Documente Academic
Documente Profesional
Documente Cultură
4/06/2018 - 4/07/2018
(R.Dutta)
Project Manager
Simplex Infrastructure Ltd.
CERTIFICATE
This is to certify that MS. BABY DIHINGIA , MR. PRAMJOT
SINGH KAPOOR , MS.MEETASHREE BORA, MS.ANANNYA
RAJLAKSHI, MR.NEELIM KONWAR, MR.AJAY KUMAR, MR.
PRATIK KUMAR,MR.ASHUTOSH ANAND ,MR. SANTANU
MALAKAR , student of Batch (Civil-3rd Year) of Tezpur
University,Tezpur attended the Summer training from 4-06-
2018 to 05-06-2018 in the project 4 - lane highway connecting
km 17.3 of NH 37A and km 182 of NH 52 between Dolabari
and Jamuguri ,Tezpur under my supervision. During Training
period his/her conduct was very good.
(R.Dutta)
Project Manager
Simplex Infrastructures Ltd.
ACKNOWLEDGMENT
We take this opportunity to extend my gratitude to NATIONAL HIGHWAY
INFRASTRUCTURE & DEVELOPMENT CORPORATION LIMITED as
well as SIMPLEX INFRASTRUCTURE LIMITED for having me provided
with an unbelievable practical learning experience during summer training. It was
indeed a pleasure to be a part of this organization.
First and foremost I would like to thank Mr. R.Dutta,Project Manager and
special thanks to Mr.Somnath,Site Engineer who supported me through inspiring
towards this report. They had provided me a nice industrial experience.
Last but not the least;I express my gratitude towards my teachers and college
friends for their kind co-operation and encouragement which help me in
completion of this training.
BABY DIHINGIA :- CIB15006
PRAMJOT SINGH KAPOOR:-CIB15008
MEETASHREE BORAH:-CIB15009
ANANNYA RAJLAKSHI:-CIB15019
NEELIM KONWAR:-CIB15025
AJAY KUMAR:-CIB15037
PRATIK KUMAR:-CIB15042
ASHUTOSH ANAND:-CIB15061
SANTANU MALAKAR:-CIB15068
VI Semester
Civil Engineering Department
Tezpur University
TABLE OF CONTENT
DESCRIPTION
Introduction to Company
Introduction to Project
Project Details
Project map
Q/A & Q /C
Batching Plant
Formwork
Project Execution
Equipments & Machines used
Ongoing work
Box Type Culvert
Pile foundation
Guide Bank
Embankment
Surveying
Guide Bank
Flyover
Duties of Project Manager
Conclusion
INTRODUCTION TO COMPANY
Simplex Infrastructures Ltd. is a diversified company established in 1924 and
executing projects in several sectors like Transport, Energy & Power, Mining,
Buildings, Marine, Real Estate etc.
Simplex is one of the construction leaders in India for nearly 90 years executing
projects with consistent quality assurance, cost control and adherence to milestones
in a safe environment as per the customer requirements. It promotes the culture of
sharing rich and varied experience with staff members, as also with clients and
thereby benefits and helps the growth of the construction fraternity and society at
large.
The Company has been closely associated with the country’s infrastructure
building with over 2600 completed projects spanning almost all the gamut of
construction industry.
PROJECT DETAILS
PROJECT:- 4 - lane highway connecting km 17.3 of NH 37A and km
182 of NH 52 between Dolabari and Jamuguri Road Project.
CLIENT:- NATIONAL HIGHWAY INFRASTRUCTURE AND
DEVELOPMENT CORPORATION.
CONSULTANT:-Getinsa Consultants-Rodic JV Consultants
TYPE OF CONTRACT :-Engineering,Procurement and
Construction(EPC basis)
CONSTRUCTION PERIOD:- 3 Years
DEFECT NOTIFICATION PERIOD:-365 days
PROJECT COMPONENT:-
Two Bridges
4-lane Highway
Flyover
PACKAGE UNDER SIMPLEX INFRASTRUCTURES LTD.:-
Batching plant
Q/A or Q/C testing laboratory
Safety
PROJECT LOCATION AND AREA :-
Connecting km 17.3 of NH 37A and km 182 of NH 52 between Dolabari
and Jamuguri
PROJECT PLAN PHOTO/MAP
https://www.wikiloc.com/outdoor-trails/4-lane-highway-connecting-km-
17-3of-nh-37a-and-km-182-of-nh-52-between-dolabari-and-jamuguri-
on-epc-20492195
SAFETY INDUCTION
Safety is very important part of any work.Most accidents can be prevented by
taking simple measures or adopting proper working procedures.It is very important
to discuss issues on safety & health that should be paid attention to an construction
sites for easy reference by the workers.If we work carefully & take appropriate
safety measures,there will definitely be fewer work injuries cases and our sites wil
become a safe & secure place to work in.It is important to educate everyonein site
regarding safety for following purposes.
Workers safety
Construction progress
Standard procedure
Legal cases
Working efficiency
Two standard guidelines are followed for health & environmental safety
ISO 14001-2004
OHAS 18001-2007
There are different color of helmet for different person at construction site:
PROCEDURE:
Take 400 gms of cement collect in a porcelain dish and add approximately 25%
of water initially to prepare the mix.
Mix the cement till uniformity of the paste achieved anf fill the mould with
tamping to remove air bubbles any inside within timeframe of 5 minutes.
Immediately after the preparation of mould keep the arrangement under
penetration needle and allowed to penetrate.
Note the reading on the gauge if it is in the range of 5 to 7mm from bottom then
the % of water added will be represented as consistenct of the cement
PROCEDURE:
Take about 400 gms of cement and add water to it approximately 0.85P where P is the
consisteny of cement of the same batch.
Mix the cement paste thoroughly to get a uniform paste and prepare the mould.
Keep the arrangement below the vicats apparatus needle to fall freely on the mould and
note the readings
Note the time taken to penetrate the needle about 5-7mm from bottom as initial Setting
time
Then change the needle and fit the final setting time needle which is having a round
shape a tip.
This is the time taken taken to keep an impression of the circular ring the mould.
RESULT:
Sl no Descriptions Unit Observation Specified
limits as
per is IS-
8112
1 Sample G 400
taken
2 Water G 29.5
required
3 Actual G 118
water
requirement
4 Time at the Hr:min 10:45am
time of
adding
water
5 Initial Hr:min 12:30pm
setting time
at
6 Final setting Hr:min 2:20pm
time at
7 Initial Min 105min >30 mins
setting time
observed
8 Final setting Min 215min >600mins
time
observed
TEST ON AGGREGRATE
NAME OF THE TEST:GRADATION TEST
IS CODE: 383-1970
Apparatus required:
1. IS sieve set
2. Weighing balance
PROCEDURE:
1. Take about 5 to 10 kg of sample for coarse aggregate and 1kg for fine aggregate
for gradation check.
2. Arrange the sieves from big to small size as per the grading required.
4. Note the weights retained on each sieve and calculate percentage passing
through each sieve.
RESULT:
TABLE FOR 20mm AGGREGATE:
IS Sieve Weight Cumulative Cum wt Total Limits
Size mm retained wt retained retained passing
gms gms % %
40 0 0 0 100 100
20 771 771 7.1 92.9 85 to
100
10 9080 9851 90.7 9.3 0 to 20
4.75 891 10742 98.9 1.1 0 to 5
TABLE FOR 10mm AGGREGATE:
IS Sieve Wt Cum. Wt Cum.Wt Total Limits
Size mm retained retained retained passing
gms gms % %
12.5 0 0 0 100 100
10.0 206 206 4.4 95.6 85 to 100
4.75 3944 4150 88.6 11.4 0 to 20
2.36 421 4571 97.6 2.4 0 to 5
OBJECTIVE:-
To determine the aggregates impact value (AIV) of aggregate.
APPARATUS:-
Steel cylinder
Hammer
Tamping rod
Mould
2.36mm sieve
PROCEDURE:-
1 .Th e a g g e r e g a t e s a mp l e i s p r e p a r e d b y f i r s t s i e v e d t h e a g g r e g a t e
a n d o b t a i n t h e portion passing 12mm sieve and retained on the 10mm sieve .
CONCLUSION:-
After conducting this experiment, we can say that it is important to test the
aggregates in order to construct a quality pavement for the highway construction.
Thus, the result of the experiment, the aggregates impact value is 24.5%. This
value is acceptable because it is between 20-30%. which classified as satisfactory
for road surfacing. The lower the value, the higher the strength of the road surface.
TEST ON SOIL
OMC & MDD TEST
OBJECTIVE
To determine moisture content and dry density relationship using heavy
compaction or modified compaction method as per IS-2720-Part-8.
APPARATUS
• Proctor mould (volume = 1000 cm3)
• Balance (capacity = 10 kg, least count = 1g)
• Oven (105 to 1100C)
• Sieve (19 mm)
• Proctor rammer (weight = 4.9 kg)
PROCEDURE
Dry the soil sample by exposing it to air or sun light.
Sieve the air dried soil through 19 mm sieve.
Add suitable amount of water with the soil and mix it thoroughly. For sandy and
gravelly soil add 3% to 5% of water. For cohesive soil the amount of water to be
added should be 12% to 16% below the plastic limit.
Weigh the mould with base plate attached to the nearest 1g. Record this weight as
‘W1’.
Attach the extension collar with the mould.
Compact the moist soil into the mould in five layers of approximately equal mass,
each layer being given 25 blows, with the help of 4.9 kg rammer, dropped from a
height of 450 mm above the soil. The blows must be distributed uniformly over the
surface of each layer.
After completion of the compaction operation, remove the extension collar and
level carefully the top of the mould by means of straightedge.
Weigh the mould with the compacted soil to the nearest 1 g. Record this weight as
‘W2’.
After weighing remove the compacted soil from the mould and place it on the
mixing tray. Determine the water content of a representative sample of the
specimen. Record the moisture content as ‘M’.
Broken up the remainder of the specimen and repeat step 5 to step 9 by adding
suitable increment of water to the soil. For sandy and gravelly soils the increment
in general is 1% to 2%. For cohesive soils the increment in general is 2% to 4%.
The total no. of determinations made shall be at least five, and the moisture
contents should be such that the optimum moisture content, at which the maximum
dry density occurs, is within that range.
CALCULATION
Bulk density, γb in g/cm3 of each compacted specimen is calculated from the
following equation.
γb = (W2-W1)/Vm
where,
W1 = Weight in g of mould + base plate
W2 = Weight in g of mould + base plate + soil
Vm = Volume of mould i.e. 1000 cm3.
Dry density, γd in g/cm3 of each compacted specimen is calculated from the
following equation.
γd = 100 γb/(100+M)
Where,
γb = Bulkdensity of soil in g/cm3.
M = Moisture content of soil
GRAPH
The dry densities, γd , obtained in a series of determinations is plotted against the
corresponding moisture content ‘M’. A smooth curve is then drawn through the
resulting points and the position of the maximum on this curve is determined,
which is called maximum dry density (M.D.D). And the corresponding moisture
content is called optimum moisture content (O.M.C.)
OBSERVATION
CALIFORNIA BEARING RATIO TEST (CBR TEST )
California bearing ratio is the ratio of force per unit area required to penetrate in to
a soil mass with a circular plunger of 50mm diameter at the rate of 1.25mm / min
APPARATUS
Moulds 2250cc capacity with base plate, stay rod and wing nut confirming to 4.1,
4.3 and 4.4 of IS: 9669-1980.
Collar confirming to 4.2 of IS: 9669-1980.
Spacer Disc confirming to 4.4 of IS: 9669-1980.
Metal rammer confirming to IS: 9189-1979.
Expansion measuring apparatus with the adjustable stem, perforated plates,
tripod confirming and to weights confirming to 4.4 of IS: 9669-1980.
Loading machine having a capacity of at least 5000kg and equipped with a
movable head or base that travels at a uniform rate of 1.25mm / min for use in
forcing the penetration plunger in to the specimen. Penetration plunger
confirming to 4.4 of IS: 9669-1980.
Dial gauge two numbers reading to 0.01mm.
IS sieves 37.50 or 22.50 or 19mm and 4.75mm.
Miscellaneous apparatus such as mixing bowl, straight edge, scales, soaking tank,
drying oven, filter paper, dishes and calibrated measuring jar.
PROCEDURE
There are two types of methods in compacting soil specimen in the CBR moulds
i. Static Compaction method.
ii. ii. Dynamic Compaction method.
The material used in the above two methods shall pass 19mm sieve for fine
grained soils and 37.50mm sieve for coarse materials up to 37.50mm.
Replace the material retained on 19mm sieve by an equal amount of material
passing 19mm sieve and retained on 4.75mm sieve
Replace the material retained on 37.50mm sieve by an equal amount of material
passing 37.50mm sieve and retained on 4.75mm sieve.
Static Compaction
In this method calculate the mass of wet soil at required moisture content to give
a desired density when compacted in a standard test mould as given below Volume
of mould = 2250cc. Weight of dry soil (W) = 2250 x MDD. m Weight of wet soil
=1+ ---------- x W 100 Weight of water = Weight of wet soil - Weight of dry soil.
m = Optimum moisture content obtained from the laboratory compaction test.
Take oven dried soil sample of calculated weight and thoroughly mix with water
(OMC) as obtained from the above equation.
Record the empty weight of the mould with base plate, with extension collar
removed (m1).
Place the correct mass of the wet soil in to the mould in five layers.
Gently compact each layer with the spacer disc.
Place a filter paper on top of the soil followed by a 5cms displacer disc.
Compact the mould by pressing it in between the platens of the compression
testing machine until the top of the spacer disc comes flush with the top of the
mould.
Held the load for about 30 seconds and then release.
In some soil types where a certain amount of rebound occurs, it may be necessary
to reapply load to force the displacer disc slightly below the top of the mould so
that on rebound the right volume is obtained.
Remove the mould from the compression testing machine.
Remove the spacer disc and weigh the mould with compacted soil (m2).
Replace the extension collar of the mould.
Prepare two more specimens in the same procedure as described above.
Dynamic Compaction
Penetration Test
After 96 hours of soaking take out the specimen from the water and remove the
extension collar, perforated disc, surcharge weights and filter paper.
Drain off the excess water by placing the mould inclined for about 15 minutes
and weigh the mould.
Place the mould on the lower plate of the testing machine with top face exposed
To prevent upheaval of soil in to the hole of surcharge weights, place 2.5kg
annular weights on the soil surface prior to seating the penetration plunger after
which place the reminder of the surcharge weights.
Set the plunger under a load of 4 kg so that full contact is established between the
surface of the specimen and the plunger.
Set the stress and strain gauges to zero.
Consider the initial load applied to the plunger as the zero load.
Apply the load at the rate of 1.25 mm / min.
Take the readings of the load at penetration of 0, 0.5, 1.0, 1.5, 2.0, 2.5, 3.0, 4, 5,
7.5, 10 and 12.5.
Raise the plunger and detach the mould from the loading equipment.
Collect the sample of about 20 to 50gms of soil from the top 30mm layer of
specimen and determine the water content in accordance with IS: 2720 (Part 4)
1973.
Examine the specimen carefully after the test is completed for the presence of
any over size soil particles, which are likely to affect the results if they happen to
be located directly below the penetration plunger.
CALCULATION OF CBR FROM LOAD PENETRATION CURVE.
Plot the load penetration curve in natural scale, load on Y - axis and penetration
on X – axis as shown in Fig: 2.9.2.
If the curve is uniformly convex upwards although the initial portion of the curve
may be concave upwards due to surface irregularities make correction by drawing
a tangent to the upper curve at the point of contra flexure.
Take the intersection point of the tangent and the X – axis as the origin. Calculate
the CBR values for penetration of 2.50mm and 5.00mm.
Corresponding to the penetration value at which CBR is to be desired, take the
corrected load values from the load penetration curve and calculate the CBR from
the equation PT x Cf California Bearing Ratio = ------------- x 100. PS
PT = Corrected unit test load corresponding to the chosen penetration from load
penetration curve
PS = Total standard load for the same depth of penetration
Cf = Proving ring correction factor.
REPORT
PRECAUTIONS
Clean the holes of the base plate and that of perforated disc thoroughly.
Align the surcharge weight with the plunger so that the plunger penetrates freely
in to the soil.
OBSERVATIONS
TESTS ON FRESH CONCRETE
CONCRETE SLUMP TEST
INTRODUCTION:-
OBJECTIVE:-
APPARATUS:-
The apparatus required for conducting Slump test essentially requires minimum
apparatus, which consists of Mettalic Mould in the shape of frustum cone, A
tamping rod with bullet end, Scale or tape for measuring the slump. Metallic sheet
for placing Slump and trowel for pouring concrete in the slump.
Frustum Cone:- Frustum cone has two different diameters one at the top and other
at the bottom. The dimensions of Frustum cone is mentioned below
S. No. Description Dimension
Tamping rod:- This rod has a Dia. of 16mm and bullet end at one side. The height
of tamping rod should be 0.6m long.
Sampling of Materials for Slump Test
Figure-2: Sampling of Materials for Slump
NOTE:
The above operation should be carried out at a place free from Vibrations or shock
and within a period of 2 minutes after sampling.
True Slump – True slump is the only slump that can be measured in the test. The
measurement is taken between the top of the cone and the top of the concrete after
the cone has been removed.
Zero Slump – Zero slump is the indication of very low water-cement ratio, which
results in dry mixes. These type of concrete is generally used for road construction.
Collapsed Slump – This is an indication that the water-cement ratio is too high, i.e.
concrete mix is too wet or it is a high workability mix, for which a slump test is not
appropriate.
Shear Slump – The shear slump indicates that the result is incomplete, and
concrete to be retested.
CONCLUSION:-
The concrete slump test measures the consistency of fresh concrete before it test. It
is performed to check the workability of freshly made concrete . Here our slump
for the given sample is 60mm and slump shape is collapsed. This is an indication
that concrete mix is too wet or it is a high workability mix, for which a slump test
is not appropriate.
WATER CONTENT
I)RAPID MOISTURE METER TEST:
PURPOSE
The purpose of this test is to determine the moisture content of soil quickly,
without having to wait for the moisture to evaporate.
SOIL SPECIMEN
This test requires about 6 g of soil sample. Sand requires no special preparation.
Coarse powders may be ground and pulverized. Cohesive and plastic soils and
material are tested with addition of stee1 balls in the pressure vessels.
EQUIPMENTS:RAPID MOISTURE METER:
The components of a rapid moisture meter :
1.SCOOP
2.BALANCE DISC
3.INDEX MARK
4.BALANCE ARM
5.STIRRUP
6.PAN
7.GAUGE 0.5%
8.DULY
9.CUP
10.U-CLAMP
11.CLAMP ACREW
PROCEDURE
The apparatus required for the test includes one metallic pressure vessel with
clamp for sealing cup and a gauge calibrated in percentage water. One counterpoint
balance, a scoop for measuring calcium carbide and three steel balls of 12.5 mm
diameter and one steel ball of 25 mm diameter.
Set up the balance and place the sample in the pan till the mark on the balance arm
mass lines up with the index mark.
Unclamp the clamping screw to move the U-clamp off the cup. Lift off the cup.
Clean the cup and the body.
Hold the body horizontally and gently deposit one level scoopful of calcium
carbide halfway inside the chamber. Then lay the chamber down without
disturbing the calcium carbide charge and transfer the soil weighed out as above
from the pan to the cup.
Holding cup and chamber approximately horizontal bring them together, without
disturbing sample or calcium carbide, bring the U clamp round and clamp the cup
tightly into place.
With the gauge downwards, shake the moisture meter up and down vigorously for
5 seconds, then quickly turn it so that the gauge is upwards, give a tap to the body
of the moisture meter to ensure that all the contents fall into the cup.
Hold the rapid moisture meter downward, again shake for 5 seconds, then turn it
with gauge upwards and tap. Hold for one minute. Repeat this for a third time.
Once more invert the rapid moisture meter and shake up and down to cool the gas.
Turn the rapid moisture meter with the gauge upwards, and dial horizontal held at
chest height when the needle comes to rest, take the reading. The readings on the
meter are the percentages of water on the wet mass basis.
Alternatively, the three smaller steel balls can be placed in the cup along with the
soil and the larger one in the body along with the absorbent and seal up the unit as
usual. Hold the rapid moisture meter vertical so that the material in the cup falls
into the body. Now holding the unit horizontally, rotate it for 10 seconds so that the
balls are rolled round the inside circumference of the body. Rest for 20 seconds.
Repeat the rotation – rest cycle until the gauge reading is constant (usually this
takes 4 to 8 min). Note the reading as usual.
Finally release the pressure slowly (away from the operator) by opening the clamp
screw and taking the cup out, empty the contents and clean the instrument with a
brush.
Calculate the water content (W) on the dry mass from the water content (M)
obtained on the wet mass basis as the reading on the rapid moisture meter, as
follows:
W = [M/(100-M)]*100
Where,
W = percent water content of the dry mass
M = percent water content of the wet mass
RESULT
TEST ON CONCRETE
COMPRESSION TEST:
OBJECTIVE:
To find compressive strength value of concrete cubes.
Required Equipment & Apparatus
150 mm Cube Moulds (with IS Mark)
Electronic Weighing Balance
G.I Sheet (For Making Concrete)
Vibrating Needle & other tools
Compressions Testing Machine
PROCEDURE:
CUBE CASTING:
Measure the dry proportion of ingredients (Cement, Sand & Coarse Aggregate) as
per the design requirements. The Ingredients should be sufficient enough to cast test
cubes
Thoroughly mix the dry ingredients to obtain the uniform mixture
Add design quantity of water to the dry proportion (water-cement ratio) and mix
well to obtain uniform texture
Fill the concrete to the mould with the help of vibrator for thorough compaction
Finish the top of the concrete by trowel & tapped well till the cement slurry comes
to the top of the cubes.
CURING:
After some time the mould should be covered with red gunny bag and put
undisturbed for 24 hours at a temperature of 27 ° Celsius ± 2
After 24 hours remove the specimen from the mould.
Keep the specimen submerged under fresh water at 27 ° Celsius. The specimen
should be kept for 7 or 28 days. Every 7 days the water should be renewed.
The specimen should be removed from the water 30 minutes prior to the testing.
The specimen should be in dry condition before conducting the testing.
The Cube weight should not be less than 8.1 Kgs
TESTING:
Now place the concrete cubes into the testing machine. (centrally)
The cubes should be placed correctly on the machine plate (check the circle marks
on the machine). Carefully align the specimen with the spherically seated plate.
The load will be applied to the specimen axially.
Now slowly apply the load at the rate of 140kg/cm2 per minute till the cube collapse.
The maximum load at which the specimen breaks is taken as a compressive load.
OBSERVATION RESULT:
1)Weight of cube= 8.27 kg
Crushing strength of the cube=868.9KN
2)Weight of cube=8.15 kg
Crushing strength of the cube=875 KN
3)Weight of cube(M35)=8.295 kg
Crushing strength of the cube=853 KN
AIM
To determine the field density of soil at a given location by sand replacement
method
REFERENCE
IS-2720-Part-28-Determination of dry density of soils in place, by the sand
replacement method
APPARATUS
Sand pouring cylinder
Calibrating can
Metal tray with a central hole
Dry sand (passing through 600 micron sieve)
Balance
Moisture content bins
Glass plate
Metal tray
Scraper tool
THEORY AND APPLICATION
Determination of field density of cohesion less soil is not possible by core cutter
method, because it is not possible to obtain a core sample. In such situation, the
sand replacement method is employed to determine the unit weight. In sand
replacement method, a small cylindrical pit is excavated and the weight of the soil
excavated from the pit is measured. Sand whose density is known is filled into the
pit. By measuring the weight of sand required to fill the pit and knowing its density
the volume of pit is calculated. Knowing the weight of soil excavated from the pit
and the volume of pit, the density of soil is calculated. Therefore, in this
experiment there are two stages, namely
Calibration of sand density
Measurement of soil density
PROCEDURE
STAGE-1 (CALIBRATION OF SAND DENSITY)
Measure the internal dimensions (diameter, d and height, h) of the calibrating can
and compute its internal volume, Vc = πd2h/4.
Fill the sand pouring cylinder (SPC) with sand with 1 cm top clearance (to avoid
any spillover during operation) and find its weight (W1)
Place the SPC on a glass plate, open the slit above the cone by operating the valve
and allow the sand to run down. The sand will freely run down till it fills the
conical portion. When there is no further downward movement of sand in the SPC,
close the slit. Measure the weight of the sand required to fill the cone. Let it be W2.
Place back this W2 amount of sand into the SPC, so that its weight becomes equal
to W1 (As mentioned in point-2). Place the SPC concentrically on top of the
calibrating can. Open the slit to allow the sand to run down until the sand flow
stops by itself. This operation will fill the calibrating can and the conical portion of
the SPC. Now close the slit and find the weight of the SPC with the remaining sand
(W3)
STAGE-2 (MEASUREMENT OF SOIL DENSITY)
Clean and level the ground surface where the field density is to be determined
Place the tray with a central hole over the portion of the soil to be tested.
Excavate a pit into the ground, through the hole in the plate, approximately 12 cm
deep (same as the height of the calibrating can). The hole in the tray will guide the
diameter of the pit to be made in the ground.
Collect the excavated soil into the tray and weigh the soil (W)
Determine the moisture content of the excavated soil.
Place the SPC, with sand having the latest weight of W1, over the pit so that the
base of the cylinder covers the pit concentrically.
Open the slit of the SPC and allow the sand to run into the pit freely, till there is no
downward movement of sand level in the SPC and then close the slit.
Find the weight of the SPC with the remaining sand (W4).
PRECAUTIONS
If for any reason it is necessary to excavate the pit to a depth other than 12 cm, the
standard calibrating can should be replaced by one with an internal height same as
the depth of pit to be made in the ground.
Care should be taken in excavating the pit, so that it is not enlarged by levering, as
this will result in lower density being recorded.
No loose material should be left in the pit.
There should be no vibrations during this test.
It should not be forgotten to remove the tray, before placing the SPC over the pit
OBSERVATIONS
Bulk density of sand: 1.310
Maximum dry density: 1.68
Optimum moisture content: 12.90
Weight of sand in cone: 963 gm
FUNCTION:-
Mixing system: - The heart of the concrete batching plant is the mixer, and there
are three types of mixers namely tilt, twin shaft and pan. Central mix concrete
batching plant is usually used JS series of twin shaft batch mixer as the main
mixer. A twin shaft mixture has higher mixing efficiency and provide an even
mixture of the concrete through the use of high horsepower motors, while ensuring
a large production. On the other hand, a tilt mixer ensures a consistency mix with
less labour and costs. Compared to twin shaft mixer, a tilt mixer doesn’t provide a
large output.
Cement silo (cement tank) is a cylindrical structure, cement silos are typically one
or two compartments, but at times up to 4 compartments in a single silo. The
bottom of the tube is supported by four legs to support the entire body positions,
and the whole warehouse is full of steel, welded while the top part has duster and
pressure relief valve.
Aggregate bins have 2 to 6 compartments for storage of various sand and
aggregate (rocks, gravel, etc.) sizes, while. Conveyors are typically between 24-48
inches wide and carry aggregate from the ground hopper to the aggregate bin, as
well as from the aggregate batcher to the charge chute.
Control System:- Concrete Plant is totally run by an operator who uses a
computer to input the required measurements of concrete. The PLC programmable
controller can control the production process with high reliability and stability. It
can control the unloading ingredients, mixing and automatic control of the whole
process of the concrete. Moreover, it also can dynamic display the process of
weighing and discharging. If there are some problems during production, the
software will detect the error and light up alarm lamp on computer screen or
indicator display, so that the operator can stop the production till problems solved.
WORKING:-
1. Once we pressed the start button, the control system of mixer is connected to an
electricity source, the operation interface of the man-machine interaction will
appear and system will begin to process initialization which includes the formula
number, concrete slump, concrete grade and productivity.
2. Each silo and weighing hopper is tested according to weighing system. Its
control system will output the signal of the amount of material to prompt the
operator to decide whether to start the control program or not.
3. The belt conveyor is initiated to transmit the aggregate to the weighing hopper;
the valve of the fly ash and cement tank should be opened and the screw conveyor
and motor initiated to transmit them into the weighing hopper;
4. The control valve of the water sump and admixture sump needs to be opened to
make water and admixture flow into the weighing hopper.
5. Once the weight of all material types meets the needs of specific amounts, the
door of the weighing hopper is opened automatically.
6. The materials will then be mixed by a concrete mixer. Once the setting time is
over, the loading door of the concrete mixer opens and the resulting mix is released
into a transport trunk and it’s finally transported to a construction site.
At the site; concrete batch plant used
has capacity to produce 0.75m^3
concrete in a single batch. The
concrete batch plant at the site is
computer aided control to assist in
fast and accurate measurement of
input constituents or ingredients. With
concrete performance so dependent on
accurate water measurement, accurate
admixture (super-plasticizer)
measurement, systems often use
digital scales for cementitious
materials, and aggregates, and
moisture probes to measure aggregate
water content as it enters the
aggregate batcher to automatically
compensate for the mix design water/cement ratio target.t Many producers find
moisture probes work well only in sand, and with marginal results on larger sized
aggregate.
Experts always suggest that proper planning should be done under expert
supervision before at concrete batching plant is ordered onto a manufacturer.
Following factors should be kept in mind while designing of a batching plant:
1. Land availability.
2. Distance of the plant from raw materials like aggregates, cement, sand, water
and chemicals.
3. Distance of the plant from a major construction sites since the concrete has to be
delivered eventually to those places.
4. Availability of trained personnel to run the plant efficiently.
DUST AND WATER POLLUTION:-
1) SIGNIFICANCE OF FORMWORK
1. Formwork constitutes 30% of cost & 60% of time in concrete
construction.
2. Quality of concrete finish and soundness of concrete depends very
much on type of formwork system.
3. Desired shape of concrete is not possible if formwork is done
properly.
4. Formwork should be properly designed fabricated and erected to
receive concrete.
5. Accident happen because of faulty formwork and scaffolding or
staging.
5.TYPES OF FORMWORK
1. Flex system-
Components of Alumunium
Kicker
Rocker
Wall panel
Slab corner
External and internal corner
Prop Length
Prop head
Stub pin
Wall tie
FORMWORK USED AT CONSTRUCTION SITE
REFERENCE:
1. Drawing
2. Technical Specifications for Civil works
3. Inspection and test plan
4. Survey Layout showing control stations
REFERENCE:
1. Drawing
2. Technical Specifications for Civil works
3. Technical Data sheet of Nitobond EP
REFERENCE:
1. Tender Specification
2. Approved Drawings
3. IS 10262,IS 3370 & IS 456
4. IS 383
EQUIPMENTS & MACHINES USED
1) Transit mixer for transporting ready mix concrete(R.M.C)
DISCHARGE CHUTE
HOPPER
USED AS A
CONVEYOR BELT
CRANE
The most standard and versatile type of crane used in construction today.
The mobile hydraulic crane consists of a steel truss or telescopic boom mounted on
a mobile platform, which could be a rail, wheeled, or even on a cat truck. The
boom is hinged at the bottom and can be either raised or lowered by cables or
hydraulic cylinders.
What makes this crane so versatile is it’s footprint and mobility. In construction
situations, it can sometimes be difficult to get close to where you need to hoist the
materials. Moving a crane into a postition that allows it to lift the material with the
correct crane capacity is effected by the footprint of the crane. The foot print is the
area required to have the crane set up it’s outriggers into position that allows it to
hoist the material while inside the crane chart requirements.
TOWER CRANE
long
horizontal
jib
Tower cranes are a modern form of balance crane that consist of the same basic
parts. Fixed to the ground on a concrete slab (and sometimes attached to the sides
of structures), tower cranes often give the best combination of height and lifting
capacity and are used in the construction of tall buildings. The base is then attached
to the mast which gives the crane its height. Further, the mast is attached to the
slewing unit (gear and motor) that allows the crane to rotate. On top of the slewing
unit there are three main parts which are: the long horizontal jib (working arm),
shorter counter-jib, and the operator's cab.
The long horizontal jib is the part of the crane that carries the load. The counter-jib
carries a counterweight, usually of concrete blocks, while the jib suspends the load
to and from the center of the crane. The crane operator either sits in a cab at the top
of the tower or controls the crane by radio remote control from the ground. In the
first case the operator's cab is most usually located at the top of the tower attached
to the turntable, but can be mounted on the jib, or partway down the tower. The
lifting hook is operated by the crane operator using electric motors to manipulate
wire rope cables through a system of sheaves. The hook is located on the long
horizontal arm to lift the load which also contains its motor.
CRAWLER TYPE CRANE
A crawler crane has its boom mounted on an undercarriage fitted with a set
of crawler tracks that provide both stability and mobility. Crawler cranes range in
lifting capacity from about 40 to 3,500 short tons (35.7 to 3,125.0 long tons; 36.3
to 3,175.1 t).
The main advantage of a crawler crane is its ready mobility and use, since the
crane is able to operate on sites with minimal improvement and stable on its tracks
without outriggers. Wide tracks spread the weight out over a great area and are far
better than wheels at traversing soft ground without sinking in. A crawler crane is
also capable of traveling with a load. Its main disadvantage is its weight, making it
difficult and expensive to transport. Typically a large crawler must be
disassembled at least into boom and cab and moved by trucks, rail cars or ships to
its next location.
HR-260
The HR 260 is a self erecting, 75 ton drilling rig particularly suitable for drilling
great diameters using the kelly bar system and with casing tubes directly with the
rotary. The HR 260 is able to perform the following applications:
- Drilling large diameters and great depths with augers or buckets
- Execution of direct rotary drilling with casings and casing oscillator
- Continuous Flight Auger (CFA) & Diaphragm Walls
- Execution of Double Head drilling
BUCKHOE LOADER
Backhoe loaders are very common and can be used for a wide variety of tasks:
construction, small demolitions, light transportation of building materials,
powering building equipment, digging holes/excavation, landscaping,
breaking asphalt, and paving roads. Often, the backhoe bucket can also be replaced
with powered attachments such as a breaker, grapple, auger, or a stump grinder.
Enhanced articulation of attachments can be achieved with intermediate
attachments such as the tiltrotator. Many backhoes feature quick coupler (quick-
attach) mounting systems and auxiliary hydraulic circuits for simplified attachment
mounting, increasing the machine's utilization on the job site. Some loader buckets
have a retractable bottom or "clamshell", enabling it to empty its load more quickly
and efficiently. Retractable-bottom loader buckets are also often used for grading
and scraping. The front assembly may be a removable attachment or permanently
mounted.
Because digging while on tires intrinsically causes the machine to rock, and the
swinging weight of the backhoe could cause the vehicle to tip, most backhoe
loaders use hydraulic outriggers or stabilizers at the rear when digging and lower
the loader bucket for additional stability. This means that the bucket must be raised
and the outriggers retracted when the vehicle needs to change positions, reducing
efficiency. For this reason many companies offer miniature tracked excavators,
which sacrifice the loader function and ability to be driven from site to site, for
increased digging efficiency.
Their relatively small frame and precise control make backhoe-loaders very useful
and common in urban engineering projects such as construction and repairs in
areas too small for larger equipment. Their versatility and compact size makes
them one of the most popular urban construction vehicles. For larger projects,
a tracked excavator is generally used.
ONGOING WORK
CULVERT:
INTRODUCTION: Culvert is a tunnel carrying a stream under a road or railway.
A culvert may act as a bridge for traffic to pass on it. They are typically found in a
natural flow of water and serves the purpose of a bridge or a current flow
controller.
TYPES OF CULVERT: Culverts are available in many and shape like round,
elliptical, flat-bottomed, pear-shaped, and box-like constructions. Following are
the different types of culvert.
Pipe culvert (single or multiple)
Pipe-Arch culvert (single or multiple)
Box culvert (single or multiple)
Arch culvert
Bridge culvert
Metal box culvert
PIPE CULVERT
Pipe culverts are the most common types of culverts due to competitive price and
easy installation. They are found in different shapes such as circular, elliptical and
pipe arch. Generally, their shapes depend on site conditions and constraints. Pipe
culverts on a small scale represent normal pipes like concrete pipes.
Arch culverts are suitable for large waterway opening where fishes can be
provided with a greater hydraulic advantage. Moreover, they provide low clearance
and are definitely, much artistic. Pipe arches are particularly useful for sites where
headroom is limited and also have a hydraulic advantage at low flows.
BOX CULVERT
Box culverts are made up of concrete and especially, RCC (Reinforced
Concrete). The most challenging part in constructing a box culvert is that dry
surface is needed for installing it. However, due to the strength of the concrete
floor, water direction can be changed when a large amount of water is expected.
This feature makes box culverts, one of the most commonly found types of the
culvert
Advantages of Box Culvert
Box Culverts are economical for the reasons mentioned below:
The box culvert is a rigid frame structure and very simple in construction
It is Suitable for non-perennial streams where scrub depth is not significant
but the soil is weak.
The bottom slab of the box culvert reduces pressure on the soil.
Box culverts are economical due to their rigidity and monolithic action and
separate foundations are not required.
It is used in special cases, weak foundation.
DESIGN DETAILS:
1.The box culvert constructed is of width 26m but recent works are being carried
on for the construction of 16m.
2.Size of the RCC box culvert at chainage of 25+ is 1/2mx3m with earth cushion
upto .
3.The diameters of reinforcements bars on bottom slab are 10mm and 12mm.
4.The diameters of reinforcements bars of top slab are 10mm are 12mm.
5.Clear cover to outermost steel is as follows:
For top slab- 50mm(top & bottom face)
For bottom- 75mm
For wall- 75mm.
6.A slope is also provided in a culvert and is called haunch. A haunch is generally
provided to distribute the hydraulic forces acting on the corners. If haunch aren’t
provided the concentrated hydrostatic forces may damage the edges.
7.Base slab thickness is 1200mm.
8.Concrete depth for culvert for base slab is 900mm(minimum).
9.Formworks provided are casing and shuttering.
10.Spacing provided in the bottom slab reinforcementsis 150/cc.
11. When the sliding forces on a structure are more than restoring forces ,the
structure has the tendency to slide laterally in the direction of sliding force as in the
case of Retaining wall ,so a shear key is provided at the bottom of wall to prevent
sliding of the wall laterally.
12.A retaining wall is provided of thickness 270mm. Retaining walls are generally
used whenever they are more economical to construct than acquiring additional
right-of-ways to extend a slope. Retaining wallsare used in both cut and fill slopes,
and this sometimes controls which wall type is used ata particular location. The
basic wall types are cast-in-place walls, precast walls and tieback walls
Method of concreting:
The concrete is prepared in the batching plant as per the required concrete mix
design and is transported to the site with the help of transit mixer. The concrete is
then poured into the formwork with the help of a conveyor belt from a height of
.If this height is exceeded then there will be segregation of concrete and also the
internal bonds between the water and concrete may be disturbed which may result
in the decrease in the strength of concrete.
PILE FOUNDATION
BORING:
Boring is drilling a hole, tunnel, or well in the earth.
Boring is used for various applications in geology, agriculture, hydrology, civil
engineering, and mineral exploration. Today, most earth drilling serves one of the
following purposes:
return samples of the soil and/or rock through which the drill passes
access rocks from which material can be extracted
access rocks which can then be measured
provide access to rock for purposes of providing engineering support.
The types of boring methods are:
Displacement Boring
Wash Boring
Auger Boring
Rotary Drilling
Percussion Drilling
Continuous Sampling
DISPLACEMENT BORING:
It is a combined method of sampling and boring operation. Closed bottom sampler
slit cup, or piston type is forced in to the ground up to desired depth. Then the
sampler is detached from soil below it, by rotating the piston, & finally the piston
is released or withdrawn. The sampler is then again forced further down & sample
is taken. After withdrawal of sampler & removal of sample from sampler, the
sampler is kept in closed condition & again used for another depth.
WASH BORING:
It is a popular method due to the use of limited equipment. The advantage of this is
the use of inexpensive and easily portable handling and drilling equipment. Here
first an open hole is formed on the ground so that the soil sampling or rock drilling
operation can be done below the hole. The hole is advanced by chopping and
twisting action of the light bit. Cutting is done by forced water and water jet under
pressure through the rods operated inside the hole.
AUGER BORING:
This method is fast and economical, using simple, light, flexible and inexpensive
instruments for large to small holes. It is very suitable for soft to stiff cohesive
soils and can be used to determine ground water table. Soil removed by this is
disturbed but it is better than wash boring, percussion or rotary drilling. This
method of boring is not suitable for very hard or cemented soils, very soft soils, as
then the flow into the hole can occur. This method is also not suitable for fully
saturated cohesionless soil.
ROTARY BORING:
Rotary drilling method of boring is useful in case of highly resistant strata. It is
related to finding out the rock strata and to access the quality of rocks from cracks,
fissures and joints. It can conveniently be used in sands and silts also. Here, the
bore holes are advanced in depth by rotary percussion method which is similar to
wash boring technique. A heavy string of the drill rod is used for choking action.
The broken rock or soil fragments are removed by circulating water or drilling mud
pumped through the drill rods and bit up through the bore hole from which it is
collected in a settling tank for recirculation. If the depth is small and the soil stable,
water alone can be used. However, drilling fluids are useful as they serve to
stabilize the bore hole.
At site: Bentonite slurry was used with a specific gravity of 1.02g/cc which is also
known as drilling fluid. The drilling fluid is used to stabilize the borehole partly
due to higher specific gravity than water and due to the formation od mud cakes on
the sides of the hole. The Torque of the machine is 260KN. The bentonite slurry
requires 24 hours for its maturity and the boring time was 8-9 hours.
PERCUSION DRILLING:
In case of hard rocks or soft rock, percussion drilling hole is usually adopted. Here
advancement of hole is done by alternatively lifting and dropping a heavy drilling
bit which is attached to the lower end of the drilling bit which is attached to the
cable.
One main disadvantage of this process is that the material at the bottom of the hole
is disturbed by heavy blows of the chisel and hence it is not possible to get good
quality undisturbed samples. It cannot detect thin strata as well.
CONTINUOUS SAMPLING:
The sampling operation advances the borehole and the boring is accomplished
entirely by taking samples continuously. The casing is used to prevent the caving
in soils. It provides more reliable and detail information on soil condition than the
other methods. Therefore, it is used extensively in detailed and special foundation
exploration for important structures.
PILE FOUNDATIONS:
A pile is basically a long cylinder of a strong material such as concrete that is
pushed into the ground to act as a steady support for structures built on top of it.
Pile foundations are used in the following situations: When there is a layer of weak
soil at the surface.
TYPES OF PILE FOUNDATIONS:
There are three types of pile foundations according to construction methods:
Driven Piles.
Cast -in-situ piles.
Driven and cast-in-situ piles.
Driven Piles: -
Driven Pile foundations can be made from concrete, steel or timber. These piles are
prefabricated before placing at the construction site. When driven piles are made of
concrete, they are precast. These piles are driven using a pile hammer.
When these piles are driven into the granular soils, they displace the equal volume
of soil. This helps in compaction of soil around the sides of piles and results in the
densification of soil. The piles which compact the soil adjacent to it is also called
as compaction pile. This compaction of soil increases its bearing capacity.
Cast-in-situ piles: -
Cast-in-situ piles are concrete pile. These piles are constructed by drilling holes in
the ground to the required depth and then filling the hole with concrete.
Reinforcements are also used in the concrete as per the requirements. These piles
are of small diameter compared to drilled piers.
Driven and cast-in-situ piles: -
Driven and cast-in-situ piles have the advantages of both driven and cast-in-situ
piles.
A steel shell of diameter of pile is driven into the ground with the aid of a mandrel
inserted into the shell. After driving the shell, the mandrel is removed, and
concrete is poured in the shell.
There is one more type of pile foundation that has been used in the construction
site which is known as shore piling.
At site: Cast-in-situ piles are used, and the design details are as follows according
to the drawing shown below:
DESIGN DETAILS OF PILE FOUNDATIONS
After the boring is done we insert the reinforcement and concreting is done with
the help of treami pipe. Then after 24 hours after concreting the casing is removed.
After completion of the construction of pile, Pile Load Test is done on the pile to
ensure the safe load capacity of piles and to detect any unusual performance
contrary to the findings of initial test.
PILE LOAD TEST:
Load tests on piles are conducted on completion of 28 days after casting of piles.
Two types of tests namely initial and routine tests, for each type of loading viz.
vertical, horizontal (lateral) pull out, are performed on piles.
STEPS:
This is a dynamic pile load test. A rectangular steel sheet is placed over the pile to
uniformly distribute the pressure on the pile. The steel sheet is reinforced with the
help of steel bars.
A cylindrical drop hammer is used in the pile load test. The hammer is attached to
a crawler type crane and it is dropped from a specified height.
The load induced by the hammer is recorded on the pile drive analyzer which is
connected at the pile foundation above the ground level.
The cylindrical hammer is held and placed the center of the pile with ropes on both
sides of the hammer.
The hammer is then allowed then to free fall on the pile and the allowable load is
recorded on the pile drive analyzer.
Normally, the coarser fill materials are placed at or near the bottom or base of the
embankment in order to provide a firm foundation for the embankment and also to
facilitate drainage and prevent saturation. The top portion of an embankment
usually is constructed of relatively high-quality, well-compacted subgrade material
that is capable of supporting the overlying pavement layers and imposed wheel
loadings without deflection or undesirable movement.
The area on which the road is going to be built on must be cleared of all
vegetation, which requires the removal of trees, shrubs and bushes. Excavation
vehicles will also dig up and remove rocks and stones from the future road's
pathway. To prevent the cleared land from erosion, control devices, including
fences, ditches and basins are installed.
Sub-grade act as a cushion for other layers i.e. In order to achieve durable road
sub-grade should be strong. Sub-grade is provided by digging up the sub-soil and
the level of the sub-grade is decided by subtracting the total thickness of the
pavement from the finished level of the road pavement. The sub-grade is
thoroughly compacted by rollers weighing 8 tonnes by sprinkling water one night
before.
Sub grade preparation
On the prepared sub-base or directly on the sub-grade, as the case may be, the
specified materials of the base course is spread and proper grade, thickness and
cross sections maintained as per design shown on the supplied drawings.
This course may be laid in one or two layers according to the total designed
thickness and the thickness of each layer should not exceed 10 cm. this component
being very important, the following steps may be taken systematically.
i. Check the defective portions/patches of the newly laid base course i.e.
soling and rectify them.
ii. Provide either bricks on end edging or earthen kerbs strong enough to
prevent the new road material from spreading outward and also to
retain water used in consolidation of the wearing course.
iii. Spread the road metal evenly over the prepared base to the specified
thickness and hand pack them so that the finished surface is brought to
the required camber.
iv. Spread the coarse aggregate over the surface and roll it dry with a
suitable roller till interlocking of the aggregate is achieved with
sufficient void space. The rolling is started from the edges and
gradually shifted towards the centre.
v. After dry rolling, spread the screening materials (stones upto 12 mm
size) with uniform rate so that voids of coarse aggregates get filled
properly. This is achieved by dry rolling and brooming alternatively,
till the voids of the coarse aggregates are filled.
vi. After spreading the screening material, sprinkle sufficient quantity of
water, sweep the surface and roll it with roller again.
vii. Now apply the binding material in two to three thick layers at a slow
and uniform rate. Each layer of binding material is rolled after adding
sufficient water. The slurry is swept in with brooms to fill the void
properly. The moving wheel of the roller should be cleaned with
water. Continue the operations of spreading of binder, sprinkling of
water, sweeping with brooms and rolling till the voids get filled and
slurry forms a wave before the moving wheel of the roller.
viii. After proper compacting allow it to dry over night. Spread a layer of
sand or earth, about 6 mm thick and roll the surface again after
sprinkling water lightly.
ix. The surface may be allowed for 7 to 10 days of curing.
Spreading binder material
While curing the pavement surface, prepare the shoulders by filling earth to the
specified cross slope and compact them properly by rolling or by tamping. Width
and thickness of the shoulder should be as per specification.
STEP ̶ 7 (Opening to traffic)
After properly drying, the road pavement may now be opened to traffic, ensuring
that the traffic is distributed uniformly over the full width of the pavement.
SURVEYING
TOTAL STATION SURVEY
A total station or total station theodolite (TST) is an electronic/optical instrument
used in modern surveying and building construction that uses electronic transit
theodolite in conjunction with electronic distance meter (EDM).
COMPONENTS OF TOTAL STATION:-
A total station is composed of four main components; EDM (Electronic Distance
Measurement), electronic theodolite,
FUNCTION:-
Angle measurement
Most total station instruments measure both horizontal and vertical angles by
means of electro-optical scanning of extremely precise digital bar-codes etched on
rotating glass cylinders or discs within the instrument. The best quality total
stations are capable of measuring angles to 0.5 arc-second. Inexpensive
"construction grade" total stations can generally measure angles to 5 or 10 arc-
seconds.
Distance measurement
Measurement of distance is accomplished with a modulated infrared carrier signal,
generated by a small solid-state emitter within the instrument's optical path, and
reflected by a prism reflector or the object under survey. The modulation pattern in
the returning signal is read and interpreted by the computer in the total station. The
distance is determined by emitting and receiving multiple frequencies, and
determining the integer number of wavelengths to the target for each frequency.
Most total stations use purpose-built glass prism (surveying) reflectors for the
EDM signal. A typical total station can measure distances with an accuracy of
about 1.5 millimetres (0.0049 ft) + 2 parts per million over a distance of up to
1,500 meters (4,900 ft).
Coordinate measurement
The coordinates of an unknown point relative to a known coordinate can be
determined using the total station as long as a direct line of sight can be established
between the two points. Angles and distances are measured from the total station to
points under survey, and the coordinates (X, Y, and Z or easting, northing
and elevation) of surveyed points relative to the total station position are calculated
using trigonometry and triangulation. To determine an absolute location a Total
Station requires line of sight observations and can be set up over a known point or
with line of sight to 2 or more points with known location, called Resection (Free
Stationing).
For this reason, some total stations also have a Global Navigation Satellite
System receiver and do not require a direct line of sight to determine coordinates.
However, GNSS measurements may require longer occupation periods and offer
relatively poor accuracy in the vertical axis.
APPLICATIONS:-
Total stations are mainly used by land surveyors and civil engineers, either to
record features as in topographic surveying or to set out features (such as roads,
houses or boundaries). They are also used by archaeologists to record excavations
and by police, crime scene investigators, private accident Reconstructionist and
insurance companies to take measurements of scenes.
Mining
Total stations are the primary survey instrument used in mining surveying.
A total station is used to record the absolute location of the tunnel walls, ceilings
(backs), and floors as the drifts of an underground mine are driven. The recorded
data are then downloaded into a CAD program, and compared to the designed
layout of the tunnel.
The survey party installs control stations at regular intervals. These are small steel
plugs installed in pairs in holes drilled into walls or the back. For wall stations, two
plugs are installed in opposite walls, forming a line perpendicular to the drift. For
back stations, two plugs are installed in the back, forming a line parallel to the
drift.
A set of plugs can be used to locate the total station set up in a drift or tunnel by
processing measurements to the plugs by intersection and resection.
Mechanical and electrical construction
Total stations have become the highest standard for most forms of construction
layout.
They are most often used in the X and Y axis to lay out the locations of
penetrations out of the underground utilities into the foundation, between floors of
a structure, as well as roofing penetrations.
Because more commercial and industrial construction jobs have become centred
around building information modeling (BIM), the coordinates for almost every
pipe, conduit, duct and hanger support are available with digital precision. The
application of communicating a virtual model to a tangible construction potentially
eliminates labour costs related to moving poorly measured systems, as well as time
spent laying out these systems in the midst of a full-blown construction job in
progress.
Meteorology
Meteorologists also use total stations to track weather balloons for determining
upper-level winds. With the average ascent rate of the weather balloon known or
assumed, the change in azimuth and elevation readings provided by the total
station as it tracks the weather balloon over time are used to compute the wind
speed and direction at different altitudes. Additionally, the total station is used to
track ceiling balloons to determine the height of cloud layers. Such upper-level
wind data is often used for aviation weather forecasting and rocket launches.
The total station has come a long way in terms of its technological complexities.
Nowadays, with robotic total stations and Automatic Target Recognition (ATR),
only one user is needed since the surveyor can remotely control his device
(although this is debatable since the instrument on occasion loses its target and
goes through a series of about-turns in an attempt to auto-find the reflector).
Moreover, the line of sight predicament is being overcome with total stations that
come integrated with GPS receivers.
2. Bubble tubes:- Bubble tubes are provided to check the level of the instrument.
Two bubble tubes are provided in a dumpy level which are arranged perpendicular
to each other on the top of the telescope. One tube is called as longitudinal bubble
tube and another is called as cross bubble tube. The instrument is said to be in
perfect position when both the bubbles of the tubes are at centre or middle of the
tube.
3. Compass:- Compass is used to determine the magnetic bearing of line. In case of
dumpy level, circular compass is provided just under the telescope. The compass
contains a pointer in it and readings are marked inside it. The pointer is set to zero
when it faces the north line from which the magnetic bearings are measured.
4. Vertical spindle:- Vertical spindle is located at the centre of the whole
instrument. The telescope can be rotated in horizontal direction with respect to
vertical spindle. The instrument is connected to the tripod stand using vertical
spindle.
5. Tribrach:- Tribrach plate is parallel to the levelling head or trivet. It is connected
to trivet by levelling screws or foot screws which can adjust the tribrach plate. The
horizontal level of the instrument can be achieved by adjusting this tribrach plate.
6. Foot screws:- Foot screws are provided to regulate the tribrach position and
hence the instrument can be levelled which is known by observing the bubble tube.
The tribrach plates can be lowered or raised using foot screws. The position of
tribrach is said to be correct when the bubble in bubble tube is at centre.
7. Levelling head:- Levelling head is also called as trivet. It contains two triangular
shaped plates which are arranged parallel to each other. Three groves are provided
at the three corners of the plates in which foot screws are supported.
8. Tripod:- Tripod is used to support the whole levelling instrument on its top. It
consists three legs which can be adjustable to required position. The legs are of
same height and they may be solid or hollow. Steel shoes are provided at the
bottom of each leg to hold the ground in a fixed position.
For computation of reduced levels of various points, two methods are used:-
Height of instrument / Height of collimation method.
Rise and fall method
Geomembrane
A geomembrane is impermeable synthetic membrane made from relatively thin
continuous polymeric sheets. Geomembrane installation as part of the construction
of a base liner system of a landfill.
FUNCTION :-
Prevents seepage in vertical direction
Prevents leaching, contains pollutants
Reinforces soil by giving tensile and shear strength
Reduces settlement
Reduces erosion
Geo bags
Geobags are sand-filled high-strength geotextile bags available in the various sizes
and are used in protection of riverbank or, in beach protection. Geobags are also
called as Geotextile Sand
Containers (GSC) which is a low cost, soft and reversible solution for shore
protection structures and for the reinforcement of existing coastal barriers and
structures. Due to their numerous strengths , the GSCs become increasingly
popular as an alternative to conventional hard structures. Geobags, are filled with
locally available sand but,sometimes with mortar and stitched manually on site to
form a bag. The Geotextiles Bag can also includes a protection layer which is
elevated UV resistant and provides protection against vandalism. Geotextiles Sand
Containers are excellent erosion control, protection and force absorbant product,
ideally for coastal, off-shore, waterfront, waterway structures, foundation and any
applications that required exceptional protection, flexibility to conform to uneven
terrain, long term durability and performance. The Geo Bags are environmental
friendly whereby they allow vegetation that provides additional protection while
creating a habitat zone.
Advantages:
Erosion control, filtration and drainage in one product for coastal, off-shore,
waterfront, waterway structures and foundation applications
Soft Rock RS includes UV resistance and an anti- vandalism protection layer
Superior to woven geotextile bags for friction properties and abrasion resistance
utilizes local fill materials
Improves installation safety due to robust nonwovens
Conforms to uneven terrain without sacrificing strength
Environmentally smart: reduces carbon footprint, creates habitat zones, minimizes
site disturbance
Transforms erosion-prone soils into erosion-resistant systems
Long-term durability and performance
ANCHOR BAR
The main requirement for safety against bond failure is to provide a sufficient
extension of the length of the bar beyond the point where the steel is required to
develop its yield stress and this length must be at least equal to its development
length. However, if the actual available length is inadequate for full development,
special anchorages must be provided, such as cogs or hooks or mechanical end
plates. Thus, adding reinforcement increases the strength in tension. The other
purpose of providing reinforcement in concrete is to hold the tension cracked
sections together.
At the jamuigiri site; Guide bank is made for stability of road embankment against
erosion due to river water. In which, First of all they place Geomembrane on
ground surface & road embankment along the river bank. Then, Geobag is placed
over the geomembrane and installing the anchor bar for safety against bond failure
of geobag and then, making a hole at every 15m interval and filling the geo bag
with Mortar of Grade M24 under pressure.
CONCLUSION
It was a wonderful learning experience at Simplex Infrastructure Ltd . at the site
from Dolabari to Jamuguri for one month at Tezpur.We gained a lot of insight
regarding almost every aspect of site.we were given exposure in almost all the
departments at the site.The friendly welcome from all the employees is
appreciating ,sharing their experience and giving their peace of wisdom which they
have gained in lon journey of work.I hope this experience will surely help me in
my future and also in shaping my career.