INSTRUCTION TO BIDDERS
SCOPE OF WORKS:
1. Site clearing
2. Excavation works
3. Concrete works in accordance with the plans and standard specifications for concrete and
reinforced concrete works.
4. Formworks
5. Rebar fabrication.
6. Permits
7. Utilities
8. Housekeeping & Sanitation
9. Hauling out, disposal of garbage, and construction of wastes
10. As-built plans
11. Temporary Facilities
12. Bonds and insurances
EXCLUSION:
A. GENERAL CONDITIONS
1.0. The WORKS shall include all labor, materials, tools, equipment and services required to execute the
works necessary to complete the said items of work, as shown on the drawings, as specified herein,
and or as required by job conditions to provide and complete the construct ion.
2.0. All works shall comply with the requirements of the contract, including general and special conditions,
along with the drawings and all other contract documents.
3.0. Labor, materials, equipment, tools, supervision and services deemed necessary to complete the
WORKS as per industry practice, but NOT specifically shown and mentioned in the plans, details,
specifications or in the other bid and contract documents, shall be supplied by the Bidder without extra
cost to the Owner.
SteelAsia Head Office: 2/F Building 2, Bonifacio High Street, Bonifacio Global City, Taguig City 1634
Tel: (02) 856-6888 • Fax: (02) 858-0585
5.0. Sufficiency of Resources
5.1. Bidders are advised to ensure that they are thoroughly and completely familiar with the full extent
and character of the Works and are to satisfy themselves as to the supply of and conditions affecting
labor, plant, equipment, materials and goods, etc. for use in the execution of the Works.
5.2. Submission of Bids shall be deemed to indicate that the Bidder is fully aware of and has made due
allowance in pricing the Bill of Quantities for the aforementioned factors and either has satisfied
himself that there are sufficient resources available or undertakes to provide sufficient resources in
order to complete the works within the Time of Completion.
6.0. Pricing
The bidder shall submit the best proposal attributed to the works specified on the drawings,
specifications and scope of works provided.
6.1. The Bidder shall allow in his Bid the provision for Temporary Site Office for Owner or his
representatives with furniture (office tables, conference table and chairs, etc.), fixtures, fittings &
equipment including its maintenance during the entire construction period. (for Greenfield projects
and those outside the plants, as applicable).
6.2. The Bidder shall include the cost to abide by all environmental, health and safety regulations by
relevant authorities including compliance to safety and security rules & procedures being
implemented by the Owner’s Plant Administration for the issuance of work permit. Safety
orientations are being carried out by the Owner or his representative prior to mobilization and as a
minimum, the Bidder shall allow for the following:
a) Staff, workers, operators medical test result (Xray and Drug tests)
b) NBI Clearances of workers and operators
c) Third-party certification of skilled workers & operators (i.e. NC II or equivalent)
d) Third-party certification of construction equipment (i.e. backhoe, cranes, dozers, Ready-mix
concrete trucks, boom trucks, etc.)
e) Personal Protective Equipment (PPE’s) for Contractor’s staff, workers & operators
f) Safety officers/ practitioners as part of Contractor’s site organization.
6.3. The Bidders shall include cost for protecting, clearing up, restoration and making good of all
existing facilities and utilities including but not limited to pavements, sidewalks, finish flooring, walls,
waterline, drainage line, etc. that may be affected by the works during the course of construction.
6.4. The Bidders shall allow for the proper housekeeping, site sanitation and maintenance during the
entire construction period. This includes provision and maintenance of toilet facilities for the use of
his site personnel.
6.5. The Bidder shall at all times maintain a site organization under the control of qualified and
experienced staff that is capable of assuming complete responsibility for a contract of this nature.
Whenever required, the Contractor shall remove and replace any members of its site management
SteelAsia Head Office: 2/F Building 2, Bonifacio High Street, Bonifacio Global City, Taguig City 1634
Tel: (02) 856-6888 • Fax: (02) 858-0585
and supervision team if deemed incompetent and unfit to dispose his duties and responsibilities
required for the position as determined by the Owner or his representatives.
6.6. The Bid shall allow for providing shop drawings including revisions until approved, samples,
brochures & catalogues, and for obtaining the Owner’s approval for the same. This includes
preparation of As built drawings duly certified by the Contractor, to the satisfaction and approval of
the Owner or his representative.
6.7. The Bidder shall ensure the availability of measurement device, tools & instruments for the proper
execution of the Works. These instruments shall all be in proper adjustment and always kept in
perfect working condition and shall be made available whenever required by the Owner or his
representatives. This includes survey instruments for the purpose of validating site layouts, levels and
reference points.
6.8. The Bidder shall consider the provision for adequate temporary supply of all necessary electrical
power for the Works, and for paying all charges for the connection and consumption of electricity.
On Contractor’s discretion, it may include the supply, operation and maintenance of generators at
his own expense including for all testing and commissioning and until final handing over of the
Works. If the capacity permits, all other Contractors directly engaged by the Owner shall be allowed
to tap to the nearest existing temporary power line set up by the Bidder including the provision of
sub-meter, subject to payment of appropriate charges, as applicable.
Similarly, the Contractor shall arrange for a temporary supply of water suitable for the Works
throughout the duration of the project and including for all requirements during testing and
commissioning. In so far as reasonably practicable, having regard to local conditions, allow for
adequate supply of drinking water for the use of his staff and workers.
7.1. The bid shall be submitted via email and shall contain the following:
a. Gantt Chart indicating all activities with specific target completion per scope of work; and
b. Manpower and Equipment schedule for the whole duration of Works.
8.1. The Bidder and any of his employees or agents will be granted permission by the Owner to enter upon his premises and lands for the purpose of inspection in connection with the proposed Bids, but only on the condition that the Bidder will release and indemnify the Owner and his representatives and agents from and against all liability in
respect of personal injury, loss of or damage to property and any other loss, damage, cost and expense however caused but for the exercise of such permission would not have arisen.
ITEM DATA
SteelAsia Head Office: 2/F Building 2, Bonifacio High Street, Bonifacio Global City, Taguig City 1634
Tel: (02) 856-6888 • Fax: (02) 858-0585
SCOPE OF WORKS The CONTRACTOR shall supply the WORKS and SERVICES for the PROJECT
according to the Detailed Time Schedule, Program of Works, Plans, Specifications,
and Drawings approved by the OWNER.
CONTRACT PRICE The OWNER shall pay the CONTRACTOR, for the Project, the Contract Price in the
total amount as computed based on the percentage of progress
accomplishments.
COMPLETION PERIOD The CONTRACTOR shall commence the WORKS one (1) day after receipt by the
CONTRACTOR of the Notice to Proceed issued by the OWNER and shall complete
the project in compliance with what is stipulated in the Purchase Order, subject
to any extensions which may be granted by the OWNER.
The CONTRACTOR shall submit to the OWNER for its approval the
Detailed Project Time Schedule.
If the progress of the WORKS does not conform to the Detailed Project
Time Schedule or if the OWNER considers it desirable or necessary to change the
Detailed Project Time Schedule to catch-up with the WORKS, the OWNER can
instruct the CONTRACTOR to revise the Detailed Project Time Schedule. Such
revision shall be made within five (5) days from receipt of the written instruction
from the OWNER at the CONTRACTOR's expense.
Upon completion of the WORKS for the PROJECT, the CONTRACTOR shall
request the OWNER for Final Inspection and Acceptance. The OWNER shall issue
Certificate of Final Inspection and Acceptance from submission of request.
However, if the WORKS are not ready for turnover, the CONTRACTOR shall be
notified and provided a Punch List which must commenced within seven (7) days
and completed within fifteen (15) days from receipt thereof. Should the
CONTRACTOR fail to commence or complete the Punch List within said period,
the OWNER may carry out the completion of the works in Punch List, which cost
(actual cost plus 20% supervision) will be charged to or offset against any
outstanding monies due to the CONTRACTOR and/or applied to the
CONTRACTOR's Performance Bond.
The issuance of the Final Acceptance Certificate shall not release the
CONTRACTOR from its liabilities and its obligations.
The CONTRACTOR shall prepare and submit six (6) complete sets of as-
built drawings or plans in blue prints (A2 size) and its electronic file in AUTOCAD
Format to the OWNER immediately after completion. These "As-built"
drawings/plans shall indicate all approved changes or revisions, made during the
SteelAsia Head Office: 2/F Building 2, Bonifacio High Street, Bonifacio Global City, Taguig City 1634
Tel: (02) 856-6888 • Fax: (02) 858-0585
construction, in respect of the original drawings/plans showing the exact as-built
locations, dimension, and kinds of materials, equipment, accessories and other
items of work, exposed or concealed. No Certificate of Final Acceptance shall be
issued to the CONTRACTOR without the as-built drawings/plans approved by the
OWNER. The review and approval by the OWNER of such record or "As-built"
drawings/plans shall not relieve the CONTRACTOR of any responsibilities arising
out of false or otherwise inaccurate Record or "As-built" drawings/plans prepared
and submitted by the CONTRACTOR.
TERMS OF PAYMENT The OWNER shall pay according to the following schedule:
The OWNER shall have the right to withhold any payment from any
billing of the CONTRACTOR's work: (1) which are found to be defective, irregular
or otherwise unsatisfactory; or (2) with respect to which the CONTRACTOR failed
to make prompt and proper payment for labor, materials, or equipment.
Progress payment(s) will be paid within 60 days from the date of receipt
of the billing by Accounting.
SteelAsia Head Office: 2/F Building 2, Bonifacio High Street, Bonifacio Global City, Taguig City 1634
Tel: (02) 856-6888 • Fax: (02) 858-0585
PARTIAL The OWNER may terminate the PROJECT or delete any WORKS at any stage
ACCOMPLISHMENTS without incurring any liability to the CONTRACTOR after giving fifteen (15) days
prior written notice. In such an event, CONTRACTOR shall be entitled only to the
WORKS actually accomplished. Payments for partial accomplishments of WORKS
shall be based on the Program of Works with Schedule of Unit Rates / Itemized
Cost Breakdown.
CHANGES IN WORKS The OWNER may order changes or revisions in the WORKS. In such eventuality,
the OWNER shall inform the CONTRACTOR in writing of such changes or
revisions. The CONTRACTOR shall not implement any change or revision without
an agreed and fully signed CHANGE ORDER from the OWNER.
ADDITIONAL WORKS - are WORKS required by the OWNER, which are not
covered in Article 2. In all cases, the costing of the additional WORKS shall not
exceed the unit rates indicated in Program of Works. Any consequential increase
in Contract Price including adjustment in the period of completion shall be
discussed and agreed by the parties and expressly approved by the OWNER in
writing.
ADJUSTMENT OF This is a lump sum contract hence, the CONTRACTOR shall not make any claim for
CONTRACT PRICE an increase in the PROJECT Contract Price for any reason whatsoever, including
but not limited to increase in the prices of materials or use of equipment due to
any cause whatsoever, such as but not limited to the enactment of laws and tax
measures, the difficulty of sourcing said materials and equipment, and increase in
the cost of labor and Peso-Dollar exchange rate.
However, the OWNER may order at any time in writing for revisions on Technical
Specification and Design, alterations by correction or deduction of works to be
commenced or being commenced by the CONTRACTOR. These orders shall be
supported by fully signed Change Order form and shall be carried out.
Any order to revise, alter, modify the works will remain invalid and will not be
allowed to request for claims unless supported by a written order from the
OWNER. Additional works ordered by the OWNER shall be assessed based on the
unit rates established at the CONTRACTOR’s final bid proposal.
BILLING GUIDELINES The OWNER shall pay the CONTRACTOR the advance payment upon submission
of the Surety and Performance Bond.
After thorough evaluation and approval, the Billing Statement will then
SteelAsia Head Office: 2/F Building 2, Bonifacio High Street, Bonifacio Global City, Taguig City 1634
Tel: (02) 856-6888 • Fax: (02) 858-0585
be endorsed to Accounting for payment processing.
The Final Billing less the 10% retention shall only be processed for
payment if the CONTRACTOR submitted the Notarized Warranty Certificates, the
Guarantee Bond and Test Certificates, if applicable.
BONDS AND Timely delivery of the bonds and guarantees shall be a condition precedent to
GUARANTEES the CONTRACTOR’s right to receive the advance payment for the PROJECT that
has already issued Notice to Proceed. The CONTRACTOR, at its own cost, shall
arrange to secure the requisite bonds and guarantees from reputable insurance
company in form and substance acceptable to the OWNER.
Notwithstanding the foregoing, the CONTRACTOR shall cause the renewal of the
foregoing bonds and/or extension of its validity to cover for the approved
contract time extensions without additional cost to the OWNER
ACCREDITED BONDING PRUDENTIAL GUARANTEE
COMPANIES Allyssa Balanzat (63) 917 8512050
allyssa.balanzat@prudentialguarantee.com
SteelAsia Head Office: 2/F Building 2, Bonifacio High Street, Bonifacio Global City, Taguig City 1634
Tel: (02) 856-6888 • Fax: (02) 858-0585
MALAYAN INSURANCE
Jun dela Paz (63) 927 6198390
junjundlp@yahoo.com
MAA GENERAL
ASSURANCE PHILS., INC.
Stanley Cheng (63) 917 8176789
sycheng.moc@gmail.com
MAPFRE INSULAR
Faustino Barcelon, Jr. (63) 917 630 1955
faustinobarcelonjr@yahoo. com
PERMITS AND LICENSES The CONTRACTOR undertakes to obtain the necessary approval, permits and
licenses from the local authority or other statutory body concerned for the Works
as described herein. The OWNER shall provide all necessary documents needed
for this permit & licenses.
DELAYS AND PENALTIES It is understood and agreed that time is of the essence, and that in case the
CONTRACTOR fails to complete the WORKS within the stipulated time due to its
own fault, the CONTRACTOR shall pay the OWNER One-Tenth (1/10) of One
Percent of the Contract Price for each day of delay until completion of the
WORKS as liquidated damages.
SteelAsia Head Office: 2/F Building 2, Bonifacio High Street, Bonifacio Global City, Taguig City 1634
Tel: (02) 856-6888 • Fax: (02) 858-0585
TIME EXTENSION The WORKS shall be completed within the period of time as indicated in the
Purchase Order subject to any time extension duly granted by the OWNER. The
CONTRACTOR may claim an extension of the time for Completion if it determines
delay in completing the WORKS by any of the following causes:
In case of a Force Majeure status lasting for more than thirty (30) days, the
CONTRACTOR and the OWNER will meet to reach proper agreements taking into
account the existing situation. The CONTRACTOR shall endeavor to continue to
perform his obligations so far as reasonably practicable. The CONTRACTOR shall
notify the OWNER of the steps it proposes to take, including any reasonable
alternative means for performance, which is not prevented by Force Majeure.
The CONTRACTOR shall not take any such steps unless directed so by the
OWNER.
Failure of the CONTRACTOR to notify the OWNER of any event that causes delay
within the two (2) day period as given in Article 12.2 shall be deemed a waiver on
its part to claim that such an event is one that may constitute permissible delay.
The OWNER shall, after due consideration of all the facts, and provided that the
CONTRACTOR has submitted its claim according to the foregoing, grant the
CONTRACTOR from time to time, either prospectively or retrospectively, such
extension of time for completion as may in its opinion be justified.
It does not follow that any delaying event would automatically entitle the
SteelAsia Head Office: 2/F Building 2, Bonifacio High Street, Bonifacio Global City, Taguig City 1634
Tel: (02) 856-6888 • Fax: (02) 858-0585
Contractor to an extension of time. The Contractor is required to demonstrate
that the event has a direct impact on the project completion date. For this
purpose, the Detailed Project Time Schedule is required to be produced using the
Critical Path Method in Microsoft Project or Primavera format. The OWNER shall
have the right to withhold payment if the Contractor is unable to provide the
Detailed Project Time schedule or the progress updates in the required format.
TERMINATION OF THE The OWNER shall have the sole discretion to terminate the Contract for default
AGREEMENT when any of the following conditions attend its implementation:
SteelAsia Head Office: 2/F Building 2, Bonifacio High Street, Bonifacio Global City, Taguig City 1634
Tel: (02) 856-6888 • Fax: (02) 858-0585
In any event and for any reason whatsoever, the OWNER may terminate, in
whole or in part, without incurring any liability to the CONTRACTOR, by giving a
written notice at least fifteen (15) calendar day before the effective date to the
CONTRACTOR.
TAKE OVER - The OWNER may, without prejudice to any other rights and redress
it may have against the CONTRACTOR, immediately take over or take possession
of the Works for any of the causes stated therein, including all tools and
equipment and finish the Works by whatever method may be deemed expedient.
The amount of Take-over works shall be on the expense of the Contractor and
shall be charged on the next approved billing.
EFFECTS OF The OWNER may expel the CONTRACTOR from the Project site. Any such
TERMINATION expulsion and termination shall be without prejudice to any other rights or
powers of the OWNER.
SteelAsia Head Office: 2/F Building 2, Bonifacio High Street, Bonifacio Global City, Taguig City 1634
Tel: (02) 856-6888 • Fax: (02) 858-0585
reduce WORKS related expenditures to a minimum. The CONTRACTOR shall
submit within seven (7) days from receipt of Notice of Termination a certification
of the value of the WORKS to the OWNER for evaluation and approval.
ANNEX 1
(This declaration is to be made out on the Bidder's Company letter)
______________
______________
______________
Dear Sir,
We, _________________________ hereby declare that we have visited the Site and inspected/ reviewed
all details of the Project Site, the nature of the ground, geotechnical investigation report, topographic survey
report and we declare furthermore that the Site is free of obstacles, surface obstructions and we have no
queries on any matter with the prevailing site conditions.
Therefore, we shall have no right to any claims in respect of the above mentioned, in the future whether
during the execution or after completion of the Works, should this Project be awarded to our Company.
In confirmation of the above, we append hereunder the signature of our authorized representative.
Signature: ____________________________________________
Date: ____________________________________________