Documente Academic
Documente Profesional
Documente Cultură
Assignment Title: -
Variation: it’s Regulation & Management under the MDB-FIDIC (2006) &
the PPA (2011) Conditions of Construction Contracts & the Applicable Laws
Prepared by:
Name ID /No
1. Mukhtar Mohamed ……………………..…..SGS/870 /11
2. Samson Diribssa………………………….... SGS/830/11
I
4.3.6 Tarnish firm's reputation: ............................................................................................. 16
4.3.7 Poor safety conditions: ................................................................................................. 16
4.3.8 Poor professional relations: .......................................................................................... 16
4.3.9 Additional payments for the contractor: ....................................................................... 17
4.3.10 Disputes among professionals: ................................................................................... 17
4.3.11 Completion schedule delay:........................................................................................ 17
4.4 To reduce the number and the Impact of Variations ........................................................... 18
4.4.1 Design Stage Approach to Control Variations ............................................................. 18
4.4.2 Construction Stage Approach to Control Variations .................................................... 19
4.4.3 Design-Construction Interface Stage Approach to Control Variations ........................ 21
4.5 Variation procedure ............................................................................................................. 22
4.6 Valuation of Variation ......................................................................................................... 23
4.7 Right to Vary ....................................................................................................................... 24
4.7.1 Employer’s Right to Vary through Engineer ................................................................ 24
4.8 Discussion about having no variation clause in the contract .............................................. 25
CHAPTER FIVE: APPROVED VARIATION ............................................................................ 26
5.1 introduction ......................................................................................................................... 26
5.2 Scope of Approved Variation .............................................................................................. 26
5.3 Procedure for Approved Variation ...................................................................................... 27
5.3 Result of approved variation ............................................................................................... 27
5.4 Possible Design Liability of the Contractor ........................................................................ 27
5.5 value engineering ................................................................................................................ 27
5.6 Possibility to change or not change the delivery system from DBB to DB ........................ 29
CHAPTER SIX: COMPARISON BETWEEN INSTRUCTED AND APPROVED
VARIATION ................................................................................................................................ 30
CHAPTER 7: THE ROLE OF ENGINEER ................................................................................. 31
7.1 Role of the Engineer in Construction: Overview ................................................................ 31
7.2 Role of the Engineer in Instructed Variation ...................................................................... 33
7.3 Role of the Engineer in Approved Variation ...................................................................... 34
7.4 Contribution of Design to Scope Change ............................................................................ 34
CHAPTER 8: CASE STUDY ABOUT THE VARIATION ........................................................ 35
8.1 introduction ......................................................................................................................... 35
8.2 Background of the case ....................................................................................................... 35
8.3 purpose of the project .......................................................................................................... 35
8.4 Project and contract information ......................................................................................... 35
8.5 Proposed solution ................................................................................................................ 36
8.6 discussion recommendation ................................................................................................ 36
CHAPTER 9: COMPARATIVE TABLE AND ANALYSIS ...................................................... 37
CHAPTER 10: CONCLUSION AND RECOMMENDATION .................................................. 40
10.1 conclusions ........................................................................................................................ 40
10.2 recommendation ................................................................................................................ 40
Reference ...................................................................................................................................... 42
II
LIST OF ABBREVIATIONS AND ACRONYMS
LIST OF TABLE
Table 1: comparison between instructed and approved variation ................................................. 30
III
ABSTRACT
Variation is inevitable in construction projects due to the complex nature of the construction
industry. It is common in all types of construction projects and it determines the time limits and
anticipated budget of the projects. Variation order is observed as one of the most frequently
occurring issues in construction projects in Ethiopia.The main objective of this study to analyze
MDB-FIDIC (2006) and PPA (2011) condition of the contract with respect to variation. This deals
with variation to the contract terms or conditions which referred to as an amendment to the
contract. In other words, it is a change to the terms that the parties had agreed and accepted when
the contract was signed. According to FIDIC (2006), "variation" means any change to the works,
which is instructed or approved as a variation. According to PPA-2011, the term "variation" is
changed to "Modifications" and describes as, the Engineer shall have the power to order any
modification to any part of the works necessary for the proper completion and /or functioning of
the works. This study focused on the variation orders in construction projects and the right and
obligation of the engineer in a variety of works.
Keywords: variation, modification instructed variation, approved variation, contract.
IV
CHAPTER ONE: INTRODUCTION
1.1 Background of the study
The construction projects in Ethiopia have been on fast-growing mode which plays a vital role
in the development of the country. These projects include roads, bridges residential, commercial
buildings and industries which are constructed by domestic contractors or foreign contractors, it
is common to see such contracts variations and conflicts between parties during the course of a
construction project. Whether they decrease or increase the venture’s schedule or cost, any
deletion, addition or any other revision to the terms of the project is known as variation in orders
(Assbeihat and Sweis 2015).
On the other hand, a variation is an alteration to the scope of works in a construction contract in
the form of an addition, substitution or omission from the original scope of works.
Almost all construction projects vary from the original design, scope, and definition. Whether
small or large, construction projects will inevitably depart from the original tender design,
specifications, and drawings prepared by the design team.
This can be because of technological advancement, statutory changes or enforcement, change in
conditions, geological differences, non-availability of specified materials, or simply because of
the continued development of the design after the contract has been awarded. In large civil
engineering projects,, variations can be very significant, whereas on small building contracts
they may be relatively minor.
Developing countries such as Ethiopia need to effectively eliminate this issue from the
construction sector as the country cannot afford delays and cost overruns in the projects with
any value being added to the project, hence the primary goal of this paper is to study the adverse
impacts and causes of these undesired variations, it is also focused on the discussion, First, by
highlighting what constitutes a variation and the common causes and sources of variations. This is
followed by a discussion and comparison between the local Conditions of Contract (PPA, 2011) and
the international Standard Conditions of Contract (MDB-FIDIC, 2006) and the applicable Law and
case study which is related to the variation and finally provides recommendations on how to
effectively eliminate this plague from the construction industry of Ethiopia.
1|Page
of delay, disputes and sometimes generate significant cost and environmental impacts are
variation orders issued during the construction of projects. Despite the fact that changes are
inevitable phenomena in the construction projects, emphases must be given to accommodate
changes in construction contracts. A change clause has to be incorporated to define the way how
owner, consultant and contractor handle changes. Therefore, change clauses and procedures
must be set to process a change from the conceptual development until it is realized to its
material equivalent in the field.
The general objective of this paper is to define & discuss the concept; types; categories
(instructed & approved variation); and management of such variations including the impacts of
the absence of variation clause; and how to mitigate the impact of variation in construction
projects; and lastly effective recommendation about variation in construction contracts.
a) Background Related
To discuss the legal possibility of varying contracts
To discuss the legal regulation of contract variation
To identify & discuss types of variation (as textual variation & variation in the works)
and then to focus on variation in the works.
To identify & discuss the two categories of variation in the works (instructed vs.
approved); then to discuss each separately.
b) Instructed Variation Related
To define variation in the works or instructed variation;
To identify & discuss the causes for instructed variation;
To discuss the right to vary of the employer through the Engineer and its significance
in the construction industry & construction process;
To identify & discuss the scope of instructed variation;
To identify & discuss the grounds for the contractor, if any, to refuse instructed
variation;
To discuss the procedure for instructed variation;
To identify & discuss the effects of instructed variation;
To discuss the valuation of variations in detail;
To discuss the need for textual variation in terms of the cumulative effects of
instructed variation;
To discuss the way to minimize the need for instructed variation.
2|Page
c) Approved Variation Related
To define approved variation or value engineering;
To discuss the scope of approved variation as related to value engineering;
To discuss the procedure for approved variation;
To discuss the effects of approved variation/value engineering;
To discuss the possible design liability of the contractor & the scope of such design
liability, if such approved variation were including design for the permanent works
by the contractor;
To define & discuss the concept of value engineering & its overall process & effect
including its advantages and disadvantages, if any;
To discuss ways to encourage approved variation or value engineering in Ethiopia;
to discuss, for example, the need for the introduction of alternative design during
tendering;
d) Instructed & Approved Variation Related
To discuss the importance of the inclusion of a variation clause in any construction
contract from the construction industry perspective;
To identify & discuss the possible adverse effects, if any, resulting from having no
variation clause in a given construction contract;
To discuss the legal way how to introduce & manage variation in the project in the
absence of a variation clause in the underlined construction contract;
3|Page
CHAPTER TWO: RESEARCH METHODOLOGY
2.1 general
This chapter presents the methodology adopted and identifies the tools and techniques employed
in conducting this study. The methodology is a plan of action that shows how the problems will
be investigated, what information will be collected using which methods, and how this
information will be analyzed in order to arrive at conclusions and develop recommendations.
This study follows some steps and procedures when conducted. Once the problem statement has
been formulated, it should become evident what kind of data will be required to study the
problem, and also what kind of analysis would be most appropriate to analyze the data. The
problem investigated in this study is the impact of variation orders on construction projects. It
is anticipated that the identification of the causes of variation orders may lead to their reduction,
possible elimination, and improvement in the overall performance of construction projects.
2.2 limitations
The current situation of the construction activity in Dire Dawa is not good, so it’s difficult for
us to compare experiences of organizations towards variations. Historical data related to
variation order is not well recorded hence getting data for this study was very difficult. The
scope of the study is under the Ethiopia construction industry, the concept of value engineering
is not exercised and not incorporated in PPA conditions of contract so it limits our discussion
on the value engineering concept.
2.3 Method of Data Analysis
This study started with problem identification which was done through unstructured literature
review and informal discussion with colleagues and professionals in the sector. Upon obtaining
the identified problems, conceptual and contextual literature reviews were conducted to have an
in-depth understanding on the issue of variation and variation order, focusing on causes and
effects and methods on how to minimize variations. The literature reviewed includes books,
dissertations, magazines, journals, newspaper, etc. Understanding the legal and contractual
aspects of variation in the international condition of contract (MDB FIDIC 2006), local
conditions of contract (PPA 2011) and in applicable law (Civil Code 1960). A case study from
one of the huge building construction projects in Dire Dawa is selected to see the management
process applied for variation works. With this, we will see the coordination between major
stakeholders of the project, the potential cause of variation and the method followed by these
parties to manage it before escalated to dispute.
2.4 Discussion of the Results
This study is divided into Ten chapters, the first chapter discusses on general introduction, in
the second chapter Research methodology, Chapter three will described Review of related
literature , Chapter four Instructed variation, Chapter five approved variation, chapter six
comparison between Instructed and approved variations, chapter seven role of the engineer,
chapter eight case study, chapter nine comparative table, and analysis Finally, in Chapter Ten
4|Page
from the analysis of result and brief discussion; conclusions and recommendations were
forwarded
5|Page
3.2.2 Judicial Variation of Contract
Judicial variation or variation of contracts by the court is not allowed, in principle. As article
1763 of the Civil Code,, “the court may not vary a contract or alter its terms on the ground
of equity except in such cases as are expressly provided by law”
Judicial variation of Contracts, as opposed to variation of Contract by the parties, is regulated
by the applicable law.
Under the applicable law, the Ethiopian court may vary the terms of the contract under the
following circumstances.
o Where it is expressly provided by law;
article 1763 of the Civil Code “the court may not vary a contract or alter its terms on the
ground of equity except in such cases as are expressly provided by law
o Where a special relationship between the contracting parties exists;
Article 1766 of civil code “the court may vary a contract where the parties do not agree
and a family or other relationship giving rise to special confidence exists between parties
and compels them to deal with each other in accordance with equity”.
o Where one of the contracting parties is a state or one of its institutions; as Article 1767
“the court may vary a contract made with a public administration where the
circumstances in which it was made have changed through an official decision in
consequence of which the obligations assumed by the party who contracted with the
administration have become more onerous or impossible”
o Where it is partially impossible to perform the contract; as Article 1768 "the court may
reduce the obligations of one party where the performance by the other party of his
obligations has become partially impossible and there is no ground for canceling the
court"
3.3 Definition of Variation
There is no single definition of what constitutes a variation. The term „variation‟ as described
and/or defined by various standard forms of contract differs from one to another but in principle,,
the definition and/or meaning is more or less similar. Usually, any standard form of building
contract will contain a definition of a variation in terms of specific actions and activities. The
building contract dictionary defined variations as alterations, additions or omissions in work,
materials, working hours, workspace, etc.
FIDIC (2006) conditions of the contract, “variation” “Variation” means any change to the
Works, which is instructed or approved as a variation under Clause 13 [Variations and
Adjustments].
6|Page
Various authors had identified different causes of variation orders in construction projects both
on the private and public projects so in this paper two authors are considered
a variation order is written order issued to the contractor after the execution of the contract by
the owner, which authorizes a change in the work or an adjustment in the contract sum or even
the contract time (Clough and Sears, 1994).
Hayati (2006) described that each standard form of building contract has its own definition but
clearly ‘variation', in the generic sense, refers to any alteration to the basis upon which the
contract was let.
7|Page
3.4.1.2 Variation in Work
The more common understanding and indeed the use of the term variation relates to a variation
in the scope of works. Since the very concern of this study is more focused on the variation in
works my evaluation and the main part will elaborate with this respect.
Under MDB Harmonized Edition March 2006, Variation in work is regulated and administered
Under Clause 13.1 Right to Vary (means variation which are physical include):
Changes to the quantities of any item of work included in the Contract (however,
such changes do not necessarily constitute a Variation),
Changes to the quality and other characteristics of any item of work,
Changes to the levels, positions and/or dimensions of any part of the Works,
The omission of any work unless it is to be carried out by others,
Any additional work, Plant, Materials or services necessary for the Permanent works,
including any associated Tests on Completion, boreholes and other testing and
exploratory work, or
Changes to the sequence or timing of the execution of the Works.
According to the PPA- 2011 General Condition of Contract, Modifications by Change Orders is
regulated and administered under clause 15, which comply with the Applicable laws where the
site is located.
Under PPA 2011, Sub-clause 15.1: The Engineer shall have the power to order any
modification to any part of the works necessary for the proper completion and /or functioning
of the works. Such modifications may include additions, omissions, and substitutions, changes
in quality, quantity, form, character, kind, position, dimension, level or line and changes in the
specified sequence, method or timing of execution of the works.
Under applicable law, either party can ask variation in works as per the following articles of
the Civil Code.
Article 3031: Alterations required by the client
1. Right of client
The client may demand that alterations be made in the work as originally planned where such
alterations can technically be made and are not such as to impair the solidity of the work.
Article 3034: Alterations required by the contractor
(1) Where it appears necessary for technical reasons to make alterations in the work as originally
agreed, the contractor shall, except in urgent cases, give notice thereof to the client.
(2) The contractor shall give such notice notwithstanding that the proposed alterations do not
result in the client having to pay an increased price.
The contract will usually, but not always, provides a method that allows a client to make changes
to the scope of works. By signing to this the contractor effectively consents to such changes
being made.
In construction contract and applicable law, the variation is divided into two. These are discussed
below.
8|Page
3.4.2 Nature of Variation Order
The nature of a variation order can be determined by referring to both the reasons for their
occurrence and subsequent effects. Arain and Pheng (2005) distinguished two types of variation
orders namely: beneficial and detrimental variation order.
9|Page
The valuation of variation orders may be in the form of:
Rates where contracted rates are adopted where the varied works are of similar character and
extent and executed under similar conditions to items in the contract bills (Wainwright &
Wood, 1983; JBCC, 2005);
Day works which consist of the payment of executed works on a basis calculating the prime
cost of works including materials, labor, plant hire, and transport plus a percentage addition
as agreed between parties to the contract (Harbans, 2003);
Quotation, where contractors submit a quotation to effect the work, contained in a variation
order; and
Quantum Meruit is a miscellaneous method where negotiated or agreed rates or payment are
made on a reasonable sum (Harbans, 2003).
Ming et al. (2004) defined a generic variation management process this consists of four stages,
startup, identify & evaluation, approval, and implement & review.
Start-Up
This contains the proactive requirements that are essential for effective variation management.
These requirements enable the project team to respond readily to variation, to manage variation
effectively, and to facilitate contingency plans for any anticipated variation.
Identify and Evaluate
During a construction project, some variations can be anticipated while others may occur
unexpectedly. The aim of the project team is to actively seek to identify potential variations at
the earliest opportunity. This can be achieved by considering whether any of the potential
variation causes are likely to be present in a project. Once a potential variation is identified,
evaluation can be carried out in order to assist with the decision making the process. Evaluation
steps may include implications assessment and optimum selection of variation options.
Approval
Once the evaluation step has been completed it will need to be approved by an appropriate
member of the team (usually the project manager) and maybe by the client depending on the
nature of the variation. In order to approve a variation, it is necessary for the people involved to
see the impact that the variation will have on the project. There may be several iterations during
the approval process.
Implement and Review
Once a variation is approved, it needs to be communicated to all team members whose work is
affected by the variation. If necessary, the schedule of work needs to be adjusted and a new
schedule needs to be agreed on by the whole team. Finally, the project team should review and
learn lessons from the process of the variation event.
Both instructed and approved variations are discussed in detail in the next chapters.
10 | P a g e
3.4.5 Supplemental agreement
A supplemental agreement (SA) is a formal agreement between the contracting parties amending
the contract.
Use a Supplemental Agreement to:
assign the contract changes from one entity to another
change the legal name of the contractor or
settle disputes involving a surety.
3.4.5.1 Assignments
Under FIDIC clause 1.7 Neither Party shall assign the whole or any part of the Contract or any
benefit or interest in or under the Contract. However, either Party:
may assign the whole or any part with the prior agreement of the other Party, at the sole
discretion of such other Party, and
may, as security in favor of a bank or financial institution, assign it's right to any amounts of
money due, or to become due, under the Contract.
3.4.5.2 Change the Legal Name of the Contractor
When a contractor changes its legal name they must advise the department so that any
incomplete contract may be modified to reflect the new legal name. A supplemental agreement
is used to accomplish the modification of the contract.
Submit name change requests received from the contractor to Construction Division, Contract
Letting & Contractor Prequalification Branch for approval Construction Division will:
verify the legal filing of the name change
obtain administrative approval
prepare the supplemental agreement
obtain the executed agreement, insurance, and applicable bonds in the new name of the
contractor for construction contracts.
send copies to the contractor, Finance Division, and the district
3.4.6 ENGINEER
An independent engineer, designated ‘the Engineer’ is appointed by the employer to supervise
construction, ensure compliance with the contract, authorize variations, and decide payments
due; but his decisions can be taken by the employer or contractor to conciliation procedures,
adjudication and/or arbitration. (Alan C. Twort and J. Gordon Rees 2004)
According to MDB FIDIC 2006, Sub-Clause 1.1.2.4 “Engineer” means the person appointed
by the Employer to act as the Engineer for the purposes of the Contract and named in the
Contract Data, or other person appointed from time to time by the Employer and notified to the
Contractor under Sub-Clause 3.4 [Replacement of the Engineer].
According to PPA 2011, the “Engineer” is the person named in the Special Conditions of
Contract (or any other competent person appointed by the Employer and notified to the
Contractor, to act in replacement of the Engineer) who is responsible for supervising the
execution of the Works and administering the Contract.
11 | P a g e
3.4.7 Value engineering
Value engineering is a systematic application of recognized techniques which identify the
functions of the product or service, establish the worth of those functions, and provide the
necessary functions to meet the required performance at the lowest overall cost. (Urmila A
Mahadik, Anil B Mahadik 2015)
Value engineering has for its purpose the efficient identification of unnecessary cost, i.e., the
cost which provides neither quality nor use nor life nor appearance nor customer features. It
focuses the attention of engineering, manufacturing, and purchasing on one objective –
equivalent performance for a lower cost. It results in the orderly utilization of low-cost
alternative materials, low-cost alternative processes including new processes, and abilities of
specialized suppliers to procure items at lower costs. ( Miss Apurva J Chavan 2013)
Value engineering studies may be performed by Consultants during design development as a
contractor performed pre-construction services or by the contractor during construction. The
most effective time to conduct such studies is during design development. Some construction
contracts contain a value engineering incentive provision that allows the contractor to share in
the savings that result from approved value engineering change proposals. Value engineering
change proposals submitted by the contractor are reviewed by the consultant and owner for
acceptability. If approved, up to 50% of the savings in construction cost may go to the contractor.
The percentage split between the owner and the contractor will be stated in the value engineering
provision of the contract.
Benefits of VE
Value engineering is used :( Urmila A Mahadik 2015)
To determine the best design alternative
To reduce cost
To identify problems and develop solutions for them
To improve quality
To increase reliability, availability, and customer
To save time
12 | P a g e
CHAPTER FOUR: INSTRUCTED VARIATION
4.1 definition
The phrase "instructed variation" in construction contracts has no direct technical meaning. It is
a written order issued to the contractor after agreement of the contract by the owner, which
authorizes a change in the work or an adjustment in the contract sum or even the contract time
(Clough and Sears, 1994). In general, it can be defined as the instruction given by the
employer/engineer to the contractor in order to vary the scope of the work after the execution of
the contract.
4.2 Causes of Instructed Variation
These causes of Variations were grouped under four categories:
Employer-related Variations,
Consultants related Variations;
Contractor-related Variations and
Other Variations.
The root causes of Variations some of which are financial, design aesthetics, changes in
drawings, weather, geological and geotechnical reasons.
13 | P a g e
Lack of coordination:
Design complexity:
Inadequate working drawing details:
Inadequate shop drawing details:
Consultant's lack of judgment and experience:
Lack of consultant's knowledge of available materials and equipment:
Honest wrong beliefs of consultant:
Consultant's lack of required data:
Obstinate nature of consultant:
Ambiguous design details:
Design discrepancies (inadequate design):
Noncompliance of design with government regulations:
Noncompliance of design with owner's requirements:
Change in specifications by the consultant:
14 | P a g e
4.2.4 Other Variations
This section discusses the causes of Variations that were not directly related to the project team.
Weather conditions
Safety considerations
Change in government regulations
Change in economic conditions
Socio-cultural factors
Unforeseen problems
15 | P a g e
normally led to disruptions and these disruptions were responsible for labor productivity
degradation. The most significant types of disruptions were due to the lack of materials and
information as well as the work out of sequence. Lack of material was reported as the most
serious disruption, because labors could not continue their works and end up idling while waiting
for the materials to be available. Hence, to manage Variations, one needed to manage these
disruptions. However, the disruptive effects could not be avoided in many instances.
16 | P a g e
consultant in terms of a fair valuation of a variation. Bower (2000:264) argued that parties to a
contract have been left to argue over the cost, time effects and due compensation of a variations.
Since the contractors are pessimists of the outcome of the negotiations, they usually allow higher
value than the real cost incurred. Bower (2000:264) opined that this causes the contention
between parties as to the contractor continually push the client to settle the claim for
additional costs while invariably feeling that the reimbursement has been insufficient. As a
consequence, this can be very damaging to the relationship between all parties' representatives
(Bower 2000:264). Charoenngam et al (2003:197) remarked that disputes between the Employer
and the contractor can occur if the Variations undertaking is not managed carefully. Harbans
(2003:42) warned that unless a mutually acceptable solution is agreed by the parties, the
valuation of variations would remain at the forefront of disputes and claims making their way
ultimately to arbitral tribunals or the corridors of justice. Ssegawa (2002:92) revealed that more
than one-third of disputes occur pertain to how to ascertain losses arising from variations. The
excessive occurrence of variations due to design errors or omission may undermine the
professionalism of the designer. Furthermore, workers get demoralized when they demolish a
portion of work that has already been done.
17 | P a g e
4.4 To reduce the number and the Impact of Variations
Controls for Variations and Variation Orders have been suggested by many researchers
(Mokhtar et al., 2000; Ibbs et al., 2001). Below are 30 approaches identified from a literature
review to reduce the number and the impact of Variations. These approaches were categorized
into three categories: Design stage, Construction stage and Design-Construction interface stage.
18 | P a g e
may reduce the design errors and noncompliance with the Employer's requirements. (O'Brien,
1998)
Reducing contingency sum
The provision of a large contingency sum may affect the construction team' working approaches.
This is because the designer may not develop a comprehensive design and would consequently
carry out the rectifications in design as variations during the later stages of the construction
project. Therefore, reducing the contingency sum would be helpful in ensuring that the
professionals carry out their jobs with diligence.
19 | P a g e
Appointment Project manager from an independent firm to manage the project
The involvement of a project manager from an independent firm would assist in eliminating
variations that arise due to the lack of coordination among professionals. This practice may assist
in reducing design discrepancies through early reviews of the contract documents and drawings.
(Arain et al., 2004)
Restricted pre-qualification system for awarding projects
A restricted pre-qualification system for awarding projects would act as a filter to select only
the capable Contractors for project bids. (Chan and Yeong, 1995; Fisk, 1997)
20 | P a g e
4.4.3 Design-Construction Interface Stage Approach to Control Variations
Prompt approval procedures
One of the most aggravating conditions is the length of time that elapses between the time when
a proposed contract modification is first announced and when the matter is finally rejected or
approved as a variation. However, the longer the period between recognition and
implementation, the more costly the change will be. (Fisk, 1997).
21 | P a g e
Comprehensive site investigation
Comprehensive site investigations assist in proper planning for construction activities. Differing
site conditions are an important cause of delays in large building projects. Therefore, a
comprehensive site investigation would help in reducing potential Variations in a project. (Fisk,
1997).
Use of collected and organized project data compiled by Employer, consultant and
Contractor
The Variations works should always be documented for future references. Hence, better controls
for Variations were achievable by sharing a database compiled by all the team members
(Fisk,1997).
A Change Order is a written instrument prepared by the Architect and signed by the Owner,
Contractor, and Architect (Libor et al, 2003).
A variation order is a formal document that alerts some conditions of the contract documents.
The word 'formal' implies legal binding and as such all variations should be in writing and verbal
variations should be avoided( Edward 1998). Although, there is no mandatory form, owners
usually have their own forms and procedures that must be followed to process a variation.
The complexity of procedures is a problem in large organizations. Too many control systems
and technical department approvals become barriers to an efficient variation order procedure.
The inefficiency cost could be quite enormous. In addition, the level of trust between the parties
has a direct impact on the simplicity or complexity of the variation order procedures. The less
the trust, the more cumbersome is the procedure.
22 | P a g e
If the Engineer requests a proposal, prior to instructing a Variation, the Contractor shall respond
in writing as soon as practicable, either by giving reasons why he cannot comply (if this is the
case) or by submitting:
(a) a description of the proposed work to be performed and a program for its execution,
(b)the Contractor’s proposal for any necessary modifications to the program according to Sub-
Clause 8.3 [Programme] and to the Time for Completion, and
(c) the Contractor's proposal for the evaluation of the Variation. The Engineer shall, as soon as
practicable after receiving such proposal (under Sub- Clause 13.2 [Value Engineering] or
otherwise), respond with approval, disapproval or comments. The Contractor shall not delay any
work whilst awaiting a response. Each instruction to execute a Variation, with any requirements
for the recording of Costs, shall be issued by the Engineer to the Contractor, who shall
acknowledge receipt. Each Variation shall be evaluated in accordance with Clause
12[Measurement and Evaluation], unless the Engineer instructs or approves otherwise in
accordance with this Clause.
4.6 Valuation of Variation
Construction contracts are complex both in nature and the process required to realize the finished
product. So variation is common on construction projects. Variation orders are typically issued
in the form of contract instructions. Once a variation order has been instructed and works are
carried out, the employer has to reimburse the contractor for the same. This obligation of the
employer involves certain activities or stages for the measurement of works, valuation of the
varied works and payment for the varied works.
Under Sub-Clause 13.5 of MDB FIDIC 2006, Provisional Sums, it is stated that;
Each Provisional Sum shall only be used, in whole or in part, in accordance with the Engineers
instructions and the Contract Price shall be adjusted accordingly. The total sum paid to the
Contractor shall include only such amounts, for the work, supplies or services to which the
Provisional Sum relates, as the Engineer shall have instructed.
For each Provisional Sum, the Engineer may instruct work to be executed (including Plant,
Materials or services to be supplied) by the Contractor and valued under Sub-Clause 13.3
[Variation Procedure];
Valuation of Variation can also be done in day work bases MDB FIDIC 2006 Sub-Clause 13.6.
As per the Clause 15.5 of PPA 2011, the prices for all modifications ordered by the Engineer in
accordance with GCC Clause 15.2 and 15.4 shall be ascertained by the Engineer in accordance
with the following principles:
Where work is of similar character and executed under similar conditions to work priced in the
bill of quantities or price schedule it shall be valued at such rates and prices contained therein;
Where work is not of a similar character or is not executed under similar conditions, the rates
and prices in the contract to be agreed through negotiation between the Engineer and the
Contractor shall conform to the prevailing market price;
If the nature or amount of any modification relative to the nature or amount of the whole of the
contractor to any part thereof shall be such that in the opinion of the Engineer any rate or price
23 | P a g e
contained in the contract for any item of work is by reason of such modification rendered
unreasonable, then the Engineer shall fix such rate or price as in the circumstances he shall think
reasonable and proper.
4.7 Right to Vary
The employer’s right to vary derives from the contract and therefore it must be exercised in
accordance with the express restrictions and procedures set out in the contract. This section also
discusses the way in which implied terms may restrict the power to vary the works. Generally
speaking, the power to vary the works under a construction contract is drawn very widely. It is
of considerable benefit to the employer to have no, or limited, restrictions on its right to vary. If
unexpected problems arise on a project the employer will want as much flexibility as possible
to vary the works so as to achieve its objectives. This power will often allow the employer not
just to change the permanent works, but also many other aspects of the conditions on site and
how the works are undertaken.
24 | P a g e
Article 3284(1) – 2. New work
The administrative authorities may, against payment of additional remuneration, require the contractor
to perform works which were not mentioned in the contract.
Variation clauses are not always expressly called “variation clauses”. When considering any
proposed variation, it is important to first review all of the documents that make up the contract.
If it is still unclear whether or not there is a clause covering a particular variation, seek
appropriate advice.
If there were no provision in the contract for varying the work to be done, then any attempt by
the employer to vary it would require the agreement of the contractor. The lack of a provision
for variations would effectively enable the contractor to negotiate a new price for the whole
contract every time the employer tried to make a change. This apparent difficulty is not as
rigorous as it sounds. The absence of a variations clause undoubtedly makes it difficult to vary
the terms of the contract but it is at least possible that the courts would imply a term allowing
minor variations to be made. In any event, it would, of course, be most unusual for a contractor
to attempt to refuse to carry out small changes and even less likely that the contractor would go
to court over an attempt to impose them.
By inserting a clause allowing for changes to be made to the works as they are being built, the
employer, through the contract administrator, can alter the works as and when necessary. The
purpose of the variations clauses is to allow such changes to be made, and also to permit any
consequential changes to be made to the contracts.
25 | P a g e
CHAPTER FIVE: APPROVED VARIATION
5.1 introduction
The contractor normally has no right to vary/alter and/or modify of the permanent works and
the terms of the contract. But he can make suggestions as to how the work might be varied, for
his own benefit or the benefit of the employer or both. When the contractor submits his proposal
by his own opinion or by a request of the engineer for the Contractor to submit a proposal and
approved by the engineer we call it an approved variation.
The Contractor shall not make any alteration and/or modification of the Permanent Works,
unless and until the Engineer instructs or approves a Variation. (MDB FIDIC 2006, Sub-Clause
13.1)
If the variation is needed by the contractor it is required to submit a proposal to the engineer for
his approval.
The Contractor may, at any time, submit to the Engineer a written proposal which (in the
Contractor’s opinion) will, if adopted, (i) accelerate completion, (ii) reduce the cost to the
Employer of executing, maintaining or operating the Works, (iii) improve the efficiency or value
to the Employer of the completed Works, or (iv) otherwise be of benefit to the Employer. (MDB
FIDIC 2006, Sub-Clause 13.2).
Therefore, if such a written proposal is approved by the engineer, the variation due to it is called
an approved variation.
The benefit to the Employer: When the proposed variation benefits the employer.
26 | P a g e
5.3 Procedure for Approved Variation
As per MDB FIDIC 2006, Sub-Clause 13.2 and 13.3, the procedure for an approved variation
shall be as follows;
The proposal shall be prepared at the cost of the Contractor and shall include the items listed
in Sub-Clause 13.3 [Variation Procedure].
A description of the proposed work to be performed and a Program for its execution,
The Contractors proposal for any necessary modifications to the Program, according to
Sub-Clause 8.3 [Program] and to the Time for Completion, and
The Contractors proposal for the evaluation of the Variation.
The Engineer shall, as soon as practicable after receiving such a proposal respond with
approval, disapproval or comments.
If the proposal approved, the contractor proceed to perform the work
If this change results in a reduction in the contract value of this part, the Engineer shall
proceed in accordance with Sub-Clause 3.5 [Determinations] to agree or determine a fee,
which shall be included in the Contract Price.
In the case of PPA condition of contract, there is no clause that states the procedure of variation
5.3 Result of approved variation
If the Contractor has a proposal which would reduce its costs without reducing the value to the
Employer, According to MDB FIDIC2006, Sub-clause 13.3 The Contractor is required to submit
its proposal for the benefit of both employer and contractor by way of improving efficiency or
cost of operating or maintaining the works and if such value engineering under MDB FIDIC
2006, Sub-Clause 13.2 (c) In that case the Engineer is required to make a determination under
Sub-Clause 3.5 of the reduction in value to the Employer. If the reduction in value is less than
the reduction in cost to the Employer, the benefit is split 50/50.
5.4 Possible Design Liability of the Contractor
As per MDB FIDIC 2006, Sub-Clause 13.2; if a proposal, which is approved by the Engineer,
includes a change in the design of part of the Permanent Works, then unless otherwise agreed
by both Parties: The Contractor shall design this part and sub-paragraphs (a) to (d) of Sub-Clause
4.1 [Contractor’s General Obligations] shall apply.
That means the contractor shall be responsible/liable for this part and it shall, when the Works
are completed, be fit for such purposes for which the part is intended as are specified in the
Contract. (Sub-Clause 4.1 (c))
5.5 value engineering
Value Engineering (VE) is a management technique that seeks the best functional balance
between cost, reliability, and performance of a product, project, process or service.
Value engineering is a powerful problem-solving tool that can reduce costs while maintaining
or improving performance and quality requirements. Value engineering can improve decision-
making that leads to the optimal expenditure of owner funds while meeting the required function
27 | P a g e
and quality level. The success of the VE process is due to its ability to identify opportunities to
remove unnecessary costs while assuring quality, reliability, performance, and other critical
factors that meet or exceed customer's expectations.
The construction industry uses the concept of value engineering to improve a project by coming
up with alternatives to design, processes and materials. All of this hinges on understanding the
needs of the owners, users and the spirit of the project.
The intention of Value Engineering is to encourage Contractors to apply their knowledge and
experience to the benefit of both the Contractor and the Employer. A Contractor may benefit in
two ways from a variation it proposes. It may benefit because its costs of production are reduced
but the Employer receives a product which is as good as that originally designed. Alternatively,
it may find a way in which it increases the value of the final product to the Employer without
incurring additional costs.
As per MDB FIDIC 2006, Sub-Clause 13.2: It is the Contractor’s written proposal (with his
opinion) submitted to the engineer for his approval if adopted, the proposal accelerates
completion, reduce the cost to the Employer of executing, maintaining or operating the Works,
improve the efficiency or value to the Employer of the completed Works, or otherwise be of
benefit to the Employer.
As per PPA 2011, Clause 75: When the Public Body wants the Contractor to finish before the
Intended Completion Date, the Engineer will obtain priced proposals for achieving the necessary
acceleration from the Contractor. If the Public Body accepts these proposals, the Intended
Completion Date will be adjusted accordingly and confirmed by both the Public Body and the
Contractor. (Sub-Clause 75.1)
If the Contractor’s priced proposals for acceleration are accepted by the Public Body, they are
incorporated in the Contract Price and treated as a modification. (Sub-Clause 75.2)
The effects of value engineering are as follows; (MDB FIDIC 2006)
Value engineering is under the control of the contractor since it is restricted to his opinion on
the matter. (Sub-Clause 13.2)
The contractor costs additional costs in preparing a proposal. (Sub-Clause 13.2)
It benefits both parties if the reduction of the cost being the case of value engineering.
The contractors will seek different alternatives to gain the advantages of value engineering if it
is properly habited in the construction industry.
If designing part of the works in the contract is constituted in value engineering, the contractor
will be liable for this part. Thus, the obligation of the contractor increased.
Determination of fee for approve variation will be done as per Sub-Clause 3.5 and at this Clause,
the estimation of what is reasonable is left to the discretion of the engineer that may lead to
dispute when the parties disagreed.
28 | P a g e
5.6 Possibility to change or not change the delivery system from DBB to DB
The Contractor has the right to submit proposals for variations which may accelerate completion,
reduce the cost either of completing the Works or of their ultimate maintenance or operation,
improve the efficiency or the value of the Works or otherwise benefit the Employer.
The proposal is provided at the Contractor’s cost and must include a description of the proposed
changes and a program, details of any modifications necessary to the pre-existing program and
the Time for Completion and the proposed payment.
If the proposal requires a design change, then, unless otherwise agreed, the new design will have
to be prepared by the Contractor, according to MDB FIDIC 2006 sub-clause 13.2
If the Contract specifies that the Contractor shall design any part of the Permanent Works, then
unless otherwise stated in the Particular Conditions, the Contractor shall be responsible for this
part and it shall, when the Works are completed, be fit for such purposes for which the part is
intended as are specified in the Contract, according to MDB FIDIC 2006 sub-clause 4.1(c).
Therefore, if the contractor prepares his proposal to redesign the whole permanent work for the
benefit of both employer and contractor and approved by the engineer, then the contractor shall
redesign and responsible for the whole permanent works. This means the responsibility will be
transferred from the designer/consultant to the contractor. But the project delivery method shall
not be changed from DBB to DB.
29 | P a g e
CHAPTER SIX: COMPARISON BETWEEN INSTRUCTED
AND APPROVED VARIATION
the contractor shall not make any alteration The proposal should include
of permanent work unless and until the Description of proposed work to be
engineer instructs or approves the variation. performed and program for its
execution.
The contractor's proposal for the
For work of minor nature, the engineer may evaluation of the variation.
instruct that a variation shall be executed on
a day work basis if a day work schedule If a proposal which is approved by the
includes a contract. engineer, includes a change a change of
permanent works the contractor should
design this part
30 | P a g e
CHAPTER 7: THE ROLE OF ENGINEER
32 | P a g e
B. Contract administrator Especially the role of the consultant as a contract administrator divided
into the following distinct role.
Agent Role
When the engineer act as an agent it has its own power and function
The following are some of the important powers of the consultant.
If it is authorized by the client it has the Power to make contracts.
If it is authorized by the client it has the Power to instruct variations,
If it is authorized by the client it has the Power to order a suspension of the performance
of the works,
The following are some of the important functions of the Engineer advising the employer;
on costs of the project;
on the appointment of particular contractors;
On the appointment of subcontractors;
Contract documents;
Contract drawings;
and any other amendment thereof (BOQ);
Professional or independent Role;
Consultative role;
Professional Role
The independent role of the consultant may be expressed in the following professional functions.
Certification function; the consultant may certify & issue the following certificates under the
terms of the construction contract.’
Interim Payment Certificates;
Final Payment Certificate;
Event Recording Certificates;
Consultative Role Undertaking Consultation both with the employer & the contractor, under the
relevant construction contract, before making any determination.
33 | P a g e
Under PPA 2011 GCC:
Have the power to Order any modification to any part of the works necessary for the
proper completion and /or functioning of the works in writing by notifying the
Contractor of the nature and form of such modification (Sub-Clause 15.1, 15.2 & 15.3)
If the contractor submitted the proposal about the variation after engineer’s notification,
the Engineer shall, after due consultation with the Public Body and, where appropriate,
the Contractor, decide as soon as possible whether or not the modification shall be
carried out. (Sub-Clause 15.4)
If the Engineer decides that the modification shall be carried out he shall issue the
change order stating that the modification shall be carried out at the prices and under the
conditions given in the Contractor's submission or as modified by him. (Sub-Clause
15.4)
Ascertain prices for all modifications ordered by him. (Sub-Clause 15.5)
Determines any reduction from the contract price after consultation with the Public
Body and the Contractor as a consequence of the application Sub- Clause 15.5. (Sub-
Clause 15.7)
Under civil code: The role of the engineer has not been mentioned.
Change of plan or design of the project is one of the most significant causes of variation and scope
change in construction projects. The contribution of design to scope change is due to poor design
like Errors and omissions in design, not involvement of owner during design, design complexity, the
client may change his needs and requirements on project design and using value engineering
regarding to design may change the scope of the projects.
34 | P a g e
CHAPTER 8: CASE STUDY ABOUT THE VARIATION
8.1 introduction
A variation (sometimes referred to as a variation instruction, variation order (VO) or change
order), is an alteration to the scope of works in a construction contract in the form of an addition,
substitution or omission from the original scope of works. Almost all construction projects vary
from the original design, scope, and definition. Whether small or large, construction projects
will inevitably depart from the original tender design, specifications, and drawings prepared by
the design team. This can be because of technological advancement, statutory changes or
enforcement, change in conditions, geological anomalies, non-availability of specified
materials, or simply because of the continued development of the design after the contract has
been awarded. In large civil engineering projects, variations can be very significant, whereas on
small building contracts they may be relatively minor
8.2 Background of the case
The project located in Dire Dawa city, around Mariam sefer and its an apartment building
project. The original project cost is 983,068,939.66 birr (Nine hundred eighty-three million
sixty-eight thousand nine hundred thirty-nine birr & sixty-six cent).
There were numerous additional works associated with the continuously revised works this is
the main reason for the occurrence of variation.
Causes of variation
1. Some additional works by the contractor due to design problems
2. Due to change in some finishing materials
3. Some activities are not listed on the previous document
4. Due to the current cost of construction materials
5. Quantity variation due to improper preparing of take-off sheet and BoQ
35 | P a g e
Variation amount 92,827,015.65
Total project cost 1,075,895,955.31 ETB (including variation)
Contract Time – 1095 Calendar Day
Site Hand Over – June 1/2017
Mobilization Time – 60 Calendar Day
Commencement Date- July 31/2017
Contract Completion Date – July 31/2020
Total number of blocks- 20 Blocks
Based on their number of bedroom classified as
One bed type 5
Two-bed type 8
Three-bed type 7
36 | P a g e
CHAPTER 9: COMPARATIVE TABLE AND ANALYSIS
37 | P a g e
3. Value Engineering The basic concept of Value There is no a value engineering
Engineering is more detailed and concept under PPA-2011
properly addressed by MDB-FIDIC General Conditions of Contract
2006
Similarity: there is no similarity.
Difference: exist.
38 | P a g e
7. Adjustments for In MDB-FIDIC 2006 the contractor In PPA-2011 Sub Clause 16.1
Changes in has the right to ask any adjustments Unless otherwise expressly agreed
Legislation regarding to cost and time whenever in the SCC. if, after the deadline
he feels that he suffers from for submission of the Bid then such
additional cost as a result of changes Contract Price shall not
in the laws of the country, including be correspondingly increased or
the introduction of new laws and decreased and/or the Completion
modification of the Date shall not be adjusted to the
existing one. extent that Contractor has thereby
been affected in the performance
of any of its obligations under the
Contract
Similarity: no similarity
Difference: exist
TABLE 2 COMPARATIVE TABLE AND ANALYSIS
39 | P a g e
CHAPTER 10: CONCLUSION AND RECOMMENDATION
10.1 conclusions
Variations are often a source of dispute and consume a lot of time and money in arguments and
negotiations. Accordingly, for building and engineering works, the causes of variation in works
are: Employer related variations, Consultants related variations, and Contractor related
variations and other variations. For those variations, some of the root causes are financial, design
aesthetics, changes in drawings, weather, geological and geotechnical reasons. The studies have
shown that inadequate workings drawing details, design discrepancies, and conflicts between
contract documents are the most prevalent sources of variations due to consultants, change of
plans or scope by the owner, impediment in the prompt decision-making process, and inadequate
project objectives contributed mostly to variations by the owner. Contractors' prevalent reasons
for variations are differing site conditions, shortage of skilled manpower, and contractor's
desired profitability.
To minimize the above causes of variations, we have to follow and apply the approaches that
use to reduce the number and the impact of variations, which are the Design stage, Construction
stage and Design-Construction interface stage.
In our study we have seen the most of variations occurred due to improper design, poor project
objective/ scope, design discrepancies, and conflicts between contract documents are the most
prevalent sources of variations due to owner /engineer and differing site conditions are the main
reasons for variations by Contractors. Those different variations result in to increase in project
cost and time overruns of a project.
10.2 recommendation
This study focused on the variation orders in construction projects, while variation cannot be
completely avoided but it can be reduced. To reduce the occurrence of variation orders
recommendations from the analysis were stated as follows:
The client should allow sufficient time to prepare an elaborately detailed project brief. This
will eliminate frequent variations to the original plan of the project due to the client change
of mind.
Direct communication among the project team is a key to eliminate variations that occur due
to the communication gap during the design and execution phase.
Enhance communication and all parties should be proactive all times.
Consultants should give sufficient time for the planning and design phase, this will assist in
minimizing variation orders due to design changes at the construction stage.
The owner should give a reasonable time period to the Consultant for preparing a complete
design and records.
The owner should perform a comprehensive and integrated study for the projects
40 | P a g e
A detailed design would be able to exert control to unnecessary interference from consultants
or other external influences.
The consultants should prepare a completed contract document before the tendering stage.
This minimizes variation occurs due to the change of specifications.
Direct communication among the project team is a key to eliminate variations that occur
due to the communication gap during the design and execution phase.
There should be an improvement in project management, and improved decision-making
process on the part of the client during the project execution stage so as to minimize the
occurrence of variation.
41 | P a g e
Reference
MDB-FIDIC (2006); conditions of contract for construction for building and engineering
works designed by the employer.
PPA (2011) General Conditions of Contract for Procurement of Works
Bin-Ali, Z, 2008, ‘Causes and Steps to Minimize Variations in Construction Projects’,
Thesis, Technology University of Malaysia
CII, (1990); The Impact of Changes on Construction Cost and Schedule, Construction
Industry Institute, University of Texas, Austin
CII, (1995); Qualitative effects of Project Changes, Construction Industry Institute,
University of Texas, Austin
Arain, F.M. & Pheng, L.S. 2005b, How Design Consultants Perceive Causes of Variation
Orders for Institutional Buildings in Singapore', Architectural Engineering and Design
Management, vol. 1, no. 3.
Bin-Ali, Z, (2008); Causes and Steps to Minimize Variations in Construction Projects,
Thesis, Technology University of Malaysia Saukkoriipi, L. & Josephson, P.E. 2006
Ibbs, C.W. 1997, 'Quantitative Impacts of Project Change: Size Issues', Journal of
Construction Engineering and Management, vol. 123, no. 3.
Osman, Z., Omran, A., FOO, C. 2009, The potential effects of variation orders in
construction projects, Journal of Engineering annals of Faculty of Engineering,
Hunedoara.
Ruben, N. 2008, "An analysis of the impact of variation orders on project performance"
Zimmerman, L. & Hart, G. 1982, 'Value Engineering - A practical approach for Owners,
Designers and Contractors', New York: Van No strand Reinhold Company
Alan C. Twort and J. Gordon Rees, 2004 “Civil Engineering Project Management”
Linacre House, Jordan Hill, Oxford OX2 8DP 200 Wheeler Road, Burlington, MA
01803, Britain.
Websites
www.academia.edu
http://onlinemanuals.txdot.gov/txdotmanuals/cah/supplemental_agreements.htm
42 | P a g e