Documente Academic
Documente Profesional
Documente Cultură
CHECKLIST FOR
FUNCTIONAL ACCEPTANCE TEST IN THE
FACTORY AND PRE-COMMISSIONING
TEST ON SITE
Page 1 of 12
STANDARD EQUIPMENT MANUAL
POWER TRANSFORMERS AND OIL FILLED REACTORS
The functions, controls, alarm and trip circuits have been tested and found to be in working condition. The
timer and other control settings have been left as stated on following pages.
It remains the Contractor's responsibility to ensure full compliance with all the specified requirements under
the Contract including any TIRs and contract variations. It is also the Contractor’s responsibility to perform
any additional checking and testing, if required, to ensure that the equipment is fit for service. Powerlink
accepts no responsibility for any omissions or oversights in this checklist or during functional checking.
Further it is noted that the contractual provisions relating to the submission of Contractor supplied
documents continue to apply.
Manufacturer Representative
……………………………………………….. …………………………..
Manufacturer Representative / Installation
Contractor (Print name and sign off) Date
Before Oil Fill – Inspection, Oil and Vacuum Log, Oil Test Moisture and Dielectric Breakdown,
Functional test (Oil Level, Bag Rupture & Buchholz contacts are ON)
Pre-commissioning - Day 1
Tailgate Meeting
Oil Leak Check after 24 h Pressure Test
Inspection General
Mechanical Inspection
Functional Test
Pre-commissioning - Day 2
Functional Test Continuation
(Must be fully finished before start of Electrical Test)
Equipment data collection
Remedy issues from first day inspection
CTs Test
Paint Dry Thickness Test on touch up/repair job
Pre-commissioning - Day 3
Electrical Test in order below:
(Mag. Current > IR > DC Res. > Continuity check TV E to internal earth > DLA Tank > DLA Bushings > SFRA)
Note: There shall be no pumps operation, TC operation or 10 kV testing while transformer is pressurised or under vacuum!
Page 2 of 12
STANDARD EQUIPMENT MANUAL
POWER TRANSFORMERS AND OIL FILLED REACTORS
Mechanical/Visual Check
Equipment Serial Numbers Use Equipment Data Collection Sheet, prepared
and provided by the Manufacturer - confirm
bushings are in right position.
24 H Pressure Test (Oil Leak Test) 50 kPa above head of oil
(0.5bar, 375mmHg, 7.25 PSI)
Conservator Bag Set Up Follow manufacturer’s instruction. Check alarm
before and after set up. Log to be presented on
site.
Terminal Boxes Ensure all terminal boxes are water proof – cable
entry from the bottom, water drain pin halls on the
bottom, glands water proof etc.
Visual Check Before Crew Evacuation
Control / CT / OLTC Cubicles Pocket provided – drawings in
Silica Gel Breather, Oil Bath Level Colour, oil level correct
All labels and signs in place Confirm
Paint / Touch-up – follow Paint Repair Spec Confirm finished and OK in accordance to Paint
procedure Repair Spec / perform dry film thickness test
Valve Diagram Plate Check all valves are in for ‘Operation’ position
Radiators Butterfly Valves Open
All HV, LV, TV, N and n bushing terminals Use min. 95 mm2 Cu wire.
shorted and earthed for induction purposes. After all electrical test finished.
Oil Samples taken from the Main Tank (top To be labelled and tested by the Contractor as per Oil Temp.
and bottom - 2 x 500ml) and TC (2 x 500ml) Specification. Record oil temperature.
before departure
Oil Samples taken from the Main Tank (top To be labelled and delivered to Powerlink Oil Lab. Oil Temp.
and bottom - 2 x 500ml) and TC (2 x 500ml) Record oil temperature.
before departure
Blanking Plates on pallet and stored on Location to be discussed and agreed with the
agreed location within substation boundaries. Principal or Construction Manager or follow
minutes from pre-delivery on site meeting.
Site to be clear from rubbish and material and cleaned Confirm OK
before departure from the site. All swarf removed.
All cubicles cleaned and swarf removed. Confirm OK
Page 3 of 12
STANDARD EQUIPMENT MANUAL
POWER TRANSFORMERS AND OIL FILLED REACTORS
Insulation Resistance 500 VDC / 1 min. shall Factory Test – Not Required
be measured between CT’s secondary cores Site Test – All
(all taps shorted) to ground – from the CT
Marshalling and Main Control Cubicle
terminals
CT Resistance measured from the CT Refer also to drawing and check terminal
Marshalling Box terminals numbers are correct.
Page 4 of 12
STANDARD EQUIPMENT MANUAL
POWER TRANSFORMERS AND OIL FILLED REACTORS
Cubicle Light
Cubicle Cooling Fan(s) Stage 1 Thermostat settings (on 50 ºC) ºC
Cubicle Cooling Fan(s) Stage 2 where appl. Thermostat settings (on 55 ºC) ºC
Cubicle Condensation Heater Thermostat settings (off 35 ºC) ºC
Page 5 of 12
STANDARD EQUIPMENT MANUAL
POWER TRANSFORMERS AND OIL FILLED REACTORS
Page 6 of 12
STANDARD EQUIPMENT MANUAL
POWER TRANSFORMERS AND OIL FILLED REACTORS
Page 7 of 12
STANDARD EQUIPMENT MANUAL
POWER TRANSFORMERS AND OIL FILLED REACTORS
Page 8 of 12
STANDARD EQUIPMENT MANUAL
POWER TRANSFORMERS AND OIL FILLED REACTORS
Function Set Point
Check
Fibre Optic Probes
Verify F/O probes temp reading Factory Test Only. Compare to other available
instrumentation and measured/calculated
temperatures during heat run.
Buchholz Relay
Oil Surge Trip - before oil fill Terminals X13: 1 – 2 On
Oil Surge Trip - after oil fill (plunger) Terminals X13: 1 – 2 On
Off
Low Oil Trip - before oil fill Terminals X13: 3 – 4 On
Low Oil Trip - after oil fill (plunger) Terminals X13: 3 – 4 On
Off
Gas Alarm - before oil fill Terminals X14: 30 - 61 On
Gas Alarm - after oil fill Terminals X14: 30 - 61 On
Off
Conservator Bag
Rupture Alarm - before bag set up Terminals X14: 30 - 70 On
Rupture Alarm - after bag set up Terminals X14: 30 - 70 Off
On
Check bag rupture relay alarm after pressure Terminals X14: 30 - 70
tests. (Conservator must be bled before
pressure test)
CT Metrosil
Thermal Short Operated Alarm Terminals X14: 80 - 84 Off
On
Page 9 of 12
STANDARD EQUIPMENT MANUAL
POWER TRANSFORMERS AND OIL FILLED REACTORS
TC Alarms
Page 10 of 12
STANDARD EQUIPMENT MANUAL
POWER TRANSFORMERS AND OIL FILLED REACTORS
10
11
12
13
Page 11 of 12
STANDARD EQUIPMENT MANUAL
POWER TRANSFORMERS AND OIL FILLED REACTORS
14
15
16
17
18
19
20
21
22
23
24
25
26
27
Page 12 of 12