Documente Academic
Documente Profesional
Documente Cultură
Challenges
Remedial
measures
Analysis
Positive contribution
Problems faced
4
Scope of work
SN Description Quantity
1 Earthwork incldg. 224 lakh cum
Rock cutting
2 Concreting 2 lakh cum
3 Minor bridges 76 nos
4 Major bridges 13 nos
5 Road over bridges 13 nos
6 Road under bridges 13 nos
7 Station buildings 7 nos (3 stations
with yards with long haul loops)
8 Land acquisition 1186 acres (293
acres Forest land)
9 Signalling works Involved
10 Electrical works Involved
5
Constraints faced
Land acquisition
Forestry clearance
Frequent bandhs
Failure of contracts
MAY-18
APRIL-18
FEB-18
AMRAPALI MINES
MAGADH MINES
LEGENDS
Station
Major bridge
SURFACE ROB
CONNECTION
TO GOMOH / RANCHI
ROR 7
TO GARHWA TO RANCHI
Methodology adopted for Fast Paced Construction
Quick Survey, Alignment and Land Acquisition
process
8
Methodology adopted for Fast Paced Construction
Sequencing of parallel activities
Aerial survey by
11
Innovations
Tractorofwith
UseJCB Hydra
beingfor
Trolley being
shifting
usedof as
Panel
Special Slings
used as BOBYN
rails
BRM
attached
Use oftoTruck Front wheel
Hydra for
for ballast lifted
Sleeper/Rail
unloading in
Use of Hydra for dismantling & laying of Switch (T-28)
handling track
(UTV)
12
Problems faced and remedial measures
New temporary
roads were built
No approach road
Rough weather
13
Problems faced and remedial measures contd..
Local labourers
were trained
14
Problems faced and remedial measures contd..
Alternate sources
were arranged
Eligibility criteria in
Contract provisions
need to cater to this
aspect
15
Problems faced and remedial measures contd..
Special chemicals under
skilled supervision
arranged alongwith first
aid
Poisonous insects, snakes and bees
Local festivals
Regular liasoning
with Dam authorities
Death of 2
labourers
due to
falling into
well & Dead
breakage of body
Pier cap
shuttering
PF
17
Completed photographs
Completed photographs contd..
Commissioning
20
Slipform
construction for
Major Bridges in
Western
Dedicated
Freight Corridor.
Working
Platform and
the main
assembly
Key process
Precautions
Fast Track Modular Construction
of Pier Caps at Bridges at Yamuna
& Hindon Rivers
LUDHIANA
DELHI
KOLKATA
Sanctioned projects
MUMBAI Unsanctioned projects
Well foundation
PIER CAP:-
.
Balance reinforcement fixing and shuttering .
Concreting of Pier Cap
.
ADVANTAGES
3RD DAY 4TH DAY 5TH DAY 7TH DAY 8TH DAY
Fixing of Macalloy
Lifting arrangement Concreting of Pier
bar and Universal
and Operation Cap
Beam Assembly
CONVENTIONAL METHOD
6 days 5 days 6 days 17 days 1 day
6 days
MODULAR METHOD
Click on the
Click on the
Video Clip
Image For
Video Clip
Image For
During block
RH girder will
be removed,
and boxes
will be
positioned
from one
side.
Click on the Image
For Video Clip
No.
Total depth of IBW of
LC Depth if fractured Lithology of
Recharge Structure (metres below fract
No zones (m) aquifers
ground level mbgl) ured
zones
3 - 15 Weathered
Recharge shaft Injection Bore Rock
28 150mbgl 3 15 - 90 Fractured Rock
Well (RSIBW)
101 - 150 Fractured Rock
Adoption of two vent ways with level difference in RUBs to cater for
uninterrupted passage of vehicles in case of water logging.
The probable reasons for water logging in the RUB depend upon
the location of outlet of natural drainage arrangements which are
as follows:
1)In case the outlet of the drainage has been taken to longer
length up to availability of natural drain through piping
system/open drain in which chances of chocking of the drain is
more because of longer length.
2)In case the outlet of the drainage has taken up to the nearby
bridge, where flood level (HFL) suddenly rises due to some
temporary obstruction because of dumping the debris by local
public, slipping of side slopes of stream.
3)In case the outlet of the drainage system has been taken to
percolation pit/sump, the filter media in the pit gets chocked
over a period of time which requires a periodical maintenance.
Adoption of two vent ways with level difference in RUBs to cater for
uninterrupted passage of vehicles in case of water logging.