Sunteți pe pagina 1din 13

QUALIFICATION PROTOCOL

INSTALLATION QUALIFICATION of
HVAC SYSTEM – LVP PLANT

Doc. No. : PV/GIQ/HVAC/001


Revised No. : 00
Date of issue :

PT. OTSUKA INDONESIA


Jl. Sumber Waras No. 25
LAWANG, MALANG, JAWA TIMUR 65216
PT. Otsuka Indonesia Page :
Jl. Sumber Waras No. 25
QUALIFICATION No : PV/GIQ/HVAC/001
LAWANG PROTOCOL Date : i
Revision No. : 00.
INSTALLATION QUALIFICATION FOR Replaced :
HVAC SYSTEM – LVP PLANT No. :-
Date :-

LIST of CONTENT

History of Revision....................................................................................................................................ii
Approval Sheet.........................................................................................................................................ii
1. OBJECTIVE.......................................................................................................................................1
2. SCOPE..............................................................................................................................................1
3. RESPONSIBILITY.............................................................................................................................1
4. PROCEDURE....................................................................................................................................1
5. QUALIFICATION DESCRIPTION......................................................................................................2
6. ITEM CHECK LIST AND QUALIFICATION.......................................................................................3
7. ACCEPTANCE CRITERIA.................................................................................................................5
List of Attachment:
Installation Qualification Form

/conversion/tmp/scratch/421418239.doc
PT. Otsuka Indonesia Page :
Jl. Sumber Waras No. 25
QUALIFICATION No : PV/GIQ/HVAC/001
LAWANG PROTOCOL Date :
ii

Revision No. : 00.


INSTALLATION QUALIFICATION FOR Replaced :
HVAC SYSTEM – LVP PLANT No. :-
Date :-

a. History of revision.
Rev. No. Date Revised item Reason Remark

b. Approval record.
No. Department Approval Date Name Signature

1. GMP Department Mukhlis

2. Engineering Department Mudjiono

3. Production Department Suhari Mukti

4. QA Director Bambang Sudiyanto

/conversion/tmp/scratch/421418239.doc
PT. Otsuka Indonesia Page :
Jl. Sumber Waras No. 25
QUALIFICATION No : PV/GIQ/HVAC/001
LAWANG PROTOCOL Date :
1

Revision No. : 00.


INSTALLATION QUALIFICATION FOR Replaced :
HVAC SYSTEM – LVP PLANT No. :-
Date :-

I. OBJECTIVE

To demonstrate that the Qualification of the new Heating Ventilation Air Conditioning system (HVAC) installed in
Clean room of Large Volume Parenteral plant of PT Otsuka Indonesia conforms to the purchase specifications
and the manufacturer literatures, and to document the information that the equipment meets specifications.

II. SCOPE

For new installation, modification, replacement, or relocation of any component of the HVAC system.

III. RESPONSIBILITY

It is the responsibility of the validation team to


a. Prepare, review, and approve this protocol prior to execution.
b. Review and approve the data collected after the protocol’s implementation.

It is the responsibility of Engineering to


a. Train maintenance mechanics in the operation and maintenance of the system.
b. Prepare SOPs on the operation, cleaning and maintenance of the system.
c. Supervising performance of the IQ

It is the responsibility of QA to
a. Approving the protocol.
b. Approving data and conclusion

IV. PROCEDURE

For each AHU, fill in the prepared checklist with the detailed mechanical and electrical specifications, drawings,
etc. (as itemized in the IQ format) for each component as listed in the IQ format.

The individual component checklist includes a space to record the information plus any deviations found during
the installation check.

Responsible person verifies that the information is complete, prepares the deviation report and the Installation
Qualification Report and, submits to QA.

/conversion/tmp/scratch/421418239.doc
PT. Otsuka Indonesia Page :
Jl. Sumber Waras No. 25
QUALIFICATION 2
No : PV/GIQ/HVAC/001
LAWANG PROTOCOL Date :
Revision No. : 00.
INSTALLATION QUALIFICATION FOR Replaced :
HVAC SYSTEM – LVP PLANT No. :-
Date :-

V. QUALIFICATION DESCRIPTION

Qualification of each terminal HEPA-filtered HVAC system is to be carried out and documented. The
documentation should include as-built drawing, commissioning record, operation and maintenance manual,
etc.
The HVAC system should have been qualified upon installation. Prior to validation and after major changes,
those parts of the HVAC systems affected should be re qualified.

HVAC System
Design

Comprehensive drawing, schematic diagrams , and specifications for the complete system defining the
operating ranges for each parameter. Verify that suitable provisions have been included for servicing and
testing HEPA filter systems; such as, DOP ports, monitoring ports, scanning access and filter changing.

Equipment

Comprehensive specifications for each HVAC unit defining its function should be available. Where
applicable, operating parameters should be specified. These may vary with each HVAC unit and may
include but no be limited to the use of the following component, each of which must be calibrated and / or
qualified as required.

Services / Utilities

Electrical

Air Handling Units


For each Air Handling Unit (AHU) installed, describe the units and prepares a list of the units, the rooms
and quality of air they supply is entered in an HVAC room matrix.

VI. ITEM CHECK LIST AND QUALIFICATION

1. HVAC System for Room 10,000 / Class II & Room 100,000 / class III

Item Specification Check method / Tester


equipment

Cooling capacity: 389,790 Btu/h Visual/ Document check


Air Conditioner unit Model : CLC P.025
Brand :Trane

Capacity : 21,000 m3/h Visual/ Document check


Booster Fan unit Static Pressure : 3” WG
/conversion/tmp/scratch/421418239.doc
PT. Otsuka Indonesia Page :
Jl. Sumber Waras No. 25
QUALIFICATION No : PV/GIQ/HVAC/001
LAWANG PROTOCOL Date :
Revision No. : 00.
INSTALLATION QUALIFICATION FOR Replaced :
HVAC SYSTEM – LVP PLANT No. :-
Date :-

Brand : Kruger

Body / Box A.H.U No Leakage Visual/ Leakage Test

Visual/ Leakage Test


Ducting Installation No Leakage

Document Check
Electric Installation Available
(P&ID)

Grounding 0.5 – 5 ohm Ear Test

Insulation Test
Insulation 500 – 1000mΩ

24” x 12” x 12”= 10 units


HEPA Filter unit
(Dimension) 24” x 48” x 5 7/8” = 7 units Measured

24” x 24” x 5 7/8” = 6 units

Medium Filter Unit


(Dimension) 24” x 24” x 12” = 6 units Measured

Pocket Filter 24 “ x 24” x 22” = 6 units Measured


24” x 12” x 22” = 3 units
Pre Filter unit 24” x 12” x 2” = 3 units Measured
(Dimension) 24” x 24” x 2” = 6 units

Filter position Conform Measured

Certificate of components Conform Document check

Air supply installation Conform Document Check/visual

Safety aspect Conform Document Check/visual


/conversion/tmp/scratch/421418239.doc
PT. Otsuka Indonesia Page :
Jl. Sumber Waras No. 25
QUALIFICATION 4
No : PV/GIQ/HVAC/001
LAWANG PROTOCOL Date :
Revision No. : 00.
INSTALLATION QUALIFICATION FOR Replaced :
HVAC SYSTEM – LVP PLANT No. :-
Date :-

2. Laminar Air Flow System (LAF)

Item Specification Check method / Tester


equipment

(2400x5400) + (1200x9600) + (2400x4800)


Laminar Air Flow 304,thickness 2 mm Visual/ Document check
16 pcs filter efficiency 99.99 %,6 no. centrifugal
fan,1 set Air Curtin glass thickness 6 mm
Capacity : 2230 m3/h Visual/ Document check
Booster Fan unit Static Pressure : 3” WG
Brand : Kruger
Body / Box A.H.U Visual/ Leakage Test
No Leakage
Ducting Installation Visual/ Leakage Test
No Leakage
Electric Installation Document Check
(P&ID) Available
Grounding 0.5 – 5 ohm Ear Test

Insulation Test
Insulation test 500 – 1000mΩ

24” x 12” x 12” = 10 units


HEPA Filter unit
(Dimension) 24” x 48” x 5 7/8” = 7 units Measured

24” x 24” x 5 7/8” = 6 units

24” x 12” x 2” = 3 units


Pre Filter unit Measured
(Dimension) 24” x 24” x 2” = 6 units

Filter position Conform Measured

Certificate of Conform Document check


components

Air supply installation Conform Document Check/visual

/conversion/tmp/scratch/421418239.doc
PT. Otsuka Indonesia Page :
Jl. Sumber Waras No. 25
QUALIFICATION No : PV/GIQ/HVAC/001
LAWANG PROTOCOL Date :
Revision No. : 00.
INSTALLATION QUALIFICATION FOR Replaced :
HVAC SYSTEM – LVP PLANT No. :-
Date :-

Safety aspect Conform Document Check/visual

Static Pressure Conform Document Check/visual

VII. ACCEPTANCE CRITERIA:

The HVAC System, its components, design and installation must comply with the protocol requirement,
machine and drawing specification, and proper assembling process.

/conversion/tmp/scratch/421418239.doc
PT. Otsuka Indonesia Page :
Jl. Sumber Waras No. 25
QUALIFICATION No : PV/GIQ/HVAC/001
LAWANG PROTOCOL Date :
Revision No. : 00.
INSTALLATION QUALIFICATION FOR Replaced :
HVAC SYSTEM – LVP PLANT No. :-
Date :-

DESCRIPTION:

1. HVAC System for Room 10,000 / Class II & Room 100,000 / class III
Equipment name HVAC system
Function Temperature, Relative Humidity , Particle, Microbial and
Differential Pressure controller
Location LVP BS LINE
Group LVP
Date February, 2006

Customer / Company ordering PT Otsuka Indonesia


Machine designation Temperature, Relative Humidity , Particle,
Microbial and Differential Pressure controller for
LVP BS clean room area
Year of construction 2005
Machine number -
Order number -

Description Quantity
Supply and install Air Conditioning split duel 1 unit
Cooling capacity : 389,790 BTU/h
Model : CLC P.025
Merk : Trane
Supply and install Booster Fan 1 unit
Capacity : 21,000 m3/h
Static Pressure : 3” WG
Merk : Kruger
Supply and install Ducting 1 lot
Supply and install Pre filter efficiency : 25 – 30 %
Supply and install Medium filter (bag filter90%) 1 unit
Supply and install Pre filter and Medium filter housing galvanized plat 1 unit
(customizing)
Supply and install HEPA filter 23 units
Supply and install HEPA filter housing galvanized plat (customizing) 23 units
Supply and install panel and cabling 1 lot
Dismantling existing equipment and ducting
Note : Air change 25 x / jam
Cable brand : Supreme
Panel brand : PT. SPLN
Filter brand : A.A.F
AC brand : Trane
Fan brand : Kruger

/conversion/tmp/scratch/421418239.doc
PT. Otsuka Indonesia Page :
Jl. Sumber Waras No. 25
QUALIFICATION No : PV/GIQ/HVAC/001
LAWANG PROTOCOL Date :
Revision No. : 00.
INSTALLATION QUALIFICATION FOR Replaced :
HVAC SYSTEM – LVP PLANT No. :-
Date :-

FORM IQ HVAC SYSTEM:

item Specification Check Result Date Checked Approved


method / by by
Tester
equipment
Cooling capacity: 389,790 Visual/
Air Conditioner Btu/h Document
unit Model : CLC P.025 check
Brand :Trane
Capacity : 21,000 m3/h Visual/
Booster Fan Static Pressure : 3” WG Document
unit Brand : Kruger check

Body / Box No Leakage Visual/


A.H.U Leakage Test

Visual/
Ducting No Leakage Leakage Test
Installation

Document
Electric Available Check
Installation
(P&ID)

Grounding 0.5 – 5 ohm Ear Test

Insulation Test
Insulation 500 – 1000mΩ

24” x 12” x 12”= 10 units


HEPA Filter
unit 24” x 48” x 5 7/8” = 7 units Measured
(Dimension)
24” x 24” x 5 7/8” = 6 units

Medium Filter
Unit 24” x 24” x 12” = 6 units Measured
(Dimension)
/conversion/tmp/scratch/421418239.doc
PT. Otsuka Indonesia Page :
Jl. Sumber Waras No. 25
QUALIFICATION No : PV/GIQ/HVAC/001
LAWANG PROTOCOL Date :
Revision No. : 00.
INSTALLATION QUALIFICATION FOR Replaced :
HVAC SYSTEM – LVP PLANT No. :-
Date :-

Pocket Filter 24 “ x 24” x 22” = 6 units Measured


24” x 12” x 22” = 3 units
Pre Filter unit 24” x 12” x 2” = 3 units Measured
(Dimension) 24” x 24” x 2” = 6 units

Filter position Conform Measured

Certificate of Conform Document


components check

Air supply Conform Document


installation Check/visual

Safety aspect Conform Document


Check/visual

CONCLUSION :

SUGGESTION:

Approved by : Reported by :

Mudjiono T. Joko Purnomo


Date : Date :

/conversion/tmp/scratch/421418239.doc
PT. Otsuka Indonesia Page :
Jl. Sumber Waras No. 25
QUALIFICATION No : PV/GIQ/HVAC/001
LAWANG PROTOCOL Date :
Revision No. : 00.
INSTALLATION QUALIFICATION FOR Replaced :
HVAC SYSTEM – LVP PLANT No. :-
Date :-

2. Laminar Air Flow System (LAF)

Description Quantity
Supply and install local Laminar Flow 1 unit
Size (2400x5400)+(1200x9600)+(2400x4800)
Merk:
Fan filter module : 50 pcs
Stainless Steel 304, thickness 2 mm
C/w - 16 pcs filter efficiency 99.99 %
- 6 no. centrifugal fan
- 1 set Air Curtin glass thickness 6 mm

CHECK LIST QUALIFICATION:

Item Specification Check Result Date Checked Approved


method / by by
Tester
equipment
(2400x5400) + (1200x9600)
Laminar Air + (2400x4800) Visual/
Flow 304,thickness 2 mm Document
16 pcs filter efficiency 99.99 check
%,6 no. centrifugal fan,1 set
Air Curtin glass thickness 6
mm
Capacity : 2230 m3/h Visual/
Booster Fan Static Pressure : 3” WG Document
unit Brand : Kruger check

Body / Box Visual/


A.H.U No Leakage Leakage Test

Ducting Visual/
Installation No Leakage Leakage Test

Electric Document
Installation Available Check
(P&ID)
Grounding 0.5 – 5 ohm Ear Test

Insulation Test
Insulation test 500 – 1000mΩ
/conversion/tmp/scratch/421418239.doc
PT. Otsuka Indonesia Page :
Jl. Sumber Waras No. 25
QUALIFICATION No : PV/GIQ/HVAC/001
LAWANG PROTOCOL Date :
Revision No. : 00.
INSTALLATION QUALIFICATION FOR Replaced :
HVAC SYSTEM – LVP PLANT No. :-
Date :-

24” x 12” x 12” = 10 units


HEPA Filter
unit 24” x 48” x 5 7/8” = 7 units Measured
(Dimension)
24” x 24” x 5 7/8” = 6 units

24” x 12” x 2” = 3 units


Pre Filter unit Measured
(Dimension) 24” x 24” x 2” = 6 units

Filter position Conform Measured

Certificate of Document
components Conform check

Air supply Document


installation Conform Check/visual

Document
Safety aspect Conform Check/visual

Document
Static Pressure Conform Check/visual

CONCLUSION :

SUGGESTION:

Approved by : Reported by :

Mudjiono T. Joko Purnomo


Date : Date :