CALCULO DE VOLUMENES DE LAS ZAPATAS

DATOS
COLUMNA ZAPATA
POSICION a b A B d VOLUMEN
[m] [m] [m] [m] [m] [m3]
(A1-F1) 0.3 0.3 1.4 1.4 0.16 0.259
(C1-D1) 0.25 0.25 1.6 1.6 0.19 0.398
(D2-B4) 0.25 0.3 2 1.7 0.23 0.639
(E2) 0.25 0.25 1.8 1.4 0.2 0.412
(A3) 0.3 0.25 1.6 1.4 0.17 0.313
(B3) 0.3 0.3 2.4 1.5 0.24 0.707
(A4) 0.3 0.25 1.8 1.4 0.18 0.372
(D4) 0.3 0.3 2.2 1.8 0.25 0.809
(E4) 0.25 0.25 2 1.5 0.25 0.612
(A5) 0.25 0.25 1.5 1.5 0.17 0.313
(C5-D5) 0.25 0.25 1.5 2 0.22 0.539
(F5) 0.25 0.25 1.6 1.6 0.18 0.377

TOTAL[m3]= 5.751
RESUMEN DE CANTIDADES

ACERO:
Ø Lonjitud total Peso Numero de
mm [m] [kg] barras
10 37.4 23.06 3
12 459.8 408.22 38
16 81.89 129.25 7

HORMIGON:
Volumen total[m3]= 5.75

Agua[lit]= 172*5.75= 989.2


Cemento[kg]= 363.25*5.75= 2089.1
# Bolsas= 42
Arena[m3]= .49821*5.75= 2.9
Grava[m3]= .744*5.75= 4.3
PLANILLA DE FIERROS
Nro. Nro.
zapatas pzas.
ZAPATA Posisión. Esquemas Replicas Ø Cantidad a b
Nº mm [cm] [cm]
BLOQUE C
1 1 12 42 370
E(3-4) 2 a 1 12 26 220
3 a b 2 16 4 72 46

1 a 1 12 7 370
C(3-4) 2 a 1 12 42 180
3 a b 2 16 4 72 46

1 a 4 12 42 370
A(3-4) 2 a 4 12 26 270
3 a b 16 16 4 72 46

1 a 4 12 42 260
A(1-2) 2 a 4 12 26 170
3 a b 16 16 4 72 46

BLOQUE CURBO
1 a 1 12 14 270
B(3-4) 2 a 1 12 14 180
3 a b 2 16 56 72 46

BLOQUE OFICINAS
1 a 2 12 13 270
B(3-4) 2 a 2 12 9 150
3 a b 4 16 4 72 46
E FIERROS

c d e f L. Parcial Total Peso P. Total


[cm] [cm] [cm] [cm] [cm] [m] [kg/m] [kg]

370 155.40 0.89 137.97


220 57.20 0.89 50.78
118 9.44 1.58 14.90
SUP TOTAL: 203.65

370 25.90 0.89 22.99


180 75.60 0.89 67.12
118 9.44 1.58 14.90
SUP TOTAL: 105.01

370 621.60 0.89 551.87


270 280.80 0.89 249.30
118 75.52 1.58 119.20
SUP TOTAL: 920.36

260 436.80 0.89 387.80


170 176.80 0.89 156.97
118 75.52 1.58 119.20
SUP TOTAL: 663.96

270 37.80 0.89 33.56


180 25.20 0.89 22.37
118 132.16 1.58 208.59
SUP TOTAL: 264.53

270 70.20 0.89 62.32


150 27.00 0.89 23.97
118 18.88 1.58 29.80
SUP TOTAL: 116.09

TOTAL: 2273.60
PLANILLA DE FIERROS
ZAPATA Pos. Ø Pieza a b c L. Parcial Nro. Nro. Total Peso
mm [cm] [cm] [cm] [cm] pzas. zapatas [m] [kg/m]
1 12 a 150 150 10 7 105.00 0.89
(A-B-C-D-E-F-G-H)-5 2 12 a 150 150 8 7 84.00 0.89
3 16 a b 72 46 118 4 7 33.04 1.58
SUP TOTAL:
1 12 a 150 150 8 1 12.00 0.89
E1 2 12 a 150 150 8 1 12.00 0.89
3 16 a b 76 46 122 4 1 4.88 1.58
SUP TOTAL:
1 12 a 190 190 11 2 41.80 0.89
2 12 a 160 160 10 2 32.00 0.89
E2 a 0 1 2 0.00 0.00
a 0 1 2 0.00 0.00
5 16 a b 80 46 126 4 2 10.08 1.58
SUP TOTAL:
1 12 a 150 150 9 2 27.00 0.89
2 12 a 150 150 8 2 24.00 0.89
C1 a 0 1 0.00 0.00
a 0 1 0.00 0.00
5 16 a b 77 46 123 4 2 9.84 1.58
SUP TOTAL:
1 12 a 130 130 6 2 15.60 0.89
C2 2 12 a 130 130 6 2 15.60 0.89
3 16 a b 75 46 121 1 2 2.42 1.58
SUP TOTAL:
BLOQUE CURBO
1 12 a 130 130 18 32 748.80 0.89
2 12 a 130 130 19 32 790.40 0.89
B1-B2 a 0 3 32 0.00 0.00
a 0 3 32 0.00 0.00
5 16 a b 81 46 127 4 32 162.56 1.58
SUP TOTAL:
1 12 a 170 170 9 1 15.30 0.89
2 12 a 130 130 8 1 10.40 0.89
(A4) 3 10 a 130 130 1 1 1.30 0.62
4 10 a 130 130 1 1 1.30 0.62
5 16 a b 78 46 124 4 1 4.96 1.58
SUP TOTAL:

BLOQUE OFICINAS
1 12 a 110 110 13 4 57.20 0.89
2 12 a 110 110 13 4 57.20 0.89
B1-B2 a 0 1 0.00 0.00
a 0 1 0.00 0.00
5 16 a b 82 46 128 4 4 20.48 1.58
SUP TOTAL:

1 12 a 130 130 11 2 28.60 0.89


2 12 a 130 130 9 2 23.40 0.89
C1 a 0 1 0.00 0.00
a 0 1 0.00 0.00
5 16 a b 82 46 128 4 2 10.24 1.58
SUP TOTAL:

1 12 a 140 140 7 2 19.60 0.89


C2 2 12 a 140 140 7 2 19.60 0.89
3 16 a b 74 46 120 4 2 9.60 1.58
SUP TOTAL:

1 10 a 120 120 7 2 16.80 0.62


2 10 a 120 120 6 2 14.40 0.62
D5 a 0 2 0.00 0.00
a 0 2 0.00 0.00
5 16 a b 79 46 125 4 2 10.00 1.58
SUP TOTAL:
1 10 a 170 170 16 2 27.20 0.62
D4 2 10 a 180 180 10 2 18.00 0.62
3 16 a b 75 46 121 4 2 4.84 1.58
SUP TOTAL:

1 10 a 160 160 6 2 9.60 0.62


D3 2 10 a 150 150 16 2 24.00 0.62
3 16 a b 75 46 121 4 2 4.84 1.58
SUP TOTAL:

1 10 a 120 120 8 2 9.60 0.62


D6 2 10 a 120 120 6 2 7.20 0.62
3 16 a b 75 46 121 4 2 4.84 1.58
SUP TOTAL:

1 10 a 120 120 5 2 6.00 0.62


D8 2 10 a 120 120 5 2 6.00 0.62
3 16 a b 75 46 121 4 2 4.84 1.58
SUP TOTAL:

1 10 a 130 130 11 2 14.30 0.62


E7 2 10 a 130 130 9 2 11.70 0.62
3 16 a b 75 46 121 4 2 4.84 1.58
SUP TOTAL:

1 10 a 170 170 10 1 17.00 0.62


F5 2 10 a 170 170 17 1 28.90 0.62
3 16 a b 75 46 121 4 1 4.84 1.58
SUP TOTAL:

1 10 a 210 210 31 2 65.10 0.62


F4 2 10 a 210 210 16 2 33.60 0.62
3 16 a b 75 46 121 4 2 4.84 1.58
SUP TOTAL:
1 10 a 170 170 10 2 17.00 0.62
F6 2 10 a 170 170 16 2 27.20 0.62
3 16 a b 75 46 121 4 2 4.84 1.58
SUP TOTAL:

PESO TOTAL:
P. Total
[kg]
93.22
74.58
52.15
219.95
10.65
10.65
7.70
29.01
37.11
28.41
0.00
0.00
15.91
81.43
23.97
21.31
0.00
0.00
15.53
60.81
13.85
13.85
3.82
31.52

664.80
701.73
0.00
0.00
256.57
1623.10
13.58
9.23
0.80
0.80
7.83
32.25

50.78
50.78
0.00
0.00
32.32
133.89

25.39
20.77
0.00
0.00
16.16
62.33

17.40
17.40
15.15
49.95

10.36
8.88
0.00
0.00
15.78
35.02
16.77
11.10
7.64
35.51

5.92
14.80
7.64
28.35

5.92
4.44
7.64
18.00

3.70
3.70
7.64
15.04

8.82
7.21
7.64
23.67

10.48
17.82
7.64
35.94

40.14
20.72
7.64
68.49
10.48
16.77
7.64
34.89

2583.21
PLANILLA DE FIERRO

ARMADURA TRANSVERS
Pos. Ø Pieza a b C D
mm [m] [m] [m] [m]
c
b
a
1T 12 0.4 3.3 0.15

a
b
c
1T 12 0.15 3.3 0.4
2T 12 0.4 1.3
2T 12 1.3 0.4
a

3T 12 3.25

a c
b

4T 12 0.2 3.25 0.2


ARMADURA LONGITUDIN
12 1L 10 1
1L 10 1
2L 12 1
2L 12 1
3L 12 1
4L 12 1
PLANILLA DE FIERRO

MADURA TRANSVERSAL
E L. Parcial Nro. Nro. Total Peso P. Total
[m] [m] pzas. [m] [kg/m] [kg]

3.85 3.85 14.81 0.89 13.15 0.26

3.85 3.85 14.81 0.89 13.15 0.26


1.7 7.69 13.08 0.89 11.61 0.13
1.7 7.69 13.08 0.89 11.61 0.13

3.25 6.25 20.31 0.89 18.03 0.16

3.65 7.14 26.07 0.89 23.15 0.115


MADURA LONGITUDINAL
1 13.33 13.33 0.62 8.22 0.15
1 7.69 7.69 0.62 4.74 0.13
1 14.29 14.29 0.89 12.68 0.14
1 8.70 8.70 0.89 7.72 0.115
1 29.13 29.13 0.89 25.86 0.115
1 29.13 29.13 0.89 25.86 0.115
Nro.
pzas.

4.00 0.25

4.00 0.25
8.00 0.125
8.00 0.125

8.00 0.14 7

9.09 0.11 9

10.00 0.2
10.00 0.1
16.00 0.125
10.00 0.1
31.9 0.105 32
31.9 0.105 32