Sunteți pe pagina 1din 25

Preliminary Hazard Identification Plan (HIP)

Installation of new set of pumps & associated electrical / instrument jobs in Juaymah gas plant

In accordance with the Saudi Aramco Construction Safety Manual (4 th Ed., 1993), Chapter1, Section 1.3.2, a Preliminary Hazard Identification Plan (HIP) will be provided by the
Saudi Aramco Project Management Team (SAPMT) to all prospective bidders of a Saudi Aramco Project Contract. This HIP may not be complete. It is the responsibility of all
bidders to use this HIP as a starting point for development of the final HIP required of the successful bidder for inclusion in the Contractor Safety Plan. Add any other items to this
list that your company may consider as hazards or serious safety problems during the project. It will be your responsibility, if the successful bidder, to include the costs of safely
resolving these hazards and problem areas. Therefore, it is in you best interest to have as complete a list as possible prior to presenting your final bid.

HAZARD IDENTIFICATION PUNCH LIST


CONTRACTOR :
Specific RECOMMENDED ACTIONS HAZARD
NO. AREA(S) Hazards/Concerns PROPOSED ACTIONS TO THE CORRECT THE ANALYSIS
SPECIFIC HAZARDS IDENTIFIED IN COLUMN # 3
Identified A, B, C
Fire Protection Site Offices, Laydown/ A, B, & C
& Prevention :
Fabrication Yard, Right a) Site Office - Educate workers to use emergency telephone numbers
of Ways and Emergency Phone # in case of emergency.
Entire Worksite Posted

A site Laydown yard plan of the materials storage yard


shall be submitted to the SAPMT for review.
b) Lay Down Yard/
Organization Setup
c) Generator Sets Generator sets shall be grounded. Provide Fire
extinguisher as per Saudi Aramco Stds. and protect
from weather.
d) Adequate # of fire Providing portable, mobile and auxiliary fire fighting
extinguishers/type equipment for plant, industrial area, service building
area where require as per Saudi Aramco Std.

e) Training All employees shall be provided with ongoing Safety


education and training and the development of
those skills required to perform for Fire Fighting

f) Firewatch assigned Firewatch personnel shall be assigned where welding,


where required. cutting & grinding work is being done. Firewatch is to
be assigned for Firewatch purposes only.

Ref. Construction Safety Manual: Section 1.11.0 (Pg.


60) and GI 2.711, GI 1781.001.01.
Specific RECOMMENDED ACTIONS HAZARD
NO. AREA(S) Hazards/Concerns Proposed Actions To Correct The Specific ANALYSIS
Identified Hazards/Concerns Identified In Column # 3 A, B, C

Sanitation and C
Housekeeping Site Offices, Laydown/ a) Drinking Water w/ Will provide water Igloo, paper cups & trash can for
Hygiene Fabrication Yard, Right disposable paper cups & disposal off used paper cups as per require.
of Ways and trash bag
Entire Worksite
b) Toilets (proper #) One Toilet for every 15 employees shall be provided.

c) Eating facility Eating facility shall be provided, if required.


Hand soap and hand wash stations supplied with
potable water shall be provided for employees.

d) Rubbish Containers Provide Rubbish containers with proper marking and


self-closing lids clean on a daily basis.
Periodic environmental monitoring and bio-surveillance
will be used to help to protect all employees against
exposure to Safety and health hazards.
Personal Protective Fabrication/Laydown a) Hard Hats Employees must wear Hard hats to protect the head. A&B
Equipment (PPE) : Yard Right of Ways and
entire Worksite

b) Safety shoes/boots Only safety shoes/boots are allowed on site.

c) Glasses Safety glasses shall meet ANSI & Z-87 standard

d) Body Harnesses Body harnesses are required when working in areas


Fall Arrest System when no guardrail exists at heights above 1.82 mtr.
(6 ft.)

e) All PPE items shall All personal protective equipment shall comply with
meet ANSI Standards ANSI Stds. Ref. Construction Safety Manual - Section
1.9.0. (Pg. 42) and GI 8.002, GI 8.003, GI 8.005
Specific RECOMMENDED ACTIONS HAZARD
NO. AREA(S) Hazards/Concerns Proposed Actions To Correct The Specific ANALYSIS
Identified Hazards/Concerns Identified In Column # 3 A, B, C

Temporary and Site Offices, Fabrication/ a) Electrical Shock to G.F.C.I's to be used for the protection of personnel. A
Permanent . Electricity Laydown Yard, Right of Personnel
(including the use of Ways and Entire
Gen. Sets & Utility Tie- worksite
ins):
b) Grounding of Equip. Grounding shall be provided on all equipment for
protection of workers

c) Use of Lock out & Use of Lock out & hold tags as necessary per GI 6.012.
Hold tags

d) Properly Qualified Only Qualified Electricians shall maintain temporary


Electricians and permanent electrical cords and wiring
.
Inspections of tools and equipment shall be done on a
weekly basis.

e) Coordination of tie-ins Coordination of tie-ins shall be properly scheduled and


to existing or new approved by the concerned SAPMT at least two weeks
facilities with Other prior to tie-ins
contractors & PDD

f) Hazards of the operation Review the Hazards of operations with all personnel.
Use proper PPE, GFCI. Tools to be inspected prior to
the start at any job. Properly barricade the working area
and use warning signs.

Ref. Construction Safety Manual Section IV.1.2 (Pg.


277) G. I. 2.100 & GI 6.012
Specific RECOMMENDED ACTIONS HAZARD
NO. AREA(S) Hazards/Concerns Proposed Actions To Correct The Specific ANALYSIS
Identified Hazards/Concerns Identified In Column # 3 A, B, C

Heavy Equipment : Fabrication/Laydown a) Access to site Ensure the safe and expeditious movement of B
yard, Right of Ways and pedestrians and vehicles.
entire worksite
b) Traffic Flow Submit a well planned traffic flow plan to SAPMT The
Coordination and plan is to be reviewed by Loss Prevention.
Routing
c) Trenches/Excavation Provide a flagman with warning flag for control the
traffic as required. No equipment is allowed any closer
than 1.2 meters to the edge of an excavation or trench.

e) Specific Equipment Take all necessary safety precautions to avoid personnel


Operations Hazards injury or damage to vehicles and equipment.

Review hazards of the operation with all involved


personnel

f) Reversing (back-up) Back-up alarms should be provided for all Heavy


alarms on all heavy equipment.
equipment.

Cranes/SideBooms/ Fabrication/Laydown a) Lifting Procedures/ Lift plans shall be approved by a certified Rigger-I and A
Critical Lifts : yard, Right of Ways and Lift Plans submitted submitted to PMT for approval for all critical lifting
entire Worksite to PMT for approval operations.
b) Certified Riggers Provide certified Riggers for all the crane lifting.

c) Operator's Provide certification for each specific type of crane.


Certifications.

d) Crane Inspections/ Arrange for inspection for the crane inspection sticker
Certification prior to use.
e) Controlling Loads Require tag lines whenever a lift is made to control the
Suspended load.
f) Hazards of the Equip. Warning sign and warning tape shall be used around the
operation crane operational area. Ref. GI 7.028 Review Hazards
of operation with all site personnel
Specific RECOMMENDED ACTIONS HAZARD
NO. AREA(S) Hazards/Concerns Proposed Actions To Correct The Specific ANALYSIS
Identified Hazards/Concerns Identified In Column # 3 A, B, C

Existing Above and Fabrication/Laydown a) Cables unknown/ Locate, identify all the under ground cable with the A
Underground Utilities : yard, Right of Ways and suspected Cable Detector
entire worksite
b) Piping unknown/ Locate, identify and clearly mark all under ground
suspected utilities or hazards with spray paint or another visible
method.
c) Cables Existing & Review plant drawings for location of known utilities
marked obtain excavation permit from plant.

Material Handling Fabrication/Laydown a) Properly maintained/ Monthly inspection of storage yard. A


yard, Right of Ways and Organized Warehouse
entire worksite
b) Qualified Fork Truck Provide certification for Fork truck operators.
Operators

c) Proper equipment (fork Only use the fork truck as per the marked capacity of
trucks, etc.) for the the equipment.
job (terrain)
d) Improper use of forklifts Use equipment only in accordance with manufacturers
with slings or chains on recommendations.
tins.
e) Damage of equipment Only trained personnel to work around equipment.
and personnel injury.
Hauling Materials on Fabrication/Laydown a) Electrocution Unloading Equipment will not be allowed to operate
Flatbed Trucks yard, Right of Ways and b) Contact with and near powerlines with out proper permits. In some
entire worksite Damage to powerlines instances SCECO may need to issue a separate Work
c) Plant Shutdown Permit

Cranes Will not be allowed to travel under powerlines


without the boon fully retracted and lowered.

Material will not be unloaded underneath or within a


minimum of 25 feet power lines.
Before equipment is authorized to travel with plants or
under powerlines distances will be checked for adequate
clearance.
Specific RECOMMENDED ACTIONS HAZARD
NO. AREA(S) Hazards/Concerns Proposed Actions To Correct The Specific ANALYSIS
Identified Hazards/Concerns Identified In Column # 3 A, B, C

Excavation, Manholes, Fabrication/Laydown a) Shoring Slope or bench any excavation i.e. deeper than 1.2 mtr. A
Pits, Sumps, Trenching yard, Right of Ways and (4ft) if it is not feasible then use shoring the excavation
and Shoring: entire worksite as per the classification of soil "A" "B" & "C".

b) Ground Water Use de-watering pumps, if high water table affects the
excavation.
Get approval for drainage or disposal of the water.

c) Means of Access & Safe means of getting into and out of an excavation
Egress shall be provided at intervals not exceeding 7.5 mtr.
Ladders shall be placed at an angle of 75° and extend at
least 3 ft. above the stepping off point.
d) Toxic and Flammable Conduct Gas tests daily.
Gases
e) Confined Space Entry Confined space entry permits for excavations deeper
than 4 ft. (1.2 mtr.) conduct gas tests, require the use of
appropriate respiratory and other personal protective
equipment. Use Sign In and Out Logs.
f) Rescue Equip. & Scott air pack, cascade breathing air system or cartridge
Procedures respirator, if a respiratory hazards exists
Have a trained safety standby present at all times.

g) Rescue Training Conduct the necessary training for rescue.

h) Ventilation Install mechanical ventilation when necessary.

i) Excavation Plan All the excavation work shall be planned. Excavation


Approvals plans shall be submitted to SAPMT and be reviewed by
Loss Prevention as required.
j) Hazards of the Review hazards of the operation with all involved
Operation personnel.
Provide warning signs & lights around excavation in
vehicular or pedestrian through fares. Install barricades
around all excavations. Provide flagman to direct
vehicular traffic whenever persons are working in or
around an excavation. Ref. SACSM Sec. II. 2 (Pg. 96)
Specific RECOMMENDED ACTIONS HAZARD
NO. AREA(S) Hazards/Concerns Proposed Actions To Correct The Specific ANALYSIS
Identified Hazards/Concerns Identified In Column # 3 A, B, C

Concrete, Concrete Fabrication/Laydown a) Placement Procedure Mixer equipped with 0.75 cu. mt. or larger loading skips A&B
Forms & Shoring : yard, Right of Ways and shall be equipped with mechanical device to clear the
entire worksite skip of concrete.

b) Erection of form work Form work and shoring shall be designed, erected,
supported braced and maintained.

c) Removal of form work Remove and stockpile form work promptly after
stripping.

d) Working over Rebar Employees shall not be permitted to work above


protrusions vertically protruding reinforcing steel unless it has
been bent over or capped or otherwise protected .

Use only ANSI approved personal protective equipment

e) Hazards of the Review hazards of the operation with all involved


Operation personnel.
Chemicals Handling Fabrication/Laydown a) Personal Protection To protect against chemicals, oils contaminated water or A, B, & C
and Storage (including yard and entire worksite other hazards, chemical protective clothing, boots, face
MSDS's): shields, & goggles are required.

b) Storage Proper storage locations shall be provided and it is


required to clearly marked and barricaded.

c) Maintenance of the A list of hazardous chemicals should be kept indicating


MSDS log the type, qty. of material, and hazard classification.

d) Hazards of the Chemical warning labels or chemical hazard bulletins


Operation shall be used to learn of the chemical’s hazards.
Review hazards of the operation with all involved
personnel.
Specific RECOMMENDED ACTIONS HAZARD
NO. AREA(S) Hazards/Concerns Proposed Actions To Correct The Specific ANALYSIS
Identified Hazards/Concerns Identified In Column # 3 A, B, C

Hand/Power Tools : Fabrication/Laydown a) Personal Protection Safety glasses, face shield, hearing protection, hand B
yard, Right of Ways and Equip. (PPE) provided gloves etc. shall be provided for personal protection.
entire worksite
b) Safe Operating Employees trained to operate equipment must be
procedures physically fit and have full use of both hands and eyes.

c) Electrical Shock All power tools double insulated connections shall


conform to the National Electrical Code.

d) Work Permits G.F.C.I. shall be used for personal protection.

e) Cartridge operated tools Follow the work permit procedure


Only personnel trained by a manufacturer
representative shall operate cartridge operated tools.
Training records shall be maintained in the Contractors
safety office.
f) Inventory sheet Maintain records on all cartridge shots.
maintained on all
cartridge "shots"
g) All guards properly Check that protective guards are in place on all power
installed/ maintained tools with rotating parts. Maintenance logs shall be
kept.
h) Power cords in Inspect all portable electric equipment for frayed or
serviceable condition broken electric cords and other visible damage.
i) All rotating disks and The proper size and type of wheel should be fitted to the
blades properly matched tool so that the maximum permissible running speed of
to equipment. the spindle does not exceed the maximum periphery
speed displayed on the blades or disks.

j) Power tool lock-on No lock-on power switches will be allowed on the job.
devices disabled. Only dead man switch will be allowed.

k) Hazards of the Review hazards of the operation with all involved


Operation personnel.
Power tools provide greater efficiency but also create
greater risk for accident take the proper precautions
when using them. Ref SACSM- Sec. II.10.0 & II.10.3
Specific RECOMMENDED ACTIONS HAZARD
NO. AREA(S) Hazards/Concerns Proposed Actions To Correct The Specific ANALYSIS
Identified Hazards/Concerns Identified In Column # 3 A, B, C

Fuels: Fabrication/Laydown a) Proper Storage “No Smoking”/”No Open Flame” signboards place near A&B
yard, Right of Ways and containers. the Storage area.
entire worksite
b) Refilling of Fuel Cans Only approved containers shall be used for refilling of
Tanks and Equipment tanks turn off the engine when refilling.

c) Static Electricity Provide bonding wires for fuel transfer areas. Ensure
Grounding adequate grounding source exists in the area.

d) Ventilation Need good ventilation & protection from direct


sunlight.
e) Fire extinguishers Class ABC Fire extinguishers - 12.3 kg.

Road Construction Entire worksite Right of a) Review of GI 1021 Ensure safe movement of Pedestrians & vehicles A
Traffic Control Ways
Re-routing of Existing Ensure protection of workers performing construction
Roads or maintenance.
Restore the roadway to its original condition.
b) Traffic Flow Ensure proper operation of traffic control devices and
warning devices
Warning sign/flagman to be used to control/re-route the
traffic.
c) Speeding Use proper signboard to lower the speed of vehicle near
the work areas and Right of Ways.

d) Workers Safety, i.e. Use orange vests for all involved workers and flagman.
Orange vests flagman.

e) Warning Signs (day and Barricades and warning sign to be used around the
night time) working area.

f) Warning Lights Warning lights to be used at night if required to


minimize the hazards.

g) Review hazards of All personal protective measures shall be taken for


the operation with all minimizing the hazards.
Involved personnel Ref. GI 1021.000
Specific RECOMMENDED ACTIONS HAZARD
NO. AREA(S) Hazards/Concerns Proposed Actions To Correct The Specific ANALYSIS
Identified Hazards/Concerns Identified In Column # 3 A, B, C

Welding, Cutting & Fabrication/Laydown a) Oxy-Acet. Storage Cylinders should be stored only in safe, dry, well-
Brazing : yard, Right of Ways and ventilated locations
entire worksite
Shaded Storage Loc. Oxygen & Acetylene cylinder shall be stored separately.
At least 20 ft. apart or separated by a fire proof 1.6 mtr.
High partition (12mm thick). Empty & full cylinders
shall be stored separately.
b) Properly spaced

c) Bottles secured Secure the cylinders with a chain to avoid any violent
contact.
Cylinders shall be secured in an upright position.
d) Protective caps in Protective caps shall be provided well tightened.
Place

e) Gases properly Keep Gas cylinders and oxygen separated by a min. 20-
ft. distance.
Separated Segregate different types of flammable gases

f) Fire Watch assigned Fire watch man must be assigned when welding &
cutting jobs are in progress

g) Proper training for the Personnel working with welding equipment shall be B
equipment being trained, competent, and provided with personal
operated protection equipment.

h) Personal Protective Helmet, Welding hoods, hand gloves and goggles are
Equipment provided necessary to protect employees from the effect of
intense light emitted by welding operations.
Welding, Cutting & Fabrication/Laydown i) Ventilation Properly ventilated working place can minimize the
Brazing: yard, Right of Ways and hazards of welding fumes.
entire worksite
j) Correct regulator Make sure the acetylene maximum working pressure
Pressures determined is less than 15 PSI and oxygen is less than 50 PSI.

k) Equipment in good Maintain the equipment in good working condition.


state of repair
Specific RECOMMENDED ACTIONS HAZARD
NO. AREA(S) Hazards/Concerns Proposed Actions To Correct The Specific ANALYSIS
Identified Hazards/Concerns Identified In Column # 3 A, B, C

Welding, Cutting & l) Fire Extinguishers Proper types of Fire extinguishers shall be used at all the
Brazing: provided at work work location.
Location

m) Proper grounding of weld Maintain all the grounding cables and connections in good
leads as well as condition. External Ground cable to be
welding machine frame. Maintained from frame to Ground.

n) Proper shield for arc Provided proper types of protective shields for employees
welding. involved in are welding.
o) Arc welding shielded Provide Shields for welding activities.
p) Hazards of the operationReview hazards of the operation with all involved personnel.
Provided personal protective like welding hoods, goggles.
Ref. Construction Safety Manual – Section II 5.0 (Pg. 134)
and GI 401.081
Pressure Testing Cross Country Pipelines Rupture affecting Major Traffic control methods shall be planned and implemented
Pipe Cleaning /Drying and In-plant facilities Highways or Roads prior to any pressurization of piping.
Lay-up. New Construction
Traffic Control Plans Government affairs and concerned Departments shall be
Restricted Access informed prior to tests.

Communications Test personnel shall keep a safe distance from the line being
Between Long Distances tested.

Publication of schedule Personal Protective Equipment shall be worn by all personnel


in Saudi on site.
Aramco Highlights
Locations to dispose of Hydrotest water shall be approved
Letters to all concerned prior to the test.
Departments.
Chemicals used in the cleaning process shall be properly
Disposal of Test Water disposed of in approved locations.
Disposal of Chemicals Blow down areas shall be carefully chosen with consideration
used in Cleaning given to driver visibility.
Process. Obstruction of highways or public roads may result from high
Dust from Blow Down concentrations of dust generated from blow down operations.
Impacting Public Roads Pressure Gages shall be calibrated. Bleed valves shall be
Communities or provided on the test system..
operating Facilities Ref .Saudi Aramco SAES-A-004 and GI 2.102.
Specific RECOMMENDED ACTIONS HAZARD
NO. AREA(S) Hazards/Concerns Proposed Actions To Correct The Specific ANALYSIS
Identified Hazards/Concerns Identified In Column # 3 A, B, C

Scaffolding/Ladders Fabrication/Laydown a) Ladders properly Ladders shall be maintained in good condition at all
yard and entire worksite maintained times.
(items a thru e are for use Joints shall be tightened, all hardware and fitting shall
of ladders. Items f thru n be securely attached. Movable parts shall operate freely
are for scaffolding without binding or undue play.

b) ANSI approved Only ANSI approved ladders shall be used.

c) Proper angle set Use only the approved angle as per the height of the
ladder.

d) Ladders properly tied Ladders Shall be properly tied off.


off

e) Ladders extended to Ladder extent to the minimum distance is 3 ft. above the
proper distance above roofline.
roof line
f) Base Foundations Compact and level surface required for all base
foundation.
g) Loading Only one person at a time is allowed on a ladder.

h) Erection Plumb & To be erected plumb & square for level and sturdy.
Square

i) Decking Work decks are to be clear of unnecessary tools and


materials.

j) Handrails & to be Scaffolds shall be provided with handrails, midrails,


boards in place toe-boards in place to protect workers.

k) Access ladders Ladders shall be installed in a safe location .

l) Mobile scaffolding Apply all the requirements for mobile scaffolding


within the allowed within the allowed height that 12 mtr. (40 ft.)
height requirement or
properly modified
Specific RECOMMENDED ACTIONS HAZARD
NO. AREA(S) Hazards/Concerns Proposed Actions To Correct The Specific ANALYSIS
Identified Hazards/Concerns Identified In Column # 3 A, B, C

m) Competent person Advance approval for all scaffolding over 40' height to
inspections and be obtained from PMT and Loss Prevention.
approves all scaffolds Only qualified personnel shall supervise erect and
approved scaffolds.

n) Hazards of the Require barricades and warning signs to be placed at


operation ground level to warn people working below.

Review hazards of the operation with all involved


personnel Ref. Construction Safety Manual -
Section II 9.0 (Pg. 155) and GI 8.001
Slings & Rigging Entire worksite area A
Gear a) Wire rope slings Wire rope slings shall be provided properly identified
properly identified for SWL and manufacturer.

b) Regular inspections Inspections shall be done by authorized personnel and


performed on all slings the Safety Dept. shall keep the records.
c) Sling log maintained Sling log maintained by the Safety Dept. on monthly
basis.

d) Shackles properly Maintained and inspected regularly by the Safety Dept.


maintained and
inspected

e) Safe Working Load Safe working load stamp shall be provided by Mfg.
stamped on all Ref. Construction Safety Manual - Section III 2.0
lifting gear
Specific RECOMMENDED ACTIONS HAZARD
NO. AREA(S) Hazards/Concerns Proposed Actions To Correct The Specific ANALYSIS
Identified Hazards/Concerns Identified In Column # 3 A, B, C

Sandblasting : Fabrication/Laydown a) GI 6.021 reviewed & Safety meeting with all the involved employees to A&B
yard Right of Ways discussed with all discuss hazards on the job and review up-to-date
Employees involved procedures to prevent accidents.
In the operation

b) Appropriate Work The Work Permit system shall be used and gas tests
Permits obtained, i.e. shall be carried out in the area to be abrasive blast
Hot Work, Confined cleaned.
Space, etc.

c) Noise levels and proper To protect the proper hearing protection shall be used
Hearing protection when noise level exceeded 90dBA, the ear-plug or ear-
muff and warning sign shall read "Ear Protection
Required".

d) Work to be All operators of abrasive blast cleaning equipment shall


accomplished Only by be instructed and trained in the correct work methods
trained and Qualified and hazards associated with abrasive blast and cleaning
personnel equipment and materials.

e) Protective guards All protective guards and controls in place and working
Operable equipment properly in accordance with the manufacturers
recommendations.
f) Area properly Suitably barricade the area to keep unauthorized to
barricaded personnel out of the hazardous area.

g) PPE provided as Body harness required when working at the high above
required, i.e., body 1.82 mtrs. (6 ft.) ANSI approved.
Harness

h) Medical exams provided Pre-placement professional medical examination


to employees including including Chest X-rays and a pulmonary functions
Chest x-rays. study.

i) Approved Supplied Air Provide air supplied hood type "CE" and supplied air
Respirator respirator approved by NIOSH.
Specific RECOMMENDED ACTIONS HAZARD
NO. AREA(S) Hazards/Concerns Proposed Actions To Correct The Specific ANALYSIS
Identified Hazards/Concerns Identified In Column # 3 A, B, C

Sandblasting : j) Supplied Breathing Air Breathing air shall meet the requirements of and be
complies with GI tested in accordance with GI 8.003 Breathing apparatus.
8.003

k) Equipment properly Equipment shall be properly bonded or grounded for


bonded/grounded personal protection.

l) "Deadman" switch "Deadman” switch shall be in operable condition


operable
m) Proper ventilation in The recommended ventilation requirement for various
all confined spaces vessel capacities are shown in Table II.6; ref. SAES-H-
102 Shall be followed.
n) Residue properly Advance approval for disposal of residue.
disposed of as directed
by area
Industrial Hygiene Ref. Construction Safety Manual - Section II 11.0 (Pg.
Services 220) and GI 6.021
Paints and Coatings : Fabrication/Laydown a) Review the MSDS on A copy of the MSDS should be obtained for all material A
yard, Right of Ways and all paints and coatings used studied carefully and the required safety
entire worksite to be applied precaution shall be implemented
b) Survey work area to Over Spray Shall Be Controlled By The
determine : Installation Of Protective Tarps Around The Area
1) ventilation Ventilation shall be used for all operations involving the
requirements application of coating materials, and the paint curing/
drying process.
2) LEL A LEL test shall be obtained in the area near opened
solvent containers and near the nozzle of a spray
painting gun in operations.

c) Determine proper Only cleaning and preparation methods using as per the
surface cleaning and Construction Safety Manual.
preparation methods.
d) Provide proper PPE Only ANSI approved PPE shall be used.
e) Orient personnel to All workmen spray painting shall wear chemical
hazards involved. cartridge respirators or airline hoods depending upon
the hazards of the paint and other PPE. Ref. C.S.M. -
Sec. II 11.0 (Pg. 220)
Specific RECOMMENDED ACTIONS HAZARD
NO. AREA(S) Hazards/Concerns Proposed Actions To Correct The Specific ANALYSIS
Identified Hazards/Concerns Identified In Column # 3 A, B, C

Mechanical (Heavy) Fabrication/Laydown a) Work Permits obtained The Operator is Required to have a Hot Work Permit for A
Equip. yard, Right of Ways and the operation of his equipment.
entire worksite
b) Personnel qualified and Only certified operators will be allowed to operate
trained to operate heavy equipment.
equipment.

c) Equipment belts and Belts and gears guarded inspected daily basis by
gears guarded authorized person.
d) Equipment in good state Keep the records for all equipment pertaining to the
of repair, maintenance. Only qualified mechanics shall be
including emergency shut authorized to make repairs.
down devices.
e) PPE provided to Use the approved PPE for all employees involved with
employees the equipment.
f) Fire Extinguisher Keeping Fire extinguishers in proper place and shall be
provided with equipment. inspected by authorized person by monthly basis.

g) Locking pins utilized on Make sure the locking pins are used to minimize the
air line/hose potential for accidents
Connections Or personal injury. Ref. Construction Safety Manual –
Section III 3 (Pg. 257)
Liquid Petroleum Gas : Fabrication/Laydown a) Cylinder Storage. Cylinder shall be stored only in a safe, dry, well- A
(continued) yard, and entire worksite ventilated location.

b) Warning signs in place Warning signs and barricades around the storage area.
c) Bottles are to be kept Keep away the gas cylinder out of the excavations and
away from excavations confined spaces.
and confined spaces
Specific RECOMMENDED ACTIONS HAZARD
NO. AREA(S) Hazards/Concerns Proposed Actions To Correct The Specific ANALYSIS
Identified Hazards/Concerns Identified In Column # 3 A, B, C

Live Plant Operations Ras Tanura a) Specific Work Permit The Work Permit Receiver must first obtain an appropriate
requirements Work Permit from the operations supervisor before starting
Abqaiq any work. Contract personnel will follow all RIMs/OIM’s

Juaymah
b) Operation of plant valves Under no circumstance will the contractor operate any valves,
Shedgum and switches switches; equipment or other devices in an operating area. If
the work dictates such action, the contractor supervisor will
call the in-charge operation supervisor to perform the service.

If the job involves work on equipment that is in service, a


c) Live equipment specific set of written procedures will have to be prepared
and approved in advance by the Operations Safety personnel.

The contractor will have to with agree with and follow this
procedure and shall not deviate unless prior approval is
obtained from the operations supervisor. The contractor will
ensure close supervision and monitoring on this type of job.

Emergency reporting Emergency Procedures will be developed and followed.


procedures Reporting of any fires or leaks will be as per the contractors
approved emergency reporting procedures.
d)

Confined Space Entry Excavations over 4 feet a) Atmospheric Testing Work Permit procedures shall be implemented in all confined
space locations.
Tanks Vessels Atmospheric tests shall be conducted.

Large Bore Piping b) Established Approved Confined Space Procedures shall be developed and approved
Procedures by SAPMT
c) Emergency procedures Emergency rescue and assistance procedures shall be
developed and followed.
d) Rescue training Personnel shall be trained in the confined space entry
procedures.
e) Ventilation Adequate ventilation shall be provided. Air movers or
blowers will be used if required. Special attention will be
f) Heat Stress given to address heat stress. Rotation of personnel in/out of
high heat jobs may be required. Specific limits on the amount
of time spent in high heat locations needs to be determined &
Specific RECOMMENDED ACTIONS HAZARD
NO. AREA(S) Hazards/Concerns Proposed Actions To Correct The Specific ANALYSIS
Identified Hazards/Concerns Identified In Column # 3 A, B, C

the maximum limits adhered to.


Specific RECOMMENDED ACTIONS HAZARD
NO. AREA(S) Hazards/Concerns Proposed Actions To Correct The Specific ANALYSIS
Identified Hazards/Concerns Identified In Column # 3 A, B, C

Steel Erection Structural Steel Shelters a) Danger from falls. Wherever possible, a safe working platform will be
b) Improperly erected and provided through use of properly erected scaffolding and
Pipe Racks maintained scaffolding. ladders.
Scraper Traps

c) Defective erection All operations involving lifting equipment will follow


equipment and procedures outlined in this plan.
accessories.
d) Failure to follow The use of safety personal devices by all personnel
precautions for lifting performing the erection, especially the use of safety belts,
equipment.
will be enforced.
e) Non-use of personal Secured permanent connections (bolting/welding) between
protection devices, i.e. steel members precast panels will have been completed
hard hats, gloves,
goggles, safety harnesses, before the crane releases the lifted load.
etc.
f) Unsecured permanent and Erection area will be clear of unnecessary materials to allow
temporary connections safe access and egress.
(bolting/ welding) which
can allow materials Heavy Lift Procedures will be observed when
to fall
unexpectedly. required.
g) Unqualified supervisors Guy wires will be used until such time as the structure is
carrying out the work. completely stable and no danger of collapse or component
failure exists. Guy wires shall be attached to immovable
objects such as cast in Anchor bolts.

Steel will be erected per the manufacturers supplied


erection drawings. Plumb and align first bay before
proceeding. Use High Strength Bolts where appropriate
and required. Tighten High Strength Bolts AFTER final
alignment.

Demolition Existing Facilities a) Asbestos or hazardous Identification of original construction/plant equip. materials
Where Required materials identification. & coatings shall be made to rule out or identify Asbestos
Specific RECOMMENDED ACTIONS HAZARD
NO. AREA(S) Hazards/Concerns Proposed Actions To Correct The Specific ANALYSIS
Identified Hazards/Concerns Identified In Column # 3 A, B, C

Containing Materials, PCB’s, Lead, Heavy Metals or other


b) Falling objects. hazardous materials. Protective measures shall be employed
to prevent falling materials from injuring workers below.
c) Full Disconnection of all All utilities shall identified and disconnected prior to
utility services is not demolition.
completed or identified
d) Adjacent structures or Adjacent buildings shall be protected from demolition
lines are not protected. activities.
e) The area is not fenced or Demolition areas shall be fenced to prevent unauthorized
barricaded. entry.
Prior Approval of the of Demolition plans shall be reviewed and approved by SAPMT.
f)
Contractors Plan Debris shall be disposed of in approved locations.
Lead/Heavy Metal See Lead Contamination Recommendations
g) exposure
Lead Contamination Storage Tanks a) Exposure to lead and Conduct tests and sampling Identify hazards and
associated health exposure levels.
Soil Within Diked Areas effects
Near Tanks or Loading b) Develop
Racks, Comprehensive
Welding on Existing Procedures to protect
Structures employees against
exposure All Employees will undergo preliminary Blood Lead
Level (BLL) Testing to determine preliminary BLL’s
c) Medical Concerns
Blood Testing Monthly Blood Tests will be conducted on employees to
Preliminary, determine if any increase has occurred based on initial
Interim documented BLL’s
Post-work,
Physical Exams After conclusion of the work an exit blood test will be
d) Safe Work Practices conducted to determine the employees final BLL’s
Selection of PPE
Gloves Physical Exams for all involved personnel to determine
Coveralls their ability to perform the work, wear required
Boots Respiratory Protection Equipment etc.
Respiratory
Protection All PPE selected for use will be suitable for work with
Equip. Selection the associated with the chemicals agents and provide
e) Industrial Hygiene adequate and protection of employees.
Air Sampling,
Specific RECOMMENDED ACTIONS HAZARD
NO. AREA(S) Hazards/Concerns Proposed Actions To Correct The Specific ANALYSIS
Identified Hazards/Concerns Identified In Column # 3 A, B, C

Soil Sampling Preliminary sampling of the affected area will be


Personnel conducted to determine the actual levels of potential
Monitoring Program exposure. Ongoing monitoring of employees will be
Hygiene Facilities conducted to monitor the exposure levels they are
Provided on Site subjected to and determine whether the PPE remains
Daily adequate.
Decontamination.
Waste Water, and Onsite Decontamination facilities will be provided
Solid Waste including showers and laundry facilities if required.
Management Plans Waste management plans will be developed and
Identify Approved submitted to Saudi Aramco Environmental engineering
Disposal Locations Dept.
Material Handling
Specific RECOMMENDED ACTIONS HAZARD
NO. AREA(S) Hazards/Concerns Proposed Actions To Correct The Specific ANALYSIS
Identified Hazards/Concerns Identified In Column # 3 A, B, C

Thrust Boring Where required: a) Excavation of Properly engineered shoring plans shall be developed
Thrusting and and approved by SAPMT and reviewed by Loss
Major Highways Receiving Pits Prevention where sloping and benching methods are not
Operation of practical.
Public Roads b) Auger/Rotating
equipment Piles shall be used where
Qatif Junction c) Belt and Rotating
Equipment Guards All Rotating parts and belts shall be properly guarded.
d) Loose Clothing All personnel shall be trained in the hazards associated
e) Sheet Piling with rotating equipment.
Extraction of Piles
Workers shall not wear loose fitting clothes around
rotating equipment.

Cranes Shall Not be used for Pile Driving Operations


All air compressors and steam boilers shall be fitted
with calibrated relief valves.

Hammers and extractors shall be inspected for damage


prior to each shift.

Only Steam Air or electric Extractors shall be used.


Cranes Shall Not be used to extract driven piles.

Roads shall be properly marked, and barricaded. Traffic


shall be controlled so that it does not present a hazard to
those working in the pits.
Flagmen will be used if required.
Lights will be used to illuminate the area at nighttime.
Night watchman will be assigned as required.
Specific RECOMMENDED ACTIONS HAZARD
NO. AREA(S) Hazards/Concerns Proposed Actions To Correct The Specific ANALYSIS
Identified Hazards/Concerns Identified In Column # 3 A, B, C

Desert Driving Remote Locations a) Vehicle Breakdowns All Vehicles and employees will be accounted for at the
between Cities b) Getting Stuck end of each shift.
c) Heat Stress/Exhaustion
d)) Heat Stroke Sign in and out boards shall be used to used to track the
e) Search And Rescue locations of vehicles and employees working in remote
locations
Search and rescue procedures shall be developed and
followed.

Employees shall be trained in the signs, symptoms of


heat related illnesses and the emergency treatment of
such illnesses.

Safety Equipment shall be provided for all vehicles.

Spare tires and Jacks shall be provided to all vehicles.

Desert Survival techniques will be reviewed with all


employees.
Blasting Operations Where required and a) Storage Magazines Notification of concerned departments prior to blasting.
approved b) Qualified Blasting Magazines shall be designed and constructed as per
personnel Saudi Aramco Standards.
c) Securing Blast Area
Proper security/fencing shall be installed around
Magazines.

Blast mats to be used where required

Warning signs shall be used to clearly mark the blast


area
Transportation of Explosives shall be in approved types
of vehicles. Vehicles shall be properly marked.

Radio Transmitters shall not be allowed with 100 feet of


electric detonators unless they have been de-energized
and locked.
Specific RECOMMENDED ACTIONS HAZARD
NO. AREA(S) Hazards/Concerns Proposed Actions To Correct The Specific ANALYSIS
Identified Hazards/Concerns Identified In Column # 3 A, B, C

Exposing Pipelines & Where encountered Temporary Support Temporary Supports shall be provided as required.
Working Near Excavations shall be done in accordance with Saudi
Intersecting Pipelines Aramco Construction Safety Manual.

Shoring excavations Engineered Shoring will be provided if benching or


sloping is not practical

Rupture No mechanical equipment shall be allowed to work


within 10 meters of unidentified underground pipes
powerlines or other utilities.

Fire Fire Protection equipment will be available.

Welding Pipe Entire Project a) Personnel in Trench No Personnel will be allowed in the trench while piping
&Lowering Pipe Into the b) Thermal Expansion is being lowered into the trench.
Trench Unexpected &
Uncontrolled Precautions shall be taken to prevent pipe from entering
Movement the trench unexpectedly due to uncontrolled movements
and thermal expansion..
Hot Taps Where and If Required a) Proper flow SAEP 311 shall be reviewed and followed.
b) Fire Protection Saudi Aramco Fire Prevention shall be contacted and
services. consulted prior to beginning of work.
c) Standby equipment Sufficient standby equipment shall be provided for use.
d) Welding machines,
e) Generators
Auxiliary Lighting Lighting shall be provided in the event work extends
Water Tankers and into the night.
Proper fittings Water tankers will be provided as required.
available
Overhead Obstructions : Entire worksite a) Special emphasis Overhead lines are usually not insulated. Therefore, any A
(warning signs) given to kind of metallic object coming near or contact with
Right of Ways all overhead power lines. them can cause a hazardous situation, keep the
considerable distance from the Power line minimum 20
Use the warning sign " DANGER OVERHEAD
POWERLINE" to minimize the hazards. Install goal
posts and tell tales as required.'
Specific RECOMMENDED ACTIONS HAZARD
NO. AREA(S) Hazards/Concerns Proposed Actions To Correct The Specific ANALYSIS
Identified Hazards/Concerns Identified In Column # 3 A, B, C

S-ar putea să vă placă și