ANALYSIS OF RATE FOR PROVIDING/FIXING OF SINGLE LIGHTS

Analysis for one Km


S. No. Description Qty Unit Rate Amount
PART "A"

Supply and installation of GI 24 Rft high section pole


1 6"x5"x3: dia double arm with base plate 15"x15x3/4" with 22 Each 27681 608982
protected paint two coats i/c junction jox with connector

Supply and installation of 1-1/2" dia GI pipe in road


A 390 Each 263.70 102843
crossing (heavy quality) CH:23 Item22 III-e

2 FOUNDATIONS

Making foundation having kerb 1:4:8 (6" thick of 3'x3' and


RCC 1:2:4 i/c the cost of concreting of 5'x2'x2' with a ratio
22 Each 15665 344630
of 1:2:4 jobs also covers the cost of excavation of 45 Cft
cost i/c 4 Nos anchor bolts (Analysis attached)

3 EXCAVATION

Excavation of trench for cable and conducts in all type of


had and soft soil having a size of 2x2.5 i/c the cost of 16400 %0Cft 3833.30 62866
black filling with excavated warth complete in all respect

4 EARTHING AND JUNCTION BOX


Supply and installation of "B" class warthing i/c inspection
22 P.Job 3578.65 78730
chamber (Ch:24 Item68 P-151)
5 FEEDERS & CABLES
Supply and laying of PVC sheated 4 core 660/1100 volt non
amoured cables (C-24-13-C
i) 4Cx7/0.064PVC/PVC/SWA 200 P.Rft 260.15 52030
ii) 4Cx7/0.044PVC/PVC/SWA 3564 P.Rft 127.85 455657
iii) 4Cx7/0.029PVC/PVC from junction box to light fixute 792 P.Rft 60.15 47639
6 LIGHT FIXTURE

130 Watts LED light Make philips/ indal/ thorn ( white


44 Each 62345.00 2743180
LED) for 10 m high pole (Anaysis Attached)

Supply and erection of iron / aluminum cable 500 volts


main switch with triple pole and neutral and RC fuses of
7 angle iron board with 1/8"thick M.S sheet covering i/c 1 Each 2906.1 2906
bounding of earth with necessary flexible pipe and
thimbles 60/65 Amp (C-24-18-C-III)

Supply and erection of bus bars for 500 volts 8 phase A.C
supply with 4 copper bars i/c glazed porcel in bridges on
8 angle iron board fixed with rag bolts and M.S sheet box 1 Each 2712.85 2713
1.5mm thick etc complete 60 Amp with 4 coopers bars size
1.5"x1/8" (C-24-21-I)

Total= 4502177
Rate Per Pole 4490427/22= 204644

Amount of 44 Pole= 9004353


3% Contigency= 270131
P/W of Trancformer 50 KVA PEL /Scimens Made Complete= 2 No. 400000= 800000
Provision of Electrict Connection charges paid to WAPDA= 2 No. 100000 200000
G.Total 10274484
Sub Engineer Sub Divisional Officer
Road Construction Sub Division
Bahawalnagar

DESCRIPTION OF ITEM
and washed aggregate, in required sahpe and design,i/c forms, moulds, shuttring, liffting, compacting, curring

(a) (i)
Reinforced cement in roof slab, beems