Documente Academic
Documente Profesional
Documente Cultură
- ANb -
WATER
AUTHORITY
RUM JUNGLE
REHABILITATION
PROJECT
Office of the
Supervising
Scientis t
M.O
POWER AND WATER AUTHORITY
RUM JUNGLE
REHABILITATIDN
PROJECT
Darwin
September 1988
ABSTRACT
151 : TJV4
CONTENTS
ABSTRACT
CONTENTS
LIST OF TABLES
LIST OF FIGURES
1. INTRODUCTION
1.1 Location
1.2 History
1.3 Scope Of The Problem
4.1 Achievements
4.2 Monitoring
6. REFERENCES
151:TJV4
LIST OF TABLES
LIST OF FIGURES
151 : TJV4
1. INTRODUCTION
'.
The Rum Jungle Rehabilitation Project , a Commonwealth
Government financed project managed by the Northern
Territory Government , was aimed at reducing the
environmental pollution that resulted from mining and
processing activities at the abandoned Rum Jungle mine
site .
1.1 Location
1.2 History
Fig.1.1
151 : TJV4
Territory Enterprises, a subsidiary of Consolidated
Zinc pty Ltd (now CRA Limited) commenced mining and
exploration at Rum Jungle on behalf of the Australian
Government . Mining was initially by underground
methods, followed in 1954 by the development of Whites
Open Cut . Mining continued until 1969 ; the sequence is
summarised in Table 1.2, and shown on a plan of the
site as Figure 1.2 .
151:TJV4
- - - - I - --- __
1--- .;.
\"¥
,
4"
II
h - - __
- ___ I
~ q :
I '
!
q
'• I
I
I
I
Heap I
J
/'
/'
/'
/'
/ LEGEND
/' /' I~
;I=I =
II AREAS OF MAJOR WORK
lSl : TJV4
2. REHABILITATION AGREEMENT AND PROJECT MANAGEMENT
2. 2 Project Management
lSl:TJV4
Various elements of the rehabilitation work were
carried out by contract. Supervision was either direct
by the project team or, in the case of the Water
Treatment Plant, by a consultant (Mining and Process
Engineering Services) •
The project team was disbanded in mid 1986 following
completion of the works. Project management for the
two year monitoring/maintenance program was provided by
Water Resources staff in the Power And Water Authority.
Three conunittees were involved in the oversight and
inter-governmental co-ordination of various aspects of
the project : Liaison Conunittee, Monitoring Committee,
and Technical Committee (Reference 3).
lSl:TJV4
3. DESIGN CRITERIA AND WORKS COMPLETED
lSl:TJV4
tack Fenc e
---~-
LEGEND
AREAS OF WATER
I II I TREATMENT AND
AREAS OF VEGETATION
a 100200S00.00100
I
... - ....
"T1
cpo
RUM JUNGLE
c.>
SITE PLAN AFTER COMPLETION OF REHABILITATION
PROBLEM· RELEASE OF POLLUTANTS
FROM WASTE ROCK HEAPS
I
SI.lt.PHUFIIC ACID
& OISSOlveo METALS
I
--SOL
~
- !----
' •• CT_ __
- -
'bet...
'.&en.-I
DEEP GROUN)WATER
SLOPES REDUCED TO A
¢==:'===_~'~~" VEiTATtON
GI'IAOIENT OF 3: '
CLAV CAPPING
,
sURF"CE AUH9':F )
CflO;:,::J=:]---
t '--1
SOil
.ucn.
- --
•...
,-
DEEP GROUNOWATER
Fig. 3.1(a)
Acid mine drainage carrying the products of the
oxidation processes entered the environment via both
the groundwater system and surface water runoff from
the heaps.
HEAP VOLUME OF
OVERBURDEN AREA
(cubic metres) (hectares)
151:TJV4
fORIGINAL TOP OF HEAP
TOP Of HEAP
ORIGINAL SURFACE
' - BERM GRADE POINT
AFTER
. ,. . .
- " ''-'_1...'---""-'----""0 _u..
'._I~
Fig, 3 , He)
Because Dysons Overburden Heap was only a relatively
small source of acid mine drainage, to maximise cost
effectiveness only the top surface was reshaped,
, covered, drained and revegetated. The batters of the
heap were not altered. Subsequent monitoring has shown
the success of these measures.
lSl:TJV4
BEFORE
AFTER
- _ ..1._ ....:;::.1"'-.-".,.. - ..
' -0.,
CONTOUIt Dlla.... _ ._ .
Fig. 3.2(a)
To protect the heap leach material from the intrusion
of water and thus prevent further oxidation, all placed
material was thoroughly compacted and filter layers
were constructed directl y above the tailings (prior to
placing the heap leach material) and on each side of
the fill against the original open cut surface and
directly beneath the cover system. Figure 3.2(b) shows
typical detail. The resultant land form was then
covered, drained and revegetated in a similar manner to
the overburden heaps.
151:TJV4
COVER z
COPPER HEAP LEACH PILE MATERIAL z MATERIALS ;;:
ALTERNATELY LAYERED WITH SUBSOIL ;;: a: ,
0 ,
a: 3 to 1
o·
o ") /----
",I (MAX.)
""
'W
... -T I
ro;,~TI
~ I......
1---'-
__ l '
...
TAANSV~ASE GRADE (MIN.) 500 THICK
ROCK BLANKeT
150mm ZONE 2A
2f)Omm ZONE 3A
300nvn ZONE , B
300mm ZONE
300mm ZONE 1A 300mm THICK
450mm ZONE
TOP SURFACE WIRE MESH MA TIRESSES
SA ITER COVER COVER
ORIGINAL
SURFACE
ORIGINAL
250mm SURFACE
. FILTER LAYER FIL TEA F ABRle
THICK ROCK BLANKET
GRANULAR
FILTER MATERIAL
FILTER FABRIC
COVER & DRAINS : TYPICAL DETAILS
150mm DIA. U.P.V.C.
CORRUGATED SLOTTED
SUBSOIL DRAIN
MIN. GRADE .1 IN 300
Figure 3.2(b) DYSONS OPEN CUT
TYPICAL CROSS SECTION
......
-
_ t ..
co.
BEFORE
AFTER
CO"'CKlII O"A* - _ _ _ _
Fig. 3 .2 (c)
The flow sheet for the water treatment plant is shown
in Figure 3 . 3(a) and c omprised:
Raw water was pumped from the open cut via a
pontoon mounted suction line with the depth
from which the water was taken being
controlled by a winch mounted on the pontoon.
Lime, which had previously been slurried with
potable water, was mixed with the raw water
in two neutralising tanks.
The neutralised water was transferred to a
primary clarifier where overflow was returned
to the open cut and underflow was transferred
to the secondary clarifier .
Flocculant was added to the neutralised water
prior to its entry to the primary clarifier
to aid settlement.
Overflow from the secondary clarifier was
transferred either as recirculating load or
to the primary clarifier as overflow and
underflow was transferred to the filter press
feed surge tank .
Liquor was transferred from the filter feed
surge tank to the filter press where the
filtrate was returned to the primary
clarifier overflow. The filter cake was
transferred to a stockpile for disposal as
landfill.
lSl : TJV4
UllllE DELIVERY TRUCK FOIltKUFT TIIUCK .m.DI,. - •
~'II'~
INSTRUIUHT
A'It DllllYEIt
l i l t J, _"
"LT£R PRESS
w.url[ ITOCkI"ILIE
-------
iIIIrXI:1I
NEUTRALlZIHIl
TANK NO . 1
'1
NEUTRALll:INIf
TANK No.2
Copper 55 60 1.5
Iron 440 0.9 1.0
Manganese 230 53 1.0
Zinc 8 6.5 5.0
Chromium 0 . 55 0 . 08 0.1
Cadmium 0 . 21 0 . 04 0.1
Arsenic 0 . 45 0.003 0.05
Barium <: 0 . 002 < 0 .002 1.0
Lead 0.5 0 . 038 1.1
Si l ver 0.11 0 . 130 0.1
Mercury < 0 . 001 < 0.001 0 . 005
Selenium < 0 . 005 < 0 . 005 0 . 001
Nickel 15 12 1.0
Cobalt 15 13 . 6 1.0
Radioactivity (pCi / L) 2363 865 5.0
pH 2.6 3.7 7.0
Calcium 445 200 1000
Sulphate 8400 2800 2000
151 : TJ V4
si tu by the direct addi tion of hydrated lime,
encouraging heavy metals to precipitate and settle to
the pit floor, and removal of the accumulated sludge
(see Figure 3.3(b». .
151 : TJV4
AERATION AND LIME ADDITION
,
LIME DELIVERY LINE
PONTOON
COMPRESSOR
... .. ..
'
" . ..,
...
.
.. . . ',' '
'
. . . .:: .: ....
.'
.' .' .
.....
'.
".. ,. " .... .
' . ' ' "
"~ ,' .
',' .
AERATION MANIFOLD
WITHDRAWAL OF PRECIPITATES
CLARIFIER
RAW WATER
PONTOON
SOWING RATE
,
kg/ha
Most Common Chloris gayana (Pioneer
Introduced rhodes grass) * 5
Species Sown: Cynodon dactylon (Speedy
green couch) 2
Paspalum notatum
(Pensacola bahia grass) 3
Brachiaria decumbens
(Signal grass) 4
Urochloa mozambicensis
(Sabi grass)* 4
Stylosanthes hamata
(Verano stylo)* 6
Stylosanthes guianensis
(Graham stylo) 4
Sown on rock Stylosanthes scabra
batters only (Seca stylo) 4
Macroptilium atropurpureum
(Siratro)*
*Denotes most successful species .
lS l : TJV4
Ryan (Reference 4) has reported that strong vigorous
pastures developed in the first season . The pastures
have repeatedly demonstrated their ability to recover
, well after dry season fires and after six months
without rain .
Ryan has found that jUdicious timing of mowing and
fertilising throughout and at the end of each wet
season has enabled the dominant species to achieve
three or four seed sets within one wet season , thereby
greatly increasing the quality of organic matter and
seed in the soil. Native species are gradually
increasing .
lSl : TJV4
4. PROJECT ACHIEVEMENTS AND THE ROLE OF MONITORING ·
4.1 Achievements
lS l : TJV 4
Establishing the extent to which the
rehabilitation program achieved the project
objectives .
151 : TJV4
120 •
~
.
Possible Pre-rehabilitation " ____
_. 73174
III
CD
c:
c:
100 Relationship y
-
~
0
~
C
<C
0
80 /
/ " ·71172
...J
a: 72173./
• Pre-rehabilitation
W
Il.
Il.
0
(.)
60
/ Annual Load
• Post-rehabilitation
(of Whites Heap)
...J
<C
:J
Z
Z
40 /
<C
20
1.82/83 • 83/ 84
.84/ 85
85 / 86
oI - ·.86/8"7
o 10 20 30 40 50 60 70 80 90 100
ANNUAL DISCHARGE (10 6 m3 )
IN EAST FINNISS RIVER AT G.S. 815097
~
~
N
e: ANNUAL COPPER LOADS IN EAST FINNISS RIVER
LEGEND
,
..-
1
2
3
5 E
~
g li:
1 '"
--10 W
-11 C
---- 12
____ 13
.._ . "
TIME (y)
Fig. 4.2(b)
shows an accelerated rate of
temperature decrease since Whites
Overburden Heap was covered,
indicating that oxidation (the
chemical process generating mobile
pollutants) has stopped .
(iv ) Monitoring of radiation levels by the
Radiation Safety Consultant during
rehabilitation . Results were used to
verify one of the Agreement objectives .
(v) Monitoring aethetic and other improvements by
P Ryan and the Conservation Commission . This
has included surveys of vegetation, erosion
hazard, drain stability, rock batter
stability, soil fauna and trees growth on
overburden heaps.
lS l : TJV4
5. SITE MANAGEMENT PLAN
151 : TJV4
6. REFERENCES
151:TJV4