Sunteți pe pagina 1din 9

Matara-Kataragama Railway Extension Project (Phasel) Sri Lanka Matara-Beliatta Sector

Matara-Kataragama Railway Extension Project

Matara-Beliatta Sector (phase I)

(DKO+44 - DK26+461)

Method Statement for Termite Treatment in Railway Station Buildings

MS-IS7

Rev. A

Contractor: China National Machinery Imp. & Exp. Corp.

No Date Prepared Checked Approved Remark

REV.A 20 16.12.2 1
~ ~Indunil Bandula Chen Yue Lin
(Build.Eng) (SLStr.Eng) (Chief Engineer)

Ref.Letter No :
Matara-Kataragama Railway Extension Project (Phase1) SriLanka Matara-Beliatta Sector

Contents 

1  Introduction and General Information ........................................................... - 1 - 


2  Material and Equipment ................................................................................... - 2 - 
2.1  Material ........................................................................................................................ - 2 - 
2.2  Equipments ................................................................................................................... - 2 - 
3  Organization Chart for the Construction Activity ......................................... - 2 - 
4  Methodology of pre -construction termite treatment .................................... - 3 - 
4.1  Surface preparation ...................................................................................................... - 4 - 
4.2  Execution of work ........................................................................................................ - 4 - 
4.2.1  Plinth Treatment.................................................................................................... - 4 - 

4.2.2  Treatments under floor slabs ................................................................................. - 5 - 

5  Risk assessment .................................................................................................. - 5 - 


6  QA/QC Measures ............................................................................................... - 6 - 
7  HSE Measure ..................................................................................................... - 6 - 

ii 

 
Matara-Kataragama Railway Extension Project (Phase1) SriLanka Matara-Beliatta Sector

1 Introduction and General Information

Pre-construction soil treatment implies laying down a chemical barrier to prevent termites from
getting back and forth between wood and soil. Termites need wood for food and soil for
moisture, so they constantly travel back and forth between wood and soil. Where this situation
does not exist, termites build the “shelter tubes” (Mud tubes) to span foundation walls and other
parts of the building that separate wood from the soil. In the case of the ground slab of a building,
the termites are entered through expansion joints, cracks, opening for utility and service
connections.

Anti-termite treatment should be carried out in all the building area prior to complete the ground
floor construction works. The materials used for this activity is harmful poisons to animals and
humans. So it is prohibited to precede this activity by the ordinary workers. Therefore it has been
decided to get the service and materials for this activity by local specialist company. The material
and source approval were obtained by CMS/CMC/B/S/05 (Rev 0).

This method statement is explained and confirmed the procedures and materials which are used
for anti-termite treatment in railway station building.

Figure 1.1 Subterranean termite colony illustrations


‐ 1 ‐ 

 
Matara-Kataragama Railway Extension Project (Phase1) SriLanka Matara-Beliatta Sector

2 Material and Equipment

2.1 Material

Following primary materials are used in this activity as stated

 Chemicals (Biflex TC / Bisect 10EC (BIFENTHRIN 10EC))


 Water
 protective layer (screed concrete)

2.2 Equipments

 Chemical spray machine with spray nozzle


 Chemical injecting machine
 Chemical mixing machine
 Personal protective equipment such as safety helmet, safety gloves, safety shoes,
eye protection or goggles, approved respirator and safety jacket.
 Other ordinary equipment and tools which used to pour the screed concrete

3 Organization Chart for the Construction Activity

Well experienced staff is allocated to carry out the railway station building and platform
construction activity as per this method statement. The organization chart for this activity is
described in the following figure.

Figure 3.1 Organization structure for railway station building and platform construction
‐ 2 ‐ 

 
Matara-Kataragama Railway Extension Project (Phase1) SriLanka Matara-Beliatta Sector

4 Methodology of pre -construction termite treatment

Figure 4.1: Flow chart of anti-termite treatment

‐ 3 ‐ 

 
Matara-Kataragama Railway Extension Project (Phase1) SriLanka Matara-Beliatta Sector

4.1 Surface preparation

 the ground surface where the termite treatment to be carried out should be free from any
items containing cellulose such as tree stumps, roots, logs, waste wood, etc. In case the
termite mounds are discovered within the plinth area of the building they should be
destroyed and removed from the building area. The soil should be free from large crumbs
of gravel.

 Before to start the anti-termite treatment all underground service lines should be placed,
identified and protected (if required) in treating area.

 Prior to the commencement of anti-termite treatment, it is essential to complete the


backfilling works and any field tests pertaining to check the compaction or any other
properties of soil.

4.2 Execution of work

All the buildings in this project are new constructions and there are no any renovated buildings.
Therefore the pre-construction termite treatment methods shall be applied. The termite treatments
in building area are described below under two parts in the view of the explanations convenience.

4.2.1 Plinth Treatment


The backfilling and surface preparations works should be completed and should be obtained the
engineer’s concern prior to start the treatments works. The holes are drilled on compacted ground
along the edges of ground floor beams. The depth of the holes is 3ft and holes spacing are 3ft
maximum. The chemicals are injected to the ground through those drilled holes by chemical
injecting machines. The chemical coverage, dilution rate and pressure pump rate shall be as
follows. (Those details were submitted in CMS/CMC/B/S/005)

The chemical dilution rate = 1:200

Termite pump pressure rate = 15-25 psi

Chemical coverage = 5 L/m2

‐ 4 ‐ 

 
Matara-Kataragama Railway Extension Project (Phase1) SriLanka Matara-Beliatta Sector

4.2.2 Treatments under floor slabs

The chemicals are spraying to the whole building area except the area described under chapter
4.2.1.(below the ground floor beams) The screed concrete layer should be placed within 48 hours
of termite treatments are completed. Please note that the termite treatments are done by specialist
contractor as proposed by CMS/CMC/B/S/005 document. However the screed concrete layer
placement is not included to the above contractor’s scope. This screed concrete layer placement
methodology is described in MS-156 (Method statement for ground floor construction in
kekanadura railway station building). The treated area should be covered until placed the screed
layer if it is unable to lay screed concrete within specified period.
The chemical dilution rate and chemical coverage data are 1:200 and 5 L/ m2 respectively.

5 Risk assessment

The materials used for anti-termite treatments are harmful toxic to the humans and animals. So
there is a hazard to the environment due to use of those types of chemicals. But that hazard
should be minimized by proper application. This chemical should not be sprayed to any free
water flow or should not move with ground water table. Also this chemical should not be sprayed
to the atmosphere.

No person should enter the uncovered treated area until the spray has dried. However if prior
entry is necessary, the personal protective equipment should wear well. If this poisonous is
swallowed, then eyes will damage and will irritate the skin as per the detail given in material
safety data sheet. If spray is contact the skin, then immediately should wash the area with soap
and water.

A risk assessment check list is attached in annexure. Also please refer the material safety data
sheets that submitted with CMS/CMC/B/S/005

‐ 5 ‐ 

 
Matara-Kataragama Railway Extension Project (Phase1) SriLanka Matara-Beliatta Sector

6 QA/QC Measures

1. Site layout strictly according to the design drawing.


2. It is highly recommended and instructed to all the technical staff to refer all civil
drawings with conjunction of electrical, plumbing and firefighting drawings to avoid the
rework and unnecessary demolishing.
3. The materials are from approved sources and compliance with requirements.
4. The service lines should be identified and protected prior to start the pest control
treatments.
5. A joint inspection shall be carried out prior to start the pest control treatment to check the
surface preparations.
6. The maximum distance of drilling holes and chemical coverage per unit area should be
followed strictly
7. The covering screed should be placed within 48 hours of the completion of treatment.
8. The treated area should be covered until placed the screed layer if it is unable to lay
screed concrete within specified period

7 HSE Measure

1. Chemicals used for anti-termite treatment shall be handled (mixing & application) by skill
workmen who have gained experience in this type of work
2. Use protective equipment when mixing & handling chemicals ( respirators , rubber
gloves , full protective clothing including long sleeved shirt , and safety shoes)
3. Minimize as far as possible the exposure of other workers to the chemical treatment
4. Handle chemicals in such a manner as to avoid contamination of the site
5. Staff and workers have not permission to enter the construction site without wearing
personnel protective equipment such as safety helmet, safety shoes/boots and etc.
6. Plan, manage and monitor construction work under fully control and it is carried out
without risks to health and safety of the workers as well as public.
7. Sufficient safety measure with barricade tapes and other relevant materials are arranged
for ensuring the safety of workers and public.

‐ 6 ‐ 

 
Matara-Kataragama Railway Extension Project (Phase1) SriLanka Matara-Beliatta Sector

Annexures

‐ 7 ‐ 

S-ar putea să vă placă și