Sunteți pe pagina 1din 14

Method for Determining Minimum 'Vaiting-on-cement Time

By R. FLOYD FARRIS·
(Tulsa and Houston Meetings, October 1945)

ABSTRACT prescribed by this formula were found to drill


"firm to hard," thus confirming the laboratory
A METHOD is presented for determining mini-
tests.
mum waiting-on-cement time, which takes into
These tests prove that many of the present
account the differences that exist between
regulations for waiting on cement require a
types and brands of cements and such indi-
longer time than is absolutely necessary. Use
vidual well conditions as depth, temperature,
of the method herein proposed offers the possi-
and pressure.
bility of a saving of $1200 per well.
The basis for the method was determined
by laboratory tests. Being a laboratory devel-
INTRODUCTION
opment, several steps were required to prove
its merit. The first step consisted of laboratory The length of time allowed for cement
tests designed to determine the minimum to set after casing is determined either by
cement strength required in wells. Basis was state-wide rules, field rules, or self-imposed
found for setting a minimum value of 8 lb. rules written into drilling contracts. In
per sq. in. tensile strength. Next, it was shown
general, the time is dictated by experience
by laboratory tests that the time to 8 lb. per
sq. in. tensile strength may be expressed as
and common practice, However, owing to
a function of consistometer stirring time to differences in opinion and in experience
100 "poises," the approximate relation being of the various groups involved, waiting-
"the time to 8 lb. per sq. in. tensile strength on-cement time often varies from one area
equals the time to 100 'poises' times three." to the next. For example, an operator
Next, it was shown that the time of maximum in an area where no rules exist may drill
temperature development in cement slurries, out of surface pipe at 24 to 36 hr., while
due to heat of hydration, is also related to another operator in another area may wait
consistometer stirring time to 100 poises, but 48 hr. or more to comply with state or
only by a factor of approximately two. It was
field rules, although the depth of the well,
shown also that the shut-in casing pressure
will build up after cement is placed and register
hole size, type of cement, and other data
a maximum pressure at approximately the arc identical. An even greater difference
same time the slurry down the hole attains in practices will De found by making
maximum temperature. From this and the similar comparisons with respect to oil-
relationships listed above, the general rule string cement jobs. Differences in waiting-
was established that minimum waiting~on­ on-cement times of 36 to 48 hr. are common.
cement time (time to 8 lb. per sq. in.) after Further complicating the picture is
casing cement jobs in any well is equal to the the rather common practice of allowing
time when the shut-in casing pressure reaches more waiting time for cement to set at
a maximum, as measured from the initial
the greater depths than is allowed at the
mixing of cement, times a factor of 1.5.
Cement plugs drilled in the field at the time shallow depths. This practice has existed
for years in spite of the common knowl-
Manuscript received at the office of the edge 1,I,a that the temperature of the earth
Ipnstitute Sept. 4, 1945. Issued as T.P. 1968 in at the usuaJ setting depths of surface
ETROLEUM TECHNOLOGY, January 1946.
• Stanolind Oil and Gas Co., Tulsa, Okla-
homa.
1 References are at the end of the paper.
175
176 METHOD FOR DETERMINING MINntUM WAITING-ON-CEMENT TIME

casing is much less than that at the gested that cement in wells Olay set and
depths at which oil strings are set, and gain adequate strength in much less time
that increased temperature grea,tly accel- than normally is allowed for that purpose.
erates the rate of setting and hardening of This finding led to the development of a
cement. simple method for determining the mini·

MEAT CEME.NT

FIG. I.-CEMENT IN ANNULUS. FIG. 2,-ApPARAl'US FOR MEASURING BONDING


End view of S%-in. o.d. casing inside 9~·in. STRENGTH OF CEMENT IN ANNULUS.
o.d. casing.
mum waiting-on-cement time, which will
The foregoing thoughts suggest lack of a apply to any welJ condition. The purpose
fundamental basis for determining waiting- of this paper is to describe the laboratory
on-cement time. and field tests that contributed to the
The minimum strength cement must development of this method.
develop in a well before it will secure
pipe in the hole, exclude undesirable well BASIS OF METHOD
fluids, and withl)tand the shock of drilling, The expression "waiting-on·cement
and how long cement must stand before time," hereinafter referred to as woe
it attains that minimum strength, are time, simply means the time spent in
questions often discussed but never com- waiting for the cement to set and gain a
pletely answered. The industry has oper- given. minimum strength. Thus, any
ated to the present time without the logical system for determining woe
answers to these questions, simply by time must be based on minimum require-
allowing long waiting periods for the ments for cement strength used in wells.
cement to set. Thus, since experience has Once this has been established, the time
taught that waiting periods ranging from to that strength can be reasonably accu·
36 to 72 hr. would give satisfactory rately determined.
results, these periods have become standard To obtain information as to what
practice in many areas; however, it is easy strength cement should develop in wells
to understand how a practice derived in before it is drilled out, laboratory tests
this manner might include more time than were conducted in which a correlation was
is absolutely necessary. made between cement tensile strength and
Experiments conducted in the Stanolind the bonding strength of cement in an
Oil and Gas Co. Re!ICarch Laboratory sug- annulus. The apparatus consisted of seven
R. FJ..OYD .FARRIS 177

pieces of 9~-in. o.d. pipe s ft. long, m-


Returning to the questiGn of how much
to which were €entered t,imilar lengths strength cement should develop in a well
of sU-in. o.d. pipe. Standard portland before it is drilled out, one can reason that
cement slun:y weighing 15.6 lb. per gal. it would not be safe to drill out cement
was poured into the annulus of each unit', before it reaches the initial set, even though
to a height of 4 ft. Some of the same the data in Table 2 indicate that the
slurry was placed in briquette molds for slurry may support the pipe, because it is
tensile-strength tests; also, cement slurry not until after the initial set that the slurry
was placed in Vicat molds for determina- " passes from the fluid state into that of a
tion of initial and final set. The cement was l solid. In fact, solidification of cement
cured at atmospheric temperature, approxi- may not be caIled complete until it has
mately go°F. An end view of the cement reached the final set. Therefore, since
in the annulus between the two sizes of pipe drilling inside of casing before the cement
is shown in Fig I. on the outside reaches its final set could
The bonding strength of the cement possibly reduce it to the fluid or semifluid
in the annulus was determ,ined by meas- state, it is obvious that cement should not
uring the force that must be appUed to the be drilled out before it reaches the final
5N~in. pipe to break the cement bond and set, which corresponds to a tensile strength
move it with respect to the outside (9%-in.) of approximately 8 lb. per sq. inch.
pipe. The means of doing this is illustrated
by Fig. 2. Each time the bonding strength TABLE 2.-Strength 0/ Cement
of cement in the annulus was tested, Length of Pipe
observations were made of the correspond- FOf1)8 *Ft. of Cement
ill Support. Pt.
ing cement strength and the progress Ce. to
ment Break Cement Tensile
1 Ft. St~h.Lb.
toward the initial and final set. Table I 1f;,. Cement
f~. l~.• 13"
per • In.
presents a slimmary of the test results. Bond. In..
Lb. 17
Lb. l~. l:.
TABLE I.-Cemenl Btmdlng S{;rlngth
- roo
-- -- -
Force to Ceftlent
1.S3
l 137
0
0 l·a.0 4·1
$.7
1.3
1.9
Ceo Break
ment Bond of
Tens,Ue
Strength. Remarks
2. 3
3.0
8.66
325 o (initial set)
4 est.
10.1 13
,1,8.a
.g 4.$
13. 8
T.S 1 ~..6
1.000
Au. 4 Pt. of 'b . 4.42 4.550 8 est. (final set) 63.1
lfr. Cement.
Lb.
... per
Sq. In. ~.so
·50
5.000
$.000
t 12
ao
-----I·-------~~
1.83 400 o Soft cell1ent aturry
2.33 $SO o Soft cement slurry If cement should not be drilled out
3.08 1.300 o Initial set
3.66 4.000 4 eat. Cement stilIenins rapidly before it attains a tensile strength of 8 lb.
4·42 18.200 Sest. Pinal set
5.50 20.000+ 13 Could not l1reak bone! per sq. in., the next question is: Would it
6.50 20,000+ 10 Could not brea.k bond be safe to drill it out at a tensile strength
of 8 lb. per sq. in.? The foregoing data
The rate of increase in cement bonding strongly suggest that it would be safe to
strength is better demonstrated when these drill out cement at that strength. At-a
data are plotted on a graph. Fig. 3 shows strength of 8 lb. per sq. in., for example,
that cement has an enormous bonding Table 2 indicates that each foot of cement
strength at its final set. ia the annulus should support 267 ft. ~f
Table 2 shows the calculated load each sN-in. o.d. 17-lb. pipe, and Fig. 3 shoWs
foot of cement in an annulus win support at that the rate of bonding-strength develop-
various cement strengths, together with ment is extremely rapid at that point 'and
the length of various pipes of equivalent probably reaches even greater proportions
Weight. shortly after that time. These considera-
178 METHOD FOR DETERMINING MINIMUM WAITING-ON-CEMENT TIME

tions, together with the general feeling govern the time required for it to stitIen
that "green" cement may be drilled with to a given consistency, reach a final set or
less damage to the cement in the annulus, attain a given strength, will be water-
and in view of the fact that the full weight cement ratio, temperature, and pressure.
en
c
z
;:)
oGo I
I

~24000 I

I
60
oCD I
I

ffi 20000 I

I
50~
:r:.-
I
I-
~ 16000 40~
I&J
~ ~
I&J 12000 30 en
85 ~
o
I-
8000 1/ ./
in
20~
fiI ~
~ 4000 J / 10

tl~~~ V-~ ~
a:
: INIAL SET
I&J
o o o
a: o 2 345 6 7
ou. AGE OF CEMENT, HRS.
FIG. 3.-DEVELOPMENT OF BONDING STRENGTH.

of casing is apt to be set down on cement When well conditions or laboratory condi-
only when the casing is cemented to the tions accelerate the stiffening time of
surface, prompted the tentative conclusion cement to a given consistency, the time
that the minimum cement-strength re- to the initial set will be decreased cor-
quirement before the plug is drilled out is respondingly. Since both times are affected
approximately 8 lb. per sq. inch. by the same factors, it appears that it
should be possible to express one as a
PUDICTION OF CEMENT-STRENGTH function of the other. If the time for cement
DEVELOPMENT IN WELLS stiffening to a given consistency is related
to the time of final set (8 lb. per sq. in.
Fi,st Method
tensile strength), and if laboratory tests
Having determined by laboratory tests could be conducted to predict the actual
what appears to be the minimum strength time of stiffening of cement in wells, it
requirement of cement in wells, the next would be possible to predict with approxi-
step is to develop a method of determining mately the same accuracy the time when
when cement in wells will attain that cement in wells reaches the final set, or a
strength. Cement slurry, whether in a well strength of 81b. per sq. inch.
or a laboratory apparatus, will remain In 1941, Stanolind Oil and Gas Co.
fluid for a time after the slurry is formed, developed a method 1 of testing cements in
then it will stiffen, set, and start to develop which temperatures and pressures are
strength. Also, regardless of whether or not varied to correspond with the increasing
the slurry is in a well or in a laboratory temperatures and pressures imposed upon
apparatus, the factors that will largely cement slurries as they are pumped from
R. FLOYD FARRIS 179

surface to bottom-hole conditions of wells constant. The average ratio multiplied by


of various depths. The results obtained the time to 100 poises would quite accu-
from these tests are called cement stirring- rately predict when cement in the average
time tests to 100 poises at simulated well well attains a strength of 8 lb. per sq. in.
depths. Field tests have shown that this However, since it is desirable that cement
method of evaluating cements describes in all wells, not just in the average well,
reasonably accurately the actual perform- reach a strength of 8 lb. per sq. in. before
ance of cement slurries in wells. Table 3 it is drilled out, the largest ratio, 3, must
is a tabulation of cement stirring-time be used. In general, therefore, cement in
tests to 100 poises at various simulated wells will attain a tensile strength of at
well depths, the time to 8 lb. per sq. in. least 8 lb. per sq. in., the minimum strength
tensile strength (assumed to be equivalent requirement in wells, at a time correspond-
to the time of final set), and the ratio of ing to three times the time required for
these times. the cement to reach a consistency of 100
poises at well conditions of temperature
TABLE 3.-Cement Stirring-time Tests and pressure. Or, for practical purposes,

Well Stir. Time to I Time to 8 Lb. Minimum woe time = TS1b.J)OrOQ.iD.


Depth ring 8 Lb. per per Sq. In.
Type of Simu· Time Sq. In. = T 100 poises X3
Cement lated, to 100 Tensile Where:
Ft, Poises, Strength, Time to 100
Hr. Hr. Poises TS1b.perOQ.iD. =
time to a tensile
---- strength of 8 lb. per sq.
Standard 3.5 5·4 1. S4 in.
Portland. 2'0001
4,000 3.0 3.8 1. 27
6,000
Slow-set A. 8,000
2.5 •. 9 1. 16 T loo poises X 3 = well simulation stirring-
4·0 8.5 2.12
10,000 3·4 8.0 '·35 time tests to consistency
12,000 1 3.0 7.9 2.63
Slow-set B. 6,000 3.7 10.6 2.86 of 100 poises.
8,000 3. I 9·3 3.0
10,000 2.5 7.5 3.0 It will be shown later that this method
Slow-set C. 6,000 4·0 10. I •. 52
8,000 3. I 8.8 2.84
of predicting development of cement
10,000 2.6 7·8 3·00 strength in wells is actually more accurate
Slow-set D. 6,000 3.7 6.5 1. 75
8,000 3·3 5.' 1.57 than may be believed at this point.
10,000 1 4·4 5·4 1. 23
However, since the method involves several
assumptions, thought was turned to the
Data in the fourth column of Table 3 development of a simpler, more accurate
were obtained from time-versus-strength method of determining strength develop-
data by extrapolation from actual test ment in wells.
points in the neighborhood of 20 to 30 lb.
per sq. in. tensile strength. For that reason, Second Method
and also becau.se the strength tests were When water is added to dry cement,
made at atmospheric pressure, the data chemical reactions occur that give off heat.
under this heading do not exactly describe It is this behavior of cement slurry that
the time to 8 lb. per sq. in. tensile strength permits one to run a recording temperature
in a well. The times are a little longer instrument into a well after a casing cement
than would be found in actual practice, job and find the location of the top of the
and thus become an added safety factor to cement behind the pipe. It has been
the method herein proposed. But, in spite found that the temperature of cement
of the fact that the test data in Table 3 behind casing may remain higher than
are not perfectly representative, the ratio the temperature of the adjacent formation
of the time to 8 lb. per sq. in. strength to for as long as 60 to 70 hr. after pumping
the time to 100 poises is surprisingly the cement into the well. Field tests have
180 METHOD FOR DETERMINING MlNIMtn! WAlTINQ-oON-CEMENt TtME

280

240

200

~I~O
,. '"
0:." , ,.
2!
~ l20

OL-~~~ ____ ~ __ ~____ ____ ___


~ ~

o 2 3 4. 5 6
TIME,HOURS
FIG. 4.-T&1oU'EUTURE DEVELOPMENX IN stANDAlID PokT1.Afn> CF.M£l'It SL~Y.

II) 12r-----r---r-
~
o
.
:t
II)
iii
II)

.~
o
~
~ 6,~--~~---+----~~--~----+---~

W
t:
4'~---+----~----~--~~--~--~
~
~
~ 2~--~~~~~--~-----4-----+----~
~
w
:E
t:O 2468.012
TIME TO PEAK TEMPERATURE. HOURS
FIo. 5.-STllUUNG TIns 01' CEMENtS.
R. FLOYD FARRIS

shown also that temperature surveys rnade on standard portland and slow-set cements,
at 24 hr. or less after cementing show the to throw some light on this subject.
tops of cement more distinctly, suggesting A plot of the stirring time of various
that some time after cement is placed cements at various conditions of tempera-
200
T -T-r--r~
K. ~EAK IEMP.-§ I:IBS. 3QMINS •
180 )100 'POlSES' - • HRS. 56 M~. • .•

160 -'-
:I ~
u: 140
j ~

(1:-
:Ii
~120
L
. OO·POISES· ----t---
100 .---- --"--- ---'

eo
o 4 8 12 16 20 24
TIME, HOURS
FIG. 6.-PEAK TEMPERATURE IN RELATION TO STIRRING TIME.

in a well the temperature increases to some ture and pressure, corresponding to wells
maximum value above the surrounding of various depths, versus the time to the
strata, then slowly decreases to the normal peak or maximum temperature develop-
temperature at that depth. Laboratory ment (Fig. 5) suggests that these factors
tests were made to determine the time may be reasonably closely related to each
of maximum or peak temperature of other. In other words, knowing the stirring
cement slurries at various pressures and time to 100 poises, one can multiply that
temperatures is simulation of various time by a factor (K), which is more than
well depths. one but less than two, and predict the
An example of maximum temperature approximate time when cement in wells
development in!l standard portland cement will reach the peak temperature. Fig. 5
slurry at three stimulated well depths is indicates that the average K factor is
shown in Fig. 4, which shows that the somewhere between 1.5 and 2.0.
greater the depth, the more quickly the Field tests were then made to determine
cement reaches the maximum temperature. when cements in wells actually reach
Viewing this behavior brings to mind the peak temperature and to determine how
fact that the greater the depth, the more it is related to laboratory tests of stirring
quickly cement stiffens and sets. That time to 100 poises, The first test was run in
thought, in turn, suggests that the time a well in North Cowden field, Ector
to maximum temperature development in a County, Texas, where 572-in. o.d. casing
.well Inay be related to stirring time to was set at 4624 ft. and cemented with 12S
100 poises. A Dumber of tesb: were made sacks of a standard portland <:"!JII'!nt.
182 METHOD FOR DETERMINING MINIMUM WAITING-ON-CEMENT TIME

2~0

TEMEI
V
-/ r--_
200 rl80"

190 rlSOO
i0.:1
/1 ,
~i400- K- PEAK TEMP.-9 HRS. 28 MIN. • 2 S-
180 100 'POISES!'- 3HRS. 39MIN. .
u: ;:)
•0.:-
I
(/)
(/)
w
:IE
~ 170 8:1200- PRESS.

160 -1000
I
f.-100 "IOISES·
I
I
150
° 4 8 12 16
TIME, HOURS FROM STARTING
20
TO MIX
24

FIG. 7.-RELATION OF PRESSURE AND TEMPERATURE.

3000

2500 / rr--- --- ----


\PEAK PRESS.
iii
0.:
1.2000
/V
m
If
~OOPOISES
C)1500 /'

/
z
in
~
1000

/
500
K. PEAK PRE§SURE-12 HRS.16 MIN~.• 282
I
100" "rOISESi 4 HRS. fO MIN5. . 1
o 8 12 16 20 24
TIME-HOURS
FIG. S.-PRESSURE BUILD-uP ON CASING.
R. FLOYD FARRIS

Immediately after the cement was pumped (Fig. 8) confirmed the thought that pres-
down, a recording temperature element was sure on the casing after cement is placed
lowered into the casing to a point well below reflects heat of hydration of cement in a
the estimated top of the cement and was well. The ratio of time to peak pressure to
left at that point for approximately 24 hr. stirring time to 100 poises was 2.82 in this
The temperature recorded during that time case. Why the peak temperature occurred
is plotted on Fig. 6. The ratio of the time
in one well at 9 hr. and 28 min. and the
to the peak temperature in this well to
peak press ure occurred at 12 hr. and 16 min.
the stirring time to 100 poises, as deter-
mined by a laboratory well-simulation in another well of approximately the same
test on the same cement, is 2.2, or slightly depth is understandable in view of the
higher than the K factor indicated by previ- fact that the cement showed different
ous laboratory tests. setting-time characteristics, although the
Since the maximum temperature re- same brand was used in both cases.
corded in this well was so very much Also, another possible difference between
greater than the normal static formation these wells is the fact that the latter
temperature, approximately 94°F., at that was cemented during a season of the year
depth, the thought occurred that perhaps when the atmospheric temperature was
if the casing being cemented is closed in probably less than that at the time of
after the cement is pumped down, expan- cementing the first well. It is a well-known
sion of the fluid in the casing should cause fact that mud-pit temperatures are affected
an increase in the shut-in casing pressure, by atmospheric temperature, which, in
which would reach a maximum at approxi- turn, affect the bottom-hole temperatures
mately the same time that the cement down and, therefore, the setting time of cement
the hole reaches its maximum temperature. placed therein.
This thought was investigated in the next A pressure build-up test was made on a
field test. well in West Edmond field, Oklahoma,
In the next field tests, the test procedure where 7-in. o.d. casing was set at 7028 ft.
used on the previous well was followed, and cemented with 700 sacks of a special
except that hourly readings of the shut-in experimental oil-well cement. Fig. 9 shows
casing pressure were taken. This well was that the ratio of peak pressure to 100 poises
drilled in Tri-Cities field, Texas, where was 2.4.
5%-in. o.d. casing was set at 7681 ft. Surface pipe, 10% in., was set at 649 ft.
and cemented with 600 sacks of a slow-set in a well in Sour Lake field, Texas, and
cement. Fig. 7 shows the results of these cemented to the surface with 500 sacks of a
tests. The pressure built up with tempera- standard portland cement. Fig. 10 shows
ture to approximately the peak, but, that the ratio of peak pressure to 100
unfortunately, the pressure on the casing poises was 2.1. Pressure was bled down
was bled off at that time. Ratio of the time once, to permit installation of a recording
to peak temperature to the time to 100 pressure gauge. Pressure was bled down
poises was found to be 2.6. at first to avoid subsequent high pressure
Another test was run in Tri-Cities field on the casing. When the peak pressure was
to obtain a record of the pressure build-up reached, a transit was set up some distance
on the casing, since readings were not taken from the well and trained to a mark on the
to the maximum pressure on the previous pipe to observe any settling of the pipe
well. In this test, 5%-in. o.d. casing was set when the strain was released. The weight of
at 7612 ft. and was cemented with the same the pipe was set down on the cement,
tyPe and amount of cement. The results but no movement was observed.
184 MXTHOD FO~ DETERMINING MINIMUM WAITINO*ON*CEMENT T1ME

800
I'pEAK PREssURE 15 HRS.
.I
700 K= Inn"pOISES.S HRS.14MINS. • 2.4

OS
600 /
0.:
cl;
:!isoo
a:
t 100 ·POISES·

0..

g
C!I
z
-400
II
100
J -- -

200
o
IV 4 8 12 16 20 24
TIME, HOURS
FIG. g ....... PdSSURE[BUILD-UP ON CASING.

KodAK PRESS. 14 HRS. 2,5 M!N.=I 2.


IOO"POI ES",7 HR5. I '
/
600
I V --I'--
II
-; /
1 -7 f7
200 /
100 ./
V .
/
--
v V
\1--
1--100 • POISES· i
(ESTIMATED A~ 7 HRS.)
o
o 2 4 6 8 10 12 14 16
TlME,HOURS
FIG. to.-PRESSURE BUILD-UP ON CASING.
1l. BLOYD FARRIS

:&rlier in the discussion it was shown has to do to determine the minimum woe
by laboratory tests that the ratio of the time in any well is to read the shut-in c.asing
tirtle to maximum temperature develop- pressure after landing the cement until
rtlent in cement to the stirring time to it reaches a maximum, then multiply the
toO poi!les is equal to a factor (K} slightly time to that point, as measured from the
less than 2 but more than 1.5. All field tests time of mixing the first sack of cement, by
show that the ratio is slightly more than :2 a factor of 1.5. This method is much si~pler
but less than 3. Since the difference between than the first method and is much more
laboratory tests and field tests is small, accurate, as it will reflect differences in well
one might strike a compromise with the conditions and differences in cement
statement or conclusion that cements in behavior.
wells reach peak or maximum temperatures 'the foregoing equations describe rela-
at a time corresponding to approximately tionships that laboratory tests indicate to
twice the thne required for the cement be true, or approximately true, in wells
to attain a consistency of 100 poises, under with respect to minimum strength require-
the particular laboratory consistometer test ments and minimum woe times. Whether
conditions used in this case. This relation- or not the laboratory predictions hold
ship. with others pointed to throughout the true in field practice is quite another
discussion, may be written as equations as ma.tter. Field tests were made to (heck the
follows: correctness of these hypotheses.

Talb._tII.la. =- TrtJIA. woe [x) FIELD TESTS


1... woo - T 100 poises X 3 [21 If the trends indicated by laboratory
1-'"II1II. "'" T __._. (31 tesb are fundamentally correct, the equa-
T___ '* T100J)O/Mos X :2 f41 tion for predicting minimum woe time
will apply to all portland-type cements in
Therefore, any well at any depth. Therefore, excep-
tions to field rules were obtained where
Tmln.woc'" TIb&L ..... _ X 1.5 [5)
necessary to permit drilling out of cement
where: as early as might be required to check
laboratory tests. Wells were selected in
Tam.._IQ,I6.... time from mixing ot the various areas and at various stages of
cemen t to a tensile strength drilling in order to obtain data on jobs at
of 8 lb. per sq. in. various depths and with different typE;S
l'1Dm. woo -= minimum waiting-on-ce- and brands of cements. Each job differed
ment time. from normal practice only in the time of
T ,oo ..- ... cement well simulatiollstir- drilling out of the plug. Field men were
ring-time test to 100 poises instructed to take hourly readings of the
(pressure consistometer; shut-in casing pressure until it reached a
Stanolind test procedure). maximum, release pressure at that point,
T-'''''''11. '"" time to maximum tempera- run the bit into the hole, and start drilling
ture development in ce- the plug at a time equal to the time to
ment. the maximum pressure times 1.5. Inci-
T....... _ _ ... time to maximum shut-in dentally, field men were advised to.bleed off
pressure on casing. the pressure at intervals if it reached
Eq. 5, which expresses the second method dangerous proportions. The criterion is
for Predicting development of cement not necessarily the magnitude of the pres-
strength in wells, simply means that all one sure. but. rather, is the point when the
186 METHOD FOR DETERMINING MINIMUM WAITING-ON-CEMENT TIME

duids inside the casing stop expanding that releasing the pressure after it reaches
as a result of an increase in temperature. the maximum is a more critical test than
TABLE 4.-WOC Field Tests
Elapsed Time. Hr.• tal Time
to
Casing Cement Maxi· Dril-
Re- Plug mum ling Wt. Rev.
Maxi- Stir- lea"e Dri1- Cas- Rate. on
Field mum ring per
Cas- Time, Cas-of led at. ing Min. Bit Min.
ing 100
Hr. Pres- per MIs
illg
Pres- Poises Pres- sure Ft.
Size. Depth. Type Sacks sure X2 X 1.5.
In. Ft. sure Hr.
--- .-- .--- --- - - - - - - - - - - - - - - --
Fullerton. Tex .... 7~~
Fullerton. Tex .... 7%
3.771
3.805
Common
Common
2,000
1,800 ·
7.25
6.16 7.38
7. 23 8.0
12.25 g.24'
16.0 10.87
5
5
5
2
55
50

···
Fullerton. Tex .... 7~. 3.785 Common 1,900 7.05 6.16 7.20 II.2 10.57 2·4 2 SO
Fullerton. Tex .... 5H 6.765 Slow-set 350 8.0 7.07 26.2 12.0° 2.0 3 50
Sittner. Kans ..... 53-2 3.612 Common ISO 8.5 g.53 16.2 12.75' 3 3 50
W. Edmond. Okla. 7 7.005 COlnmon 700 5.33 6.g2 b 8.0'
Sour Lake. Tex .... 10% 647 Common 500 14·77 14. 0 14·77 24·27 22. IS 0.5 6 100
Riverside. Tex .... 5302
High Island. Tex .. 7
6.415
5.704
Slow-set
Slow-set
750
750
10.12 8.8 II.O
15.67 11,10 15.67
•• 15.16
'3.5
Elk Basin. Wyo •.. 7 5.300 Common 300 8.00 7·40 8.0 24·3 12.0 2.5 6 go

• Head leaked.
• Not drilled early.
• T to 100 "poises" X 3.

Table 4 presents a summary of eight the test of drilling the shoe. They reason
field tests in which attempts were made to that if the cement is soft it will back up
drill out cement at the minimum woe into the casing when pressure is released,
time indicated by laboratory tests. especially if the common type of float
equipment is not used, as in two of the wells
DISCUSSION OF RESULTS
tested.
The field tests summarized in Table 4 The writer is of the opinion that the
show by the drilling rates that the cement tests conducted on the surface pipe
in each well had passed the final set, and cement work at Sour Lake were more severe
therefore had attained a tensile strength than those at any other location. The
of at least 8 lb. per sq. in. as predicted cement was likely to have been much
by laboratory tests. It is also interesting more "green" when it was drilled than
to note the reasonably close agreement at any other test location, owing to the
between the time to maximum pressure low curing (formation) temperature and
on the casing and laboratory stirring pressure. Immediately after the pressure
time to 100 poises X 2. These data show was released, which, as stated before, may
that cement tests can be made in the be a critical test of whether or not the
laboratory that will predict the approxi- cement has set, the master valve and blow-
mate stiffening time of cement in wells. out preventer for lo%-in. casing were set
In three field tests, unforeseen events down on the casing. The cement not only
delayed drilling of the plug to a time that supported the full weight of the casing
approached the usual drilling out time and at that point but held the very large weight
thus rendered those tests practically of that equipment. Next, after drilling
useless as far as the subject experiment was the wooden plug and baffle collar and 4 or
concerned. The only information of signifi- 5 ft. of cement, the driller stopped rotation
cance obtained from thos-e tests was that and set all the weight of the drill pipe,
no slurry flowed back into the casing when kelley, and swivel (8 points) down on the
the pressure was released. Many believe cement, then increased the pump speed
R. FLOYD FARRIS

to a relatively high rate to see whether the changing rams on blowout preventers
cement could be washed out. The weight and in the installation of the master valve
indicator had picked up 110 weight after and the blowout preventer after setting
circuiating 6 min. The driller termed the surface pipe. If this equipment were made
cement as drilling "firm to hard." up in a shop ready to be flanged onto the
The cement in all the tests where the surface pipe, it appears that it could
plug was drilled reasonably soon after be installed as a unit with a great deal
the specified time drilled firm to hard more efficiency.
inside the pipe and showed no evidence of As an example of the saving that might
flow of cement into the casing after the be effected by reducing WOC time, the
shoe was drilled. Also, in no case was the over-all average WOC time on Stanolind
cement sufficiently soft to be circulated out. Oil and Gas Co. properties is approximately
These data indicate that basing WOC 51 hr. per casing cement job. This figure
time on the time to maximum casing is lower than might be expected because it
pressure times a factor is fundamentally includes practices in areas where no regula-
sound and applicable to field practice. It tions exist. The over-all average WOC
would appear that such a system as this time indicated by the method proposed in
would be particularly attractive as a basis this paper is estimated to be approximately
for State or Field rules, since the time to 15 hr. per casing cement job. This suggests
maximum shut-in casing pressure reflects a saving of 36 hr. per job. However,
individual conditions of the well as they practical considerations teach that very
affect the particular type of cement used seldom would the crew be able to start
in that well. The multiplier 1.5 merely sets drilling on the plug so early. It has been
the time back to allow a minimum strength estimated that, at least until the present rig
to be developed. Unless further field experi- routine is appropriately modified, the plug
ence proves that the multiplier 1.5 is too cannot easily be drilled ou t before an
low, there is little reason for suggesting average time of approximately 21 hr. after
that a waiting period longer than that cementing casing. Therefore, it appears
prescribed by the formula should be used. that an average of 30 hr. per cement job
These tests indicate that seldom will rig might be saved without much difficulty.
operations permit cement to be drilled Translating rig time into dollars at
out at the minimum time. This suggests $20.00 per hour, the saving should be
that the phrase "waiting-on-cement time" an average of $600 per casing cement job,
should be deleted from our vocabulary, or at least $1200 per well, assuming two
since it has been found that the cement cement jobs per well. Realizing that more
usually waits on the drilling crew. than 24,000 wells were drilled in the United
Much must be done before full advantage States during 1944, one can appreciate
can be taken of the indicated savings in how reducing WOC time might benefit
time. Aside from the fact that certain the industry.
regulations will have to be modified
certain of the routine of rigging up and SUMMARY
handling of rig operations may have to It has been shown that the minimum
be shifted. For example, much of the rigging waiting-an-cement time in wells can be
up or repair around a rig that now is reasonably accurately predicted by labora-
deferred until woe time may be handled tory well-simulation tests, but can be more
by extra roustabout help, or may be done simply determined by observing the shut-in
by the rig crew during slack time while pressure on the casing to a maximum
drilling. Also, much time is not spent in value then multiplying by a factor of 1.5
188 METHOD FOR DETERMINING MINIMUM WAITING-ON-CEMENT TIME

the time from initial mixing of cement paper; to S. C. Oliphant and D. B. Burrows
to the time when maximum pressure is for suggestions that encouraged the devel-
reached. Field tests show that the cement opment of this method; to J. B. Clark for
has ample strength to support the pipe helpful suggestions and criticisms i to
and withstand the shock of drilling at C. R. Fast for his assistance in conducting
that time. both the laboratory and field tests; and to
A great deal of woe time may be Stanolind Oil and Gas Company's Division
eliminated if regulations are relaxed and and Field'personnel for arranging and con..
if rigging up and drilling routine is adjusted ducting the field tests.
to fit in with minimum waiting-time
REFERENCES
requirements.
I. R. F. Farris: A Practical Eva.1uatilln of
Cements for Oil Wells. Amer. Petro lnst ..
ACKNOWLEDGMENT Drill. and Prod. Prac. (1941).
2. N. Healey and S. L. Pease: HardeniUB Times
for Casing Cementation. Itu. Inst. of
The author wishes to express his appre- Petro (1942) 28.
ciation to Stanolind Oil and Gas Co. 3. R. W. French: Geothermal Gradients in
California Oil Wells. Amer. Petro lnst.
for permission to prepal'El and publish this Drill. and Prod. Pl'ac. (1939).

S-ar putea să vă placă și