Business case
With a large pipeline of projects,
availability of people was the key
challenge. Dramatically increasing
productivity was the only promising
direction.
Results Obtained
70% increase in Throughput/ Operating
expenses ratio in 2 years
Key Solution Elements
Network building, Buffering, Daily task
About Company management, Fortnightly project
reviews, Monthly review of Throughput
Thermax’s e nergy efficient and based on % CC and T/OE.
eco-friendly technologies offer reliable
business-to-business partnerships to
respond to this critical challenge.
SSHF
having real economic impact
Business case
L&T wanted to invest Rs. 2000 Cr for a
facility for special steel and special
forgings at Hazira. The economic impact
was 40-50 Lakh Rs/ day.
Results Obtained
The PMBOK + CCPM system was
established, operated and handed over
to LTSSHF managers with payment of
success bonus to TPMS in about one
year.
QA, Training, master scheduling and
analytical support is extremely critical.
L&T HED
Business case
With 7-8 SBUs sharing resources across
5-6 execution locations and plants,
synchronization of priorities was critical
increase profits & satisfy customers.
Results Obtained
Overall Delivery Performance Index
increased from 40% to nearly 80% and
sustained for over six months, as a six
months’ moving average.
Business case
Results Obtained
It was demonstrated that with an
investment of Rs. 2.6 Cr, and
implementation of Critical Chain, it was
possible to finish the project 6 months
EARLY. The net impact could be about
20 Cr Rs additional income from tolls.
Key Solution Elements
Project network creation, CCPM
About Company planning, Analysis of financial impact of
recovery decisions.
Gammon India is amongst the largest
physical infrastructure construction
companies in India. Its track record
spans significant landmark projects built
over several decades, with a prominent Lessons Learnt
presence across all sectors of civil , Implementing Critical Chain requires
design and construction. It has a track addressing the overall business scenario.
record of building landmark structures,
Commit to make all the required
some of which have become iconic. . changes in policies and measurements
to reap the benefits of better project
management.
Opportunity & Problems
Business case
TP’s was losing 20% customers per annum,
with 63% business repeat business, and its
OE % was much higher than industry norm.
Results Obtained
15-30% TAT reduction, 40% WIP reduction,
OTIF increase from 43% to 93%, profit
improved by 62% (All results in one year)
Business case
Tata Steel had embarked upon a “Viable
Vision” initiative. CCPM was chosen to
manage capacity expansion all other
projects. The value of each day of blast
furnace shutdown reduction was Rs. 2.5
Cr.
Results Obtained
The project time of blast furnace
shutdown was reduced by 23%. The
About Company method was then expanded to cover all
other projects.
Tata Steel is currently the world’s
second-most geographically diversified
steel producer. Today, TS operate in 26
countries and have a commercial
presence in over 50 countries with Key Solution Elements
employees across five continents. And
CCPM planning, task priorities, daily
the numbers are growing. Raw Material
updates and Weekly reviews based on
operations are spread across India and
CCPM measures. Fever Chart, buffer
Canada which help us to be
management reports.
self-sufficient in steel production. In
India, TS’s downstream business
activities are structured into strategic
business units such as Ferro-alloys and
Minerals, Tubes, Wires, Bearings, Agrico Lessons Learnt
& Industrial By-products.. It is critical to ensure that all key
participants win, and understands
exactly how they will win.
Top managers must proactively identify
and remove procedural, measurements
and behavioral obstacles.
Business case
Results Obtained
In FY’19, NLL completed 32% more
projects, while reducing delays to less
than half. Both the trends are continuing
with a much stronger PMO.
Systems
Business case
GPS needed to greatly increase output of
Brahmos assemblies, while ensuring timely
deliveries of all other products.
Results Obtained
Output of Brahmos assemblies
increased 60%, lead time reduced by
35%. Revenues increased 64%,
components expediting decreased from
30% to 5%
execution. The opportunity was to
Properties
Business case
With a profit sharing model, managing
supply chain, and subcontractors
performance was difficult. Faster
execution was critical for profitable
growth
Results Obtained
As per Mr. Satish Jadhav, Project
manager of the Planet Godrej Project
finished at least 12 months faster.
Business case
Results Obtained
8 - 50% reduction in refit project cycle
times was achieved in specific projects
which were managed by the system.
Key Solution Elements
Multi-Projects planning, CCPM planning,
Fortnightly promulgation of task
priorities, daily updates and Weekly
reviews based on CCPM measures.
About Company
Naval Dockyard, Mumbai i s the premier
ship repair yard of the Indian Navy. With Lessons Learnt
a history of over 200 years, it is one of the Effective handover of the system from
largest of its kind in Asia. The yard is the top managers to new top managers is
frontliner in technology for repair of essential in the Naval Dockyard
ships. environment as transfers are frequent.
Internal skills development, reasonably
verified by certifications and linked to
the growth of the concerned people is
vital for sustenance of the system.
Opportunity & Problems
How to finish projects on-time with
full-scope despite inherent uncertainties,
resource contention and coordination
challenges across multiple departments.
Business case
Results Obtained
The desired practices of planning, updates
and reviews were established along with
project and task templates. ND-V decided
to go ahead with the next steps.
Key Solution Elements
Multi-Projects planning, CCPM planning,
About Company Fortnightly promulgation of task priorities,
daily updates and Weekly reviews based on
Naval Dockyard, Vizag i s one of the CCPM measures.
major ship repair yards of the Indian
Navy. This is one of the most important
dockyards in India, after Mumbai
Dockyard.
Lessons Learnt
Presence of an internal champion is the
most critical need for a major change
effort like to succeed.
Opportunity & Problems The planning process must be enhanced
How to finish projects on-time with to a workshop format to involve the line
full-scope despite inherent uncertainties, managers. Real purpose of updates is to
identify and remove obstacles.
resource contention and coordination
challenges across multiple departments.
Opportunity & Problems
Business case
Pilot implementation of Critical Chain
Project Management (CCPM) for Repairs
of drilling rig ‘Perro Negaro 3’. The value
of each day of reduction was Rs. 17 Lakh
for HSL and US$ 75,000/- for Perro
Negaro.
Results Obtained
The repairs of Perro Negaro 3 finished 15
days ahead of schedule, despite
significant scope increase, including on
the critical path.
About Company
Hindustan Shipyard Ltd., strategically Key Solution Elements
located on the East Coast of the Indian
CCPM planning, task priorities, daily
peninsula, at Visakhapatnam, Andhra
updates and Weekly reviews based on
Pradesh, is the nation’s premier
CCPM measures. Fever Chart, buffer
shipbuilding organization catering to
management reports.
the needs of shipbuilding, ship repairs,
submarine construction and refits as
well as design and construction of
sophisticated state-of-the-art offshore
and onshore structures. Lessons Learnt
Major changes can work only with full
support of the top management.
The project became successful, when
the subcontractor understood exactly
how he will win by collaborating in the
cycle time reduction goal.
Results Obtained
The CCPM system was established, and
handed over to AEL managers with local
support being provided by Goldratt Group,
South Africa
About Company
African Explosives Limited-Mining
Services is a c
ompany based in Lessons Learnt
Johannesburg. The company's principal
activity is the manufacture of e
xplosives.
Strategy execution can greatly benefit from
It serves the mining and construction formal project management, by solving the
industries throughout Africa. priority dilemma of running operations v/s
driving growth and better managing human
behavior - resulting in higher velocity (more
throughput).
Opportunity & Problems
Since most resources are drawn from
operations as per need, and some could not
be increased easily, a mechanism to
synchronize people and make the best use
of limited resources was required.