Importance of planning the open pits in the conditions of contemporary


mining: A case study: The open pit South mining district Majdanpek

Article · January 2017


DOI: 10.5937/mmeb1702015K

CITATIONS READS

2 38

4 authors, including:

Daniel Krzanovic
Mining and Metallurgy Institute Bor
30 PUBLICATIONS   23 CITATIONS   

SEE PROFILE

Some of the authors of this publication are also working on these related projects:

TR 33034 the Ministry of Science and Technological Development¹ View project

Project TR 33021 View project

All content following this page was uploaded by Daniel Krzanovic on 19 February 2018.

The user has requested enhancement of the downloaded file.


MINING AND METALLURGY INSTITUTE BOR ISSN: 2334-8836 (Štampano izdanje)
UDK: 622 ISSN: 2406-1395 (Online)

UDK: 622.271(045)=111 doi:10.5937/mmeb1702015K

Daniel Kržanović*, Nenad Vušović**, Milenko Ljubojev*, Radmilo Rajković*

IMPORTANCE OF PLANNING THE OPEN PITS IN THE


CONDITIONS OF CONTEMPORARY MINING - A CASE STUDY:
THE OPEN PIT SOUTH MINING DISTRICT MAJDANPEK***

Abstract

In today’s financial and environmental climate, it is imperative to develop the robust projects with
good economics. Successful business in conditions of limited resources is impossible without analyzing
all the technical and economic parameters and scenarios of sustainable operation. In this sense, it
requires the application of mathematical algorithms implemented in the contemporary software tools
able to efficiently provide the effective troubleshooting of design in complex conditions of modern
mining.
This paper, an example of the open pit South Mining District Majdanpek, shows the importance of
planning and design the ore exploitation in achieving the maximum net present value (NPV).
Keywords: planning, optimization, net present value, open pit South Mining District Majdanpek

INTRODUCTION

Mine planning is aimed at one goal: defines the minable reserves and associat-
maximizing the value to be realized from ed amount of waste to be removed during
extracting the mineral resources. This goal the operation life. Over the past 50 years,
achievements depends primarily on the determining the optimum open pits has
ability of an engineer to realize the all been in the areas of operational research in
issues related to the production process in the mining industry.y and many algo-
terms of the number of alternatives related rithms have been published.
to the investment and exploitation factors. The design and scheduling of open pit
The decisions are updated through time, mines is a significant and complex prob-
usually annually, as a new information lem in the mine planning. The principal
becomes available. aim of mining operation is to ensure that
The size, location and final shape of an an ore body is exploited in a way such that
open pit are important in planning the lo- the value realized from the mine is maxi-
cation of waste dumps, stockpiles, pro- mum. A well-known early contribution to
cessing plant, access roads and other sur- this field was made by Lerchs and Gross-
face facilities, and for development the mann [8], who presented a graph-theoretic
production program. The pit design also algorithm for determining the final con

*
Mining and Metallurgy Institute Bor, e-mail: daniel.krzanovic@irmbor.co.rs
**
University of Belgrade, Technical Faculty in Bor
***
The work is the result of the Project TR 33038 „Improvement the Technology of Copper Ore Mining
and Processing with Monitoring of Living and Working Environment in RTB Bor Group“, funded by
the Ministry of Education, Science and Technological Development of the Republic of Serbia

No. 1-2, 2017 15 Mining & Metallurgy Engineering Bor


tour of the open pit, known as the ultimate non-profit blocks of waste, allows engineers
pit, such that the total profit from the mine to select the appropriate mining methods
is maximized. and plan the necessary equipment and infra-
Some optimization methods for solving structure that are essential for development
problems of mine scheduling are the heuris- the process of ore mining. Blok model of
tics (Gershon [1]), dynamic programming deposit is a major input in the optimization
(Onur and Dowd [2], Wang [3], parametric process of the open pit.
methods (Whittle [4]), Tolwinski and Un- Optimization of the open pit comprises
derwood [5], Tolwinski i Golosinski [6]), obtaining a possible contour of the open pit,
integer linear programming (Gershon [7], based on a block model of deposit, which
Smith [8], Caccetta and Hill [9]) and Mixed has an economic value, and which can be
Integer Linear Programming – MILP (Vahid calculated. The term a possible contour of
Rafiee i Omid Asghari [10]). the open pit means an open pit contour with
maximum inclination of general slope,
METHODOLOGY formed after mapping the transport routes
and safety berms, and which meets the sta-
Mining processes are complex and bility criteria.
complicated, with many different economic, To calculate the economic value, the se-
technical, environmental and other parame- quence of excavation has to be firstly de-
ters that must be planned before the project fined, and then, progressively with excava-
gets its practical value. Many of these pa- tion, to accumulate the income and expens-
rameters are evaluated independently of the es. Application the principle of the time
other, due to the expediency and difficulty value of money, or that a dollar that is ob-
in predicting the values of variables under tained today, is more valuable than the one
consideration. Costs, prices, reserves, ore that will (maybe) be obtained next year,
mining and processing, as well as many means that discounting of revenue and costs
aspects of society, such as the issuance for is done by a factor that increases over the
implementation of works are absolutely life of the mine.
essential for the project evaluation. Another thing to note is that the calcula-
Each ore body is different, but the main tion of values is made for each block in the
steps in the open pit planning, when the block model, or each block has its economic
main objective is the maximization of NPV, value. Calculation the economic value of
take place on the same principle. These the block (EVB) requires a detailed
steps are for simplicity represented as linear. knowledge of a large number of parameters,
The actual planning process is an iterative such as the content of useful component in a
process in which some steps or combination block, the selling price of useful component,
of steps are repeated many times with the the costs of mining and processing, cut-off
sensitivity analysis. grade in mining and processing, recoveries
Achieving the maximum NPV is real- in mining and processing.
ized by the procedure which comprises first Today's the open pit optimization tech-
the optimization of open pit and defining niques, which are implemented in special-
the phase of open pit development ized software, finding the optimal contour
(pushbacks) with calculation the ore amount of the open pit are based on maximizing the
and mineral content in each phase. The next NPV. This ensures that there is no inde-
step is to optimize the mining dynamics. pendent block or combination of blocks that
Blok model of deposit, created by the can be added or subtracted within the con-
method of geostatistical modeling, with tour of the pit, which would lead to an in-
separate areas of useful mineral blocks and crease in the NPV.

No. 1-2, 2017 16 Mining & Metallurgy Engineering Bor


Optimization the open pit limit and mi- design despite the a strong software deve-
ning dynamics was carried out in this work lopment and computer equipment.
using Whittle software. Whittle process is In the process of optimization of mining
based on a rapid implementation the series dynamics, a simulation and discounted cash
of the Lerchs-Grossmann (LG) algorithm. flow analysis (DCF) are done to obtain the
This algorithm provides the mathematically most favorable solution, that is, to deter-
optimal ultimate open pit limit when the mine the number of phases which affects
criterion for optimization is the maximum maximization of the net present value in a
undiscounted cash flows. The process is long - term planning of the open pits.
used for selection the optimum final pit The analysis is based on the Milawa al-
limit for the best and worst case of the min- gorithm, which is specifically designed to
ing excavation plans for which the NPV optimize the mining dynamics in the long-
curves are obtained. A wide range of possi- term planning strategy of mining.
ble open pits is generated by this way in- The Net Present Value is calculated by
cluding an engineer selecting the optimum discounting the estimated annual cash flows
open pit, which once again confirms that an at the current time using the discount rate,
engineer still has an irreplaceable role in which represents the risk of investment.

(1)

where: the south of the town of Majdanpek in its


k - discount rate immediate vicinity. Mining of copper ore at
t - number of years. the open pit South Mining District is carried
The importance of planning the open pits out using a discontinuous technology of
is seen in the case of the open pit South Mi- excavation, using the drilling - blasting
ning District Majdanpek in which the copper works and loading - transport machines.
ore is mined. The analysis of mining dyna- The open pit South Mining District op-
mics for current real indicators of mining erates within the company Copper Mine
conditions at the open pit and designed mi- Majdanpek, which is part of the company
ning dynamics, and within the framework of Mining and Smelting Basin Bor Group
the project defined the optimal contours of (RTB Bor Group).
the open pit, has shown how the business In 2013, the project was developed that
operations of a mining company is sensitive reviewed the long-term development of the
to the changes in mining production. open pit South Mining District Majdanpek
[11]. Input data for defining the final limits
CASE STUDY
of the open pit and mining dynamics in the
The open pit South Mining District of software Whittle are provided in the follo-
the Copper Mine Majdanpek is located in wing Table 1.

No. 1-2, 2017 17 Mining & Metallurgy Engineering Bor


Table 1 Techno-economic data for analysis [11]
Parameter Unit Value
Base metal prices
- Copper $/t 6,000
- Gold $/kg 35,000
- Silver $/kg 650
Costs of ore mining $/t 1.50
Costs of waste mining $/t 2.50
Costs of flotation ore processing
- Up to 2014 $/t 4.00
- Period after 2014 $/t 3.20
Costs of metallurgical treatment of concentrates
- Costs of copper production from concentrates
- 2013 $/t Cu cathode 850
- Period after 2013 $/t Cu cathode 600
- Costs of gold refining $/kg 150
- Costs of silver refining $/kg 15
Flotation copper recovery from ore
- Up to 2014 % 80
- Period after 2014 % 86
Metallurgical copper recovery from ores
- Up to 2014 % 94
- period after 2014 % 98
Total recovery of gold % 50
Total recovery of silver t/year 50
Annual processing capacity of ore t/year 8,500,000
Discount rate t/year 10

The basic problem of production system The conducted analysis is aimed to de-
at the open pit, in the period from 2013 to termine the resulting implications in the
the present day, is related to a delay in relo- company business, which is reflected pri-
cation the major infrastructure facilities, marily in the lost profit due to deviations
located in a newlydefined contour of the from the optimal mining dynamics defined
open pit (the route of the state road M22 I B by the mining project.
series, a part of the route of the existing The amount of ore and overburden in
35 kV transmission line, the riverbed of the the early years, from the first to the fifth
river Mali Pek, the urban waste water col- year, represent the real amounts, excavated
lector), as well as pumping of the mine at the open pit South Mining District Maj-
water, whose starting level was at a height danpek [12].
of k+221, and these are amounts of Geological reserves of the copper de-
15,136,286 m3. This caused a delay in the posit South Mining District Majdanpek are
ore stripping and therefore deviation from calculated by the method of mini blocks,
the designed solutions and parameters that sizes 15x15x15 m. The basis for calculation
guarantee the maximum NPV, which is veri- the geological reserves is a digital block
fied by the techno-economic analysis of the model of the deposit which was formed in
project. the software Gems [13, 14]. Geostatistical

No. 1-2, 2017 18 Mining & Metallurgy Engineering Bor


method that, used to assess the content of Figure 1 shows a three-dimensional
metals in the process of deposit modeling is block model of Cu in the deposit South
a method of real kriging. Mining District.

Figure 1 View the 3D block model of the deposit South Mining District Majdanpek

On the basis of a defined block model development phases of the open pit; six
of the deposit, the optimization of the pjases are defined, wherein the sixth pha-
final contour of the open pit was done se is the final contour of the open pit,
in the software Whittle and defined Figure 2.

Figure 2 View of the final contour of the open pit mining South Mining
District Majdanpek (3D) [15]
a) Phase 1; b) Phase 2; c) Phase 3; d) Phase 4; e) Phase 5; f) Phase 6 (final contour of the open pit)

No. 1-2, 2017 19 Mining & Metallurgy Engineering Bor


RESULTS AND DISCUSSION

Maximization of the NPV of the project The results of carried out analysis are
in the life time of the mine was carried out shown in the following graphs in Figures
by optimization the mining dynamics. 3 and 4.

Figure 3 Mining dynamics for the project design and conducted analysis

The following can be concluded from and then decline steadily until the end of
the graph in Figure 3: mining life.
1) During the period from the first to 3) The conducted analysis shows that
the sixth year, significantly lower amounts it is necessary to significantly increase the
of ore and overburden were mined relative annual amounts of overburden to achieve
to the designed amounts. the required capacity of ore mining.
2) The amounts of overburden are- 4) The lifetime of the mine was in-
balanced by the project, which in the peri- creased by 4 years, while the amounts of
od up to 13th year have a uniform value, ore and overburden are the same.

Figure 4 Cash flows for the project design and conducted analysis

No. 1-2, 2017 20 Mining & Metallurgy Engineering Bor


Graph in Figure 4 indicates the follo- The main value of the conducted analy-
wing: sis is that the real case shows how important
1) Cash flows in the period up to 3rd it is the planning in the mining system in
year of mining are negative for the terms of achieving the best business results.
conducted analysis and total to – Analysis indicates that any deviation from
35,771,590 $. In the project design, the planned solutions in a project can lead
the negative values of cash flows the business to be affected, not only mine,
are up to 2nd year of mining and but also the entire company of RTB Bor
amount to $ -16,912,075. Group.
2) The curve of cash flows for the Analysis has showed that the deviation
conducted analysis, after reaching a from the planned mining dynamics, within
positive value grows much slower the project defined optimal contour of
and has less value compared to the the mine, resulting in a reduction the pro-
curve of cash flows for the solution jected values of the NPV for 30%, or
provided in the project. 152,857,774 $.
Based on the generated cash flows, the
maximum NPV are calculated and to be REFERENCES
achieved in the following cases:
- NPV obtained by the project design [1] E. M. Gershon, An Open - Pit
is 507,621,108 $, Production Scheduler: Algorithm and
- NPV obtained by the conducted Implementation, Mining Engineering
analysis is 354,763,334 $. 39 (1987) 793-796.
[2] A. H. and P. A. Onur Dowd, Open-Pit
Due to a deviation from the given so-
Optimization - Part 2: Production
lution in the project, or the planned min-
ing dynamics, there was a realization of Scheduling and Inclusion of Road-
smaller cash flows in the initial years of ways, Transactions of the Institute of
Mining and Metallurgy Section A 102
operation and longer mining life of the
(1993) A105-A113.
open pit, what have also increased the
discounting time that has a significant [3] Wang Q., Long - Term Open - Pit
reduction in the NPV in the amount of Production Scheduling Through Dyna-
152,857,774 $ in the end result. mic Phase - Bench Sequencing, Tran-
sactions of the Institute of Mining and
CONCLUSION Metallurgy Section A 105 (1996)
A104-A99.
Planning every mining operation has the [4] Whittle J., The Facts and Fallacies of
main goal to achieve the best economic Open Pit Optimization, Whittle Pro-
effects of business in the life time of the gramming Pty., Ltd., North Balwyn,
mine. Also, the mining company may want Victoria, Australia. 1989,
to simultaneously maximize the NPV, the [5] B. Tolwinski and R. Underwood, A
life time of the mine and metal content in scheduling Algorithm for Open Pit
the ore, and on the other hand to minimize Mines, IMA Journal of Mathematics
the capital expenditures, which is difficult to Applied in Business 7 and Industry
achieve. The most common case is that the (1996) 247-270.
main objective of the company is to maxi- [6] Tolwinski B. and Golosinski T. S.,
mize the NPV, and that the life time, re- 1995, Long Term Scheduler Open Pit,
serves and capital costs are in certain accep- in Proceedings of the International
table limits.

No. 1-2, 2017 21 Mining & Metallurgy Engineering Bor


Symposium on Mine Planning and [13] D. Kržanović, M. Žikić, R. Pantović:
Equipment Selection, p. 256-270. Important Improvement of Utilization
[7] E. M. Gershon, Mine Scheduling Opti- the Available Geological Reserves of
mization with Mixed Integer Progra- the South Mining District Deposit
mming, Mining Engineering 35 (1983) Majdanpek and the New Defined
351-354. Optimum Contour of the Open pit
[8] M. L. Smith, Optimizing Inventory using the Whittle and Gemcom Soft-
Stockpiles and Mine Production: An ware, Mining Engineering - Mining
Application of Separable and Goal Engineering, Mining and Metallurgy
Programming to Phosphate Mining Institute Bor, 2012, pp. 29-36
Using AMPL/CPLEX, CIM Bulletin [14] D. Kržanović, M. Žikić, Z. Vaduves-
92 1030 (1999) 61-64. ković: Innovated Block Model of the
[9] L. S. Caccetta and P. Hill, An Appli- Copper ore Deposit South Mining
cation of this Branch and Cut Open Pit District Majdanpek as a Basis for
Mine Scheduling, Journal of Global Analysis the Optimum Development
Optimization 27 (2003) 349-365 of the Open Pit Using the Software
[10] V. Rafiee, Asghari, O., 2008, A Heuri- Packages Whittle and Gemcom,
stic Traditional MIP Solving Approach Mining Industry - Mining Engineering,
for Long Term Production Scheduling Mining and Metallurgy Institute Bor,
and Open Pit Mine, Journal of Applied 2011, pp. 69-76
Science 8 (24), pp. 4512-4522. [15] D. Kržanović, R. Rajkovic, M. Mikić,
[11] D. Kržanović et all, Supplementary M. Ljubojev, Analyzing the Possibility
Mining Project of the Copper Ore Mi- of Increasing Capacity of Copper Ore
ning from the Deposit South Mining Mining at the Open Pit South Mining
District of the Copper Mine Majdan- District Majdanpek at 11x106 t
pek, Mining and Metallurgy Institute Annually, Mining and Metallurgy
Bor, 2013 (in Serbian) Engineering Bor, 3/2015, Mining and
[12] Source: Group RTB Bor Metallurgy Institute Bor, pp. 73-80.

No. 1-2, 2017 22 Mining & Metallurgy Engineering Bor