MONTHLY PROGRESS REPORT

PROJECT : SYNTHESIS RESIDENCE KEMANG


MAIN CONTTRACTOR : PT. NUSA RAYA CIPTA
SUB CONTRACTOR : PT. ALU MAKRO KOREA
PERIODE : BULAN IV ( 01 November 2018 S/D 30 November 2018 )

Last Month This Month Up to This Month


Bekisting
No Uraian Pekerjaan Bobot (%) Progress Progress Progress
(m2) Bobot (%) Bobot (%) Bobot (%)
(%) (%) (%)
PEKERJAAN STRUKTUR PODIUM
1 LANTAI BASEMENT 4
a. Bekisting Konvensional
- Tangga 24.85 0.014% 95.00% 0.014% 0.00% 0.000% 95.00% 0.014%
b. Bekisting Konvensional
- Kolom 657.82 0.381% 90.00% 0.343% 1.53% 0.006% 91.53% 0.349%
- Retaining wall 710.44 0.412% 69.28% 0.285% 17.95% 0.074% 87.23% 0.359%
- Ground slab basement 4

SUMMARY 1,393.11 0.808% 0.642% 0.080% 0.722%


2 LANTAI BASEMENT 3
a. Bekisting Konvensional
- Slab 4,201.47 2.437% 75.14% 1.831% 4.17% 0.102% 79.31% 1.932%
- Balok 504.49 0.293% 75.14% 0.220% 4.17% 0.012% 79.31% 0.232%
- Tangga 153.14 0.089% 83.30% 0.074% 0.00% 0.000% 83.30% 0.074%
- Balok Ramp 244.11 0.142% 36.88% 0.052% 0.00% 0.000% 36.88% 0.052%
- Plat Ramp 538.15 0.312% 25.66% 0.080% 0.00% 0.000% 25.66% 0.080%
- Dinding Parapet Ramp & Void 333.79 0.194% 48.99% 0.095% 0.00% 0.000% 48.99% 0.095%
b. Bekisting Konvensional
- Kolom 1,514.96 0.879% 62.50% 0.549% 28.30% 0.249% 90.80% 0.798%
- Shearwall 877.70 0.509% 80.00% 0.407% 15.00% 0.076% 95.00% 0.484%
- Retaining wall 1,251.49 0.726% 50.89% 0.369% 5.95% 0.043% 56.84% 0.413%
- Ground slab basement 3
- GWT 611.31 0.355% 95.00% 0.337% 0.00% 0.000% 95.00% 0.337%
- STP 1,089.96 0.632% 76.00% 0.480% 0.00% 0.000% 76.00% 0.480%

SUMMARY 11,320.57 6.565% 4.495% 0.482% 4.977%


3 LANTAI BASEMENT 2
a. Bekisting Konvensional
- Slab 7,931.51 4.600% 70.14% 3.226% 7.99% 0.368% 78.13% 3.594%
- Balok 2,285.86 1.326% 70.14% 0.930% 7.99% 0.106% 78.13% 1.036%
- Tangga 97.84 0.057% 83.33% 0.047% 0.00% 0.000% 83.33% 0.047%
- Balok Ramp 118.56 0.069% 0.00% 0.000% 0.00% 0.000% 0.00% 0.000%
- Plat Ramp 263.20 0.153% 0.00% 0.000% 0.00% 0.000% 0.00% 0.000%
- Dinding Parapet Ramp & Void 163.27 0.095% 0.00% 0.000% 0.00% 0.000% 0.00% 0.000%
b. Bekisting Konvensional
- Kolom 1,536.72 0.891% 55.00% 0.490% 22.38% 0.199% 77.38% 0.690%
- Shearwall 874.35 0.507% 50.75% 0.257% 44.25% 0.224% 95.00% 0.482%
- Retaining wall 1,572.22 0.912% 18.95% 0.173% 3.58% 0.033% 22.53% 0.205%

SUMMARY 14,843.53 8.608% 5.124% 0.930% 6.054%

Page 1 of 2
MONTHLY PROGRESS REPORT
PROJECT : SYNTHESIS RESIDENCE KEMANG
MAIN CONTTRACTOR : PT. NUSA RAYA CIPTA
SUB CONTRACTOR : PT. ALU MAKRO KOREA
PERIODE : BULAN IV ( 01 November 2018 S/D 30 November 2018 )

Last Month This Month Up to This Month


Bekisting
No Uraian Pekerjaan Bobot (%) Progress Progress Progress
(m2) Bobot (%) Bobot (%) Bobot (%)
(%) (%) (%)
4 LANTAI BASEMENT 1
a. Bekisting Konvensional
- Slab 7,785.03 4.515% 64.76% 2.924% 5.27% 0.238% 70.03% 3.162%
- Balok 2,532.98 1.469% 64.76% 0.951% 5.27% 0.077% 70.03% 1.029%
- Tangga 113.44 0.066% 0.00% 0.000% 66.67% 0.044% 66.67% 0.044%
- Balok Ramp 130.97 0.076% 0.00% 0.000% 0.00% 0.000% 0.00% 0.000%
- Plat Ramp 288.49 0.167% 0.00% 0.000% 0.00% 0.000% 0.00% 0.000%
- Dinding Parapet Ramp & Void 178.87 0.104% 0.00% 0.000% 0.00% 0.000% 0.00% 0.000%
b. Bekisting Konvensional
- Kolom 1,587.18 0.920% 37.04% 0.341% 18.89% 0.174% 55.93% 0.515%
- Shearwall 1,135.35 0.658% 62.20% 0.410% 32.80% 0.216% 95.00% 0.626%
- Retaining wall 2,055.81 1.192% 27.01% 0.322% 19.98% 0.238% 46.99% 0.560%
- Capping beam - 0.000% 0.00% 0.000% 0.00% 0.000% 0.00% 0.000%

SUMMARY 15,808.11 9.168% 4.948% 0.987% 5.935%


5 LANTAI GROUND FLOOR
a. Bekisting Konvensional
- Slab 5,793.77 3.360% 18.38% 0.618% 38.84% 1.305% 57.22% 1.923%
- Balok 1,279.75 0.742% 18.38% 0.136% 38.84% 0.288% 57.22% 0.425%
- Tangga 153.09 0.089% 0.00% 0.000% 50.00% 0.044% 50.00% 0.044%
- Balok Ramp 121.12 0.070% 0.00% 0.000% 0.00% 0.000% 0.00% 0.000%
- Plat Ramp 291.64 0.169% 0.00% 0.000% 0.00% 0.000% 0.00% 0.000%
- Dinding Parapet Ramp & Void 180.82 0.105% 0.00% 0.000% 0.00% 0.000% 0.00% 0.000%
b. Bekisting Konvensional
- Kolom 846.41 0.491% 20.29% 0.100% 0.00% 0.000% 20.29% 0.100%
- Shearwall 1,265.85 0.734% 50.00% 0.367% 25.61% 0.188% 75.61% 0.555%
- Tulangan Diafragma
- Tulangan Cord
- Tulangan Collector

SUMMARY 9,932.45 5.760% 1.221% 1.826% 3.046%


6 LANTAI 1 (Bangunan Penghubung)
a. Bekisting Konvensional
- Slab 280.14 0.162% 0.00% 0.000% 0.00% 0.000% 0.00% 0.000%
- Balok 171.23 0.099% 0.00% 0.000% 0.00% 0.000% 0.00% 0.000%
- Tangga 153.91 0.089% 0.00% 0.000% 0.00% 0.000% 0.00% 0.000%
b. Bekisting Konvensional
- Kolom 120.74 0.070% 0.00% 0.000% 0.00% 0.000% 0.00% 0.000%

SUMMARY 726.02 0.421% 0.000% 0.000% 0.000%


TOTAL SUMMARY 54,023.78 31.330% 16.429% 4.305% 20.734%