    sintex  meter  set 2 3976  7952
box with  40A KWHr Three Phase Meter   
53  Supply,  Fixing,  Testing  and  commissioning  of  Switch  Fuse  No 10 1140  11400
Unit  (Re  wireable  type)  Three  pole  with  neutral  link  63 
A/415V for Staff Qrs.  Make: Havells/Kenbar/Standard 
54  Supply,  Fixing,  Testing  and  commissioning  of  Switch  Fuse  No 5 3774  18870
unit  (Re  wirable  Type)  Single  pole  and  neutral  32A/240V 
for staff Qrs.  Make; Havells/Kenbar/Standard 
55  Supply, fixing, testing and commissioning of 70w MH Lamp  No 8 7560  60480
with  suitable  control  gear  and  pipe  bracket  with  clamps 
wherever necessary.  Make Havells/Crompton/Bajaj 
Total 36,44,659
( Rupees thirty six lakhs forty four thousand six hundred and fifty nine only) 
PAYMENT CONDITIONS: 
1  For Supplied Items 80% Payment shall be made on receipt, acceptance and accountals of the materials.  
The Invoices shall be accompanied with (i) Manufacturer & Supplier's Challan.  (ii) Inspecting certificate 
by the nominated Inspecting Agency.                          
2  Another 10% payment shall be made after installation, erection, laying etc of the particular item. 
3  The remaining 10 % shall be paid after commissioning of the relevant portion of the work. 
4  Inspection charges if any  to be borne by the contractor. 
 

64 Volume II – Bill of Quantities